kiiru electrical

download kiiru electrical

of 12

Transcript of kiiru electrical

  • 8/7/2019 kiiru electrical

    1/12

    CHECKINGAND TESTINGELECTRICAL

    INSTALLINGWORKDepartment ofConsumer EnergySafetyand Employment Protection

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    PrefaceIt is a requirement of the Electricity (Licensing) Regulations 1991 that allelectrical installing work carried out in Western Australia complies with therelevant standards, including Australian/New Zealand StandardAS/NZS3000:2000(known as the Wiring Rules) and the WA Electrical Requirements.The application of minimum electrical requirements and standards is essential for

    the safety of persons, livestock and property.A clear understanding of these requirements is essential for those involved withelectrical installing work carried out in Western Australia.

    All completed electrical work must be checked and tested by a licensedelectrician before the electrical contractor certifies the work to the relevantnetwork operator.This booklet has been produced as a guide to meet the checking and testingrequirements for electrical installing work, as specified in the Wiring Rules. Whilstthe details are focussed on domestic electrical installations, the principles applyto all electrical installing work.The testing methods in this booklet are not exclusive. Other test methods may beused provided that they meet the minimum requirements of the Wiring Rules.More detailed testing information is contained in the Australian/New ZealandStandardAS/NZS 3017 Electrical installations - Testing and inspection

    guidelines.CHECKING AND TESTING ELECTRICAL INSTALLING WORKCHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Table of ContentsChecking, Testing and Certification of Electrical Installing Work 1Installation Test Certificate 2Checking and Testing 4Checking and Testing Procedure 51. Visual Inspection 52. Earth Resistance and Continuity Tests 5Test Equipment 6

    Test Procedure 73. Insulation Resistance Test 8Test Equipment 8Test Procedure 84. Polarity/Functional Test 10Test Equipment 10Test Procedure 105. Correct Circuit Connections 116. Fault-loop Impedance Test 11Test Equipment 11Test Procedure 117. Verification of RCD Operation 12Testing Alterations and Additions 12

  • 8/7/2019 kiiru electrical

    2/12

    Test Equipment 13Table 1 - Maximum resistance values of final subcircuit 14protective earthing conductorTable 2 - Comparison of voltage drop and fault-loop 15impedance to determine circuit maximum distanceFurther Information 16

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK1

    Checking, Testing and Certification ofElectrical Installing Work

    All completed electrical installing work must be checked and tested to confirmthat it complies with the Wiring Rules and is safe for connection to the electricitysupply. The required steps to comply with the current regulatory requirements areas follows:1. When the electrical installing work has been completed, a licensed electrician(which may be the contractor or an employee) is required to carry out checksand tests of the installation, to ensure the electrical work meets therequirements of the Wiring Rules. The checking and testing should be carriedout in accordance with a formalised checking and testing procedure.

    2. Once these checks and tests have been completed, the electrician confirmson the relevant section of the Notice ofCompletion or Notice ofCompletion-Minor Work, that the checking and testing has been carried out.3. For electrical installing work that requires the network operator to attend(eg. for electricity supply connection or alteration to the supply serviceapparatus), the electrician then completes an Installation Test Certificate andfixes it inside the meter enclosure of the installation.4. Then, in the usual manner, the electrical contractor (or nominee) completesthe Notice ofCompletion, thereby certifying the work, and submits the Notice

    to the network operator.5. When the Notice ofCompletion is received, the network operator willdetermine if an inspection of the installing work will be carried out, to ensurethat the standards of electrical safety of the installation are being maintained.The network operator will also arrange for the connection of the electricity

    supply if necessary.Notes1. Minor work, ie. alterations and additions to existing electrical installations, isalso subject to a similar system except that the work is connected to theelectricity supply by the electrician.2. Western Powers ContractorConnect Scheme permits accredited electricalcontractors and authorised electrical workers to connect the electricity supplyto the installation and to then submit the Notice ofCompletion followingconnection.

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Installation Test CertificateWhen a Notice ofCompletion is to be submitted for completed electrical installingwork that may require the network operator to attend (eg. new connection orupgrade of supply), the electrician carrying out the checking and testing must

    complete an Installation Test Certificate.An Installation Test Certificate is an adhesive label (included in books ofPreliminary Notices / Notices ofCompletion and also available from networkoperators) that must be filled in by the electrician who performed the checkingand testing of the completed electrical installing work.

    An Installation Test Certificate is to be fixed by the electrician to the inside of themeter enclosure to indicate to the network operator and the customer that theinstallation is completed, has been checked and tested and is safe to beconnected to the electricity supply.The electrician is requested to record the following key installation test resultsand the underground consumers mains cable route on a self adhesive label

  • 8/7/2019 kiiru electrical

    3/12

    which is also to be placed inside the meter enclosure:

    main earth conductor resistance;

    either the earth continuity or fault-loop impedance values for each sub circuit;and

    insulation resistance values for each sub circuit.The information will benefit subsequent electrical work and inspection, as well asassist in preventing electric shocks and accidents.23

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    INSTALLATIONTESTCERTIFICATEInstallationAddress: _________________________I confirm that I have carried out the checks and testsof this electrical installation, as required by Electricity(Licensing) Regulations 1991.Signature of A Grade Electrical mechanicDate E.W. Licence NoThis work has been carried out for and on behalf of:Electrical contractors name and licence No.Note 1. The Electrical Mechanic is responsible forthe issue of this Test Certificate.2. This Test Certificate is to be fixed to theinside of the meter enclosure.DONT MEDDLE WITH ELECTRICITY -ALWAYS USE A LICENSED ELECTRICAL CONTRACTOR

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK4

    Checking and TestingOn completion of the electrical work and before the electricity supply is

    connected and energised, the electrical contractor is responsible to ensure that:

    the electrical work has been carried out in accordance with the Electricity(Licensing) Regulations 1991; and the installation has been checked and tested and is safe for connection tothe electricity supply.To achieve this, the following minimum checks and tests should be carried out bythe electrician:1. Visual Inspection - should be carried out whilst referring to a plan (to ensurea systematic check to pick up any omissions and to ver ify that the workcomplies with the requirements of the applicable standards).2. Earth Resistance and Continuity Tests - this test is to include the mainearthing conductor, protective earth conductor and bonding conductor.3. Insulation Resistance Test - this test is necessary to ensure that theinsulation resistance between live parts/conductors and earth is adequate.4. Polarity Test - used to ensure correct connection of active, neutral andearthing conductors.5. Correct Circuit Connections - this test checks earthing conductors do notcarry current during normal operation and no short circuit exists.6. Fault Loop Impedance - measures the fault loop impedance of each circuit toverify the protective device will operate.7. Verification of RCD (residual current device) Operation - testing of RCDs iscarried out to ensure that the RCD operates.

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Checking and Testing ProcedureThe following procedure will meet the key checking and testing

  • 8/7/2019 kiiru electrical

    4/12

    requirements. Ensure that test results are recorded carefully. Other testingprocedures may be used, provided that they meet the minimumrequirements of the Wiring Rules.It is also recommended that the tests be carried out whilst there is noelectricity supply connected (except for the Fault Loop Impedanceverification or the RCD operation test) to the installation, or, in the case ofalterations to an existing installation, that the circuits to be tested have

    been isolated from the electricity supply and have been securely taggedand where possible padlocked.

    1. Visual InspectionA visual inspection is carried out to ensure that all work has been correctlycompleted, by checking that:

    all cables and equipment have been correctly installed and terminated, and the installation complies with the relevant parts of the Wiring Rules and theWA Electrical Requirements.

    2. Earth Resistance and Continuity TestsEarth resistance tests are required to confirm the installed earthing system willcause circuit protective devices to operate and maintain cable integrity if there isa fault between live parts and exposed conductive parts.Earthing System Impedance

    The resistance from any point of the electrical installation required to be earthed,to the point where the main earthing conductor is connected to the neutralconductor (MEN connection) of the supply system, shall be low enough to permitthe passage of current necessary to operate the circuit protective devices. Toconfirm this value (which is dependent upon the type and rating of the protectivedevice and the fault-loop impedance of the associated conductors) requires thefollowing test to be performed:Test 1: Obtain the resistance value of the protective earthing conductor using a

    quality ohm meter (see next page for procedure) and compare this valuewith the maximum allowable resistance as tabulated in Table 1, page 14of this booklet.5

    CHECKING AND TESTING ELECTRICAL INSTALLING WORKOr, where the electricity supply IS connected:

    Test 2: Obtain the fault-loop impedance of each sub circuit using a quality faultloopimpedance meter (refer to manufacturers instructions and page 15of this booklet for procedure).Compare the measured fault-loop

    impedance value with the maximum value provided at Appendix B,Table B4.1 of the Wiring Rules.Notes:1 If the application of a fault-loop impedance test onto an RCDprotected sub circuit results in the RCD operating, then:

    the earth resistance and continuity test requirements areconsidered to be satisfied; and

    the fault-loop impedance value need not be considered further.2 If the value measured is GREATER than the allowable maximum,then the following steps must be performed:

    Test 2.1 Check the MEN connection, active, neutral and earthconductor/equipment connections are all solidly made.Repeat the fault-loop impedance Test 2, above.If the fault-loop impedance values exceed the requirementsof Table B4.1, then perform Test 2.2Test 2.2 Perform the earth continuity measurement, Test 1 andconfirm results.Repeat the fault-loop impedance Test 2, above. If the fault-loopimpedance values do not satisfy the requirements of Table B4.1then contact the network operatoradvising them of thediscrepancy.

  • 8/7/2019 kiiru electrical

    5/12

    Main Earthing ConductorThe resistance from the earthing electrode to the point where the main earthingconductor is connected to the neutral conductor of the supply system shall notexceed 0.5 ohms.

    Test Equipment

    A multimeter set to ohms.

    Insulated copper conductor of suitable length (long lead).6CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Test ProcedurePreparation:1. Ensure that the electricity supply has been disconnected.2. Connect an insulated copper conductor of suitable length (long lead) to oneterminal of the ohm meter.3. Connect a standard length test lead to the other terminal of the ohm meter(short lead).4. Connect the two leads together, and

    zero the multimeter or, if this is not possible, record the resistance of the test leads.5. Disconnect the water pipe equipotential bonding conductor and the waterheater earthing conductor (if applicable).Care must be taken that there are no parallel earth paths whenconducting this test, ie. the earthing system must not be connected toeither the water or gas pipes.6. Disconnect the MEN link from the main neutral link and connect it to the longlead (ie. long lead now connected to the earth bar).A: Main Earthing Conductor

    Connect the short lead to the earth electrode and measure the earthresistance of the main earthing conductor.

    The resistance shall not exceed 0.5 ohms for the main earthing conductor.B: Earth Continuity Test

    Using the long lead and zeroed multimeter, measure, for each circuit, theearth conductor resistance from the circuit extremityto the switchboard. Confirm the measured values are LESS THAN those values as provided atTable 1, page 14 of this booklet foreach sub circuit.

    This test is applicable to all circuits, including socket outlet circuits, lightingcircuits and fixed equipment (eg. water heater supply) circuits.7. Re-connect the MEN link to the main neutral link.8. Re-connect the water pipe equipotential bonding conductor.7

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    3. Insulation Resistance TestAn insulation resistance test is performed to ensure that the resistance between

    all live conductors and earth, or as the case maybe, all live parts and earth, isadequate to prevent electric shock hazards, fire hazards and equipment damage.It is a requirement ofClause 6.3.3.3.1 of the Wiring Rules that the insulationresistance between all live conductors (including the neutral) connected together,and earth, measured with all protective devices in circuit and all switches on, isnot less than 1 Megohm (see Note below). This applies to the completeinstallation and all parts of the installation.This does not preclude the use of appliances incorporating heating elements

    provided that, when tested with all elements in circuit, the insulation resistancebetween live parts and the earthing terminal or earthing contact of the applianceis not less than 0.01 Megohm (10,000 ohms).

  • 8/7/2019 kiiru electrical

    6/12

    Note: Whilst the minimum reading is 1 Megohm, the ideal reading is infinity.This indicates a sound installation.

    Test EquipmentWhere the supply voltage does not exceed 250 volts between conductors andearth, a 500 volt insulation tester should be used to perform this test.

    Test Procedure1. Ensure that all protective devices are in circuit and that all switches are on. If

    there are two way lighting circuits in the installation, tests must be carried outwith the two way switches in all positions, so all circuit conductors are tested.2. Set the insulation tester (eg. Megger) to Megohms.3. Connect one lead of the insulation tester to the main earthing bar (MEN Linkdisconnected) and the other lead to the actives and neutrals connectedtogether. Do not test between actives and neutrals.4. Measure the insulation resistance of the total installation (including theconsumers mains).If the insulation resistance is 1 Megohm or more - re-connect the MENLink and return the installation to normal.

    8

    CHECKING AND TESTING ELECTRICAL INSTALLING WORKIf the insulation resistance is less than 1 Megohm - test all circuitsindividually, starting with circuits supplying appliances incorporating heating

    elements.Where a circuit is less than 1 Megohm, disconnect the appliance orappliances. Then test the circuit and appliance (separately) to ensure that theinsulation resistance of both the circuit and the appliance complies with thefollowing:

    not containing a heating element - is not less than 1 Megohm, or containing a heating element - is not less than 0.01 MegohmNote: Where the insulation resistance of an appliance containing heating

    elements is found to be less than 0.01 Megohm and the defect cannot berectified at the time of checking and testing, the electrical contractor mustmake arrangements for correction of the defect prior to submission of theNotice ofCompletion. Alternatively, the following procedure may be used:a) Isolate the defective circuit, including the neutral conductor, by

    disconnecting at the appropriate switchboard.b) Attach an out of service tag to the circuit protection device, advising thatthe circuit has been disconnected due to low insulation resistance.c) Check that the earth conductor has been reconnected at the MEN point.d) Then submit the Notice ofCompletion.Ensure that all circuits and the MEN connection are re -connected when thetesting is complete.9

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    4. Polarity TestPolarity tests are carried out to ensure the correct connection of active, neutraland earth conductors to electrical equipment and to ensure that switches are notinstalled in neutral conductors. Clause 6.3.3.4 Polarity of the Wiring Rulesspecifies the testing requirements for this mandatory test.

    Test EquipmentTo carry out these tests, a continuity tester such as a multimeter (set to ohms)should be used.

    Test ProcedureTo ensure that the installation circuits/equipment will function as intended, it isnecessary that the following tests be performed:

    Isolate the active conductors by turning the main switch OFF and tagging. Confirm consumer and sub mains cables/connections by simply testing fromthe point of supply or distribution board to the main switchboard using an

  • 8/7/2019 kiiru electrical

    7/12

    ohm meter and long test loads. Test result ,0 .

    Confirm active conductor switching by using an ohm meter with the long leadconnected to the active conductor at the switchboard and the short leadconnected to the switch terminals (one at a time) in the following manner:

    i) Switch ON ,0 for both terminals

    ii) Switch OFF ,0 for one terminal and infinity for the other terminal

    With the MEN link in place, confirm the polarity of socket outlets using a 10resistor and an ohm meter. Connect the 10resistor between the circuitactive conductor and the neutral bar then at each socket outlet connect onelead of the multimeter to the earth terminal and the second lead to the activeterminal. Test the resistance value for:

    i) socket outlet switch OFF ,infinity

    ii) socket outlet switch ON ,10.10

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    5. Correct Circuit ConnectionsThese tests are required to ensure the following:1. that protective earthing conductors do not carry current;2. to prove there are no short circuits within the installation; and

    3. for the circuit continuity test, to prove each circuit for electrical continuity andthat all switches operate in the active conductors.

    6. Fault-loop Impedance TestThis test is carried out to confirm the fault-loop impedance value of each circuitwill be low enough to ensure the operation of the protective device during a fault.

    Test EquipmentTo perform the fault-loop impedance test, a fault-loop impedance meter isrequired.

    Test Procedure

    Energise all circuits

    Using the fault-loop impedance meter, proceed to the equipment to be testedand measure the earth-loop impedance at this point. Repeat for other items

    on the circuit. The measured value must be less than the maximum values as tabulated atTable B4.1 of the Wiring Rules.

    If an RCD operates during the test, the test result can be consideredsatisfactory.11

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    7. Verification of RCD OperationThis is normally achieved by operation of the integral test device (typically testbutton on the RCD) to confirm:1. the RCD is functioning correctly; and2. the tripping device mechanisms are operating.Warning: Operation of the integral test device does not provide a means ofchecking:

    continuity of the main earthing conductor or the associated circuit protectiveearthing conductor; or

    any earth electrode or other means of earthing or the associated electricalinstallation earthing.

    Testing Alterations and AdditionsWhen alterations are carried out to an existing electrical installation, it isessential that the electrician tests the work to ensure compliance with the

  • 8/7/2019 kiiru electrical

    8/12

    relevant standards and specifications.The tests described in this booklet must also be carried out on alterations andadditions to ensure the electrical installing work is safe to remain connected tothe electrical installation.The majority of tests described in this booklet are designed to be carried outwithout power being connected. When performing these tests, make sure thatelectricity supplies are disconnected where necessary and that the appropriate

    isolation and tagging has been carried out.A Notice of Completion - Minor Work form must be submitted to thenetwork operator to certify this type of work.12

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Test EquipmentBefore performing any tests, ensure that the test equipment is correctly set, isfunctional and is in good condition, particularly the test leads.Remember, when testing:

    check that the test equipment is operating correctly perform the required tests re-check the test equipment to confirm that it still operates correctly.Some types of test equipment (eg. multimeters) are fitted with fuseprotection. Ensure that at all times only the correct type and rated fuse isused. This is for your protection.Electrical test equipment is a very important part of an electricians tools. Testinstruments should be tested at intervals not exceeding one year and records

    kept to verify this.13

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Table 1Maximum resistance values of final sub circuit protective earthing conductorsProtective Circuit - breakers FusesType B Type C TypeDDevice Earthing Disconnection timesRating Conductor

    Size 0.4sec 0.4secA mm2 Maximum final subcircuit earth conductor

    resistance 6 1 3.08 1.65 1.00 3.6910 1.5 1.85 1.00 0.60 2.0616 2.5 1.16 0.62 0.38 0.9920 2.5 0.93 0.50 0.30 0.6825 2.5 1.07 0.57 0.34 0.7632 2.5 0.72 0.38 0.23 0.5140 2.5 0.66 0.35 0.21 0.4450 4 0.54 0.29 0.17 0.3463 4 0.44 0.23 0.14 0.2614

    CHECKING AND TESTING ELECTRICAL INSTALLING WORK

    Table 2Comparison of voltage drop and fault -loop impedance to determine circuitmaximum distanceThis table details the single phase voltage drop for a combination of conductorsize, maximum demand current and distance. It also displays the maximumcircuit length for a Type C circuit breaker (as normally used in most installations)to ensure the operation of the circuit breaker during a earth fault. You will noticethat compliance for voltage drop is the predominant requirement compared to thefault-loop distance for the given circuit breaker type.15

  • 8/7/2019 kiiru electrical

    9/12

    Notes:#1: Maximum demand determined using (a) full load, and (b) half the rating ofthe protective device assuming distributed load. Refer to Wiring RulesClause 3.6.2

    #2: Voltage drop determined using 230V @ 5% = 11.5V maximum allowable.#3: Distances obtained from Wiring Rules Table B5.1.mm2A A #1 V (11.5V = maximum)1.0 1010 10.3 - - - - 22* 555 5.2 7.7 10.3 - - 45* 551.5 1010 6.6 9.9 - - - 35* 825 3.3 5.5 6.6 9.9 - 70* 822.5 1616 5.8 8.6 - - - 40* 858 2.9 4.3 5.8 8.6 - 80* 854.0 2525 5.6 8.4 11.2 - - 41* 6712.5 2.8 4.2 5.6 8.4 10.2 82 67** Denotes limiting parameterConductorSize

    ProtectiveDeviceRatingMaximumDemand ForVoltageDrop #2For Type CCircuitBreaker #3Distance20m 30m 40m 60m 80mVoltage DropMaximumDistancem

    CHECKING AND TESTING ELECTRICAL INSTALLING WORKFurther InformationFor further information on testing electrical installing work, please contact theElectrical Inspector at the relevant network operator, as listed in the manual WAElectrical Requirements.For further information, please contact:EnergySafety303 Sevenoaks StreetCannington WA 6107Telephone: (08) 9422 5200Facsimile: (08) 9422 5244Email: [email protected]: www.energysafety.wa.gov.au16

    Issued by

    EnergySafety

    ESWA E022 1106Certelec Ltd provides a full range of Testing and Inspection services on fixed

    wiring systems, inspecting and testing low and medium voltage systems in commercial,

    industrial and domestic premises.

    Fixed Installation Testing (FIT) involves testing the electrical services and systems thatconduct electricity around a building. Anything electrical in a building that is fixed such as

  • 8/7/2019 kiiru electrical

    10/12

    lighting, socket outlets, air conditioning and

    other fixed plant needs to be tested. Certelecis a specialist FIT company and has no

    interest in remedial repairs. Its objective is to present an unbiased installation assessment.

    New Installations andAlterations or Additions to the Installation

    The IEE Wiring Regulations require every electrical installation to be inspected and tested

    during erection and on completion before being put into service, this requirement also applies

    to alterations or additions that include the provision of a new circuit to an existing installation(for domestic installations see Part P).

    Certelec can provide an independent inspection, test and certification of new installationsincluding a first fix inspection to ensure the installation meets BS7671 and appropriate

    Building Regulations relevant to electrical work. Certelec also offer a specific service to assistclients in meeting their local Building Control requirements with regard to electrical

    'notifiable' work.Certelecs BSi Kitemark licence is specifically defined to allow us to inspect, test and certify

    any electrical contractors work.

    The test and inspections would include:

    y Visual inspection

    y Characteristics of supply at the origin of the installation

    y Protective conductors continuity test

    y Ring Circuit Continuity

    y Insulation resistance test

    y Polarity

    y Earth electrode resistance

    y Earth fault loop impedance test

    y Operation of residual current devices

    y Prospective fault currenty Site applied insulation and insulation of non conducting floors and walls

    Periodic Inspection Reports - What is a periodic

    inspection?

    The Electricity at Work Regulations state that all electrical systems and equipment used in the

    working environment should be in a safe condition.

    The Health & Safety Executive recommend that to comply with the regulations an inspectionand testing schedule must be implemented at all workplaces. INSURANCE COMPANIES

    are increasingly requiring evidence that electrical installations to Public, Commercial and

    Industrial locations are safe working and occupation environments, i.e. 'fit for purpose'.

    All installations will deteriorate/degrade with use and age. This process is often acceleratedby 'DIY' additions/extensions that may NOT have been carried out to Code. Government

    statistics say that on average 10 people die and about 750 are seriously injured in accidents inthe home involving unsafe electrical installations.

  • 8/7/2019 kiiru electrical

    11/12

    A Periodic Inspection is an inspection on the condition of an existing

    electrical installation, to identify (in order of priority) any deficiencies againstthe National Safety Standard (EAWR 1989, BS 7671:2008) for electrical

    installations. Note: Certelec does NOT undertake Electrical Inspections on alimited scope/range basis, i.e. inspection range less than 100% of the

    Installation. We believe, such limitation/s are not Industry 'best practice'.

    Not just a visual inspection but a full inspection and testing of the system

    y Identifies if any electrical circuits or equipment are overloaded

    y Detects any potential electrical shock risks

    y Discovers any fire hazards in your electrical installation

    y Finds any defective DIY electrical work

    y Reveals any lack of protective earth /bonding

    y Details the type of fixed wiring system and its condition

    y Checks the suitability of the consumer unit

    y Examines the equipment e.g. switches, socket-outlets and light fittings

    y Tests any residual current devices

    y Discovers any wear and tear, damage or other deterioration

    The report identifies and classifies problems according to the I.E.E scale:

    1. Requires urgent attention2. Requires improvement3. Requires further investigation4. Does not comply with BS7671 (this does not necessarily imply that the installation is

    unsafe)

    When is it needed?

    The IEE recommends the maximum period between periodic inspection and testing is:

    y Domestic - 10 years or change of occupancy

    y Commercial - 5 years or change of occupancy

    y Residential Accommodation - 5 yearsy Buildings open to public - 3 5 years

    y Industrial Buildings - 3 yearsy Special locations eg. Swimming Pools - 1 year

    Other instances when a periodic inspection should be carried out are:

    y When a property is being prepared to be lety Prior to selling a property or when buying a previously occupied property

    All testing is carried out to BS7671:2008. Details ofkey changes are shown on this page.

    The Health and Safety Executive leaflet Electrical Safety and You outlines basic measures to

    help you control the risks from your use of

    electricity at work.

  • 8/7/2019 kiiru electrical

    12/12