Sandra BradleyResearch Director
Consumer and Retail Applications
Alfonso GutierrezResearch Director
Healthcare and Industrial Applications
Tom YenLab Manager
Instrumentation Innovator
Raj VeeramaniFaculty Director
3
Agenda – 4:00-5:30
• Welcome / Expectations/ Advisory roles• Law and Entrepreneurship Clinic Consultations – Room 3164• IoT Lab / space & resources• Team introductions
– Each member– Project description– Approach
• Project Scope/ Resources /Work plans & timeline/ (individual teams)
• Next steps• IoT Lab remodel/equipment ideas
4
IoT Lab – This semester
• Simple/ rapid-to-show use cases and design projects in progress
• Self-directed teams• IoT Lab resources
– Devices– Space– High-level guidance (Tom/ Sandra/ Alfonso)
• Goal: successful IoT poster session and demos to the UW and Madison community on December 4
5
IoT Lab Space and Resources
• Mechanical Engineering Room ME3153
• Access at any time. Lockbox on door – try this before you leave today
• Smart cabinet for inventory items
8
Projects1. Camera in Air2. Smart Helmet3. UW Madison Augmented Reality Tour4. Avatar5. Internet of Car6. D2D (Device-to-device) Communication7. Intelligent Library System8. Bicycle RFID9. Degree Planner10. Smart Kitchen Inventory11. UbiquityVR12. Myo Band Demo
9
Criteria• Completeness of thinking• Creativity• Relevance/Impact• Strength of team• Do-able in one semester or less
10
Project Work Plan ExampleTeam # Project name: Timeline W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11
Stage 1 Product demonstration cycle 1 Deliverable Start End
3-Mar
10-Mar
17-Mar
24-Mar
31-Mar
7-Apr
14-Apr
21-Apr
28-Apr
5-May
12-May
1.1 Plan Project details (Roles / responsibilities / tasks / schedule) / Project Plan W1 W2
1.2 Review high level use case specs / performance expectations Process flow (High Level) W2 W2
1.3 Review / demonstrate product specs - high level assessment Prelim. Assessment W2 W3
1.4Define scope / script of use case demo / requirements Script W3 W3
1.5Program / test / debug Prototype W4 W5
1.6Prepare mid term demo final script W5 W6
1.7 Present at mid-term show Show / Prize W7 W7
Stage 2 Product demonstration cycle 2
2.2 Review high level use case specs / performance expectations Workflow/Use case scenarios W4 W5
2.3 Review / demonstrate product specs - high level assessment Test bed W5 W6
2.4Define scope / script of use case demo / requirements Test data W7 W8
2.5 Program / test / debug RFID protocol assessment W8 W8
2.6 Prepare mid term demo ROI model - baseline W7 W8
2.7 Present at final show
11
TimelineDate9/25/14 Kickoff projects in the lab –
working session10/10/14 Working session
10/24/14 Working session
11/7/14 Working session / Mid-term Open House
11/21/14 Working Session
12/1/14 Working session and dry run - tour of WID
12/4/14 Public Open House at WID
12
Next Steps
• Lab social / work session every two weeks
• You will be notified when your items are in
• Schedule time to meet with your team to get the project started