KHAPA PADRIWAR MANGANESE MINE - Welcome to...

27
PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE GOVT. OF INDIA Indira Bhavan, Jor Bag New Delhi 110003 KHAPA PADRIWAR MANGANESE MINE Tehsil-Sausar, Dist-Chhindwara, State- Madhya Pradesh (Area 7.088 Ha; Proposed Production Capacity Manganese Ore 50,000 TPA) PROJECT PROPONENT M/s Modern Minerals Industries Behind Milan Hall, Habib Nagar, Teka Naka Nagpur. (M.S.) EIA CONSULTANT SRUSHTI SEVA PRIVATE LTD. NABET Accreditated EIA Consultant Certificate No NABET/EIA/1518/RA027 Valid upto 02.12.2018 January 2017

Transcript of KHAPA PADRIWAR MANGANESE MINE - Welcome to...

Page 1: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

PRE FEASIBILITY REPORT

Submitted to

MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE GOVT. OF INDIA

Indira Bhavan, Jor Bag New Delhi 110003

KHAPA PADRIWAR MANGANESE MINE

Tehsil-Sausar, Dist-Chhindwara, State- Madhya Pradesh (Area 7.088 Ha; Proposed Production Capacity Manganese Ore 50,000 TPA)

PROJECT PROPONENT

M/s Modern Minerals Industries

Behind Milan Hall, Habib Nagar, Teka Naka Nagpur. (M.S.)

EIA CONSULTANT

SRUSHTI SEVA PRIVATE LTD. NABET Accreditated EIA Consultant

Certificate No NABET/EIA/1518/RA027 Valid upto 02.12.2018

January 2017

Page 2: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

TABLE OF CONTENTS

1. EXECUTIVE SUMMARY ......................................................................... …

2. INTRODUCTION OF THE PROJECT ..........................................................

i Identification of project & project proponent

ii Brief description of nature of the project

iii Need for the project

iv Employment generation (direct & indirect)

3. PROJECT DESCRIPTION ....................................................................................

i Type of project

ii Location

iii Alternate site

iv Size of magnitude of operation

v Project description

vi Raw materials sources & transportation

vii Resource recycling.

viii Water requirement & supply

ix Waste generation and waste management

4. SITE ANALYSIS ...........................................................................................

i Connectivity

ii Proposed plant land detail

iii Topography

iv Existing infrastructure

v Soil classification

vi Climate

vii Social infrastructure

5. PLANNING BRIEF ......................................................................................

i Planning concept

ii Population projection

iii Land use planning

iv Infrastructure demand

v Amenities

Page 3: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

6. PROPOSED INFRASTRUCTURE ................................................................

i Industrial area

ii Residential area

iii Green belt

iv Social infrastructure

v Connectivity

vi Drinking water

vii Sewerage system

viii Industrial waste management

ix Solid waste management

x Power requirement & supply

7. REHABILITATION AND RESETTLEMENT ...............................................................................................................

8. PROJECT SCHEDULE & COST ESTIMATION ...........................................................................................................

9. ANALYSIS OF PROPOSAL FINAL RECOMMENDATIONS ..................................................................................

ANNEXURE

I. KHASRA DETAILS ...................................................................................................

II. BOUNDARY PILLAR LOCATION STATEMENT (AS PER DGPS) ...........................

III. ENVIRONMENT MANAGEMENT PLAN ..............................................................

IV. ESTIMATED PROJECT CAPITAL COST & PRODUCTION COST .....................

Page 4: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

EXECUTIVE SUMMARY

The Government of India, Ministry of Mines has allotted Khapa-Padriwar Block (7.088

Ha.) for mining of Manganese to M/s Modern Minerals Industries, Nagpur. It is proposed

to establish an opencast mine for the production of Manganese with capacity 50000 TPA.

The surrounding areas are mildly undulating with dolomite working mines. The Khapa

Padriwar area show the contour from 370 m to 334 m i.e., a high hill relief of 35-36 m i.e.

the highest contour is 370 m & lowest contour is 334 m. The hill is running in E & W

direction.

M/s Modern Minerals Industries the project proponent is an ownership firm having

registered office in Nagpur District.

The area identified 7.088 Ha. of the lease to the proponent near village Khapa-Padriwar,

Tahsil Sausar, District Chhindwara, Madhya Pradesh.

The proposed area is protected forest land and an application for the diversion of the

forest land has been submitted to the Forest Department. The interstate boundary

between Maharashtra - Madhya Pradesh is adjoining from the proposed Mine Area. The

project is therefore categorized as Category “A” project as per EIA Notification 2006.

The proponent envisages developing mining activities based on the available reserves of

ore in Central India. The proponent is committed to operate systematic and scientific

mining operations making optimum utilization of the resources. The mining activities

shall be carried out as per the mandatory laws and regulation prevailing.

The total Mining Lease Area proposed is 7.088 Ha located in forest land Khasra No. 40 &

Forest Compartment No. 1588 of Forest division Chhindwara Kanhan Range in Taluka

Sausar, Dist-Chhindwara M.P. It is proposed to extract manganese with the annual

production capacity of 50,000 tonnes/annum.

The proposed method of mining is Opencast Semi-Mechanized mine with drilling and

blasting. Drilling shall be carried out by compressed air operated jack hammer and

blasting shall be done. There will not be any deployment of heavy machines in the area

for mining operation as the mining will be in small scale.

There is no drainage passing from the lease area and thus no diversion of the drainages is

required.

The mine is located at higher elevation and as such the water table is far below the likely

working depth of the mine pits. There is no problem of any ground water to interception

during mining. It will be only rain water accumulated during monsoon. These quantities

of water will be removed by pumping.

Page 5: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

The geological reserves established in the proposed Mining Lease Area is 1,34,358 tonnes

and the extractable reserves of manganese are 1,14,000 tonnes.

It is proposed to undertake extensive exploration within the mining lease during the

course of mining. Reserves of economic value are likely to be improved during this

exploration.

Quality of mineral - Mn - 32.90%, Fe -12.20%, SiO2 - 20.61%, P- 0.226%.

It is proposed to utilize overburden and mine waste by back filling/ leveling to help in

haul road construction, restoration and rehabilitation of the terrain without affecting the

drainage and water regimes in the initial phase. However, after this development the

waste material will be stored within the mining lease area..

The dumps will have systematic slope and arrangement for arresting surface runoff like

garland drains, catch drain etc. The water collected during monsoon season from garland

drains will be used for dust suppression & plantation after settlement.

The extracted mineral shall be transported by trucks to the desired destination of the

client.

The idea of the geological formations can be had from old Pits in the area. It is being

covered with the mica schists (weathered form) the Gondite rock exposed on top of hill.

Sub-tropical climatic condition prevails in the area. Maximum temperature recorded

during summer is 480C and the minimum temperature recorded during winter is 120C.

The region receives a average rainfall of around 1139 mm with an annual variation of

100 mm although wider variation have also been noticed in the past. About 80% - 85%

of rainfall precipitates from June to September.

The study area consisting of 7.088 Ha mining lease as core zone and 10 Km radius

around core zone is identified as buffer zone. The entire study area is covered under

two districts Chhindwara & Nagpur of Madhya Pradesh and Maharashtra state

respectively.

There is no proposal for benefication ore except dressing of the ROM by manual means

to separate the ore from siliceous material. During this dressing 80% of recovery of

saleable ore is envisaged. The balance 20% rejects / subgrade will be stored at reject

storage yard within mining lease area

The small scale mining operations will not have any major effect on the socio-economics

of the area. It will provide employment to the local people and will help in uplifting their

living standards.

The method of mining is semi-mechanized nature. There will not be any deployment of

heavy machines in the area for carrying out mining operation which will create noise

Page 6: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

pollution, air pollution or any other operational hazards due to presence of machines.

Precaution is required to be observed during drilling with jack hammers against dust or

during blasting to be in the safe distance. Apart from these no other factor are envisage

during future mining operation.

The Environment Impact Assessment and Environment Management Plan for the

proposed project shall be prepared as per the guidelines provided in the EIA

Notification 2006.

The power requirement will be met from MPSEB grid. The water requirement of the

project required for dust suppression, plantation and drinking to the tune of 15 m3/day

shall be met from the ground water. Necessary permission for the same shall be

obtained from competent authority.

There is no National Park, Wildlife Sanctuary, archeological site, historical places

located within 10 Km from the proposed mine.

The total project cost for the Khapa-Padriwar Manganese Mining Project has been

estimated at Rs. 4.0 crores.

2. INTRODUCTION OF THE PROJECT / BACKGROUND FORMATION.

i) Identification of Project and Project Proponent

The proposal under consideration is for Khapa-Padriwar Manganese Mine

7.088 Ha situated in forest land at-Village: Khapa-Padriwar, Tahsil-_Sausar,

Dist: Chhindwara, Madhya Pradesh for the production of 50,000 Tonnes

/Annum of Manganese ore. The proposed project is categorized as 'A' under

EIA notification 2006, Since it is located adjoining Madhya Pradesh interstate

Boundary. Address of Project Proponent is as under:

M/s Modern Minerals Industries, Nagpur,

Registered office at Habib Nagar,

Behind Milan Hall, Teka Naka, Nagpur.

ii) Brief description of nature of the project

The area falls under Chhindwara District of M.P. State at Khapa-Padriwar, Tahsil-

Sausar indicated as potential source of Manganese ore Deposit. The applicant has

been granted PL in the area by State Govt. of M.P. for carrying out prospecting

operation in the area. The prospecting has been done & based on the prospecting

mining plan is prepared and submitted for the approval to the competent Authority.

Page 7: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

iii) Need for the project and it’s important to the country and or region. Manganese is one of the major mineral deposits occurring in the Indian sub-

continent. It has played a great role in development of civilization and

industrialization. The occurrence of Manganese ore in the proposed area is proved by

the way of exploration and its production has important role in the steel industries.

iv) Employment Generation (Direct and Indirect) due to the project.

The mine will directly employ about 17 workers. There will be employment

generation of double this number in secondary and tertiary sectors. It is proposed to

employ the local population wherever possible in the proposed project activities.

Page 8: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

3 PROJECT DESCRIPTION

i) Type of project including interlinked and Interdependent project, if any.

The proposed Khapa-Padriwar Manganese Mine (7.088Ha.) will be by opencast

manual (50000 TPA). There is no interlinked project.

ii) Location (map showing general location, specific location, and project

boundary & project site layout) with coordinates.

Figure 1 gives the general and specific location of Khapa Padriwar Manganese

Mine. The nearest Railway station is about 5 km. The Khapa-Pardiwar ML area is

located at Khasra No. 40 Forest Compartment No. 1588 of Forest Division , Kanhan

Range which lies near Khapa-Padriwar village in Sausar tahsil of Chhindwara

district in M.P. It is approachable from Nagpur-Kelwad-Satnur Toll Plaza, from this

toll plaza a right turn to Sawangi village upto Grampanchyat Sawangi Office by tar

road and from here towards the area through this village by taking right/left turn

and through the dolomite mining area to applied area. The total distance from

Nagpur to Satnur 50 km and from Satnur to mines 15 kms i.e. total distance is

65/70 kms.

Page 9: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Latitude: 21029’30.4”

Longitude: 78055’5.5”

Toposheet: 55 K/15

Near Village- Khapa-Padriwar,

Taluka-Sausar,

District-Chhindwara,

Madhya Pradesh

Location of

Mine

Figure 1 Location of Map

Page 10: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

The area is covered under Toposheet No 55K/15 on 1:50,000 scale

Khasra No. Lease Area Ha. Ownership/ Occupancy

Khasra No- 40 Forest Compartment no. 1588

7.088 Govt. Forest Land

The coordinates of the boundary are given in Annexure II.

iii) Details of alternate sites considered and the basis of selecting the proposed

site, particularly the environmental consideration gone into should be

highlighted.

Mining is a site specific and has to be undertaken at the place of the occurrence of the

mineral and hence no alternative sites explored.

iv) Size or magnitude of operation.

The proposed mining Lease Area is 7.088 Ha with proposed production capacity of

Manganese Ore 50000 TPA. As per the present mining plan the production schedule will

be to the extent of 10000 TPA during the first five years subsequently due to anticipated

increase in reserves the production shall be enhanced to 50,000 TPA.

v) Project description with process details (a schematic diagram/ flow chart

showing the project layout, components of the project etc. should be given).

The manganese ores of Chhindwara district are confined to portion of valley of Kanhan

river situated in Sausar tahsil. The strip of metamorphic and crystalline country in which

Mn ore deposit occurs is 25 km from North to South with average width about 11 to 12

kms to west. The rocks of the metamorphic and crystalline complex are described

consists of interbanded granulites, gneisses schists, quartzites calcyphyres and

crystalline limestone. Manganese ore as lenticular bands intercalated between these

rocks occur as manganese silicate rocks associated manganese ore.

The lease area on study could reveal from the old pits that is being covered with mica

schist (weathered form) the Gondite rock exposed on top of the hill, there are thin

quartz veins and the manganese ore exposed in Pitt & Pit 2 and near pit1 pit on the

western edge, even out of the lease boundary in west. The mica schist are weathered

and quartzites being resistant is exposed on top of hill. The general strike of rocks is E-

W to SEE-NWN, the dips are vertical from 60`, 65° to 70° due south.

Page 11: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

On mapping at the proposed mining lease has been found that the two manganese bands

shown in prospecting report are running parallel and very close to each other, with average

4m thickness .

The band 2 exposed very near to Pit 1 and extends to some southern cuttings of Pit 2 & 4.

These two bands has been plotted on Geological Plan, Band 1 has 4 m. average

width(Gondite) and band 2 has average 2m width. The strike lengths on plotting and

assuming continuous band measures about 360 m and 160 m respectively.

Reserves :

Reserves Tonnes) . N band S band Proved Category MRL 330 52566 57510 Probable Category MRL 328 12222 12060 Total 64788 69570

Mining Method: The mining method identified as opencast manual, with minimum of

machines due to topography. The proposal for mining, production, development drawn.

The Proposed Production Programme: The summary of development work and production of Mn ore during 5 years period is—

Year Workings Ore Volume (m3)

Ore Tonnes (m3)

Recovery & Quantity in Tonnes

Waste rock H/w F/w in (m3)

1st Old Pit 1 3340 10020 8016 16311

2nd Old Pit 1A 2, 3 & 4

3436 10308 8246 15910

3rd Old Pit 1A ,2, 3 & 4

3450 10350 8280 1920

4th Old Pit 1A ,2, 3 ,4,5,&6

3333 10000 8000 26676

5 th Old Pit 1A ,2, 3 ,4,5,&6

3400 10200 8160 26672

Total 16959 50878 40702 90489

Ore to OB ratio: The total production during 5 years will be 16959 cu.m. or 50,878

tonnes with 80% recovery and the recoverable ore produced will be 40,702 tonnes

leaving 10,176 tonnes of sub grade/rejects, which will be stacked separately. The

overall ore to OB ratio comes to 1:5.53 which is economical, as the market value

compared to the production cost is lucrative. It is a medium grade ore.

Page 12: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Conceptual plan: The mining operation by means of opencast method will be

continued till conceptual period.

Conceptual Mine Development: The mining operations at 10,000 tonnes/ year will

continue over the entire pit and Band-I & Band-ll by developing one more bench and

exploiting the ore down depth upto 350 m level of probable reserves and 318 m level

when band II would completely mined. After completion of first five years of mining

operation the scheme of mining will be submitted to IBM for approval based on the

prepared exploration programme. During the next scheme of mining the proposed

production is envisaged @50000 TPA.

Waste Generation and Management: The waste generated to the tune of 1.5 Lacs cu.m

would be dumped over the 5 years can get accommodated by proper terrace and mining

the height at 6 m and slopes 30° .

Processing: As such no processing is required to get the market grade Mn ore. As the

grade has been identified as medium and marketability is known. However the 20%

rejects may have to be analysed and process as simple washing, jigging, etc. or chemical

process required will be done.

Marketing /End Use: Identified as Iron & Steel as well as Silico Manganese units in

Chandrapur and geographical location Yavatmal.

Mine Drainage

The mine is located at higher elevation and as such the water table is far below the likely

working depth of the mine pits. Hence interception of ground water is not envisaged

However, the rain water may get accumulated in the working pit at top. This water will be

used for dust suppression & plantation.

vi) Raw material along with estimated quantity, likely source marketing. area of

final products, mode of transport of raw material and Finished product.

The dressed saleable ore will be loaded into trucks /tippers of 10 tonnes capacity for

further dispatch to desired destination. Precaution will be taken to cover the material

by tarpaulin during transportation.

vii) Resource optimization / recycling and reuse envisaged in the project, if any,

should be briefly outlined.

Page 13: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

The subgrade material stacked will be investigated further and whenever possible it

will be blended with the ore.

viii) Availability of water its source, Energy / power requirement and source should be given.

The water requirement of the project is estimated to 15 KLD of the water is

required for drinking/domestic purpose. Water requirement for dust suppression

(within the lease and outside the 'ease in nearby villages), plantation and vehicle

washing will be met from mine water and from rainwater collected in mining pit. The

power requirement will be met from MPSEB grid.

xi) Quantity of waste to be generated (liquid and solid) and scheme for their

Management/disposal.

There is no soil as such. However, the schist (F/W) and the quartzites are the contact

rocks and are removed while exploiting the manganese ore which is in the form of

Band-I and Band-II in this lease area. The benches are accordingly in these rock

types; the year wise generation of waste is given below.

Year Waste

generated

in cu.m.

Remarks

1 16311 The mining during 5 years will be

on bench 1 to 5 to a depth of the

proved reserves level, based on

topography upto 355 m , 323 m.

2 15910 3 4920 4 26672 5 26672

Total 90485

x) Schematic representation of the feasibility drawing which give information of

EIA purpose.

The EIA will include an assessment of the potential impacts envisaged as an effect

of the project, during the operation of the mine. The assessment will be based on a

consideration of the individual components of the project.

Page 14: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

4. SITE ANALYSIS

i) Connectivity.

The area is approachable from Nagpur to Saoner town by Nagpur - Chhindwara

National Highway and from Saoner upto Kelod and then diversion towards right

for the proposed Mine Site which is 8 km from Kelod. Nearest railway station is

5.0 Km.

Land Use and land Ownership

As per the administrative records the Land use of the Mine is as given below.

ii) Topography (along with map).

The Khapa-Padriwar Manganese Mine after topographic survey and plotting the

contours, shows the contour from 370 m to 334 m i.e. a high hill relief of 35 to 36 m i.e.

the highest contour is 370 m and lowest contour is 334 m. The hill is running E-W

having steep slopes in E & W side and then sloping down in North-East & South-West

direction

iii) Existing land use pattern (agriculture, non-agriculture, forest, water bodies

(including area under CRZ), shortest distances from the periphery of the project

to periphery of the forest, national park, wild life sanctuary, eco sensitive areas,

water bodies (distance from the HFL of the river), CRZ. In case of notified

industrial area, a copy of the Gazette notification should be given.

A key plan showing landuse and shortest distance from forest and other features

is enclosed as Map 3. A brief summary of the features in 10 Km buffer zone is

tabulated below;

Khasra No. Lease Area Ha.

Ownership/ Occupancy

Khasra No. 40 Forest Department No.

1588(PF) Near village Khapa- Padriwar

7.088 Govt. Forest Land

Page 15: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

v) Existing Infrastructure: This is applied area and at present no infrastructure is

available except the approach road.

vi) Soil classification: Sandy loam soil is prevalent in the area.

vii) Climatic data from secondary sources.

Sub-tropical climatic condition prevails in the area. Maximum temperature

recorded during summer is 480C and the minimum temperature recorded

during winter is 12°C.

viii) The region receives an average rainfall of around 1139 mm with an annual

variation of 100 mm although wider variation have also been noticed in the

past. About 80% - 85% of rainfall precipitates from June to September.

Social Infrastructure available.

Post Office- Sawanga 6 Km.

Nearest Railway Station - 5 Km.

Transport : The transport facilities in the tehsil are well developed and wide spread.

State or national highway link most of the urban areas.

Sr. No. Description Detail

1 Reserves Forest Lease Area with in Protected Forest

Range 2 Nearest National Highway 10 Km

3 Nearest State Highway 5.32 Km

4 Nearest Railway Station Kelwad 5Km

5 Nearest Airport 46 Km 6 Nearest Major city Saoner 10 Km

7 District Head Quarter Chhindwara 62 Km

8 Nearest River / Dam Khekranala Dam 6 Km

9 National Park, Wild Life

Sanctuary, Eco Sensitive areas

None

10 Interstate Boundary Madhya Pradesh-Maharashtra state

Boundary

11 Archaeological monument None

12 Historical and places of worship None

13 Places of tourist attraction None

Page 16: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

5. PLANNING BRIEF

Planning Concept (type of Industries, facilities, transportation etc) Town and

country planning/ Development authority Classification.

The mining will be carried out as per the approved Mining Plan. During Mining Plan

period, the mining operation will be done by development of opencast method. The

statutory provisions for the development of mine shall be followed to ensure safe

mining practices and conservation of mineral. During the course of mining

protection and conservation of natural resources and protection of environment will

be ensured.

Population Projection.

The mine will provide direct employment to nearly 17 workers. The indirect

employment opportunities will automatically created with the click of Manganese

mine in this region.

Land use planning (breakup along with green belt etc.).

The landuse for the mining lease will be strictly followed as per the approved Mining Plan.

Assessment of Infrastructure Demand (physical & social).

The proposed mining will require roads for the transport of the mineral besides it will require manpower to operate the proposed mine.

Amenities/Facilities.

These include community toilets, drinking water facilities like public stand posts.

Page 17: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

6. PROPOSED INFRASTRUCTURE

Industrial area (processing area).

As such no processing is required to get the market grade Mn ore. As the grade has been

identified as medium and marketability is known. However the 20% rejects may have

to be analysed and process as simple washing, jigging, etc. or chemical process if

required will be done.

Residential Area (Non processing Area).

None

Green Belt.

It is proposed to undertake plantation of local tree species within the lease also.

Social Infrastructure.

Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways etc.)is well established

Drinking Water management (Source & Supply of water)

Drinking water for the workers will be met from the ground water

Sewerage System.

None proposed

Industrial Waste Management.

Not required

Solid Waste Management.

None

Power Requirement & Supply / Source: Through state electricity board

Page 18: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

7. REHABILITATION AND RESETTLEMENT (R & R) PLAN

i) Policy to be adopted (central/state) in respect of the project affected person

including home oustees, land oustees and landless laborers (a brief outline

to be given.)

Not envisaged as the project lies on forest land and there is no habitation on the proposed mining lease area.

8. PROJECT SCHEDULE & COST ESTIMATES

The capital budget for environmental protection measure is estimated to be 0.25

Crores. Environment Management Plan is given in Annexure-III.

i) Likely date of start of construction and likely date of completion (Time

schedule for the project to be given.)

The mining operations shall be carried out after obtaining all statutory

permissions and shall be carried out as per approved Mining Plan.

ii) Estimated project cost along with analysis in terms of economic viability of

the project.

The cost analysis in terms of economic viability of the project is presented at

Annexure IV.

Page 19: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report: Khapa Padriwar Manganese Mine

9. ANALYSIS OF PROPOSAL FINAL RECOMMENDATIONS

i) Financial and social benefits with special emphasis on the benefit to the local

people including tribal population, if any, in the area.

In compliance with the environmental procedure the environmental clearance

application is made. Necessary scientific studies will be undertaken as per the

guidelines set by the Ministry of Environment and Forests (MoEF) and prescribed

Terms of Reference. The suggestions/recommendations of all the experts,

competent authorities, and government officials are being sought for the impacts of

the proposed project. Views and guidance of the local residents, community based

organizations, social organizations are extremely important in order to devise a full

proof Environment Management Plan for the proposed mining project and also

mitigate the damages caused due to the project. Allocation of necessary funds,

manpower and machinery will be made to for the protection and conservation of all

the components of environment. It is ensured that all mandatory clearances will be

sought from respective competent authorities before operating the proposed

Manganese Mine.

Page 20: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

Annexure I

KHASRA WISE DETAILS FOR THE PROPOSED MANGANESE MINE

Page 21: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

Annexure II

Mine Boundary Pillar Location Statement ( As Per DGPS)

Khapa Padriwar Mining Lease Area ( 7.088 HA)

Page 22: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

A

Annexure III

ENVIRONMENT MANAGEMENT PLAN

1.1 For Water Environment

There is no water regime near to this mine. The water regime is Kanhan River which is

far away to have any impact. Surface water is in the form of seasonal rain fall. It takes

normal course and flows out of the area along natural slope. No impact on surface or

ground water is expected as no chemical processing is involved.

1.2 For Air Environment

The proposed mining operations are mechanized and shall be done through deployment

of mining machineries. The dust from the haul roads and drilling is expected to pollute

the air to some extent. However, considering the production and nature of proposed

mining operations particulate matter level will not be more than the permissible limit.

However, on the haulage road water will be sprinkled to minimize the raising of dust in

the area.

Further, for minimizing dust generation during drilling & blasting and loading following

measures are proposed:

Wet drilling of blast holes

The drillers will be given protective appliances to be used during drilling

operations.

1.3 For Noise Environment :

Noise Level is likely to increase due to movement of machineries, drilling, etc. The

measures will be taken to maintain the noise levels within limits. Periodical

maintenance of equipment will be carried out. Moreover, the building of green belt that

would be continued along lease boundary, dumping yards, haulage roads will help in

restricting noise level. Noise due to blasting is controlled by using NONEL.

1.4 For reducing ground vibrations :

Ground vibrations caused by blasting will be monitored in order to know their degree

and to build safe guards. The ground vibrations would be mainly at the point of blasting

and further away the vibrations will decrease and becomes imperceptible.

To reduce the ground vibrations multi-row blasting will be adopted and charge per

delay to be kept within limit. Blasting shall be carried out by using NONEL

detonators, which controls air blast and ground vibration effectively.

Page 23: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

B

lasting will be done preferably in the afternoon. This will minimize vibration due

to blasting and check noise pollution. Ground Vibration monitoring will be done

regularly.

1.5 Stabilization of Overburden Dumps :

The stabilizations of dumps will be undertaken by means of terracing of dumps

wherever necessary.

The dumps will be pitched from the slope side to a suitable height. Further,

suitable vegetation / grass shall be planted on the dumps for making it

biologically stable.

1.6 For Socio -Economic Environment

The proposed mining activity is expected to have a positive impact on the socio-

economic profile of the area. The local people shall get opportunities of

employment in the unskilled semi skilled category. The overall standard of living

in the area is expected to improve due to coming Khapa padriwar Manganese

Mining Project.

Page 24: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

Annexure IV

ESTIMATED PROJECT CAPITAL COST & PRODUCTION COST

Project Capital Cost

The total project cost for Khapa Padriwar Manganese Mining Project has been

estimated at Rs. 4.0 crores. The break-up of the total estimated capital cost for

the project is presented in following table:

All figures in Rs. Crores

Sr.

No.

Investment Head Estimated Capital

Investment

1 Land 0.50

2 Buildings & Structures 0.10

3 Additional Exploration 0.50

4 Departmental Plant & Machinery 2.25

5 Office Furniture & Fixtures 0.10

6 Office Vehicles 0.20

7 Quality Control & Environment Protection

Equipment

0.25

8 Consultancy Charges 0.10

Total 4.0

The basis of estimates for different investment heads are presented below:

Land : For obtaining forest clearance by paying all statutory fees. The capital

cost is estimated to be Rs.0.50 Crores

Buildings & Structures : This cost includes cost of office & other service

buildings. The cost is on the basis of standard structures that are likely to be

constructed. The prevailing rates have been taken. The cost estimated under this

head is Rs. 0.10 Crores.

Additional Exploration : Additional drilling and trenching is proposed within

the Mining Lease for further detailing about the geology and reserves with an

estimated cost of Rs. 0.50 Crores.

Departmental Plant & Machinery : This includes opencast consisting of drills/

Page 25: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

excavators along with accessories, etc. Further, certain machineries like DG Sets

etc may be required to be procured by the proponent.

The capital cost for departmental machinery has been estimated at Rs.2.25

Crores.

Office Furniture, Fixtures and Vehicles : The cost of the Furniture & Fixtures,

Vehicles and Office Equipment has been estimated from the available

information. The total capital cost estimated under these heads is Rs. 0.10 Crores

Quality Control & Environment Protection Cost : This includes expenses

towards pollution control due to mining activites. The cost towards this head has

been estimated at Rs. 0.25 Crores.

Consultancy Charges : This includes the fees to be paid to technical consultants

for preparation of Mining Plan, Environmental Impact Assessment /

Environmental Management Plan, Project Report etc. It is estimated that

Company has to incur Rs.0.10 Crores towards payment of Consultancy Charges.

Thus, the basic Project Cost has been estimated as Rs. 4.0 Crores.

Page 26: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

Grant of Mining Lease

Page 27: KHAPA PADRIWAR MANGANESE MINE - Welcome to ...environmentclearance.nic.in/writereaddata/Online/TOR/13...covered with the mica schists (weathered form) the Gondite rock exposed on top

Pre Feasibility Report : Khapa Padriwar Manganese Mine

FOREST NOC