Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager...

28
Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin – Project Research Coordinator Nagi Khanager – Team Development Coordinator Wael Ismaeil – Client Liaison

Transcript of Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager...

Page 1: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Kettle Island Bridge Impact on Montfort

Hospital

IMSR TeamNehad Shukur – Project Manager

Dominique Nsengiyumva – Document Coordinator

Bernard Langevin – Project Research Coordinator

Nagi Khanager – Team Development Coordinator

Wael Ismaeil – Client Liaison

Page 2: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Agenda

IntroductionThe ProjectProject ManagementTeam ManagementClient Management Lessons LearnedConclusions

Page 3: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Interprovincial BridgeNeed of a new interprovincial bridge in the NCR

Page 4: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Roche/NCE StudyNew bridge at Kettle Island

1800 vehicles/day (2031) 40% of commercial vehicles 1/3 of all truck traffic

Page 5: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Montfort Hospital

Montreal Road

Avi

atio

n P

arkw

ay

Page 6: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

I-The Project

Objective Report describing the impacts of

the bridge on the hospital• Increased traffic volume• Noise• Vibration• Pollution

Page 7: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

II-The Project

Scope Analysis of the impacts Stances of neighborhood

stakeholders

Page 8: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

III-The ProjectMethodology

Research on stakeholders Benchmarking Impact on patients (pollution, noise, vibration) Impact on Hospital equipments (vibration) Impact of increased traffic (pollution, noise,

vibration) Impact on employees – Not completed

Page 9: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project ConclusionExpected effects:

Increased traffic will impact patients and ambulance services

Noise will affect patients outside buildings

Page 10: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project Recommendations

Mitigation measures: Noise absorption barriers Vibration in-ground barriers Speed limit …

Page 11: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project Management

Initiation Plan Execute Control Close

Page 12: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project Management

Team ContractProject scope Project charter Project plan Statement of workProgress report Final report

Page 13: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project Risk AssessmentRisk Mitigation Result

Scope change

Only scope change of less than 20% rework will be accepted

Did not happen

Information availability

Obtain information through interview

Met with Judy Lishman

Stakeholder availability

Refer to stakeholder interview from newspaper.

Received information by email

Page 14: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Quality Management

Prevention over inspection Multiple reviews of the deliverable

Continuous improvement Involvement in the delivery process.

Monitoring & Control Development of quality metrics

Page 15: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Project Management

Communication management Wikispaces, emails, telephone,

meeting.

Resource management Organization chart Responsibility assignment

Page 16: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

I-Team ManagementTool / Model Impact

Team evaluation

Team behaviour adjustement

Tuckman Reaching norming and performing stages

MBTI Shared leadership

Learning Style Better communication

Page 17: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

II-Team ManagementTool / Model Impact

Brown More functional and productive team

Six-Box Better team relationships and performance

Team effectiveness

Increased mutual trust

Leadership style

Shared leadership

Page 18: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

III-Team ManagementTool / Model Impact

Team Player Styles

Compensation of challenging styleBetter communication

Page 19: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

I-Client Management

Purpose Coordinate the communication between the

client and the team regarding the scope of the project.

Share information and keep the client up to date about the project.

Manage client expectations about project details and identify additional project requirements.

Develop a positive relationship between the project’s team and the client

Page 20: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

II-Client Management

The client contract Relationship between client and

team Project charter & SOW

Communication with client E-mail, Telephone, and personal

meeting

Page 21: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Client Feedback

“The team appears to have a good comprehension of the technical issues as well as an understanding of the requirements.”

“I am very pleased with the progress”

Page 22: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

III-Client Management

Managing Client expectations Updated the client with the progress of

the work. Formally and personally met with the

client

Problems Encountered Survey

Page 23: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

I-Lessons Learned (Project)

The research contribution of each member

The need for clear project objectives and well defined scope

The impact of the client management

Page 24: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

II-Lessons Learned (Project management)

Project management is a substantial part of the project

Clear understanding of processes and the relationships between them

The components of project management learned from the various courses

Page 25: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

III-Lessons Learned(Team management)

The motivation of the teamThe collaboration of the teamThe TM tools allowed to relate the

team dynamics Lack of social activitiesCulture awareness

Page 26: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

RecommendationWrite personal objectives of each

member in the team contractTeam heterogeneous Time for team building events at

the beginning of the project Team management development

plan

Page 27: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Thank You!

Page 28: Kettle Island Bridge Impact on Montfort Hospital IMSR Team Nehad Shukur – Project Manager Dominique Nsengiyumva – Document Coordinator Bernard Langevin.

Questions?