KETRACO’S PRESENTATION TO WEPEX PRESS CONFRERENCE By MR. RAPHAEL MWORIA On 19TH OCTOBER 2015 –...
-
Upload
job-bishop -
Category
Documents
-
view
216 -
download
2
Transcript of KETRACO’S PRESENTATION TO WEPEX PRESS CONFRERENCE By MR. RAPHAEL MWORIA On 19TH OCTOBER 2015 –...
KETRACO’S PRESENTATION TO WEPEX PRESS CONFRERENCE
By MR. RAPHAEL MWORIA
On19TH OCTOBER 2015 – FAIRMONT NILE- CAIRO
KENYA ELECTRICITY TRANSMISSION CO. LTD.“Building a World Class National Grid”
1. Mandate
2. Electricity Structure in Kenya
3. Perspective
4. Electricity Demand
5. Generation Capacity
6. Generation Potential
7. Clean Energy
8. Regional Power Trade
9. Investment Opportunities2
OVERVIEW
3
KETRACO’s mandate is to design, construct, operate and
maintain new high voltage electricity transmission
infrastructure that formS the backbone of the National
Transmission Grid. These lines include 132kV, 220kV, 400kV and
500kV HVDC.
The Kenya Power and Lighting Company (KPLC) has kept its
current stock of existing 132kV and 220kV transmission lines.
MANDATE
4
Established in 2008
Invested US $2Billion in :-◦ 6 completed projects (746 kms)◦ 26 ongoing projects (3,422 kms)◦ 8 projects awaiting finances (1,324kms)
Asset Base – Kshs. 605,484,000 (US $6,054,840) in 2014
Project financing- Govt of Kenya, World Bank, AfDB, EIB, AFD, Govts of Spain, Belgium, EXIM Bank China, EXIM Bank India, JICA, etc
KETRACO STATUS
5
Inadequate generation capacity due to insufficient investment
Dependence on 37.8% Hydro generation
Inadequate investment in transmission
Low access to power at 30%, less in rural areas
KENYA ELCTRICITY SECTORPESRPECTIVES- CHALLENGES (cont….)
6
Vision 2030- Kenya’s economic development blueprint. Transform Kenya into a newly industrializing, “middle-income country by the year 2030”. Economic Pillar wishes to create a robust, diversified and competitive manufacturing sector. Other pillars Social & Political.
Devolution- 2010 new constitution. Anticipated rise in electricity demand due to oil, mining, production of iron and steel products, irrigation, agro-based industry, operation of petroleum pipelines for both crude and petro-chemical industries, airports, and new economic zones, railway,
5000+MW – 36 months. Capacity will mainly be developed from Geothermal 1,646 MW, Natural Gas 1,050 MW, Wind 630 MW and Coal 1,920 MW, through government power utilities and IPPs under the PPP framework. Aims at lowering cost of electricity.
Last Mile Programme- Aims at increasing electricity access to Kenyan non-commercial households. Three phases from Sep 2015. 314,000 households in phase I 600m from transformers. Phase II & III, to increase by 500,000 households through new transformers and extension of the low voltage network. 2.5 million Kenyans to be connected. Target is 70% by 2017 and universal access by 2020.
PERSPECTIVE (Cont…)
KENYA ELECTRICITY SUB-SECTOR STRUCTURE
7
a. Installed capacity total 2,211 MW
b. The effective interconnected capacity during normal hydrology is 2,147 MW (hydro 821, geothermal 580, thermal 745, co-generation 26, and wind 26)
c. Registered interconnected national peak demand as of May 2015 is 1,520MW
d. The total connected electricity customers currently are approximately 2.3 million.
e. National electrification is approximately 30%.
KENYA’S ELECTRICITY DEMAND
8
9
GENERATION CAPACITY
Small hydro Potential is 3,000MW Geothermal potential is between 5,000MW – 10,000MW.
Geothermal is currently the most promising indigenous resource for development of power.
GENERATION POTENTIAL
10
11
1. GEOTHERMAL ENERGY
At least 7 projects are dedicated to the transmission of geothermal energy in Kenya. These projects will evacuate power from Olkaria, Menengai and Silali geothermal sites.
THE CLEAN ENERGY CORRIDOR
12
Kenya has great potential for the use of solar energy throughout the year because of its strategic location near the equator with 4-6 kWh/m2/day levels of insolation.
The total Solar potential area capable of delivering 6.0 kW/m2 per day in the country is about 106,000 square kilometers whose potential is 638,790 TWh.
SOLAR
13
On average the country has an area of close to 90,000 square kilometers with very excellent wind speeds of 6m/s and above.
The Best wind sites in Kenya are Marsabit , Samburu, parts of Laikipia, Meru north, Nyeri, Nyandarua, Ngong hills, Lamu, off shore Malindi, Loitokitok at the foot of Kilimanjaro and Narok plateau.
WIND
KEY GENERATION SITES & TRANSMISSION LINES
14
Solar Potential Areas
Wind Potential Areas
Geothermal Potential Areas
15
1. KENYA: Geothermal, hydro, wind, coal, natural gas2. TANZANIA: Hydro, natural gas4. UGANDA: Hydro, thermal5. RWANDA: Small hydro6. BURUNDI: Small hydro7. ETHIOPIA: Hydro, Wind8. SUDAN: Hydro, thermal9. EGYPT: Hydro, thermal, natural gas10. DRC: Hydro, thermal
Isolated power systems relying on internal power sources with power shortages – limited integration and power exchange
POWER POTENTIAL IN EASTERN, CENTRAL & NORTHERN AFRICA COUNTRIES
16
Regional Power Institutions:
Nile Basin Initiative (NBI)
Nile Equatorial Lakes Subsidiary Action Program (NELSAP)
Eastern Africa Power Pool (EAPP)
East African Community Power Pool (EACPP)
REGIONAL POWER INTEGRATION
17
Interconnection Projects Feasibility Studies Completed
(i) Kenya (Lessos) - Uganda (Jinja)(ii) Uganda (Mbarara) - Rwanda (Birembo)(iii) Burundi (Kigoma) – Rwanda (Rwegura)(iv) Bujumbura (Burundi) - Kiliba (DRC)(v) Burundi – Rwanda –DRC(vi) Burundi - Rwanda and Tanzania(vii) Ethiopia – Kenya(viii) Kenya -Tanzania(ix) Ethiopia-Sudan-Egypt
POWER INTERCONNECTION PROJECTS
18
AFRICAN POWER POOLS
19
Power GenerationIndependent Power Producers (IPPs) Public Private Partnership (PPP)
Power TransmissionInfrastructure developmentCapacity Building
Project managementOperation and maintenancePower management and trade
Power Distribution & Retail Equipment Manufacturing & Supply
INVESTMENT OPPORTUNITIES
20
Power Generation & Transmission (Packages): developing power plant and transmission line together:
Independent Power Producers (IPPs) Public Private Partnership (PPP)
BOT BOOT
Equipment Manufacturing & Supply
Power Transmission Projects- EPC&F
Capacity Building
INVESTMENT & PARTNERSHIP OPPORTUNITIES
21
PROJECTS WITH COMPLETED FEASIBILITY STUDIES BUT AWAITING FINANCING
Project Name Scope (Engineering Procurement and Construction) Estimated Cost (US$) Kshs
1 Narok-Bomet 88km 132kV DC line and substation extension works ($17 million) 1.7
2 Kabarnet-Rumuruti 111km, 132kV DC line and substation extension works ($19 million) 1.9
3 Suswa - Ngong 40km, 220kV DC line with substation extension works ($21 million) 2.1
4 Meru -Maua Line 50km 132kV Line and 1 Sub-station at Maua ($14 million) 1.4
5 Rumuruti -Maralal Line 148km 132kV Line and Sub-station at Maralal ($21 million) 2.1
6 Rabai- Bamburi-Shanzu-Kilifi line
60km, 132kV DC line with associated substations ($27 million) 2.7
7 Voi - Taveta Line 107km, 132KV DC line, with substation at Taveta. ($26 million) 2.6
6 Garsen -Hola -Garissa Line 240km 220kV SC line and substation at Hola and Bura ($42 million) 4.2
7 Garissa –Habaswen -Wajir Line
330km 220kV SC Line and substation at Wajir and Habaswen
($73million) 7.3
8 Awendo -Isabenia Line 50km 132kV SC Line and substations at Isabenia ($14 million) 1.4
7 Galu - Lunga Lunga Line 60km 132kV SC Line and substations at Lunga Lunga ($16 million) 1.6
8 Ishiara - Chogoria Line 40km 132kV SC Line and substation at Chogoria ($13 million) 1.3
THANK YOU