Kerry Gamble, Syngenta CP, Basel ECPA-ECCA Conference, 12-13 March, Brussels Industry Overview on...
Transcript of Kerry Gamble, Syngenta CP, Basel ECPA-ECCA Conference, 12-13 March, Brussels Industry Overview on...
Kerry Gamble, Syngenta CP, Basel
ECPA-ECCA Conference, 12-13 March, Brussels
Industry Overview on Key Zonal Challenges
Share the Industry hopes for zonal evaluation
Present the feedback from the ECPA survey
Reflect on what has been achieved so far?
Look at the key outstanding issues still to be resolved
Make an ECPA proposal for the way forwards
Conclusions
Overview of the Presentation
Industry Hopes for Zonal Evaluation
Registration of new formulations in 12 (18) months and MR in 120 days!
– Analysis of zRMS timelines for new formulations
– Qualitative feedback on the key issues
– Analysis of timelines for mutual recognition applications
– Qualitative feedback on the key issues
– ECPA model for PR workload prediction for 2015-2018
– Capacity of MSs for zonal submissions
Feedback from the ECPA Survey
12 companies responded
Representing 75% of the EU market
177 submissions were made
58 decisions taken to date
Progress of submissions made under 1107/2009
For submissions made between June 2011 and December 2012
22
79
76
Total of 177 zRMS Dossiers Submittedfor New Formulations
North Central South
Average time reported: 15.2 months – but 119 still pending!
Progress of submissions made under 1107/2009
Overview of time taken to decision
No. of Dossiers0
5
10
15
20
25
30
11
5
26
13
3
< 12 months12 months>12 and ≤ 18 months>18 and < 24 months≥ 24 months
Progress of submissions made under 1107/2009
Decision Time Taken by Zone
North Central South0
5
10
15
20
25
7
20
15
2
6
8
Decision ≤ 18 monthsDecision >18 months
Progress of submissions made under 1107/2009
Decision Time Taken by Submission date
Jun-Dec 2011 Jan-June 2012 July-Dec 20120
5
10
15
20
25
30
35
40
45
50
47
5
12 11
3
10
42
28
22
8
26
47
43
≤12 months≤18 months≤24 months>24 monthsDecidedStill pending
Progress of submissions made under 1107/2009
Qualitative Feedback on Key Issues
Examples of Problems Encountered Comments
Lack of resources Article 75(3)
Lack of capacity for zRMS applications Article 75 (3)
Evaluation on time but delay to official decision Article 37(1)
On-going dialogue to resolve technical questions Article 37(1)
Quality of dRRs Article 37(1)
Complex national processes (multiple Authorities) Article 37(1)
Waiting for confirmatory data (and EU evaluation of it) COM Confirmation
MR submissions made under Regulation 1107/2009
between June 2011 and September 2013
15
187167
Total Mutual Recognition Submissions
NorthCentralSouth
12 companies responded
369 applications
177 decisions taken to date
Average time to decision: 9.6 months but 192 still pending!
MR submissions made under Regulation 1107/2009
between June 2011 and September 2013
No. of Dossiers Decided0
10
20
30
40
50
60
70
80
44
74
49 ≤ 4 months
> 4 - ≤ 12 months
>12
MR submissions made under Regulation 1107/2009
between June 2011 and September 2013
North Central South0
5
10
15
20
25
30
35
40
6
22
16
6
34 34
1
29
19
≤ 4 months
4 ≤ 12 months
< 12 months
Average time to decision by Zone
Mutual recognition submissions Qualitative Feedback on Key Issues
Examples of Problems Encountered Comments
Reference MS in different zone Article 40
Mutual recognition not granted for 91/414 registrations COM Confirmation
Different national requirements Harmonisation
Did not receive registration report Zonal Helpdesk
PR workload for AIR3 AIs (146)
Assume each AI is registered in 9 products in 7 countries
Submissions planned for 3 months after AIR3 AI EIF
Mixture products counted for each active separately
Only submissions from main notifier counted
ECPA Model for PR Workload Prediction 2016-2018
>10,000 PR submissions!
2016 2017 20180
1000
2000
3000
4000
5000
6000
ProductsSubmissions
AT BE CZ DE HU NL PL SI SK DK LT LV CRO ES GR IT MT PT0
5
10
15
20
25
30
35
40
45
50
55
60
65
New Formulations Re-Registrations
MS Capacity 2015
North Zone– North Zone Guidance and established ways of working
– Workshops between Industry and Authority – transparency and collaboration
South Zone– Established ways of working
– Agreed how to manage north zone residue data for applications including FR
– Improvements in resourcing (fees to agencies)
Central Zone– UK CRD harmonisation initiatives
– NL Ctgb Tour of Directors
– CZSC list of agreements
– Increase in resources in some countries
– Review of working practices between MSs (pilots)
Interzonal– dRR Workgroup could improve harmonisation
– Post Approval Issues Group – facilitating ways of working across EU
– Indications of increased willingess to mutually recognise in some countries
What has been Achieved So Far?
– Increase resources to meet the demands of the regulation
– Remove the national requirements (technical and procedural)
– Increase zonal and interzonal co-operation
• Zonal Helpdesks to co-ordinate the work and improve efficiency
– dRR quality
– Reconsideration of Article 43
The Key Outstanding Issues to be Resolved
– Insufficient resources exist to deliver the demands of 1107.....
• Zonal process and timelines
• AI processes
• Comparative assessment
• Product renewal evaluations
– Article 75(3) requires MSs to ensure Authorities have sufficient resources
– Productivity gains would minimise the need for additional resources
– However, productivity gains alone are unlikely to manage the demands of the forthcoming workload from Article 43
Resources
– Lack of harmonisation within and across zones (even within zRMS)
• Technical national requirements including mitigation
• Procedural national requirements
• Adoption of different guidance documents at different timepoints
• Different interpretation of the same guidance
• Use of different endpoints than those established at EU level
– Creates complexity
– Prevents effective work-sharing
– Creates additional work for industry, zRMS and cMSs
– Causes delays
– Harmonisation is needed if zonal evaluation and mutual recognition are going to work
Harmonisation
– Productivity gains will only be achieved through improved zonal and interzonal co-operation
– ECPA recommend a zonal and interzonal helpdesk to:
• Facilitate the work sharing
• Facilitate the ways of working
• Improve harmonisation
• Lead the change
Increased Zonal and Interzonal Co-operation
– Key message to industry is that excellence in dossier quality will support a smooth process and assist Authorities in meeting timelines
– In such a complex and uncertain regulatory environment and with long lead times to dossier production, Industry feel that they are trying to hit a moving target
– Quality needs definition – content, format, structure
– Expectations between MSs and with industry are not always the same – Industry need one agreed understanding of what this means
– Is a working group on dossier quality needed to ensure applicants know what is needed? Is this within the remit of the dRR Workgroup?
dRR Quality
– Current assumptions
• 3 months from AI EIF to PR Submission
• As complete a dossier as possible should be submitted
• Top up possible for data needed and out of applicants control
• Submission after every AI EIF in mixture products
• 6 months evaluation for zRMS and 3 months for cMSs
– Consequences
• Huge workload (10,000 submissions between 2016 and 2018)
• Living dRRs subject to constant change and re-writing
• Unmanageable timelines for Industry and Authorities
– Current COM Guidance on Renewal and Withdrawal does not solve these issues
– An urgent amendment of Article 43 is needed
Article 43
– All these problems are well known
• Re-read the presentations from ECPA Conference in Malta in Nov 12, Informa in Brussels in Apr 13, Ag Chem Forum in Brussels in Sep 13
• All Industry and Authority presentations have lots of ideas and talk about a willingness to make zonal work and yet it’s still not working
• The zonal and mutual recognition timelines in 1107 are not being met
• Delays in zRMSs are causing delays in cMSs
• Zonal has increased the complexity
– ECPA urgently propose
• Leadership and governance from the Commission
• Work with Chairs of ZSCs + iZSC (or PAIG?)
• Involve ECPA & ECCA & IBMA as relevant to find solutions
• Develop strategy, milestone plan and agreed actions with defined timelines
ECPA Proposal for a Way Forwards
Industry Hopes for Zonal Evaluation
Zonal needs to work! ECPA still want to make zonal work!
Industry had high hopes for zonal and mutual recognition
ECPA survey shows that neither are working according to the 1107 timelines and expectations
Some improvements are visible and there seems to be a willingness from Authorities to make it work
A number of key issues still need to be resolved:
– Resources
– Harmonisation of the national requirements
– Interzonal and zonal co-operation (facilitated by Zonal Helpdesks)
– dRR quality
– Article 43
ECPA propose that COM lead the way forwards to develop a strategy, milestone and action plan
Conclusions