kenya TRANSMISSION oview.docx
-
Upload
krishna-kiran-kanniganti -
Category
Documents
-
view
218 -
download
0
Transcript of kenya TRANSMISSION oview.docx
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 1/7
The electrification ratio in Kenya is low with only 22% of the population
having access to electricity and a per capita consumption of 130 kWh
against 550 kWh on average for SubSaharan Africa. Outside the main
centres, access to electricity is much lower, 7-8%, with low reliability in
some areas. There is also an additional challenge of reinforcing the powersupply to already electrified areas/towns/regions aiming at least-cost
technical solutions that offer a combination of increased capacity, improved
reliability and better voltage control. The Government of Kenya (GoK) has
translated its vision for the sector into the Energy Access Scale-Up Program
under which the country will make investments in transmission
infrastructure to the tune of USD 1,096 million by 2014.
The GoK has translated its vision for the sector into the Energy Access
Scale-Up Program, with a target of 40% access by 2020; with anintermediate target to electrify one million new customers and extend
electricity service to all priority loads in rural areas in the next five
years.The major challenge has been increasing the access rates outside the
main centres to increase the share of rural population with access to
electricity as well as reinforcing the power supply to already electrified
areas/towns/regions aiming at least-cost technical solutions that offer a
combination of increased capacity, improved reliability through a reduction
in the current high energy lossescaused by the overloading of the systemand better voltage control, i.e. an adequate supply quality as the consumer's
dependency of electricity increases.
The Government intends to develop a larger power grid that will enable
connection to many green power sources to major load centres. This project
will result in increased and reliable power supply to the affected regions
and also provide a platform for regional integration of the power systems
and regional power trade facilitated by the construction of the Kenya-
Ethiopia interconnection and the ongoing interconnection project of theNile Equatorial Lakes Countries.
GoK has decided that all new transmission infrastructure facilities will be
financed and owned by the State in order to catalyse the development of the
country ‟s generation and distribution infrastructure. In support of the
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 2/7
Electricity Access Scale-Up Project, the GOK prepared a prospectus, the
Kenya Electricity Access Investment Program Prospectus: 2009-2014which
estimates that USD 4,902 million of investments will be required in new
generation, transmission and distribution assets to meet the objectives of
the program. Of this amount, KETRACO will need to make capitalinvestments to the tune of USD 1,096 million. I
Private Sector Participation: Key sector reforms introduced by the
Government including the unbundling of KPLC in the 1990‟s,
establishment of the Energy Regulatory Commission, development of Feed
in Tariffs Policy and the creation of the Geothermal Development Company
have been instrumental in the increased participation of the private sector.
IPPs are expected to play a more important role in the future as additional
capacity of 2,130-2,430 MW is planned for development by 2015. The
presence of IPPs in the generation sub-sector encourages competition
among market participants and as such, contributes to the availability of
more reliable and cheaper power to the Kenyan economy.
Tariffs: The electricity price for KenGen is determined through Long-
term Power Purchase Agreements that were entered into with KPLC and
approved by the ERC in June 2009. The KenGen remuneration is made up
of the capital recovery charge, fixed operation and maintance charge and
the variable operation and maintenance charge. Retail base tariffs for KPLC
were increased in July 2008 after remaining unchanged since 2000.
Tariffs are adjusted automatically for monthly changes in generation
related fuel costs and exchange rate depreciation and every six months for
inflation. The domestic tariff category is divided into four consumption
blocks with increasing energy charges. The first block of up to 50 kWh per
month is the Lifeline Tariff, which is cross-subsidised by other tariff
categories in order to ensure affordability to the poorer users. As of the end
of 2009, the average tariff was about USc 11/kWh. The key motivationunderlying the creation of KETRACO was to allow the development of the
country ‟s transmission infrastructure without passing on the investment
costs to consumers through increased tariffs. As such, tariffs are expected
to remain at affordable levels to encourage new connections in the future.
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 3/7
http://www.afdb.org/fileadmin/uploads/afdb/Documents/Project-and-
Operations/KENYA%20-
Power%20Transmission%20System%20Improvement%20Project.pdf
A recent listing of plans by DFAIT (Canada’s Department of Foreign Affairs
and International Trade) says that in the next four years, Kenya is expected
to construct over 4,000 km of high voltage transmission infrastructure at
an estimated cost of US$ 1.3 billion.
http://magazine.appro.org/index.php?option=com_content&task=view&id
=1379&Itemid=44
Kenya Power reports transmission and distribution losses of 18 per cent,
almost double the best-practice benchmark of 10 per cent. As a result,
Kenya Power's operational inefficiencies make the country lose a staggering
0.3 per cent of GDP. AICD projects that the country needs to spend $1
billion annually to keep up with demand and achieve national
electrification targets, but at present only $471 million a year goes to the
power sector.
http://allafrica.com/stories/201108010016.html?page=2
Kenya Power announced plans to invest nearly $1 billion in its grid network
over the next decade to cut inefficiencies and reduce costs, its chief executive said on Friday. Kenya Power is the sole transmission and
distribution utility in east Africa's largest economy, where blackouts
happen frequently due to generation shortfalls and an ageing grid.
The investments will mainly be put into transmission lines and automation
of systems, Njororge said."We want to do it differently. In urban areas we
want to use underground cables and in rural areas we are going to use
insulated cables," he told Reuters.
http://africa.ibtimes.com/articles/169236/20110624/kenya-power-to-
spend-1-bln-on-grid-over-the-coming-years.htm
‰Planned Reggional Interconnection projects e.gg.Connection to Southern
Africa Power Pool, Ethiopia and2ndUganda line
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 4/7
Some of the major committed transmission projects in the next few years
include :
Transmission Line LengthCommissioning
date/costMombasa – Nairobi400kV double circuit
450 km 2012/135 million $
Kenya (Lessos) – Uganda (Tororo)220kV double circuit
250 2013/90 million $
Rabai – Malindi –
Garsen – Lamu220kV single circuit
320 2012/33.9 million $
Kindaruma ‐ Mwingi ‐ Garissa
250 2013/40 million $
Olkaria – Lessos ‐ Kisumu
300 2014/60 million $
Mwingi – Kitui – Wote– Sultan 153 202013Hamud
153 2013/20 million $
Lessos – Kabarnet andNanyuki 1‐ Nyahurur
144 2013/26 million $
Ethiopia (WolaytaSodo) –Kenya(Suswa) 500 kV HVDClineInterconnectoR
1200 2014
Reactive compensation
Phase 2 – Rest of Kenya Transmissionand Nairobi Sub-transmission System
2012
Kenya (Isinya) – Tanzania(Singinda) 400 KV
500 2015
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 5/7
InterconnectoR http://www.kplc.co.ke/fileadmin/user_upload/Documents/04-
2011/Media/Presentation_to_Stakeholders_Conference_on_KPLC_5_Yea
r_Corporate_Strategic_Plan_13-4-2011__2_.pdf
http://www.nation.co.ke/business/news/Kenya+woos+investors+in+the+energy... Nairobi: The government has stepped up its efforts to attract privateinvestors in the energy sector through funding from the World Bank.Consequently, it has invited expression of interest for consultancy servicesto facilitate the sector’s input. “The objective of this investment is to assistMinistry of Energy prepare a private investment prospectus and relevant
presentation materials and to assist in organising conference in Kenya anda road show outside Kenya in order to attract private investment in thesector,” said an advert by the ministry in the Daily Nation on Tuesday.
The government said demand for electricity was set to soar as projectsenvisaged in the Vision 2030 gather steam. In tandem with Kenya’s Vision2030, the advert said, demand for power is expected to rise from 1200MW currently to more than 15000MW by 2030. To sustain an overall economicgrowth rate of 10 per cent per annum from 2015, more investment isrequired.
“This has raised supply concerns as the country has limited powergeneration and transmission capacity, a situation that has been exacerbated
by lack of adequate investment in power systems infrastructuredevelopment,” it said.
The government said to meet the projected power demand andconnectivity, an investment of $10 billion in generation resources and $2
billion in transmission system was required. These projects are expected to
tap power from wind geothermal, biomass, and small hydro, coal, oil-firedand nuclear plants.
The government said it is unlikely that it will be able to mobilise therequired capital without the private sector funding part of it. It said it willcontinue to undertake reforms aimed at attracting private sectorinvestment, among them feed-in-tariffs policy for renewable energy.
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 6/7
Transmission System Development Plan of Least cost PowerDevelopment Plan(LCPDP)The transmission system development plan indicates the need to developapproximately 8316km of new lines of above 132kV, with the most of thisrequirement being covered by 400kV linesapproximated at 3715km. 220kV lines approximated to cover 2824km
while 132 kV lines will cover the remaining 1777km. The total arithmeticcost of the transmission system plan for the period 2010-2028 isapproximated to be $2.6 Billion.
The LCPDP uptil 2028 has plans develop 8316km transmission lines at acost of 2589.4 million US$
http://www.erc.go.ke/erc/LCPDP.pdf
The challenges facing the power sub-sector include:
1. A weak power transmission and distribution infrastructure, 2. High cost of power, 3. Low per capita power consumption and low countrywide electricity
access.
KETRACO will construct over 4,000 km. of high voltage transmissioninfrastructure comprising of lines, switch gears and sub-stations across thecountry over the next 3-4 years, at an estimated cost of US $ 1,300 Million.This will open up geographical areas without access to the national grid,enhance capacity for evacuating power from planned generating plants and
build inter-connectors to facilitate regional power trade with neighbouringcountries.These transmission lines and associated sub-stations will be financed by the
exchequer, development partners, internally-generated revenue, financialinstitutions and public-private partnerships (PPPs). Management of resources will be guided by operational rationalization and modernizationof key processes, while cost saving measures will be deployed to strengthenthe Company’s financial resource base.
7/28/2019 kenya TRANSMISSION oview.docx
http://slidepdf.com/reader/full/kenya-transmission-oviewdocx 7/7
The transmission line projects will include:
1. 1500 kilometers of 132kV lines;2. 700 kilometers of 220kV lines;3. 1,000 km 400kV lines; and4. 700 kilometers of 500kV lines.
http://www.ketraco.co.ke/projects/planned/