LUCOEXLarge Underground Concept EXperiments
2011 – 2014
Work Package 5 KBS-3V Emplacement tests in ONKALO
Progress and Plans Project Progress Meeting
13st May 2014
Keijo Haapala
![Page 2: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/2.jpg)
WP5 SITUATION
• The content of WP5
• LOT1: Development of bentonite
buffer and pellet installation.
• LOT2: Quality of installation
• LOT3: Problem handling tools
13th May 2014 2Haapala Keijo
![Page 3: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/3.jpg)
WP5 SITUATION
33
• Two machines has
developed
• Installation machine
(BIM) for buffer block
emplacement
• Buffer transfer device
(BTD) for transferring
of buffer blocks from
service tunnel for BIM.13th May 2014 Haapala Keijo
![Page 4: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/4.jpg)
BIM AND TRANSPORTATION CONTAINER
4423th September 2013
![Page 5: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/5.jpg)
BIM
5523th September 2013
![Page 6: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/6.jpg)
BTD
23th September 2013 6
![Page 7: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/7.jpg)
BUFFER INSTALLATION SEQUENCE
4. Block and pellet installation
1. Positioning2. Block taken from container
3. Crane over dep. hole
6. Empty gripper to the shelf
7. Shelf forwards and crane over container
5. Transfer device positioning
8. Block taken from container
13th May 2014 7Haapala Keijo
![Page 8: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/8.jpg)
LOT1, Installation of bentonite buffer and pellets
• BIM was ready for shipment from the
manufacturer in October last autum.
• Test plan of Demonstration Phase 1 has
prepared.
• Writing of Operating and Service Manual for machines.
• Test hall in Onkalo area was ready in the end
of March.
• Final programming and preparations of the
machine for the test started in Aprill.
13th May 2014 8Haapala Keijo
![Page 9: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/9.jpg)
LOT1, Installation of bentonite buffer and pellet
• Things to note:
• Laser tracker changed, Leica -> API Control
-> some extra work.
• Automation and electric has caused extra work
• Co-operation between different components
• Wiring faults -> broken components.
13th May 2014 9Haapala Keijo
![Page 10: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/10.jpg)
LOT1, Installation of bentonite buffer and pellet
• Things to note:
• Work safety is a bit harder than expected
• Limited access to test hall, only persons who
have a task in the project.
13th May 2014 10Haapala Keijo
![Page 11: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/11.jpg)
LOT2: Quality of installation
• Work has done at the same time with LOT1,
mainly programming
• Main part of the work will take place when
the buffer installation demonstrations start.
13th May 2014 11Haapala Keijo
![Page 12: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/12.jpg)
LOT3: Problem handling tools.
• What is needed if the bentonite block falls to
the deposition hole during installation?
• Demonstrations after LOT 1 and 2.
• Work has divided in two situations:
• Before canister installation.
• After canister installation.
13th May 2014 12Haapala Keijo
![Page 13: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/13.jpg)
DEMONSTRATIONS
• Demo Phase 1: Testing in test hall in
Onkalo site.
• Demo Phase 2: Testing in Onkalo demonstration
tunnel with concrete blocks.
• Demo Phase 3: Testing in Onkalo demonstration
tunnel with bentonite blocks.
13th May 2014 13Haapala Keijo
![Page 14: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/14.jpg)
DEMO PHASE 1 IN TEST HALL
• Purpose to finalize the installation
machine.
• Detailed test for different functions
• Adjusting the speed of functions in the
machine
• Perform the installation test with full
size concrete blocks
• To find out what is critical13th May 2014 14Haapala Keijo
![Page 15: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/15.jpg)
DEMO PHASE 1 IN TEST HALL
• Most important part of demonstration
• Estimated testing time 3 months: April -
June, if everything goes well.
13th May 2014 15Haapala Keijo
![Page 16: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/16.jpg)
TEST HALL
13th May 2014 16Haapala Keijo
![Page 17: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/17.jpg)
BIM IN TEST HALL
13th May 2014 17Haapala Keijo
![Page 18: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/18.jpg)
BIM IN TEST HALL
13th May 2014 18Haapala Keijo
![Page 19: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/19.jpg)
CONCRETE BLOCKS WITH CONTAINER TOPS
13th May 2014 19Haapala Keijo
![Page 20: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/20.jpg)
DISPOSAL HOLE IN TEST HALL
13th May 2014 20Haapala Keijo
![Page 21: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/21.jpg)
DEMO PHASE 2: TESTING IN ONKALO WITH CONCRETE BLOCKS
• Targets:
• To test the installation in Onkalo
conditions
• Installing of whole buffer within two hours
13th May 2014 21Haapala Keijo
![Page 22: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/22.jpg)
DEMO PHASE 3: TESTING IN ONKALO WITH BENTONITE BLOCKS
• What kind of effect the bentonite gives to installation
process?
• What is the effect of moist conditions in Onkalo
• How safe is the process?
13th May 2014 22Haapala Keijo
![Page 23: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/23.jpg)
DEMO PHASE 3: TESTING IN ONKALO WITH BENTONITE BLOCKS
• Possibly isostatically pressed bentonite blocks are not
available.
• Alternative buffer: Mixture of uniaxially pressed
benonite and concrete blocks.
• The handling of concrete blocks with vacuum lifter
is more risky than bentonite blocks
13th May 2014 23Haapala Keijo
![Page 24: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/24.jpg)
DEMO PHASE 3: TESTING IN ONKALO WITH BENTONITE BLOCKS
• Alternative buffer: Mixture of uniaxially pressed
benonite and concrete blocks.
• Bentonite blocks in critical positions:
• Bottom and top
• First and last ring
• First on the canister
13th May 2014 24Haapala Keijo
![Page 25: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/25.jpg)
WORK SAFETY OF BIM AND BTD
• During the demonstrations, access to the test
place is limited.
• Demo Phase 1 in the test hall.
• When demonstration is going on, only operators
and reponsible persons can be in the test hall!
• Special arrangements for visitors; the access is
denied, follow up of demonstrations via cameras.
13th May 2014 25Haapala Keijo
![Page 26: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/26.jpg)
WORK SAFETY OF BIM AND BTD
• Demo Phase 2 and 3
• Steering of installation will be performed
by cameras with wireless method outside
of disposal tunnel
• During the installation the access to
disposal tunnel is denied
13th May 2014 26Haapala Keijo
![Page 27: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/27.jpg)
WORK SAFETY OF BIM AND BTD
• Before the start of demonstrations, is
needed:
• Detailed test plan.
• Safety estimation of tests.
• Training of employers for working in
Onkalo area and in demonstrations.
• Operating manual of machines.
13th May 2014 27Haapala Keijo
![Page 28: Keijo Haapala](https://reader033.fdocuments.us/reader033/viewer/2022051517/56815409550346895dc2050c/html5/thumbnails/28.jpg)
13th May 2014 28Haapala Keijo