Katris architects pty ltd · 2020. 9. 22. · Katris architects pty ltd CLIENT SECTION 4.55...

7
Katris architects pty ltd CLIENT SECTION 4.55 APPLICATION Date: [email protected] P 02 9744 5421 www.katris.com.a level 1, 3-5 burwood road, concord 2137 nsw po box 703 burwood 1805 nsw FOR: Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569) MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD) Proposed relocation and construction of new Joe and Sons (Builders Hardware and Landscaping Supply Centre) at 33 - 35 Queens road, Five Dock to 177 Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 and Lot 2 DP 210783. 04.09.2020 ISSUE M SHEET DRAWING TITLE ISSUE M000 TITLE M M101 GROUND FLOOR PLAN M M103 MEZZANINE M M105 ROOF PLAN M M106 NORTH AND SOUTH ELEVATIONS M M107 WEST AND EAST ELEVATIONS M M108 SECTION M 1:200 @ A3 IMPORTANT NOTE THESE DRAWINGS HAVE BEEN ISSUED FOR DEVELOPMENT APPLICATION PURPOSES ONLY. THEY ARE NOT ISSUED FOR CONSTRUCTION OR CONSTRUCTION CERTIFICATE OR FOR THE PURPOSES OF PRICING BY ANY CONTRACTOR ARCHITECTURAL DRAWING SCHEDULE CLOUDS INDICATE AMENDMENTS

Transcript of Katris architects pty ltd · 2020. 9. 22. · Katris architects pty ltd CLIENT SECTION 4.55...

  • Katris architects pty ltd

    CLIENT

    SECTION 4.55 APPLICATION

    Date:

    [email protected]

    P 02 9744 5421

    www.katris.com.a

    level 1, 3-5 burwood road, concord 2137 nsw po box 703 burwood 1805 nsw

    FOR:

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTYSERVICES PTY LTD)

    Proposed relocation and construction of new Joe andSons (Builders Hardware and Landscaping SupplyCentre) at 33-35 Queens road, Five Dock to 177

    Parramatta road, Homebush West (cnr of Bedford road)Lot 5 DP 596728 and Lot 2 DP 210783.

    04.09.2020

    ISSUE M

    SHEET DRAWING TITLE ISSUE

    M000 TITLE MM101 GROUND FLOOR PLAN MM103 MEZZANINE MM105 ROOF PLAN MM106 NORTH AND SOUTH ELEVATIONS MM107 WEST AND EAST ELEVATIONS MM108 SECTION M

    1:200 @ A3IMPORTANT NOTETHESE DRAWINGS HAVE BEEN ISSUED FORDEVELOPMENT APPLICATION PURPOSESONLY. THEY ARE NOT ISSUED FORCONSTRUCTION OR CONSTRUCTIONCERTIFICATE OR FOR THE PURPOSES OFPRICING BY ANY CONTRACTOR

    ARCHITECTURAL DRAWING SCHEDULE

    CLOUDS INDICATE AMENDMENTS

  • REF.UP

    5D P 5 9 6 7 2 8

    2312.3m2

    EXISTING CONCRETE DRIVEWAY

    NO. 177

    3.89

    N E W D R I V E W A Y

    P R O P O S E D N E W D R I V E W A Y

    BULKY GOODS RETAIL SALES

    W A R E H O U S E S T O R A G E

    GENERAL COUNTERSERVERY AREA AS SELECTED

    BY PROPRIETOR

    OFFICE 2

    OFFICE 1

    C E M E N T S H E D & W A R E H O U S E S T O R A G E

    STAFF ROOM

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.9.

    LIN

    E O

    F M

    EZZA

    NIN

    E LE

    VEL

    ABO

    VE

    S A N D S T O R A G E A R E A

    OVERNIGHT TRUCK PARKING AND INCIDENTAL TRUCK PARKING DURING THE DAY

    SLIDING GATE

    C A R P A R K I N G A R E A

    1. 2. 3.4. 5. 6. 7. 8. 9. 10. 11.

    MALE WC

    FEMALE WC

    DIS WC

    ACTUAL BOUNDARY OF SITE

    DISABLED PERSONS CAR

    SPACE

    DISABLED PERSONS CAR

    SPACE

    SHARED ZONE

    MEZZANINE ABOVE SHOWN DOTTED

    PROPOSED LANDSCAPED AREA

    11.

    2000

    12.

    P R O P O S E D N E W D R I V E W A Y

    N E W D R I V E W A Y

    BEDFORD ROAD

    PAR

    RAM

    ATTA

    RO

    AD

    18380

    16290

    A

    M108

    A

    M108

    SLIDING GATE

    OFFICE AREA = 25.7m²

    13.

    14.

    10.LINE OF ROOF OVER

    RAM

    P U

    P @

    1:2

    0

    FFL RL 5.00

    FFL RL 5.00

    FFL RL 4.90

    FFL RL 4.90

    CREST RL 4.8 AS PER ENGS

    DETAILS

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    PROPOSEDFCGL RL 4.9

    PROPOSEDFCGL RL 4.7

    PROPOSED FENCEPR

    OPO

    SED

    FEN

    CE

    PROPOSED FENCE

    PROPOSED FENCE

    FFL RL 4.90

    PROPOSEDFCGL RL 4.90

    BIN

    BIN

    SHAD

    E T

    REE

    S TO

    CO

    MPL

    Y W

    ITH

    PA

    RT

    D 2

    .10

    (13-

    14) S

    CD

    CP

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP

    + 5.30 + 5

    .30 + 5.30 + 5

    .30 + 5.

    30

    + 5.30 + 5

    .30

    + 5.30

    + 5.30

    + 5.30

    + 5.30

    + 5.30

    1:20 ramp up

    RL 4.0

    RL 4.76

    RL 4.90

    RL 4.9

    + 4.9

    + 4.75

    RAMP

    UP @

    1:40

    + RL 4.90

    + RL 4.90

    NEW ALUMINIUM FRAMED WINDOW(S) AS SEL. BY THE PROPRIETORSAND TO CONFORM WITH THE BASIXCERTIFICATE

    NEW ALUMINIUM FRAMED WINDOW(S) AS SEL. BY THE PROPRIETORS

    AND TO CONFORM WITH THE BASIXCERTIFICATE

    PROVIDE ROLLER DOOR TO MANUFACTURERS REQUIREMENTS.

    2

    2

    3

    3

    4

    4

    5

    5

    6

    6

    7

    7

    8

    8

    9

    9

    1

    1

    A

    B

    C

    D

    fwfw

    fw

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    AS2890.6 CLEAR SPACE 2400W X 5400L X 2500H

    WT2

    B

    WT2

    WHEEL STOPS (WS) TO AS 2890.1

    CAR

    SPAC

    E 8

    2500

    CAR

    SPAC

    E 7

    2500

    CAR

    SPAC

    E 6

    2500

    CAR

    SPAC

    E 5

    2500

    2500

    CAR

    SPAC

    E 4

    2500

    CAR

    SPAC

    E 3

    2500

    CAR

    SPAC

    E 2

    2500

    CAR

    SPAC

    E 1

    2500

    S

    S

    S

    AS2890.6 CLEAR SPACE 2400W X 5400L X 2500H

    AS2890.6 CLEAR SPACE 2400W X 5400L X 2500H

    200mm CONCRETE BLOCK WALL TO ENGINEERS DETAILS. CONTRACTOR MUST ENSURE THIS WALL HAS A FIRE RATING OF 90/90/90

    2400WTYPE 1 DOOR

    2400

    HC

    HC HC

    HC

    HC

    HC

    HWU

    BOLLARDS AS PER D1.10 OF NCC

    BOLLARDS AS PER D1.10 OF NCC

    FIRE HOSE REEL & HYDRANT AS PER HYDRAULIC ENGS

    DETAILS

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    FLAT TOP WITH CRANE SPACE

    SMALL TIPPER 1

    SMALL TIPPER 2

    SMALL TIPPER 3

    HINO TIPPER

    RIGID TRUCK BOGIE SPACE

    FLAT TOP WITH CRANE SPACE

    C A R P A R K I N G A R E A

    15.

    16.

    6000

    6000

    4000

    2600

    2600

    2600

    2600

    2600

    2710

    2500

    2800

    1256

    5

    PROPOSED WALL & GARAGE ROLLER DOOR

    + RL 4.68

    + 4.75 + 4.90+ 5.13 + 5.05

    + 4.80 - AS PER ENGS DETAILS

    18.

    17.

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    WS

    820

    WS

    820

    WS 820

    WS 820

    WS

    WS

    WS

    WS

    WS

    WS

    B

    M108

    B

    M108

    A TOTAL OF EIGHTEEN (18) OFF- STREET PARKING SPACES AND SEVEN (7) LOADING BAYS, HARDPAVED, LINEMARKED, LABELLED AND DRAINED, SHALL BE PROVIDED IN ACCORDANCE WITH THE APPROVED PLANS AS PER CONDITION NO.14

    BOLLARD

    DA CONDITION 43A(b) TO BE DELETED AND TWO (2) CANOPY TREES NOT TO BE PLANTED.

    REFER TO STATEMENT OF ENVIRONMENTAL EFFECTS AND ARBORIST STATEMENT

    PREPARED BY TALC DATED 27 AUG 2020.

    2700

    BOARD SEWER AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    DP AS PER ENGINEERS DETAILS

    DP AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    FRL

    90/9

    0/90

    FRL

    90/9

    0/90

    1168

    5

    5400 6300

    2500

    2500

    5500

    5700

    6000

    8000

    10500

    5400

    64006100

    61006400

    12

    12

    11

    11

    10

    10

    FWFW

    FW FW FW FW FW FW FW FW FW

    ABOVE GROUND OSD BASIN

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    PITS TO ENGS DETAILS

    GRATED DRAIN TO ENGS DETAILS

    GRATED DRAIN TO ENGS DETAILS

    GRATED DRAIN TO ENGS DETAILS

    FWFW

    STORMWATER FILTER CHAMBER TO ENGS DETAILS

    2.4M CEILING HEIGHT UNDER MEZZANINE

    BOX GUTTER OVER BOX GUTTER OVERBOX GUTTER OVER

    DPDPDPDPDP

    DPDP

    DP DP

    DP

    DP

    3.79

    3.77

    3.703.74

    EXIST RL

    EXIST RLEXIST RL

    4.63EXIST RL

    EXIST RL4.60

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    CREST RL 4.8 AS PER ENGS

    DETAILS

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    ALL PITS SHALL BE CONSTRUCTED IN ACCORDANCE WITH AUSTRALIAN STANDARD AS3500.3 AS PER ENGS DETAILS

    RAM

    P U

    P 1:

    20

    3000

    5010

    0050

    COLUMN.

    COLUMN. COLUMN. COLUMN. COLUMN.

    COLUMN.

    COLUMN. COLUMN. COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN. COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN.

    COLUMN. COLUMN.

    COLUMN.

    COLUMN.

    COLUMN. COLUMN. COLUMN.

    LINE OF ROOF OVER

    COLUMN.

    COLUMN. COLUMN. COLUMN. COLUMN. COLUMN. COLUMN. COLUMN. COLUMN.

    COLUMN.

    COLUMN.

    COLUMN. COLUMN.

    COLUMN. COLUMN. COLUMN. COLUMN. COLUMN.

    COLUMN. COLUMN.

    COLUMN. COLUMN.

    COLUMN.

    1000

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020GROUND FLOOR PLAN M101 M

    CK M

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER

    JN 27.3.17 K ISSUE FOR CC

    HC = DENOTES HOSECOCKS. REFER TO ARCH SPECHWU = DENOTES HOT WATER UNIT. REFER TO ARCH SPEC.

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION CK

    1 : 100GROUND FLOOR WITH NOTES

    1

  • 4.60LP

    STORMWATER CHANNEL / CULVERT

    3.74

    3.273.27

    GRASS

    RIDGE

    ROOF

    ROOF R

    ROOF

    ROOF

    4.68

    2.36

    2.352.30

    2.34

    2.33

    3.413.47

    3.52

    3.593.66

    3.78

    3.413.47

    3.52

    3.593.66

    3.78

    4.60

    4.63

    4.60

    UPA

    M108

    A

    M108

    2 3 4 5 6 7 8 91

    A

    B

    C

    D

    MEZZANINE LEVEL -WAREHOUSE STORAGE

    COVERED LOADING AREA FOR SMALL RIGID DELIVERY TRUCKS (BELOW)

    ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    5D P 5 9 6 7 2 8

    2312.3m2

    EXIS

    TIN

    G C

    ON

    CR

    ETE

    DR

    IVEW

    AY T

    O B

    E R

    EDU

    CED

    TOP

    OF

    0.15

    m K

    ERB

    & G

    UTT

    ER

    CO

    NC

    RET

    E PA

    THC

    ON

    CR

    ETE

    PATH

    EXISTING CONCRETE DRIVEWAY TO BE REDUCED

    EXISTING CONCRETE DRIVEWAY EXISTING CONCRETE

    DRIVEWAY TO BE REDUCED

    0.23

    w R

    END

    . BR

    ICK

    WAL

    L

    0.23w BRICK WALL0.23w BRICK RETAINING W

    ALL

    0.23w BRICK RETAINING WALL0.23w BRICK RETAINING WALL

    0.23w BRICK RETAINING WALL

    NO. 177

    GRASS

    3.89

    P R O P O S E D N E W D R I V E W A Y

    P R O P O S E D N E W D R I V E W A Y

    C E M E N T S H E D & W A R E H O U S E S T O R A G E

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8. 9.

    OVERNIGHT TRUCK PARKING AND INCIDENTAL TRUCK PARKING DURING THE DAY

    SLIDING GATE. AS SEL. BY PROP. AND AS PER ARCH. SPEC

    C A R P A R K I N G A R E A

    ACTUAL BOUNDARY OF SITE

    11.

    12.

    BEDFORD ROADPA

    RR

    AMAT

    TA R

    OAD

    SLIDING GATE

    13.

    14.

    10.

    EXIST RL

    EXIST RL

    EXIST RL

    EXIST RL

    EXIST RL EXIST RL

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    PROPOSEDFCGL RL 4.77

    EXIST RL

    DR

    AING

    E G

    RAT

    E TO

    ST

    OR

    MW

    ATER

    ENG

    INEE

    RS

    SPEC

    IFIC

    ATIO

    NS

    PRO

    POSE

    D F

    ENC

    EPR

    OPO

    SED

    FEN

    CE

    PROPOSED FENCE PROPOSED FENCE

    FFL RL 4.77

    SHADE TREES TO COMPLY WITH PART D 2.10 (13-14) SCDCP

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP PROVIDE ALUMINIUM FRAMED 'BREEZEWAY'

    MANUAL LOUVRES AS SPECIFIED BY MANUFACTURER AND IN ACCORDANCE WITH THE

    ARCHITECTURAL SPECIFICATION

    ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    STEEL FRAMED STAIRS TO ENGINEERS DETAILS

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES

    S

    DASHED LINE INDICATES SAND STORAGE BELOW

    FALL

    4.2

    5°FA

    LL 4

    .25°

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WSWHEEL STOPS (WS) TO AS 2890.1

    PROVIDE METAL 'KLIP-LOK' ROOF SHEETING.REFER TO ARCH. SPEC

    DOTTED LINE INDICATES BLOCKWORK BELOW

    DOTTED LINE INDICATES BLOCKWORK BELOW

    THESE STOCKPILES ARE TO BE COVERED USING TARPAULIN AND WEIGHTS ( TO HOLD THE TARPAULIN IN PLACE) WHEN ACCESS IS NOT REQUIRED AS PER COND.

    93. WHEN THE STOCKPILES ARE EXPOSED, THE PERMANENTLY INSTALLED IRRIGATION SYSTEM SHALL BE

    UTILISED.

    SOLAR VOLTAIC COLLECTOR

    SOLAR VOLTAIC COLLECTOR

    STRIPS OF TRANSLUCENT ROOF SHEETING

    STRIPS OF TRANSLUCENT ROOF SHEETING

    PROPOSED GARAGE ROLLER DOOR

    B

    M108

    B

    M108

    WS

    N E W D R I V E W A Y

    + RL 4.68

    + 4.75 + 4.90+ 5.13 + 5.05

    + 4.80 - AS PER ENGS DETAILS

    GALVANISED METAL BOX GUTTER 800MM WIDE x 200MM DEEP AS PER STORMWATER ENGINEERS

    DETAILS REFER TO ARCHITECTURAL SPECS

    GALVANISED METAL BOX GUTTER 800MM WIDE x 200MM DEEP AS PER STORMWATER ENGINEERS

    DETAILS REFER TO ARCHITECTURAL SPECS

    FRL

    90/9

    0/90

    FRL

    90/9

    0/90

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    DP AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    DP AS PER ENGINEERS DETAILS DP AS PER ENGINEERS

    DETAILS

    FFL RL 8.06

    121110

    DP AS PER ENGINEERS DETAILS

    C1

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    DP TO ENGINEERS DETAILS

    1256

    5

    ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    RWH AS PER ENGINEERS DETAILS

    1000

    LOWER METAL ROOF

    2 CANOPY TREES TO BE REMOVED

    HC

    HC

    HC

    COLUMN.

    COLUMN.

    COLUMN. COLUMN. COLUMN.

    COLUMN. COLUMN.

    COLUMN. COLUMN.

    LINE OF ROOF OVER

    BOX GUTTER OVER BOX GUTTER OVERBOX GUTTER OVERDP

    W A R E H O U S E S T O R A G E B E L O W

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020MEZZANINE M103 M

    MF M

    1 : 100MEZZANINE LEVEL

    1

    STAIR NOTER.C STAIRS MUST CONFORM WITH BUILDING CODE OF AUSTRALIA AND AS PER THE ARCHITECTURAL SPECIFICATION

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER

    JN 27.3.17 K ISSUE FOR CC

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    GRIDS (2 - 8) & (10 - 11) = CENTERLINE OF MEMBERSGRIDS 1, 9, 12 = EXTERNAL FACE OF MEMBERS / CONCRETE WALL GRIDS (2 - 8) & (10 - 11) = CENTERLINE OF MEMBERS

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION CK

  • 4.60LP

    MH

    PIT

    MH

    PIT

    4.07

    4.67

    4.60

    3.98MH4.77

    26°40'50" 26°40'50"

    116°

    44' 5

    0" 3

    5.01

    5

    205°37'20"205°37'20"

    203°43'40"

    295°

    51'4

    0"

    37.

    485

    2D P 4 4 1 6 0 2 D

    D P 5 3 1 8 1 71

    STORMWATER CHANNEL / CULVERT

    STORMWATER CHANNEL / CULVERT

    STORMWATER CHANNEL / CULVERT

    SSM 71408

    4.69

    4.71

    3.27

    2.16

    2.182.27

    2.31

    4.85

    4.804.72 4.54

    4.414.20 4.15 4.09

    4.04

    3.97

    4.84

    4.68

    4.57

    4.61

    4.59

    4.64

    4.78

    4.87

    4.88

    4.58

    2.36 2.39 2.372.28

    2.24

    2.222.262.32

    2.38

    2.352.30

    2.34

    2.33

    BOLLARDBOLLARD 4.48

    4.52

    4.634.73

    4.745.034.995.095.14

    3.813.63 3.53

    3.513.43 3.38

    3.363.41

    3.473.52

    3.593.66

    3.783.70

    4.10

    4.60

    4.63

    4.05

    RL. 4.05 (AHD)GIN TOP OF KERBBM

    FALL 6 DEGREES

    NEW COLORBOND METAL ROOF NEW COLORBOND METAL ROOF (UPPER ROOF)

    PROPOSED SIGNAGE

    FALL 6 DEGREES FALL 4.25 DEGREES

    FALL 4.25 DEGREES

    A

    M108

    A

    M108

    FALL 6 DEGREES

    FALL 6 DEGREES

    FALL 6 DEGREES

    PROPOSED NEW COLORBOND METAL ROOF

    RWH DP

    COVERED LOADING AREA FOR SMALL RIGID DELIVERY TRUCKS (BELOW)

    5D P 5 9 6 7 2 8

    2312.3m2

    TOP

    OF

    0.15

    m K

    ERB

    & G

    UTT

    ER

    CO

    NC

    RET

    E PA

    THC

    ON

    CR

    ETE

    PATH

    EXISTING CONCRETE DRIVEWAY TO BE REDUCED

    EXISTING CONCRETE DRIVEWAY

    EXISTING CONCRETE DRIVEWAY TO BE REDUCED

    0.23

    w R

    END

    . BR

    ICK

    WAL

    L

    0.23w BRICK WALL0.23w BRICK RETAINING W

    ALL

    0.23w BRICK RETAINING WALL0.23w BRICK RETAINING WALL

    0.23w BRICK RETAINING WALL0.23w BRICK RETAINING WALL

    NO. 177

    GRASS

    P R O P O S E D N E W D R I V E W A Y

    P R O P O S E D N E W D R I V E W A Y

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8. 9.

    S A N D S T O R A G E A R E A B E L O W

    SLIDING GATE

    C A R P A R K I N G A R E A

    ACTUAL BOUNDARY OF SITE

    DISABLED PERSONS CAR

    SPACE

    DISABLED PERSONS CAR

    SPACE

    COMMON AREA

    11.

    12.

    N E W D R I V E W A Y

    BEDFORD ROADPA

    RR

    AMAT

    TA R

    OAD

    SLIDING GATE

    13.

    10.

    EXIST RL

    EXIST RL

    EXIST RL

    EXIST RL

    EXIST RL

    EXIST RL EXIST RL

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    FALLS TO SUMPS IN ACCORDANCE WITH STORM WATER ENGINEERS DRAWINGS

    PROPOSEDFCGL RL 4.77

    EXIST RL EXIST RL

    EXIST RL

    DR

    AING

    E G

    RAT

    E TO

    ST

    OR

    MW

    ATER

    ENG

    INEE

    RS

    SPEC

    IFIC

    ATIO

    NS

    PROPOSED FENCE

    PRO

    POSE

    D F

    ENC

    EPR

    OPO

    SED

    FEN

    CE

    PROPOSED FENCE PROPOSED FENCE

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP

    2 3 4 5 6 7 8 91

    A

    B

    C

    D

    walls below shown dashed

    walls below shown dashed

    walls below shown dashed

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    WS

    RIDGE R.L 9.56

    RIDGE R.L 12.03

    NEW COLORBOND METAL ROOF

    THESE STOCKPILES ARE TO BE COVERED USING TARPAULIN AND WEIGHTS ( TO HOLD THE TARPAULIN IN PLACE) WHEN ACCESS IS NOT REQUIRED AS PER COND.

    93. WHEN THE STOCKPILES ARE EXPOSED, THE PERMANENTLY INSTALLED IRRIGATION SYSTEM SHALL BE

    UTILISED.

    SOLAR VOLTAIC COLLECTOR

    SOLAR VOLTAIC COLLECTOR

    STRIPS OF TRANSLUCENT ROOF SHEETING

    STRIPS OF TRANSLUCENT ROOF SHEETING

    SOLAR VOLTAIC COLLECTOR STRIPS OF TRANSLUCENT ROOF SHEETING SOLAR VOLTAIC COLLECTOR SOLAR VOLTAIC COLLECTOR

    B

    M108

    B

    M108

    N E W D R I V E W A Y

    14.

    + RL 4.68

    + 4.75 + 4.90+ 5.13 + 5.05

    + 4.80 - AS PER ENGS DETAILS

    WS

    PROPOSED LANDSCAPED AREA

    2M WIDE LANDSCAPE STRIP TO COMPLY WITH PART D 2.10.1(6) SCDCP

    RWH DP

    RWH

    RWH RWH RWH RWH RWH

    STRIPS OF TRANSLUCENT ROOF SHEETINGSOLAR VOLTAIC

    COLLECTOR

    STRIPS OF TRANSLUCENT ROOF SHEETING

    EAVES GUTTER

    PARAPET TO ENGINEERS DETAILS

    121110

    GALVANISED METAL BOX GUTTER 800MM WIDE x 200MM DEEP AS PER STORMWATER ENGINEERS

    DETAILS REFER TO ARCHITECTURAL SPECS

    GALVANISED METAL BOX GUTTER 800MM WIDE x 200MM DEEP AS PER STORMWATER ENGINEERS

    DETAILS REFER TO ARCHITECTURAL SPECS

    GALVANISED METAL BOX GUTTER 800MM WIDE x 200MM DEEP AS PER STORMWATER ENGINEERS

    DETAILS REFER TO ARCHITECTURAL SPECS

    12.03

    12.18PARAPET RL

    BOX GUTTER BOX GUTTER

    BOX GUTTERBOX GUTTER

    LOWER ROOF

    12.03

    2 CANOPY TREES TO BE REMOVED

    RWH

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES AS SPECIFIED BY

    MANUFACTURER AND IN ACCORDANCE WITH THE ARCHITECTURAL SPECIFICATION

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES AS SPECIFIED BY MANUFACTURER AND IN ACCORDANCE WITH THE ARCHITECTURAL SPECIFICATION

    DP DP DPEAVES GUTTEREAVES GUTTER

    DP

    EAVES GUTTER

    CREST RL 4.8 AS PER ENGS

    DETAILS

    CREST RL 4.8 AS PER ENGS

    DETAILS

    BOX GUTTER

    BOX GUTTER

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020ROOF PLAN M105 M

    MF M

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER

    JN 27.3.17 K ISSUE FOR CC

    IMPORTANT NOTE - WALL TYPE 1The air-cell insulation proposed to Wall Type 1 must achieve a Spread of flame index not more than 9 and a Smoke-developed Index not more than 8 if the Spread-of-flame is more than 5 Sarking. The Contractor must provide evidence of compliance in accordance with Spec C1.10 Clause 7: Other Materials.

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    CK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020ROOF PLAN M105 M

    MF M

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CK

  • GROUND FFL5.00

    GROUND FFL5.00

    MAXIMUM BUILDING HEIGHT DCP - 10 METRE HEIGHT LIMIT

    B O

    U N

    D A

    R Y

    AT

    SOU

    TH-W

    EST

    ELE

    VATI

    ON

    MAXIMUM BUILDING HEIGHT LEP - 16 METRE HEIGHT LIMIT

    MEZZANINE LEVEL.8.06

    MEZZANINE LEVEL.8.06

    3969

    3060

    ROOF LINE12.03

    ROOF LINE12.03

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND

    MATERIALS AND FINISHES SCHEDULE.

    GALAVANISED STEEL FENCE. REFER TO ARCH. SPEC

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND

    MATERIALS AND FINISHES SCHEDULE.

    1860

    1000

    2180 1

    630

    700

    1630

    700

    1630

    700

    PROVIDE 'DECO-WOOD' RED CEDAR HORIZONTAL COMPOSITE TIMBER FINISH OR SIMILAR. REFER TO MANUFACTUERS DETAILS

    AND THE ARCHITECTURAL SPECIFICATION

    NEW ALUMINIUM FRAMED WINDOW(S) AS SEL. BY THE PROPRIETORS AND TO CONFORM WITH THE BASIX CERTIFICATE

    R.L 9.70

    2035

    300mm BLOCKWORK TO ENGINEERS DETAILS

    NEW ALUMINIUM FRAMED WINDOW(S) AS SEL. BY THE PROPRIETORS AND TO CONFORM WITH THE BASIX CERTIFICATE

    3970

    3060

    B O

    U N

    D A

    R Y

    AT

    SOU

    TH-W

    EST

    ELE

    VATI

    ON

    R.L 6.93

    METAL AWNING. REFER TO ARCH. SPEC.

    4.25

    °

    ROOF SHOWN DASHEDROOF SHOWN DASHED

    THESE STOCKPILES ARE TO BE COVERED USING TARPAULIN AND WEIGHTS ( TO HOLD THE TARPAULIN IN PLACE) WHEN ACCESS IS NOT REQUIRED AS PER COND. 93. WHEN THE STOCKPILES ARE EXPOSED, THE PERMANENTLY INSTALLED IRRIGATION SYSTEM AS PER COND. 81 SHALL BE UTILISED.

    GLAZING REFLECTIVITYA GLAZING REFLECTIVITY INDEX OF LESS THAN 20% MUST BE PROVIDED FOR CERTIFICATION AS PER CONDITION 67.

    RWH TO ENGINEERS DETAILS.

    RWH TO ENGINEERS DETAILS.

    RWH TO ENGINEERS DETAILS.

    RWH TO ENGINEERS DETAILS.

    ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    ROOF SHOWN DASHED

    11.35

    12.18

    COLUMNS BEHIND

    ROOF SHOWN DASHED

    4600

    650

    BUILDING IN THE DISTANCE

    DA CONDITION 43A(b) TO BE DELETED AND TWO (2) CANOPY TREES NOT TO BE PLANTED.

    REFER TO STATEMENT OF ENVIRONMENTAL EFFECTS AND ARBORIST STATEMENT

    PREPARED BY TALC DATED 27 AUG 2020.

    GROUND FFL5.00

    GROUND FFL5.00

    MAXIMUM BUILDING ENVELOPE DCP - 10 METRE HEIGHT LIMIT

    B O

    U N

    D A

    R Y

    AT

    NO

    RTH

    -EAS

    T EL

    EVAT

    ION

    B E D F O R D R O A D

    MAXIMUM BUILDING ENVELOPE LEP - 16 METRE HEIGHT LIMIT

    MEZZANINE LEVEL.8.06

    MEZZANINE LEVEL.8.06

    ROOF LINE12.03

    ROOF LINE12.03

    3060

    3970

    B O

    U N

    D A

    R Y

    AT

    NO

    RTH

    -EAS

    T EL

    EVAT

    ION

    3060

    3970

    RIDGER.L 12.03

    FIRE RATED 200mm wall

    METAL 'KLIP-LOK' ROOF

    FIRE RATED 200mm wall

    RWH TO ENGINEERS DETAILS.

    RWH TO ENGINEERS DETAILS.

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020NORTH AND SOUTH ELEVATIONS M106 M

    MF M

    GLAZING REFLECTIVITY NOTE:THE CONTRACTOR MUST ENSURE THAT THE EXTERNAL GLASS USED IN THE BUILDING HAS A REFLECTIVITY INDEX OF LESS THAN 20% AS PER CONDITION 67. REFER TO ARCH SPEC AND SECTION J REPORT PREPARED BY PARTNERS ENERGY DATED 30/03/2017.

    1 : 100SOUTH WEST ELEVATION

    1

    1 : 100NORTH EAST ELEVATION

    2

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER REVIEW

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING CHANGE

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED 18.05.2016

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER DETAILS

    JN 27.3.17 K ISSUE FOR CC

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CKCK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION

  • GROUND FFL5.00

    RL

    PROPOSED SIGNAGE. REFER TO ARCH. SPEC.

    B O

    U N

    D A

    R Y

    B O

    U N

    D A

    R Y

    C A R P A R

    MAXIMUM BUILDING HEIGHT LEP - 16 METRE HEIGHT

    MAXIMUM BUILDING HEIGHT DCP - 10 METRE HEIGHT

    MEZZANINE LEVEL.8.06

    ROOF LINE12.03

    23456789 1

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    METAL 'KLIP-LOK' ROOF TO ENGINEERS DETAILS.

    740

    740

    PROVIDE 'STEEL-LINE' OR SIMILAR ROLLER DOOR TO MANUFACTURERS REQUIREMENTS.

    REFER TO ARCHITECTURAL SPECIFICATION

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND

    MATERIALS AND FINISHES SCHEDULE.

    METAL 'KLIP-LOK' ROOF TO ENGINEERS DETAILS.

    GALAVANISED STEEL FENCE. REFER TO ARCH. SPEC

    300mm BLOCKWORK TO ENGINEERS DETAILS (WT2)

    GALVANISED STEEL FENCE. REFER TO ARCH. SPEC

    R.L 9.70

    R.L 7.90

    3060

    3970

    COLORBOND GUTTERS & DOWNPIPES & CONNECTED TO STORMWATER LINES AS PER THE STORMWATER ENG. DETAILS.

    REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    ROOF RIDGER.L 9.56

    FIRE RATED 200mm BLOCKWORK TO ENGINEERS DETAILS (WT2B)

    (WT2

    B)

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS RWH AS PER ENGINEERS DETAILS

    RWH AS PER ENGINEERS DETAILS

    12 11 10

    44384900444047184834631664325664543054315430

    ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    9283516136 8303516118

    12.1812.03

    EQEQEQ

    CENTRE LINE BETWEEN RAINWATER HEADS

    4776 4776

    650650

    1500

    GROUND FFL5.00

    RL 3.74N A T U R A L G R O U N D L I N E

    B O

    U N

    D A

    R Y

    B O

    U N

    D A

    R Y

    MAXIMUM BUILDING HEIGHT LEP - 16 METRE HEIGHT LIMIT

    MAXIMUM BUILDING HEIGHT DCP - 10 METRE HEIGHT LIMIT

    MEZZANINE LEVEL.8.06

    ROOF LINE12.03

    2 3 4 5 6 7 8 91

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC

    AND MATERIALS AND FINISHES SCHEDULE.

    GALAVANISED STEEL FENCE. REFER TO ARCH. SPEC

    ROOF RIDGER.L 9.56

    4500

    METAL KLIP-LOK SKILLION ROOVE TO COVER "OPEN AIR" LANDSCAPE MATERIAL HOLDING AREA TO STRUCTURAL ENGINEERS DETAILS AS PER PART B CLAUSE 4 IN THE NOTICE OF DETERMINATION

    NEW ALUMINIUM FRAMED WINDOW(S) AS SEL. BY THE PROPRIETORSAND TO CONFORM WITH THE BASIX CERTIFICATE

    NEW ALUMINIUM FRAMED DOOR WITH FIXED WINDOWS AS SEL. BY THE PROPRIETORS AND TO CONFORM WITH THE BASIX CERTIFICATE

    200mm BLOCKWORK TO ENGINEERS DETAILS

    COLORBOND GUTTERS & DOWNPIPES & CONNECTED TO STORMWATER LINES AS PER THE STORMWATER ENG. DETAILS.

    REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    METAL 'KLIP-LOK' ROOF TO ENGINEERS DETAILS.

    COLORBOND GUTTERS & DOWNPIPES & CONNECTED TO STORMWATER LINES AS PER THE STORMWATER ENG. DETAILS. REFER TO ARCH SPEC

    AND MATERIALS AND FINISHES SCHEDULE.

    1400

    1000

    1400

    1000

    690

    20552

    745

    PROVIDE 'STEEL-LINE' OR SIMILAR ROLLER DOOR TO MANUFACTURERS REQUIREMENTS. REFER TO ARCHITECTURAL SPECIFICATION300mm BLOCKWORK TO ENGINEERS DETAILS

    3970

    3060

    3000

    2075

    100

    RWH AS PER ENGINEERS DETAILS

    121110

    RWH AS PER ENGINEERS DETAILS

    DP AS PER ENGINEERS DETAILSDP AS PER ENGINEERS DETAILS

    4438 4900 4440 4718 4834 6316 6432 5664 5430 5431 5430

    9.70

    12.18

    EAVE GUTTERS EAVE GUTTERS

    DA CONDITION 43A(b) TO BE DELETED AND TWO (2) CANOPY TREES NOT TO BE PLANTED.

    REFER TO STATEMENT OF ENVIRONMENTAL EFFECTS AND ARBORIST STATEMENT

    PREPARED BY TALC DATED 27 AUG 2020.

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020WEST AND EAST ELEVATIONS M107 M

    MF M

    1 : 100NORTH WEST ELEVATION

    1

    1 : 100SOUTH EAST ELEVATION

    2

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER

    JN 27.3.17 K ISSUE FOR CC

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CKCK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION

  • GROUND FFL5.00BEDFORD ROAD ENTRANCE/EXIT

    OFFICEW.C.STAFF ROOM.WAREHOUSE STORAGE

    BEDFORD ROAD ENTRANCE/EXIT

    MAXIMUM BUILDING ENVELOPE LEP - 16 METRE HEIGHT LIMIT

    MAXIMUM BUILDING ENVELOPE DCP - 10 METRE HEIGHT LIMIT

    MEZZANINE LEVEL.8.06

    ROOF LINE12.03

    23456789 1

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    METAL 'KLIP-LOK' ROOF TO ENGINEERS DETAILS.

    PROVIDE GALVANISED STEEL C-CHANNEL PURLINS REFER TO STRUCTURAL ENGINEERS DETAILS

    GALVANIZED STEEL COLUMN (C1) TO ENGINEERS DETAILS

    GALVANIZED STEEL BEAM TO STRUCTURAL ENGINEERS DETAILS

    R.L 9.70

    1000

    1400

    WT1B

    C1 C1C1

    WT3WT2 WT3

    1100

    C1

    WT1

    A

    WT2

    PROVIDE 'STEEL-LINE' OR SIMILAR ROLLER DOOR TO MANUFACTURERS REQUIREMENTS.

    REFER TO ARCHITECTURAL SPECIFICATION

    PROVIDE GALVANISED STEEL C-CHANNEL PURLINS REFER TO STRUCTURAL ENGINEERS DETAILS

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    STEEL FRAMED STAIRS TO ENGINEERS DETAILS

    NEW ALUMINIUM FRAMED DOOR WITH FIXED WINDOWS AS SEL. BY THE PROPRIETORS AND TO CONFORM WITH THE BASIX CERTIFICATE

    R.L 7.90

    R.C SLAB TO ENGINEERS DETAILS

    BLOCKWORK TO ENGINEERS DETAILS (WT2)

    NEW ALUMINIUM FRAMED WINDOW (S) AS SEL. BY THE PROPRIETORS AND TO CONFORM WITH THE BASIX CERTIFICATE

    MEZZANINEFFL. 8.06

    FFL. 5.00

    GALVANIZED STEEL BEAM TO STRUCTURAL ENGINEERS DETAILS

    PROVIDE MINI ORB EXTERNAL WALL CLADDING AS PER MANUFACTURERS REQS. REFER TO ARCH SPEC AND MATERIALS AND FINISHES SCHEDULE.

    GALVANISED STEEL BEAM TO STRUCTURAL ENGINEERS DETAILS

    GALVANISED STEEL TRUSS TO STUCTURAL ENGINEERS DETAILS

    C1C1C1

    3060

    3970

    PROVIDE FULL HEIGHT OFFICE JOINERY. REFER TO ARCH. SPEC.

    FIRE RATED 200mm WALL CONTRACTOR MUST ENSURE THAT THIS WALL IS TO HAVE A FIRE RATING ON 90/90/90

    METAL AWNING ABOVE WINDOWS. REFER TO ARCH . SPEC.

    WATERPROOF WALLS & FLOORSOF ALL WET AREAS AS PER THEARCHITECTURAL SPECIFICATION

    R.C FOOTING TO STRUCT.ENGINEERS. DETAILS

    R.C FOOTING TO STRUCT.ENGINEERS. DETAILS

    FFL. 5.00

    WT1B

    DASHED LINE INDICATES FLOOR OF CARPARKING AREA (FFL. 4.90)

    WT2

    GLAZING REFLECTIVITYA GLAZING REFLECTIVITY INDEX OF LESS THAN 20% MUST BE PROVIDED FOR CERTIFICATION AS PER CONDITION 67.

    IMPORTANT DOOR NOTE:EACH DOOR ON THE GROUND FLOOR OF THE BUILDING MUST HAVE A CLEAR WIDTH NOT LESS THAN 850MM, REQUIRING A 920MM DOORWAY

    RC PILES TO ENGINEERS DETAILSRC PAD TO ENGINEERS DETAILS

    R.C FOOTING TO STRUCT.ENGINEERS. DETAILS

    RC PILES IN DISTANCE SHOWN DOTTED TO ENGINEERS DETAILS

    GALVANISED STEEL BEAM TO STUCTURAL ENGINEERS DETAILS

    12 11 10

    12.18

    4.72

    THIS RC SLAB REPRESENTS THE 1:20 RAMP AS PER ENGS DETAILS 5.00

    280

    RET. WALL TO ENGS DETAILS

    GROUND FFL5.00

    MEZZANINE LEVEL.8.06

    ROOF LINE12.03

    RC FOOTING TO ENGINEERS DETAILSRC FOOTING TO ENGINEERS DETAILS RC SLAB TO ENGINEERS DETAILS RC SLAB TO ENGINEERS DETAILSNGL

    BULKY GOODS RETAIL SALES

    MEZZANINE

    STOCKPILESSAND STORAGE AREA

    DRIVEWAY

    NEW COLORBOND METAL ROOF

    SOLAR VOLTAIC COLLECTOR

    3969

    3060

    12.03

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES

    PROVIDE ALUMINIUM FRAMED 'BREEZEWAY' MANUAL LOUVRES REMOVED

    NGL

    STEEL FRAMED STAIRS TO ENGINEERS DETAILS

    RWH AS PER STORMWATER ENGINEERS DETAILS

    2400

    2400

    4500

    12.18Parapet RL

    11.35

    1500

    katris architects pty ltd

    JOB No.DRAWN

    CLIENT

    ARCHITECT'S APPROVAL

    DRAWING No ISSUESCALEDATE

    PROJECT

    TITLE

    AMENDMENTDATE ISSUEARCHITECTURAL - GENERAL NOTESA1 All dimensions are to be confirmed on site by the builder/subcontractor, any incongruencies must be reported to the Architect before commencement of any workA2 The Builder/subcontractor will be held responsible for any construction details which have not been approved by the Architect.A3 In the event of encountering any discrepencies on these drawings, specification or subsequent instructions issued, the Builder/Subcontractor shall contact the Architect before proceeding further with any work.A4 The Builder/Subcontractor will be held responsible for the watertightness of the whole building for a minimum period of two years after the date of practical completion.A5 It is the contractor's responsibilty to have all Architectural & Structural documentation, including all site instructions any any details issued during the course of construction, approved by the relevent authorities including the local Council & the Water Board before any work may be proceeded with.A6 All construction, control joints and expansion joints in the wall, floors, & other locations shall be in strict accordance with Architectural and/or Structural Engineering details. Nojoints or breakes other than specified, are allowed without written permission from the Architect and/or Engineer.A7 Measurements for the fabrication of secondary components such as, windows, doors,internal frames, structural steel components and the like, are not to be taken from thesedocuments. Mearurements must be taken on site to suit the work as constructed.A8 All structural components shall be in strict accordance to details and specifications as prepared by a structural engineer, and those details from part of the total specification.A9 All existing structures need to be examined for structural adequacy, and it is the Contractor's responsibillty to ensure that a certificate of structural adequacy is available prior to the start of any work.A10 No construction work shall commence until a site survey has been completed. This work must be performed by a registered Surveyor.A11 Foundation set-out, is to be performed by the Surveyor mentioned in 'A10' and recovery pegs must be protected during construction.A12 All timber work is to comply with the requirments of the 'Light Timber Framing Code' S.A.A. Codes and Structural Engineer's details and specification.A13 Copyrights of all documentation and designs relating to both Architectural and Structural Engineering, are retained by this office. Written authority is required for any reproduction.A14 All Architectural documentation to be read in conjunction with the Structural Engineer's details and specification.A15 Comply with the 'hazardous materials' clause of the specification

    DRAWN

    f 02 9747 5046abn 79 001 639 970

    p 02 9744 5421level 1 3-5 burwood road, concord nsw 2137PO Box 703 burwood 1805 nsw australia

    IMPORTANT NOTEIt is the Tenderer's & Contractor's responsibility to check that all Architectural, Structural and all other job related documentation's have been recieved before tendering and/or construction may commence. Should there be any doubt to the availability of such document's the Architect should be notified before further details be needed, the tenderer and/or Contractor shall obtain such details before signing of contract documents. Failure to adhere to these conditions, the Tenderer and/or Contractor nullifies any right or claim for extras, due to interpretation of documentation, and the Architect's &/or Engineer's direction shall be carried out at no extra cost.

    www.katris.com.au

    TN

    Nominated Architects Chris Katris (reg 9724), Nick Katris (reg 3878), Peter Katris (reg 4569)

    1 : 100

    MR R LAVIANO AND MR A BROMBAL (RA PROPERTY SERVICES PTY LTD)Proposed relocation and construction of new Joe and Sons (Builders Hardwareand Landscaping Supply Centre) at 33-35 Queens road, Five Dock to 177Parramatta road, Homebush West (cnr of Bedford road) Lot 5 DP 596728 andLot 2 DP 210783. 1153-11

    04.09.2020SECTION M108 M

    MF M

    1 : 100Section A - A

    A

    MF 30.10.15 D ISSUE FOR STORMWATER & TRAFFIC ENGINEER

    MF 16.11.15 E ISSUE FOR DA CONSULTANTS MF 18.11.15 F ISSUE FOR DA CONSULTANTS - PARKING

    MF 01.12.15 G ISSUE FOR DA

    MF 15.12.15 H ISSUE FOR ADDITIONAL INFORMATION

    MF 01.06.16 I ISSUE TO ADDRESS COUNCILS DA RESPONSE LETTER DATED

    MF 10.06.16 J ISSUE TO INCLUDE UPDATED STORMWATER

    JN 27.3.17 K ISSUE FOR CC

    External walls provided with external cladding finishLocation: Refer to the architectural documentation.Provide the external cladding system nominated on the Schedule of Finishes and the Architectural drawings and fixed to the exterior of the Masonry and/or timber wall in strict accordance with the manufacturers details and specifications.

    The selected prefinished materials and colours of the external cladding are to be confirmed in writing by the Proprietors prior to the signing of any Building Works Contract.Each cladding system is to be fixed to the required substrate material in strict accordance with the manufacturers details and specifications.It is the sole responsibility of the Building Contractor to allow for the preparation of the substrate and all materials required for the fixing of the selected cladding systems.The Building Contractor must also ensure that the finished cladding system is secure, stable and watertight.The substrate system for the cladding finish is to be constructed in a position as to allow for the fixing of the cladding so that the finished exterior face of the cladding system does not encroach on the specific Council required minimum setbacks and/or encroachments on the boundaries.

    1 : 100Section B - B

    B

    CT 07.06.19 L ISSUE FOR MODIFIED CC

    SECTION 4.55 SUBMISSIONCLOUDS INDICATE AMENDMENTS

    CKCK 04.09.2020 M ISSUE FOR SECTION 4.55 SUBMISSION

    M000 - TITLESheetsM000 - TITLE

    M101 - GROUND FLOOR PLANSheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION

    M103 - MEZZANINESheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION

    M105 - ROOF PLANSheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION

    M106 - NORTH AND SOUTH ELEVATIONSSheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION

    M107 - WEST AND EAST ELEVATIONSSheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION

    M108 - SECTIONSheetsM000 - TITLEM101 - GROUND FLOOR PLANM103 - MEZZANINEM105 - ROOF PLANM106 - NORTH AND SOUTH ELEVATIONSM107 - WEST AND EAST ELEVATIONSM108 - SECTION