KANSAS STATE UNIVERSITY · 2018. 6. 3. · FY12 Fuel Oil Refuse Supplies Energy Bond Totals Cost...

25
July August September October November December January February March April May June MARCH 2013 REPORT KANSAS STATE UNIVERSITY FY 2013 UTILITIES JULY 2012 REPORT

Transcript of KANSAS STATE UNIVERSITY · 2018. 6. 3. · FY12 Fuel Oil Refuse Supplies Energy Bond Totals Cost...

  • July August September October November December January February March April May June

    MARCH 2013 REPORT

    KANSAS STATE UNIVERSITY

    FY 2013 UTILITIES

    JULY 2012 REPORT

  • Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $2,724,483 $1,413,871 $1,295,902 $1,494,885 $1,043,045 $1,244,722 $1,569,909 $1,376,176 $1,285,754 $1,037,190 $1,045,725 $1,186,834 $2,826,333 $1,398,056 $1,410,789 $1,526,141 $1,124,878 $1,283,278 $1,694,602 $1,196,205 $1,092,081 $1,235,859 $1,238,215 $1,435,716

    Budgeted $2,701,028 $1,401,699 $1,284,745 $1,482,016 $1,034,066 $1,234,006 $1,556,394 $1,364,328 $1,274,685 $1,028,261 $1,036,723 $1,176,617 $2,844,481 $1,407,033 $1,419,848 $1,535,941 $1,132,101 $1,291,518 $1,705,484 $1,203,886 $1,099,093 $1,243,794 $1,246,166 $1,444,935

    Actual $2,826,333 $1,398,056 $1,410,789 $1,526,141 $1,124,878 $1,283,278 $1,694,602 $1,196,205 $1,092,081 $1,235,859 $1,238,215 $1,435,716 $2,777,208 $1,726,849 $1,402,102 $1,239,485 $1,208,682 $1,254,786 $1,552,003 $1,119,828 $1,273,304

    ($125,305) $3,643 ($126,044) ($44,125) ($90,813) ($49,271) ($138,209) $168,124 $182,604 ($207,598) ($201,493) ($259,099) $67,273 ($319,815) $17,745 $296,455 ($76,580) $36,731 $153,480 $84,058 ($174,210)

    Total Year Budget

    105.3551% Year-to-Date Actual Expenditure 77.1255% 6.2540%

    Balance -5.3551% Balance 22.8745% 7.2453%

    MC / VM / ESARP Supplemental MC / VM / ESARP Supplemental March Savings/(Shortfall)

    Lafene Health Center Supplemental Lafene Health Center Supplemental

    Salina Campus Supplemental Salina Campus Supplemental

    Energy & Environment OOE Energy & Environment OOE

    (0)$

    Total Year Budget Remaining

    0.6273%

    Year-to-Date Actual Expenditure $17,462,153 $13,554,247

    $774,035

    March Budget $1,099,093

    ($887,585) $4,020,033 March Actual Expenditure $1,273,304

    Total Year Budget $16,574,568 $17,574,280

    FY12 FY13

    ($174,210)

    $76,431

    $37,120

    ($14,000)

    4,020,033$

    Total Year Budget $17,574,280

    Savings/(Shortfall) Projection

    Adjusted Savings/(Shortfall) $110,243

    Projected Savings/(Shortfall) $85,137 Year-to-Date Supplemental $0

    KANSAS STATE UNIVERSITYTotal Utilities Budget for FY12 - FY13

    March 2013

    Year-to-Date Actual Expenditure $13,554,247 Projected Savings/(Shortfall) $110,243

    Year-to-Date Budget $13,639,385

    Year-to-Date Actual Expenditure $13,554,247

    $4,020,033

    Year-to-Date

    Projection Remaining $3,909,790

    $0

    $500,000

    $1,000,000

    $1,500,000

    $2,000,000

    $2,500,000

    $3,000,000

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected Budgeted Actual

    Printed4/16/2013

  • COMPOSITEProjected Actual Under/

    FY 2012 Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Total Total (Over)

    Jul-11 $2,052,190 $2,134,030 $300,534 $311,581 $289,835 $286,184 $73,594 $87,005 $8,329 $7,533 $2,724,483 $2,826,333 ($101,850)

    Aug-11 $1,000,656 $982,034 $146,384 $143,167 $209,011 $211,637 $48,717 $52,484 $9,103 $8,734 $1,413,871 $1,398,056 $15,815

    Sep-11 $952,058 $1,010,254 $139,292 $147,377 $152,359 $192,264 $42,862 $52,716 $9,331 $8,179 $1,295,902 $1,410,789 ($114,887)

    Oct-11 $1,143,715 $1,126,692 $193,185 $164,237 $117,308 $198,035 $32,115 $29,533 $8,562 $7,645 $1,494,885 $1,526,141 ($31,256)

    Nov-11 $763,750 $824,064 $111,712 $119,673 $134,313 $148,423 $25,935 $26,110 $7,335 $6,608 $1,043,045 $1,124,878 ($81,833)

    Dec-11 $958,999 $986,083 $140,378 $143,889 $105,237 $114,195 $32,843 $32,723 $7,264 $6,387 $1,244,722 $1,283,278 ($38,556)

    Jan-12 $1,206,789 $1,295,686 $176,627 $189,177 $127,796 $155,461 $50,789 $47,872 $7,907 $6,407 $1,569,909 $1,694,602 ($124,694)

    Feb-12 $1,028,113 $892,999 $150,379 $130,315 $147,499 $128,394 $42,281 $38,163 $7,903 $6,334 $1,376,176 $1,196,205 $179,971

    Mar-12 $997,142 $796,492 $145,598 $116,172 $99,299 $133,787 $36,480 $33,563 $7,236 $12,068 $1,285,754 $1,092,081 $193,673

    Apr-12 $745,205 $915,657 $108,773 $133,526 $144,609 $149,895 $31,141 $30,245 $7,462 $6,536 $1,037,190 $1,235,859 ($198,669)

    May-12 $785,184 $930,947 $113,881 $135,718 $100,934 $129,145 $38,339 $42,405 $7,387 $0 $1,045,725 $1,238,215 ($192,490)

    Jun-12 $804,181 $1,105,782 $117,444 $161,015 $208,911 $125,267 $48,471 $43,652 $7,827 $0 $1,186,834 $1,435,716 ($248,882)

    TOTALS $12,437,981 $13,000,718 $1,844,189 $1,895,847 $1,837,111 $1,972,687 $503,567 $516,471 $95,647 $76,431 $16,718,495 $17,462,153 ($743,658)

    Projected Actual Under/

    FY 2013 Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Total Total (Over)

    Jul-12 $2,134,030 $2,033,413 $311,581 $297,080 $286,184 $322,991 $87,005 $110,150 $7,533 $13,573 2,826,333$ $2,777,208 $49,125

    Aug-12 $982,034 $1,211,847 $143,167 $176,359 $211,637 $274,037 $52,484 $56,481 $8,734 $8,125 1,398,056$ $1,726,849 ($328,793)

    Sep-12 $1,010,254 $1,009,137 $147,377 $146,892 $192,264 $183,022 $52,716 $47,730 $8,179 $15,320 1,410,789$ $1,402,102 $8,687

    Oct-12 $1,126,692 $917,138 $164,237 $133,296 $198,035 $150,932 $29,533 $36,109 $7,645 $2,010 1,526,141$ $1,239,485 $286,656

    Nov-12 $824,064 $881,522 $119,673 $128,660 $148,423 $156,984 $26,110 $32,584 $6,608 $8,931 1,124,878$ $1,208,682 ($83,803)

    Dec-12 $986,083 $932,440 $143,889 $136,268 $114,195 $146,032 $32,723 $31,547 $6,387 $8,499 1,283,278$ $1,254,786 $28,491

    Jan-13 $1,295,686 $1,144,396 $189,177 $167,350 $155,461 $186,651 $47,872 $45,293 $6,407 $8,313 1,694,602$ $1,552,003 $142,599

    Feb-13 $892,999 $782,609 $130,315 $114,360 $128,394 $179,890 $38,163 $35,002 $6,334 $7,966 1,196,205$ $1,119,828 $76,377

    Mar-13 $796,492 $947,145 $116,172 $138,334 $133,787 $142,054 $33,563 $38,368 $12,068 $7,403 1,092,081$ $1,273,304 ($181,223)

    Apr-13 $915,657 $0 $133,526 $0 $149,895 $0 $30,245 $0 $6,536 $0 1,235,859$ $1,235,859

    May-13 $930,947 $0 $135,718 $0 $129,145 $0 $42,405 $0 $0 $0 1,238,215$ $1,238,215

    Jun-13 $1,105,782 $0 $161,015 $0 $125,267 $0 $43,652 $0 $0 $0 1,435,716$ $1,435,716

    TOTALS $13,000,718 $9,859,648 $1,895,847 $1,438,599 $1,972,687 $1,742,595 $516,471 $433,264 $76,431 $80,142 $17,462,153 $13,554,247 $3,907,906

    KSU UTILITY COST SUMMARY

    Main ESARP Vet. Med. Lafene Health CenterSalina

    ESARP Lafene Health CenterSalinaMain Vet. Med.

    Printed4/16/2013

  • FY12 Fuel Oil Refuse Supplies Energy Bond Totals

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Heating Cooling

    Main $497,108 6,961,114 $0.071 $190,912 31,784 $6.01 $35,430 18,919 $1.87 $56,982 19,225 $2.96 $0 $7,327 $8,732 $0 $796,492

    ESARP $72,839 1,019,984 $0.071 $27,974 4,657 $6.01 $4,983 2,661 $1.87 $8,022 2,705 $2.97 $0 $1,074 $1,280 $0 $116,172

    Vet Med $83,051 1,215,120 $0.068 $38,938 4,922 $7.91 $3,954 2,118 $1.87 $7,308 2,132 $3.43 $0 $536 $0 $0 $133,787

    Salina $19,383 227,533 $0.085 $11,717 1,731 $6.77 $1,004 190 $5.28 $693 190 $3.65 $0 $766 $0 $0 $33,563

    Lafene $6,548 89,259 $0.073 $4,905 790 $6.21 $221 104 $2.13 $394 104 $3.79 $0 $0 $0 $0 $12,068

    Cost $678,929 9,513,010 $0.071 $274,445 43,884 $6.25 $45,593 23,992 $1.90 $73,400 24,356 $3.01 $0 $9,703 $10,012 $0 $1,092,081 283.0 46.0

    OTHER $88,931 1,264,366 $0.070 $58,960 7,452 $7.91 $13,585 7,273 $1.87 $21,336 7,271 $2.93 $182,812

    FY13 Fuel Oil Refuse Supplies Energy Bond Totals

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Heating Cooling

    Main $508,698 6,619,296 $0.077 $234,969 57,059 $4.12 $34,105 16,808 $2.03 $38,855 12,436 $3.12 $0 $6,740 $37,928 $85,848 $947,145

    ESARP $74,538 969,900 $0.077 $34,429 8,361 $4.12 $4,823 2,378 $2.03 $5,420 1,736 $3.12 $0 $988 $5,557 $12,579 $138,334

    Vet Med $75,858 1,033,800 $0.073 $54,405 4,949 $10.99 $4,277 2,118 $2.02 $7,021 2,125 $3.30 $0 $493 $0 $0 $142,054

    Salina $23,512 256,046 $0.092 $12,360 1,907 $6.48 $952 184 $5.17 $778 184 $4.23 $0 $766 $0 $0 $38,368

    Lafene $3,813 43,587 $0.087 $3,219 524 $6.14 $131 59 $2.21 $241 59 $4.09 $0 $0 $0 $0 $7,403

    Cost $686,419 8,922,629 $0.077 $339,382 72,800 $4.66 $44,287 21,547 $2.06 $52,315 16,540 $3.16 $0 $8,987 $43,486 $98,427 $1,273,304 847.0 0.0

    OTHER $89,470 1,180,009 $0.076 $96,784 10,067 $9.61 $21,332 10,567 $2.02 $32,338 10,567 $3.06 $239,924

    775888.88 10102638.00 436166.87 82867.00 65619.23 32114.00 84652.61 27107.00 0.00 8987.44 43485.56 98427.36

    CHANGE FROM FY12 TO FY13 FOR CURRENT MONTH

    Fuel Oil Refuse Supplies Energy Bond Total

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Difference Heating Cooling

    Main $11,590 (341,818) $0.005 $44,058 25,275 ($1.89) ($1,325) (2,111) $0.16 ($18,127) (6,789) $0.16 $0 ($586) $29,196 $85,848 $150,653

    ESARP $1,698 (50,084) $0.005 $6,456 3,704 ($1.89) ($161) (283) $0.16 ($2,602) (969) $0.16 $0 ($86) $4,278 $12,579 $22,162

    Vet Med ($7,193) (181,320) $0.005 $15,467 27 $3.08 $323 0 $0.15 ($287) (7) ($0.12) $0 ($43) $0 $0 $8,267

    Salina $4,129 28,513 $0.007 $643 176 ($0.29) ($52) (6) ($0.11) $85 (6) $0.58 $0 $0 $0 $0 $4,805

    Lafene ($2,735) (45,672) $0.014 ($1,686) (266) ($0.07) ($91) (45) $0.09 ($153) (45) $0.30 $0 $0 $0 $0 ($4,664)

    TOTAL $7,490 (590,381) $64,937 28,916 ($1,306) (2,445) ($21,085) (7,816) $0 ($715) $33,474 $98,427 $181,223 564.0 (46.0)

    Unit Cost Change $0.006 ($1.59) $0.16 $0.15

    OTHER $539 (84,357) $0.005 $37,824 2,615 $1.70 $7,747 3,294 $0.15 $11,002 3,296 $0.13 $0.00 $0.00 $0.00 $0.00 $57,112

    Percent

    change 1.10% -6.21% 7.79% 23.66% 65.89% -25.46% -2.86% -10.19% 8.16% -28.73% -32.09% 4.95% #DIV/0! -7.37% 334.34% #DIV/0! 16.59% 199.29% -100.00%

    DAYS IN BILLING CYCLE: 29

    COMMENTS:

    Electric Natural Gas Water Sewer Degree Days

    Analyzation of March 2012 vs. March 2013 Utility Report

    Electric Natural Gas Water Sewer Degree Days

    Water Sewer Degree DaysElectric Natural Gas

  • FY12 Fuel Oil Refuse Supplies Energy Bond Totals

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Heating Cooling

    Main $5,029,314 70,331,321 $0.072 $2,014,293 378,624 $5.32 $415,935 264,271 $1.57 $426,266 158,417 $2.69 $0 $64,075 $517,491 $1,580,958 $10,048,332

    ESARP $736,925 10,305,367 $0.072 $295,146 55,478 $5.32 $58,451 37,131 $1.57 $58,198 21,621 $2.69 $0 $9,389 $75,826 $231,652 $1,465,587

    Vet Med $863,070 12,569,200 $0.069 $325,179 47,489 $6.85 $52,918 34,174 $1.55 $93,922 34,244 $2.74 $0 $4,689 $65,291 $163,311 $1,568,379

    Salina $217,980 2,536,710 $0.086 $55,785 7,668 $7.28 $62,518 11,030 $5.67 $7,885 11,030 $0.71 $0 $7,126 $0 $48,875 $400,169

    Lafene $42,045 548,122 $0.077 $23,192 3,710 $6.25 $1,801 958 $1.88 $2,857 958 $2.98 $0 $0 $0 $0 $69,895

    Cost $6,889,335 96,290,720 $0.072 $2,713,596 492,969 $5.50 $591,622 347,564 $1.70 $589,128 226,270 $2.60 $0 $85,278 $658,608 $2,024,796 $13,552,363 3,959.0 1,369.5

    OTHER $851,540 12,008,326 $0.071 $421,966 59,050 $7.15 $127,050 80,211 $1.58 $207,181 79,246 $2.61 $1,607,737

    FY13 Fuel Oil Refuse Supplies Energy Bond Totals

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Heating Cooling

    Main $5,347,203 69,897,717 $0.077 $1,410,009 371,669 $3.79 $543,586 294,467 $1.85 $390,244 132,521 $2.94 $0 $66,072 $553,231 $1,549,302 $9,859,648

    ESARP $783,504 10,241,836 $0.077 $206,603 54,459 $3.79 $77,318 41,912 $1.84 $53,417 18,182 $2.94 $0 $9,681 $81,063 $227,013 $1,438,599

    Vet Med $873,906 12,046,620 $0.073 $522,943 47,561 $11.00 $64,647 34,381 $1.88 $108,803 34,465 $3.16 $0 $4,835 $27,669 $139,792 $1,742,595

    Salina $229,817 2,533,310 $0.091 $50,535 7,279 $6.94 $91,305 15,778 $5.79 $9,532 15,778 $0.60 $0 $6,894 $0 $45,181 $433,264

    Lafene $48,528 591,728 $0.082 $26,378 4,273 $6.17 $1,967 951 $2.07 $3,269 951 $3.44 $0 $0 $0 $0 $80,142

    Cost $7,282,958 95,311,211 $0.076 $2,216,468 485,241 $4.57 $778,823 387,489 $2.01 $565,265 201,896 $2.80 $0 $87,482 $661,963 $1,961,288 $13,554,247 4,720.0 1,129.5

    OTHER $905,355 11,889,292 $0.076 $731,345 75,913 $9.63 $181,313 95,511 $1.90 $278,831 93,596 $2.98 $2,096,844

    CHANGE FROM FY12 TO FY13 Year-to-Date

    Fuel Oil Refuse Supplies Energy Bond Total

    Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Usage Per unit Cost Cost Cost Cost Difference Heating Cooling

    Main $317,888 (433,604) $0.005 ($604,284) (6,955) ($1.53) $127,652 30,196 $0.27 ($36,022) (25,897) $0.25 $0 $1,997 $35,740 ($31,656) ($188,685)

    ESARP $46,579 (63,531) $0.005 ($88,543) (1,019) ($1.53) $18,867 4,781 $0.27 ($4,781) (3,440) $0.25 $0 $293 $5,237 ($4,638) ($26,988)

    Vet Med $10,836 (522,580) $0.004 $197,764 72 $4.15 $11,730 207 $0.33 $14,881 221 $0.41 $0 $146 ($37,622) ($23,519) $174,215

    Salina $11,837 (3,400) $0.005 ($5,250) (389) ($0.33) $28,787 4,748 $0.12 $1,647 4,748 ($0.11) $0 ($232) $0 ($3,694) $33,095

    Lafene $6,483 43,606 $0.005 $3,186 563 ($0.08) $166 (7) $0.19 $412 (7) $0.46 $0 $0 $0 $0 $10,247

    TOTAL $393,623 (979,509) ($497,127) (7,728) $187,201 39,925 ($23,863) (24,374) $0 $2,204 $3,355 ($63,508) $1,884 761.0 (240.0)

    Unit Cost Change $0.005 ($0.94) $0.31 $0.20

    OTHER $53,816 (119,034) $0.005 $309,379 16,863 $2.49 $54,262 15,300 $0.31 $71,650 14,350 $0.36 $489,107

    Percent

    change 5.71% -1.02% 6.80% -18.32% -1.57% -17.02% 31.64% 11.49% 18.08% -4.05% -10.77% 7.53% #DIV/0! 2.58% 0.51% -3.14% 0.01% 19.22% -17.52%

    Analyzation of Year-to Date Usage and Cost for FY12 to FY13 -- March 2013

    Electric Natural Gas Water Sewer Degree Days

    Electric Natural Gas Water Sewer Degree Days

    Electric Natural Gas Water Sewer Degree Days

  • Kansas State University Hedged Natural Gas

    Cost of Gas w/

    Added

    Contract

    Charge Nov-1

    1

    Dec-1

    1

    Jan-1

    2

    Feb-1

    2

    Mar-

    12

    Apr-

    12

    May-1

    2

    Jun-1

    2

    Jul-12

    Aug-1

    2

    Sep-1

    2

    Oct-

    12

    Nov-1

    2

    Dec-1

    2

    Jan-1

    3

    Feb-1

    3

    Mar-

    13

    Apr-

    13

    May-1

    3Jun-1

    3

    Jul-13

    Aug-1

    3

    Sep-1

    3

    Oct-

    13

    Nov-1

    3

    Dec-1

    3

    Jan-1

    4

    Feb-1

    4

    Mar-

    14

    Apr-

    14

    May-1

    4

    Jun-1

    4

    4.670$ 30 30 30 30 30 30 30 30 30

    4.587$ 30 30 30 30 30 30 30 30 30 30 30 30 30 30

    3.766$ 20 20 20 20 20

    3.766$ 50 50 50 50 50 50 50 50 50 50 50 50 50

    Total % 60 60 60 60 60 60 60 60 60 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50

    Note: The cost of gas plus .12/mcf to ONEOK Marketing for daily balancing of account and gas delivery to city gate.

    The delivery charge from the city gate to meter is added to the cost of natural gas by Kansas Gas Service, which is not part of the above costs.

  • FY12 Avg. Max Avg. MinAvg.

    MeanPrecip. Snow Rain Days Heat DD Cool DD

    Min. <

    10

    Min. <

    32

    Max.

    > 90

    Max.

    > 80

    Jul-11 98.00 74.40 86.20 2.18 0.0 11 0.0 657.5 0 0 26 31

    Aug-11 92.50 68.50 80.50 2.80 0.0 14 0.0 480.5 0 0 19 31

    Sep-11 80.20 53.30 66.80 1.37 0.0 11 85.0 137.5 0 0 6 14

    Oct-11 72.40 44.00 58.20 2.66 0.0 7 259.5 48.0 0 7 1 8

    Nov-11 55.40 32.20 43.80 4.26 0.1 7 635.0 0.0 0 15 0 0

    Dec-11 44.50 24.40 34.40 3.43 1.3 9 948.0 0.0 0 26 0 0

    Jan-12 47.90 22.20 35.00 0.02 0.0 4 928.5 0.0 3 27 0 0

    Feb-12 48.20 25.30 36.70 2.12 2.5 14 820.0 0.0 3 26 0 0

    Mar-12 70.10 44.60 57.40 2.71 0.0 11 283.0 46.0 0 9 0 10

    Apr-12 72.40 46.70 59.60 2.11 0.0 12 205.5 43.0 0 0 3 6

    May-12 82.90 58.10 70.50 1.35 0.0 8 35.0 206.0 0 0 4 21

    Jun-12 89.10 65.20 77.20 4.15 0.0 5 21.5 386.0 0 0 15 28

    FY13 Avg. Max Avg. MinAvg.

    MeanPrecip. Snow Rain Days Heat DD Cool DD

    Min. <

    10

    Min. <

    32

    Max.

    > 90

    Max.

    > 80

    Jul-12 99.00 73.00 86.00 0.69 0.0 4 0.0 651.0 0 0 29 31

    Aug-12 89.50 62.40 75.90 4.31 0.0 11 0.5 339.0 0 0 18 27

    Sep-12 80.70 53.70 67.20 2.83 0.0 8 73.5 139.5 0 0 8 14

    Oct-12 67.60 41.80 54.70 0.62 0.0 5 340.5 21.0 0 8 0 1

    Nov-12 60.50 31.40 46.00 0.62 0.0 1 571.5 0.0 0 17 0 1

    Dec-12 45.60 22.40 34.00 0.35 2.8 6 960.0 0.0 0 26 0 0

    Jan-13 44.00 20.70 32.40 0.94 6.3 8 1,011.0 0.0 4 26 0 0

    Feb-13 43.30 21.30 32.30 1.71 11.7 9 916.0 0.0 4 27 0 0

    Mar-13 48.60 26.80 37.70 1.19 4.9 15 847.0 0.0 0 25 0 1

    Apr-13

    May-13

    Jun-13

    KANSAS STATE UNIVERSITY DEPARTMENT OF COMMUNICATIONSWEATHER DATA LIBRARY - Mary Knapp, State Climatologist

    Temperatures Inches Days

    Temperature Deviation

    (Days)

    Analysis: "March was much cooler this year than last. The mean maximum temperature for 2013 was cooler than the mean temperature for last year. This was the 16th coldest March on record, while last year was the warmest March on record. Snowfall was above average, but despite this the precipitation for the month was less than normal. Year-to-date moisture is also running slightly below normal. No records were set." (Knapp, Monthly Weather Summary for Manhattan; MAR 2013).

  • KANSAS STATE UNIVERSITY WEATHER DATA

    0.00

    5.00

    10.00

    15.00

    20.00

    Inch

    es/D

    ays

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Precip. 2.18 2.80 1.37 2.66 4.26 3.43 0.02 2.12 2.71 2.11 1.35 4.15 0.69 4.31 2.83 0.62 0.62 0.35 0.94 1.71 1.19

    Snow 0.0 0.0 0.0 0.0 0.1 1.3 0.0 2.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.8 6.3 11.7 4.9

    Rain Days 11 14 11 7 7 9 4 14 11 12 8 5 4 11 8 5 1 6 8 9 15

    Precipitation

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    Deg

    rees

    F

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Avg. Max 98.00 92.50 80.20 72.40 55.40 44.50 47.90 48.20 70.10 72.40 82.90 89.10 99.00 89.50 80.70 67.60 60.50 45.60 44.00 43.30 48.60

    Avg. Min 74.40 68.50 53.30 44.00 32.20 24.40 22.20 25.30 44.60 46.70 58.10 65.20 73.00 62.40 53.70 41.80 31.40 22.40 20.70 21.30 26.80

    Avg. Mean 86.20 80.50 66.80 58.20 43.80 34.40 35.00 36.70 57.40 59.60 70.50 77.20 86.00 75.90 67.20 54.70 46.00 34.00 32.40 32.30 37.70

    Temperature

  • 0

    10

    20

    30

    40

    Day

    s

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Min. < 10 0 0 0 0 0 0 3 3 0 0 0 0 0 0 0 0 0 0 4 4 0

    Min. < 32 0 0 0 7 15 26 27 26 9 0 0 0 0 0 0 8 17 26 26 27 25

    Max. > 90 26 19 6 1 0 0 0 0 0 3 4 15 29 18 8 0 0 0 0 0 0

    Max. > 80 31 31 14 8 0 0 0 0 10 6 21 28 31 27 14 1 1 0 0 0 1

    Temperature Deviation

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Heating Estimated 0.0 0.5 34.5 191.0 605.5 1,043.5 1,262.0 1,019.0 688.5 316.0 163.0 337.0 0.0 0.0 85.0 259.5 635.0 948.0 928.5 820.0 283.0 205.5 35.0 21.5

    Heating DD Actual 0.0 0.0 85.0 259.5 635.0 948.0 928.5 820.0 283.0 205.5 35.0 21.5 0.0 0.5 73.5 340.5 571.5 960.0 1,011.0 916.0 847.0

    Cooling Estimated 450.0 457.0 160.0 15.5 0.0 0.0 0.0 0.0 6.0 10.0 105.5 0.0 657.5 480.5 137.5 48.0 0.0 0.0 0.0 0.0 46.0 43.0 206.0 386.0

    Cooling DD Actual 657.5 480.5 137.5 48.0 0.0 0.0 0.0 0.0 46.0 43.0 206.0 386.0 651.0 339.0 139.5 21.0 0.0 0.0 0.0 0.0 0.0

    0.0

    250.0

    500.0

    750.0

    1,000.0

    1,250.0

    1,500.0

    Day

    s

    Heating & Cooling Degree Days

  • KANSAS STATE UNIVERSITY

    MAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER, SALINA COLLEGE OF TECHNOLOGY, & LAFENE HEALTH CENTER

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected 14,428,375 13,103,508 10,791,453 10,096,912 8,333,361 9,552,642 7,114,658 10,344,984 9,599,686 9,173,161 9,692,374 11,242,820 14,246,980 12,972,396 11,379,480 10,536,648 9,024,777 10,336,658 8,885,410 9,395,361 9,513,010 9,680,721 10,270,990 12,248,843

    Actual 14,246,980 12,972,396 11,379,480 10,536,648 9,024,777 10,336,658 8,885,410 9,395,361 9,513,010 9,680,721 10,270,990 12,248,843 13,240,556 11,964,776 12,656,115 9,681,432 10,875,528 9,550,667 9,503,017 8,916,491 8,922,629

    0

    2,500,000

    5,000,000

    7,500,000

    10,000,000

    12,500,000

    15,000,000

    17,500,000

    KW

    H

    ELECTRICITY USAGE FY12-FY13 Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $982,958 $924,868 $820,100 $715,697 $592,060 $602,898 $461,461 $709,956 $641,803 $652,469 $718,602 $831,893 $1,025,959 $984,347 $901,880 $735,062 $636,769 $677,333 $617,123 $631,933 $678,929 $738,128 $802,574 $1,001,370

    Actual $1,025,959 $984,347 $901,880 $735,062 $636,769 $677,333 $617,123 $631,933 $678,929 $738,128 $802,574 $1,001,370 $1,046,668 $938,583 $994,705 $736,107 $801,661 $693,833 $704,692 $680,289 $686,419

    $0

    $200,000

    $400,000

    $600,000

    $800,000

    $1,000,000

    $1,200,000

    ELECTRICITY COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITY

    MAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER, SALINA COLLEGE OF TECHNOLOGY, & LAFENE HEALTH CENTER

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected 54,100 48,941 42,283 48,149 68,600 93,726 105,200 91,999 79,611 47,508 30,783 38,324 37,481 35,046 36,061 46,057 42,427 101,466 83,209 67,338 43,884 40,770 26,235 26,833

    Actual 37,481 35,046 36,061 46,057 42,427 101,466 83,209 67,338 43,884 40,770 26,235 26,833 22,792 28,767 30,342 46,809 53,687 77,937 80,447 71,660 72,800

    0

    25,000

    50,000

    75,000

    100,000

    125,000

    MC

    F

    NATURAL GAS USAGE FY12-FY13 Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $333,794 $285,969 $217,125 $258,213 $346,304 $526,967 $580,469 $516,689 $429,325 $265,199 $166,695 $204,607 $170,149 $196,510 $198,203 $253,087 $341,491 $445,011 $472,872 $361,827 $274,445 $226,461 $153,016 $167,550

    Actual $170,149 $196,510 $198,203 $253,087 $341,491 $445,011 $472,872 $361,827 $274,445 $226,461 $153,016 $167,550 $117,502 $119,637 $121,334 $194,733 $240,808 $396,524 $361,447 $325,101 $339,382

    $0

    $100,000

    $200,000

    $300,000

    $400,000

    $500,000

    $600,000

    $700,000

    NATURAL GAS COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITY

    MAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER, SALINA COLLEGE OF TECHNOLOGY, & LAFENE HEALTH CENTER

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected 42,786 63,822 46,507 48,889 28,478 20,170 20,727 24,942 26,865 19,611 38,115 38,485 62,566 59,001 55,379 44,369 27,584 29,427 23,040 22,206 23,992 23,253 39,758 44,475

    Actual 62,566 59,001 55,379 44,369 27,584 29,427 23,040 22,206 23,992 23,253 39,758 44,475 85,356 77,113 62,397 38,717 31,857 31,898 19,951 18,653 21,547

    0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000

    CC

    F

    WATER USAGE FY12-FY13 Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $61,919 $98,292 $70,355 $70,865 $39,870 $27,695 $28,986 $38,309 $41,235 $30,614 $66,186 $74,737 $107,997 $102,665 $97,646 $70,670 $42,751 $45,157 $37,019 $42,125 $45,593 $44,224 $82,810 $93,966

    Actual $107,997 $102,665 $97,646 $70,670 $42,751 $45,157 $37,019 $42,125 $45,593 $44,224 $82,810 $93,966 $182,388 $159,069 $112,644 $79,652 $62,847 $60,890 $38,633 $38,412 $44,287

    $0

    $20,000

    $40,000

    $60,000

    $80,000

    $100,000

    $120,000

    $140,000

    $160,000

    $180,000

    $200,000

    WATER COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITY

    MAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER, SALINA COLLEGE OF TECHNOLOGY, & LAFENE HEALTH CENTER

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected 27,766 32,181 26,170 28,671 19,405 23,892 25,452 20,590 21,252 19,969 24,572 28,348 32,101 28,051 25,609 20,470 17,248 28,910 27,117 22,408 24,356 18,880 23,849 24,496

    Actual 32,101 28,051 25,609 20,470 17,248 28,910 27,117 22,408 24,356 18,880 23,849 24,496 44,208 29,129 20,230 15,341 17,278 19,480 22,805 16,885 16,540

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000

    40,000

    45,000

    50,000

    CC

    F

    SEWER USAGE FY12-FY13 Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $58,868 $63,130 $52,875 $60,828 $42,543 $53,194 $57,327 $53,697 $54,822 $52,455 $59,663 $63,561 $77,268 $65,610 $58,574 $53,050 $46,429 $75,582 $71,948 $67,267 $73,400 $56,838 $66,077 $66,397

    Actual $77,268 $65,610 $58,574 $53,050 $46,429 $75,582 $71,948 $67,267 $73,400 $56,838 $66,077 $66,397 $116,989 $79,954 $42,797 $42,727 $50,678 $58,459 $69,998 $51,348 $52,315

    $0

    $20,000

    $40,000

    $60,000

    $80,000

    $100,000

    $120,000

    $140,000

    SEWER COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITY

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $1,226,185 $14,677 $61,378 $0 $0 $14,677 $424,447 $15,144 $98,427 $0 $15,144 $0 $1,408,398 $15,144 $98,427 $0 $15,144 $0 $442,075 $45,608 $0 $160,850 $15,624 $98,427

    Actual $1,408,398 $15,144 $98,427 $0 $15,144 $0 $442,075 $45,608 $0 $160,850 $15,624 $98,427 $1,239,233 $22,693 $98,427 $130,903 $15,624 $0 $339,861 $16,119 $98,427

    $0

    $200,000

    $400,000

    $600,000

    $800,000

    $1,000,000

    $1,200,000

    $1,400,000

    $1,600,000

    ENERGY BOND PAYMENTS FOR MAIN, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER, SALINA FY12-FY13

    Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $52,142 $17,272 $62,258 $379,523 $12,213 $10,651 $9,571 $34,553 $10,422 $26,392 $9,697 $3,779 $27,368 $24,031 $45,117 $403,082 $33,550 $31,925 $45,031 $38,493 $10,012 $0 $107,976 $0

    Actual $27,368 $24,031 $45,117 $403,082 $33,550 $31,925 $45,031 $38,493 $10,012 $0 $107,976 $0 $64,282 $396,023 $21,865 $43,885 $27,295 $36,071 $29,057 $0 $43,486

    $0 $50,000

    $100,000 $150,000 $200,000 $250,000 $300,000 $350,000 $400,000 $450,000

    POWER PLANT SUPPLIES FOR MAIN, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITYMAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, and VETERINARY MEDICAL CENTER

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    Actual 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 1 1 1 1 1 1

    GA

    L

    FUEL OIL USAGE FY12-FY13 Projected Actual

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

    Actual $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

    $0 $0 $0 $0 $0 $1 $1 $1 $1 $1 $1

    FUEL OIL COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • KANSAS STATE UNIVERSITYMAIN CAMPUS, EXTENSION SYSTEMS & AGRICULTURAL RESEARCH PROGRAMS, VETERINARY MEDICAL CENTER and SALINA

    March 2013

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected $8,616 $9,663 $11,811 $9,759 $10,054 $8,640 $7,648 $7,828 $9,721 $10,061 $9,739 $8,257 $9,193 $9,750 $10,940 $11,190 $8,745 $8,270 $8,535 $8,952 $9,703 $9,358 $10,139 $8,006

    Actual $9,193 $9,750 $10,940 $11,190 $8,745 $8,270 $8,535 $8,952 $9,703 $9,358 $10,139 $8,006 $10,146 $10,890 $10,330 $11,479 $9,768 $9,009 $8,314 $8,558 $8,987

    $0

    $2,000

    $4,000

    $6,000

    $8,000

    $10,000

    $12,000

    $14,000

    REFUSE COST FY12-FY13 Projected Actual

    Printed4/16/2013

  • ELECTRICITY (KWH)

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 10,712,769 10,823,123 $728,505 $777,050 1,569,699 1,585,870 $106,745 $113,858 1,746,880 1,465,140 $114,176 $101,634 318,599 309,178 $27,674 $28,249 80,428 63,669 $5,858 $5,168 14,428,375 14,246,980 $982,958 $1,025,959

    Aug-11 9,313,605 9,350,515 $657,564 $709,908 1,364,686 1,370,094 $96,350 $104,020 2,009,080 1,811,160 $136,165 $132,719 332,314 359,554 $28,476 $31,460 83,823 81,073 $6,313 $6,240 13,103,508 12,972,396 $924,868 $984,347

    Sep-11 7,790,838 8,062,572 $592,888 $640,639 1,141,560 1,181,376 $86,873 $93,870 1,436,720 1,712,240 $104,721 $130,457 341,362 353,700 $29,468 $31,281 80,973 69,592 $6,151 $5,633 10,791,453 11,379,480 $820,100 $901,880

    Oct-11 7,418,715 7,640,313 $526,511 $533,871 1,087,035 1,119,504 $77,148 $78,226 1,247,400 1,449,960 $84,294 $95,521 273,063 266,309 $22,229 $22,397 70,699 60,562 $5,515 $5,048 10,096,912 10,536,648 $715,697 $735,062

    Nov-11 5,657,713 6,127,812 $404,755 $435,375 829,002 897,883 $59,307 $63,794 1,543,000 1,693,340 $104,392 $112,830 243,932 250,890 $19,368 $20,880 59,714 54,852 $4,238 $3,891 8,333,361 9,024,777 $592,060 $636,769

    Dec-11 7,135,316 7,855,747 $449,084 $513,556 1,045,509 1,151,071 $65,803 $75,249 1,043,660 1,030,100 $62,262 $63,977 276,440 255,329 $22,086 $21,215 51,717 44,411 $3,663 $3,335 9,552,642 10,336,658 $602,898 $677,333

    Jan-12 5,264,064 6,602,682 $337,887 $458,078 771,322 967,464 $49,509 $67,120 749,940 1,016,980 $48,021 $67,496 280,185 254,359 $22,723 $21,293 49,147 43,925 $3,321 $3,136 7,114,658 8,885,410 $461,461 $617,123

    Feb-12 7,479,398 6,907,443 $515,450 $463,730 1,095,926 1,012,121 $75,527 $67,948 1,438,860 1,175,160 $92,646 $75,386 289,820 259,858 $23,347 $21,822 40,980 40,779 $2,986 $3,047 10,344,984 9,395,361 $709,956 $631,933

    Mar-12 7,301,672 6,961,114 $486,568 $497,108 1,069,885 1,019,984 $71,295 $72,839 929,440 1,215,120 $59,777 $83,051 258,091 227,533 $21,109 $19,383 40,598 89,259 $3,053 $6,548 9,599,686 9,513,010 $641,803 $678,929

    Apr-12 6,385,357 6,888,155 $455,618 $528,783 935,622 1,009,294 $66,760 $77,480 1,574,740 1,433,820 $106,696 $105,284 232,437 255,685 $20,105 $22,491 45,005 93,767 $3,290 $4,089 9,173,161 9,680,721 $652,469 $738,128

    May-12 7,407,483 7,709,738 $549,117 $602,802 1,085,390 1,129,678 $80,460 $88,326 896,560 1,162,400 $63,564 $87,296 253,509 269,174 $21,661 $24,150 49,432 0 $3,799 $0 9,692,374 10,270,990 $718,602 $802,574

    Jun-12 7,786,835 9,341,652 $577,543 $763,252 1,140,974 1,368,795 $84,625 $111,836 2,010,980 1,279,880 $143,131 $102,652 254,599 258,516 $22,414 $23,629 49,432 0 $4,180 $0 11,242,820 12,248,843 $831,893 $1,001,370

    89,653,765 94,270,866 $6,281,489 $6,924,151 13,136,610 13,813,134 $920,402 $1,014,568 16,627,260 16,445,300 $1,119,846 $1,158,303 3,354,351 3,320,085 $280,660 $288,250 701,948 641,889 $52,368 $46,134 123,473,934 128,491,274 $8,654,765 $9,431,407

    Y-T-D 68,074,090 70,331,321 $4,699,211 5,029,314$ 9,974,624 10,305,367 688,557$ 736,925$ 12,144,980 12,569,200 806,455$ 863,070$ 2,613,806 2,536,710 216,480$ 217,980$ 558,079 548,122 $41,099 $42,045 93,365,579 96,290,720 $6,451,801 $6,889,335

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 10,823,123 9,872,671 $777,050 $779,486 1,585,870 1,446,604 $113,858 $114,215 1,465,140 1,446,260 $101,634 $110,723 309,178 360,157 $28,249 $32,832 63,669 114,864 $5,168 $9,412 14,246,980 13,240,556 $1,025,959 $1,046,668

    Aug-12 9,350,515 8,517,416 $709,908 $669,677 1,370,094 1,248,023 $104,020 $98,125 1,811,160 1,801,060 $132,719 $135,168 359,554 330,305 $31,460 $30,037 81,073 67,972 $6,240 $5,576 12,972,396 11,964,776 $984,347 $938,583

    Sep-12 8,062,572 9,446,731 $640,639 $742,699 1,181,376 1,384,192 $93,870 $108,825 1,712,240 1,355,740 $130,457 $101,601 353,700 342,650 $31,281 $31,237 69,592 126,802 $5,633 $10,342 11,379,480 12,656,115 $901,880 $994,705

    Oct-12 7,640,313 6,969,312 $533,871 $533,399 1,119,504 1,021,185 $78,226 $78,157 1,449,960 1,432,300 $95,521 $101,147 266,309 242,955 $22,397 $22,121 60,562 15,680 $5,048 $1,283 10,536,648 9,681,432 $735,062 $736,107

    Nov-12 6,127,812 7,982,936 $435,375 $589,658 897,883 1,169,708 $63,794 $86,400 1,693,340 1,404,380 $112,830 $97,885 250,890 255,111 $20,880 $22,517 54,852 63,393 $3,891 $5,201 9,024,777 10,875,528 $636,769 $801,661

    Dec-12 7,855,747 7,085,963 $513,556 $515,406 1,151,071 1,038,278 $75,249 $75,520 1,030,100 1,120,640 $63,977 $76,621 255,329 241,466 $21,215 $21,368 44,411 64,320 $3,335 $4,919 10,336,658 9,550,667 $677,333 $693,833

    Jan-13 6,602,682 7,071,221 $458,078 $524,364 967,464 1,036,118 $67,120 $76,833 1,016,980 1,086,640 $67,496 $75,798 254,359 259,683 $21,293 $23,618 43,925 49,355 $3,136 $4,079 8,885,410 9,503,017 $617,123 $704,692

    Feb-13 6,907,443 6,332,171 $463,730 $483,816 1,012,121 927,828 $67,948 $70,892 1,175,160 1,365,800 $75,386 $99,104 259,858 244,937 $21,822 $22,575 40,779 45,755 $3,047 $3,902 9,395,361 8,916,491 $631,933 $680,289

    Mar-13 6,961,114 6,619,296 $497,108 $508,698 1,019,984 969,900 $72,839 $74,538 1,215,120 1,033,800 $83,051 $75,858 227,533 256,046 $19,383 $23,512 89,259 43,587 $6,548 $3,813 9,513,010 8,922,629 $678,929 $686,419

    Apr-13 6,888,155 $528,783 1,009,294 $77,480 1,433,820 $105,284 255,685 $22,491 93,767 $4,089 9,680,721 $738,128

    May-13 7,709,738 $602,802 1,129,678 $88,326 1,162,400 $87,296 269,174 $24,150 0 $0 10,270,990 $802,574

    Jun-13 9,341,652 $763,252 1,368,795 $111,836 1,279,880 $102,652 258,516 $23,629 0 $0 12,248,843 $1,001,370

    94,270,866 69,897,717 $6,924,151 $5,347,203 13,813,134 10,241,836 $1,014,568 $783,504 16,445,300 12,046,620 $1,158,303 $873,906 3,320,085 2,533,310 $288,250 $229,817 641,889 591,728 $46,134 $48,528 128,491,274 95,311,211 $9,431,407 $7,282,958

    Jul-11 32 Jul-12 30

    Aug-11 29 Aug-12 25

    Sep-11 30 Sep-12 33

    Oct-11 31 Oct-12 29

    Nov-11 30 Nov-12 34

    Dec-11 34 Dec-12 31

    Jan-12 31 Jan-13 32

    Feb-12 31 Feb-13 29

    Mar-12 29 Mar-13 29

    Apr-12 29 Apr-13

    May-12 29 May-13

    Jun-12 30 Jun-13

    KSU UTILITY SUMMARY

    LAFENE HEALTH CENTER TOTALMAIN SALINA

    ELECTRICAL BILLING CYCLE DAYS

    ESARP VETMED

    (Substations Only)

    Printed4/16/2013

  • NATURAL GAS (MCF)

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 41,042 27,148 $252,288 $116,381 6,014 3,978 $36,967 $17,053 6,716 6,053 $41,456 $34,181 53 45 $913 $868 275 257 $2,171 $1,666 54,100 37,481 333,794$ 170,149$

    Aug-11 35,374 24,202 $202,590 $126,136 5,183 3,546 $29,685 $18,482 8,071 7,012 $50,610 $49,468 36 26 $790 $744 277 260 $2,295 $1,681 48,941 35,046 285,969$ 196,510$

    Sep-11 31,173 26,485 $156,622 $137,830 4,568 3,880 $22,949 $20,196 6,220 5,384 $34,355 $37,575 34 34 $777 $796 288 278 $2,421 $1,806 42,283 36,061 217,125$ 198,203$

    Oct-11 38,639 37,117 $204,285 $199,697 5,662 5,439 $29,933 $29,261 3,479 3,096 $20,472 $20,968 54 80 $908 $1,098 315 325 $2,615 $2,062 48,149 46,057 258,213$ 253,087$

    Nov-11 55,990 33,445 $279,665 $273,239 8,203 4,901 $40,978 $40,037 3,781 3,364 $20,313 $22,876 267 352 $2,471 $2,998 359 365 $2,877 $2,341 68,600 42,427 346,304$ 341,491$

    Dec-11 74,941 82,264 $416,957 $345,815 10,980 12,054 $61,095 $50,671 6,167 5,380 $36,718 $36,472 1,279 1,337 $8,812 $9,379 359 431 $3,385 $2,674 93,726 101,466 526,967$ 445,011$

    Jan-12 83,216 64,914 $452,672 $359,300 12,193 9,511 $66,328 $52,647 7,175 6,231 $41,916 $43,720 2,082 2,042 $15,177 $14,139 534 511 $4,375 $3,067 105,200 83,209 580,469$ 472,872$

    Feb-12 71,481 51,265 $394,718 $264,984 10,473 7,512 $57,836 $38,827 7,088 6,047 $42,615 $40,981 2,381 2,021 $16,866 $14,046 576 493 $4,654 $2,990 91,999 67,338 516,689$ 361,827$

    Mar-12 62,530 31,784 $331,282 $190,912 9,162 4,657 $48,541 $27,974 5,674 4,922 $32,429 $38,938 1,793 1,731 $13,199 $11,717 452 790 $3,873 $4,905 79,611 43,884 429,325$ 274,445$

    Apr-12 35,916 30,739 $195,591 $163,346 5,263 4,504 $28,659 $23,934 4,700 4,198 $28,611 $31,796 1,181 591 $8,606 $5,381 448 738 $3,732 $2,003 47,508 40,770 265,199$ 226,461$

    May-12 21,926 18,859 $114,220 $106,163 3,212 2,764 $16,736 $15,556 4,821 4,136 $28,676 $27,608 451 476 $3,747 $3,689 373 0 $3,317 $0 30,783 26,235 166,695$ 153,016$

    Jun-12 28,367 23,302 $129,432 $144,789 4,156 3,415 $18,965 $21,215 5,282 2 $51,488 $117 190 114 $1,846 $1,429 329 0 $2,876 $0 38,324 26,833 204,607$ 167,550$

    580,595 451,524 $3,130,321 $2,428,591 85,069 66,161 $458,673 $355,852 69,174 55,825 $429,658 $384,700 9,801 8,849 $74,112 $66,284 4,585 4,448 $38,590 $25,195 749,224 586,807 $4,131,355 $3,260,622

    Y-T-D 494,386 378,624 $2,691,079 2,014,293$ 72,438 55,478 394,313$ 295,146$ 54,371 47,489 320,884$ 325,179$ 7,979 7,668 59,913$ 55,785$ 3,435 3,710 $28,666 $23,192 632,609 492,969 $3,494,854 $2,713,596

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 27,148 14,038 $116,381 $40,350 3,978 2,057 $17,053 $5,912 6,053 6,083 $34,181 $66,891 45 51 $868 $934 257 563 $1,666 $3,414 37,481 22,792 $170,149 $117,502

    Aug-12 24,202 18,755 $126,136 $35,063 3,546 2,748 $18,482 $5,138 7,012 7,024 $49,468 $77,223 26 22 $744 $774 260 218 $1,681 $1,439 35,046 28,767 $196,510 $119,637

    Sep-12 26,485 21,251 $137,830 $50,036 3,880 3,114 $20,196 $7,332 5,384 5,402 $37,575 $59,407 34 56 $796 $940 278 519 $1,806 $3,619 36,061 30,342 $198,203 $121,334

    Oct-12 37,117 37,806 $199,697 $138,487 5,439 5,539 $29,261 $20,292 3,096 3,106 $20,968 $34,197 80 86 $1,098 $1,108 325 272 $2,062 $649 46,057 46,809 $253,087 $194,733

    Nov-12 33,445 43,113 $273,239 $172,491 4,901 6,317 $40,037 $25,274 3,364 3,314 $22,876 $36,476 352 484 $2,998 $3,399 365 459 $2,341 $3,168 42,427 53,687 $341,491 $240,808

    Dec-12 82,264 61,988 $345,815 $285,376 12,054 9,083 $50,671 $41,815 5,380 5,400 $36,472 $59,357 1,337 981 $9,379 $6,761 431 485 $2,674 $3,215 101,466 77,937 $445,011 $396,524

    Jan-13 64,914 62,604 $359,300 $241,516 9,511 9,173 $52,647 $35,388 6,231 6,225 $43,720 $68,410 2,042 1,831 $14,139 $12,226 511 614 $3,067 $3,907 83,209 80,447 $472,872 $361,447

    Feb-13 51,265 55,055 $264,984 $211,720 7,512 8,067 $38,827 $31,023 6,047 6,058 $40,981 $66,576 2,021 1,861 $14,046 $12,033 493 619 $2,990 $3,749 67,338 71,660 $361,827 $325,101

    Mar-13 31,784 57,059 $190,912 $234,969 4,657 8,361 $27,974 $34,429 4,922 4,949 $38,938 $54,405 1,731 1,907 $11,717 $12,360 790 524 $4,905 $3,219 43,884 72,800 $274,445 $339,382

    Apr-13 30,739 $163,346 4,504 $23,934 4,198 $31,796 591 $5,381 738 $2,003 40,770 $226,461

    May-13 18,859 $106,163 2,764 $15,556 4,136 $27,608 476 $3,689 0 $0 26,235 $153,016

    Jun-13 23,302 $144,789 3,415 $21,215 2 $117 114 $1,429 0 $0 26,833 $167,550

    451,524 371,669 $2,428,591 $1,410,009 66,161 54,459 $355,852 $206,603 55,825 47,561 $384,700 $522,943 8,849 7,279 $66,284 $50,535 4,448 4,273 $25,195 $26,378 586,807 485,241 $3,260,622 $2,216,468

    ESARP SALINAVETMED

    KSU UTILITY SUMMARY

    MAIN LAFENE HEALTH CENTER TOTAL

    Printed4/16/2013

  • WATER (CCF)

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 32,441 48,000 $43,525 $73,265 4,706 6,797 $6,314 $10,360 4,414 4,619 $5,811 $6,910 1,157 2,997 $6,152 $17,180 68 153 $116 $282 42,786 62,566 $61,919 $107,997

    Aug-11 47,298 42,621 $63,122 $64,650 6,862 6,064 $9,158 $9,203 6,109 6,960 $8,020 $10,392 3,431 3,173 $17,789 $18,095 122 183 $203 $325 63,822 59,001 $98,292 $102,665

    Sep-11 35,427 40,366 $47,530 $61,277 5,131 5,753 $6,884 $8,736 3,648 5,793 $4,810 $8,656 2,102 3,303 $10,818 $18,679 199 164 $312 $297 46,507 55,379 $70,355 $97,646

    Oct-11 38,777 34,857 $51,856 $52,948 5,634 4,895 $7,533 $7,441 2,947 3,730 $3,894 $5,589 1,426 773 $7,408 $4,480 105 114 $175 $211 48,889 44,369 $70,865 $70,670

    Nov-11 22,284 21,441 $30,061 $32,817 3,209 2,875 $4,329 $4,410 2,525 3,034 $3,345 $4,557 414 158 $2,055 $824 46 76 $81 $143 28,478 27,584 $39,870 $42,751

    Dec-11 16,335 22,852 $22,036 $34,680 2,353 3,200 $3,174 $4,859 1,317 3,147 $1,767 $4,728 120 151 $639 $747 45 77 $79 $144 20,170 29,427 $27,695 $45,157

    Jan-12 17,440 17,934 $23,996 $28,513 2,500 2,464 $3,440 $3,925 651 2,483 $910 $3,861 93 124 $564 $650 43 35 $76 $69 20,727 23,040 $28,986 $37,019

    Feb-12 19,227 17,281 $29,170 $32,354 2,752 2,422 $4,174 $4,534 2,780 2,290 $4,179 $4,272 131 161 $690 $859 52 52 $96 $107 24,942 22,206 $38,309 $42,125

    Mar-12 21,950 18,919 $33,235 $35,430 3,090 2,661 $4,680 $4,983 1,621 2,118 $2,454 $3,954 144 190 $751 $1,004 60 104 $115 $221 26,865 23,992 $41,235 $45,593

    Apr-12 15,209 18,011 $23,246 $33,835 2,125 2,506 $3,250 $4,710 2,016 2,437 $3,044 $4,543 178 170 $915 $980 83 129 $159 $155 19,611 23,253 $30,614 $44,224

    May-12 29,974 30,579 $45,499 $57,295 4,336 4,338 $6,581 $8,129 1,780 2,725 $2,689 $5,072 1,974 2,116 $11,318 $12,314 51 0 $99 $0 38,115 39,758 $66,186 $82,810

    Jun-12 27,026 32,580 $41,039 $60,825 3,929 4,564 $5,867 $8,523 3,434 4,584 $5,152 $8,504 3,924 2,747 $22,371 $16,114 172 0 $309 $0 38,485 44,475 $74,737 $93,966

    323,388 345,441 $454,314 $567,890 46,627 48,539 $65,384 $79,812 33,242 43,920 $46,074 $71,037 15,094 16,063 $81,470 $91,926 1,046 1,087 $1,821 $1,956 419,397 455,050 $649,063 $812,622

    Y-T-D 251,179 264,271 $344,531 415,935$ 36,237 37,131 49,686$ 58,451$ 26,012 34,174 35,190$ 52,918$ 9,018 11,030 46,866$ 62,518$ 740 958 $1,254 $1,801 323,186 347,564 $477,526 $591,622

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 48,000 64,920 $73,265 $120,876 6,797 9,332 $10,360 $17,377 4,619 5,061 $6,910 $9,380 2,997 5,911 $17,180 $34,479 153 132 $282 $277 62,566 85,356 $107,997 $182,388

    Aug-12 42,621 57,919 $64,650 $107,835 6,064 8,238 $9,203 $15,339 6,960 6,825 $10,392 $12,634 3,173 3,908 $18,095 $22,817 183 223 $325 $443 59,001 77,113 $102,665 $159,069

    Sep-12 40,366 48,554 $61,277 $79,305 5,753 6,915 $8,736 $11,249 5,793 4,341 $8,656 $8,051 3,303 2,324 $18,679 $13,509 164 263 $297 $530 55,379 62,397 $97,646 $112,644

    Oct-12 34,857 29,692 $52,948 $55,454 4,895 4,127 $7,441 $7,710 3,730 2,988 $5,589 $5,558 773 1,897 $4,480 $10,903 114 13 $211 $27 44,369 38,717 $70,670 $79,652

    Nov-12 21,441 23,127 $32,817 $43,192 2,875 3,287 $4,410 $6,137 3,034 4,474 $4,557 $8,301 158 868 $824 $5,006 76 101 $143 $212 27,584 31,857 $42,751 $62,847

    Dec-12 22,852 25,879 $34,680 $48,297 3,200 3,720 $4,859 $6,941 3,147 1,870 $4,728 $3,480 151 369 $747 $2,044 77 60 $144 $128 29,427 31,898 $45,157 $60,890

    Jan-13 17,934 13,708 $28,513 $26,329 2,464 1,943 $3,925 $3,731 2,483 4,103 $3,861 $7,721 124 145 $650 $740 35 52 $69 $112 23,040 19,951 $37,019 $38,633

    Feb-13 17,281 13,860 $32,354 $28,194 2,422 1,972 $4,534 $4,010 2,290 2,601 $4,272 $5,246 161 172 $859 $855 52 48 $107 $107 22,206 18,653 $42,125 $38,412

    Mar-13 18,919 16,808 $35,430 $34,105 2,661 2,378 $4,983 $4,823 2,118 2,118 $3,954 $4,277 190 184 $1,004 $952 104 59 $221 $131 23,992 21,547 $45,593 $44,287

    Apr-13 18,011 $33,835 2,506 $4,710 2,437 $4,543 170 $980 129 $155 23,253 $44,224

    May-13 30,579 $57,295 4,338 $8,129 2,725 $5,072 2,116 $12,314 0 $0 39,758 $82,810

    Jun-13 32,580 $60,825 4,564 $8,523 4,584 $8,504 2,747 $16,114 0 $0 44,475 $93,966

    345,441 294,467 $567,890 $543,586 48,539 41,912 $79,812 $77,318 43,920 34,381 $71,037 $64,647 16,063 15,778 $91,926 $91,305 1,087 951 $1,956 $1,967 455,050 387,489 $812,622 $778,823

    VETMED SALINA TOTAL

    KSU UTILITY SUMMARY

    LAFENE HEALTH CENTERMAIN ESARP

    Printed4/16/2013

  • SEWER (CCF)

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 19,331 21,419 $41,704 $55,380 2,785 2,902 $6,010 $7,380 4,425 4,630 $10,355 $12,595 1,157 2,997 $615 $1,495 68 153 $184 $418 27,766 32,101 $58,868 $77,268

    Aug-11 19,694 15,616 $42,267 $39,854 2,817 2,108 $6,047 $5,383 6,117 6,971 $13,685 $18,523 3,431 3,173 $838 $1,361 122 183 $292 $488 32,181 28,051 $63,130 $65,610

    Sep-11 17,689 14,397 $38,174 $37,013 2,532 1,948 $5,465 $5,014 3,648 5,797 $7,814 $14,968 2,102 3,303 $975 $1,136 199 164 $447 $443 26,170 25,609 $52,875 $58,574

    Oct-11 21,123 14,005 $45,194 $37,055 3,047 1,840 $6,519 $4,893 2,970 3,738 $8,112 $10,044 1,426 773 $746 $734 105 114 $257 $323 28,671 20,470 $60,828 $53,050

    Nov-11 14,367 12,426 $31,049 $33,621 2,049 1,554 $4,429 $4,251 2,529 3,034 $5,709 $7,682 414 158 $1,217 $642 46 76 $140 $233 19,405 17,248 $42,543 $46,429

    Dec-11 19,568 22,394 $42,424 $58,036 2,827 3,133 $6,130 $8,129 1,332 3,155 $4,021 $8,568 120 151 $482 $616 45 77 $137 $234 23,892 28,910 $53,194 $75,582

    Jan-12 21,558 21,483 $48,115 $56,456 3,103 2,985 $6,928 $7,850 655 2,490 $1,728 $6,969 93 124 $422 $538 43 35 $134 $134 25,452 27,117 $57,327 $71,948

    Feb-12 15,425 17,452 $39,688 $51,868 2,194 2,446 $5,649 $7,274 2,788 2,297 $7,639 $7,265 131 161 $554 $670 52 52 $167 $190 20,590 22,408 $53,697 $67,267

    Mar-12 17,054 19,225 $43,824 $56,982 2,373 2,705 $6,102 $8,022 1,621 2,132 $4,104 $7,308 144 190 $597 $693 60 104 $195 $394 21,252 24,356 $54,822 $73,400

    Apr-12 15,514 14,191 $40,158 $42,354 2,170 1,946 $5,621 $5,812 2,024 2,444 $5,705 $7,757 178 170 $691 $627 83 129 $281 $288 19,969 18,880 $52,455 $56,838

    May-12 18,152 16,698 $46,606 $49,238 2,604 2,303 $6,687 $6,791 1,791 2,732 $5,407 $8,609 1,974 2,116 $789 $1,439 51 - $173 $0 24,572 23,849 $59,663 $66,077

    Jun-12 18,245 15,154 $46,777 $45,132 2,573 2,011 $6,611 $5,992 3,434 4,584 $8,695 $13,559 3,924 2,747 $1,016 $1,714 172 0 $462 $0 28,348 24,496 $63,561 $66,397

    217,720 204,460 $505,981 $562,990 31,074 27,881 $72,198 $76,794 33,334 44,004 $82,974 $123,847 15,094 16,063 $8,942 $11,665 1,046 1,087 $2,868 $3,145 298,268 293,495 $672,963 $778,440

    Y-T-D 165,809 158,417 $372,440 426,266$ 23,727 21,621 53,278$ 58,198$ 26,085 34,244 63,167$ 93,922$ 9,018 11,030 6,446$ 7,885$ 740 958 $1,953 $2,857 225,379 226,270 $497,284 $589,128

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 21,419 29,014 $55,380 $84,701 2,902 4,070 $7,380 $11,878 4,630 5,082 $12,595 $16,614 2,997 5,911 $1,495 $3,325 153 132 $418 $470 32,101 44,208 $77,268 $116,989

    Aug-12 15,616 16,061 $39,854 $49,899 2,108 2,105 $5,383 $6,565 6,971 6,832 $18,523 $20,736 3,173 3,908 $1,361 $2,087 183 223 $488 $667 28,051 29,129 $65,610 $79,954

    Sep-12 14,397 11,770 $37,013 $24,337 1,948 1,525 $5,014 $2,964 5,797 4,348 $14,968 $13,389 3,303 2,324 $1,136 $1,278 164 263 $443 $830 25,609 20,230 $58,574 $42,797

    Oct-12 14,005 9,297 $37,055 $28,566 1,840 1,139 $4,893 $3,513 3,738 2,995 $10,044 $9,387 773 1,897 $734 $1,211 114 13 $323 $51 20,470 15,341 $53,050 $42,727

    Nov-12 12,426 10,406 $33,621 $31,367 1,554 1,422 $4,251 $4,282 3,034 4,481 $7,682 $13,782 158 868 $642 $896 76 101 $233 $351 17,248 17,278 $46,429 $50,678

    Dec-12 22,394 15,041 $58,036 $45,142 3,133 2,133 $8,129 $6,391 3,155 1,877 $8,568 $6,079 151 369 $616 $608 77 60 $234 $238 28,910 19,480 $75,582 $58,459

    Jan-13 21,483 16,185 $56,456 $48,945 2,985 2,306 $7,850 $6,964 2,490 4,117 $6,969 $13,298 124 145 $538 $576 35 52 $134 $215 27,117 22,805 $71,948 $69,998

    Feb-13 17,452 12,311 $51,868 $38,431 2,446 1,746 $7,274 $5,440 2,297 2,608 $7,265 $8,497 161 172 $670 ($1,227) 52 48 $190 $207 22,408 16,885 $67,267 $51,348

    Mar-13 19,225 12,436 $56,982 $38,855 2,705 1,736 $8,022 $5,420 2,132 2,125 $7,308 $7,021 190 184 $693 $778 104 59 $394 $241 24,356 16,540 $73,400 $52,315

    Apr-13 14,191 $42,354 1,946 $5,812 2,444 $7,757 170 $627 129 $288 18,880 $56,838

    May-13 16,698 $49,238 2,303 $6,791 2,732 $8,609 2,116 $1,439 0 $0 23,849 $66,077

    Jun-13 15,154 $45,132 2,011 $5,992 4,584 $13,559 2,747 $1,714 0 $0 24,496 $66,397

    204,460 132,521 $562,990 $390,244 27,881 18,182 $76,794 $53,417 44,004 34,465 $123,847 $108,803 16,063 15,778 $11,665 $9,532 1,087 951 $3,145 $3,269 293,495 201,896 $778,440 $565,265

    KSU UTILITY SUMMARY

    LAFENE HEALTH CENTERSALINAESARP VETMEDMAIN TOTAL

    Printed4/16/2013

  • FUEL OIL

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Aug-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Sep-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Oct-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Nov-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Dec-11 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Jan-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Feb-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Mar-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Apr-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    May-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Jun-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Y-T-D 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Aug-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Sep-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Oct-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Nov-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Dec-12 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Jan-13 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Feb-13 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Mar-13 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    Apr-13 0 $0 0 $0 0 $0 0 $0

    May-13 0 $0 0 $0 0 $0 0 $0

    Jun-13 0 $0 0 $0 0 $0 0 $0

    0 0 $0 $0 0 0 $0 $0 0 0 $0 $0 0 0 $0 $0

    KSU UTILITY SUMMARY

    ESARP VETMED TOTALMAIN

    Printed4/16/2013

  • REFUSE POWER PLANT SUPPLIES

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-11 $6,389 $6,862 $936 $1,005 $468 $502 $824 $824 $8,616 $9,193 Jul-11 $45,478 $23,871 $6,664 $3,498 $0 $0 $52,142 $27,368

    Aug-11 $7,247 $7,318 $1,062 $1,072 $530 $536 $824 $824 $9,663 $9,750 Aug-11 $15,065 $20,960 $2,207 $3,071 $0 $0 $17,272 $24,031

    Sep-11 $9,008 $8,294 $1,320 $1,215 $659 $607 $824 $824 $11,811 $10,940 Sep-11 $54,302 $39,351 $7,957 $5,766 $0 $0 $62,258 $45,117

    Oct-11 $7,325 $8,499 $1,073 $1,245 $536 $622 $824 $824 $9,759 $11,190 Oct-11 $308,544 $294,621 $70,979 $43,170 $0 $65,291 $379,523 $403,082

    Nov-11 $7,567 $6,542 $1,109 $959 $554 $479 $824 $766 $10,054 $8,745 Nov-11 $10,653 $29,262 $1,561 $4,288 $0 $0 $12,213 $33,550

    Dec-11 $6,408 $6,152 $939 $901 $469 $450 $824 $766 $8,640 $8,270 Dec-11 $9,290 $27,845 $1,361 $4,080 $0 $0 $10,651 $31,925

    Jan-12 $5,595 $6,369 $820 $933 $409 $466 $824 $766 $7,648 $8,535 Jan-12 $8,347 $39,276 $1,223 $5,755 $0 $0 $9,571 $45,031

    Feb-12 $5,743 $6,711 $841 $983 $420 $491 $824 $766 $7,828 $8,952 Feb-12 $30,137 $33,573 $4,416 $4,919 $0 $0 $34,553 $38,493

    Mar-12 $7,294 $7,327 $1,069 $1,074 $534 $536 $824 $766 $9,721 $9,703 Mar-12 $9,090 $8,732 $1,332 $1,280 $0 $0 $10,422 $10,012

    Apr-12 $7,573 $7,045 $1,110 $1,032 $554 $516 $824 $766 $10,061 $9,358 Apr-12 $23,019 $0 $3,373 $0 $0 $0 $26,392 $0

    May-12 $7,309 $7,646 $1,071 $1,120 $535 $560 $824 $813 $9,739 $10,139 May-12 $9,225 $94,176 $410 $13,799 $63 $0 $9,697 $107,976

    Jun-12 $6,094 $5,936 $893 $870 $446 $434 $824 $766 $8,257 $8,006 Jun-12 $3,296 $0 $483 $0 $0 $0 $3,779 $0

    $83,552 $84,701 $12,243 $12,411 $6,115 $6,199 $9,888 $9,471 $111,797 $112,781 $526,445 $611,668 $101,965 $89,625 $63 $65,291 $628,473 $766,584

    Y-T-D $62,576 $64,075 $9,169 $9,389 $4,579 $4,689 $7,416 $7,126 $83,741 $85,278 Y-T-D $490,905 $517,491 $97,700 $75,826 $0 $65,291 $588,605 $658,608

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual

    Jul-12 $6,862 $7,690 $1,005 $1,127 $502 $563 $824 $766 $9,193 $10,146 Jul-12 $23,871 $56,067 $3,498 $8,215 $0 $0 $27,368 $64,282

    Aug-12 $7,318 $8,300 $1,072 $1,216 $536 $607 $824 $766 $9,750 $10,890 Aug-12 $20,960 $321,279 $3,071 $47,076 $0 $27,669 $24,031 $396,023

    Sep-12 $8,294 $7,841 $1,215 $1,149 $607 $574 $824 $766 $10,940 $10,330 Sep-12 $39,351 $19,071 $5,766 $2,794 $0 $0 $45,117 $21,865

    Oct-12 $8,499 $8,783 $1,245 $1,287 $622 $643 $824 $766 $11,190 $11,479 Oct-12 $294,621 $38,276 $43,170 $5,608 $65,291 $0 $403,082 $43,885

    Nov-12 $6,542 $7,380 $959 $1,081 $479 $540 $766 $766 $8,745 $9,768 Nov-12 $29,262 $23,807 $4,288 $3,488 $0 $0 $33,550 $27,295

    Dec-12 $6,152 $6,758 $901 $990 $450 $495 $766 $766 $8,270 $9,009 Dec-12 $27,845 $31,461 $4,080 $4,610 $0 $0 $31,925 $36,071

    Jan-13 $6,369 $6,189 $933 $907 $466 $453 $766 $766 $8,535 $8,314 Jan-13 $39,276 $25,343 $5,755 $3,713 $0 $0 $45,031 $29,057

    Feb-13 $6,711 $6,389 $983 $936 $491 $468 $766 $766 $8,952 $8,558 Feb-13 $33,573 $0 $4,919 $0 $0 $0 $38,493 $0

    Mar-13 $7,327 $6,740 $1,074 $988 $536 $493 $766 $766 $9,703 $8,987 Mar-13 $8,732 $37,928 $1,280 $5,557 $0 $0 $10,012 $43,486

    Apr-13 $7,045 $1,032 $516 $766 $9,358 Apr-13 $0 $0 $0 $0

    May-13 $7,646 $1,120 $560 $813 $10,139 May-13 $94,176 $13,799 $0 $107,976

    Jun-13 $5,936 $870 $434 $766 $8,006 Jun-13 $0 $0 $0 $0

    $84,701 $66,072 $12,411 $9,681 $6,199 $4,835 $9,471 $6,894 $112,781 $87,482 $611,668 $553,231 $89,625 $81,063 $65,291 $27,669 $766,584 $661,963

    ESARPMAIN VET MED TOTALMAIN ESARP

    KSU UTILITY SUMMARY

    VETMED SALINA TOTAL

    Printed4/16/2013

  • ENERGY BOND PAYMENTS HEATING/COOLING DEGREE DAYS

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Estimated Actual Estimated Actual

    Jul-11 $934,301 $1,081,221 $136,899 $158,427 $117,569 $130,361 $37,416 $38,389 $0 $0 $1,226,185 $1,408,398 Jul-11 0.0 0.0 450.0 657.5

    Aug-11 $12,801 $13,208 $1,876 $1,935 $0 $0 $0 $0 $0 $0 $14,677 $15,144 Aug-11 0.5 0.0 457.0 480.5

    Sep-11 $53,534 $85,848 $7,844 $12,579 $0 $0 $0 $0 $0 $0 $61,378 $98,427 Sep-11 34.5 85.0 160.0 137.5

    Oct-11 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Oct-11 191.0 259.5 15.5 48.0

    Nov-11 $0 $13,208 $0 $1,935 $0 $0 $0 $0 $0 $0 $0 $15,144 Nov-11 605.5 635.0 0.0 0.0

    Dec-11 $12,801 $0 $1,876 $0 $0 $0 $0 $0 $0 $0 $14,677 $0 Dec-11 1,043.5 948.0 0.0 0.0

    Jan-12 $330,177 $347,693 $48,380 $50,946 $34,812 $32,950 $11,079 $10,486 $0 $0 $424,447 $442,075 Jan-12 1,262.0 928.5 0.0 0.0

    Feb-12 $13,208 $39,779 $1,935 $5,829 $0 $0 $0 $0 $0 $0 $15,144 $45,608 Feb-12 1,019.0 820.0 0.0 0.0

    Mar-12 $85,848 $0 $12,579 $0 $0 $0 $0 $0 $0 $0 $98,427 $0 Mar-12 688.5 283.0 6.0 46.0

    Apr-12 $0 $140,293 $0 $20,557 $0 $0 $0 $0 $0 $0 $0 $160,850 Apr-12 316.0 205.5 10.0 43.0

    May-12 $13,208 $13,627 $1,935 $1,997 $0 $0 $0 $0 $0 $0 $15,144 $15,624 May-12 163.0 35.0 105.5 206.0

    Jun-12 $0 $85,848 $0 $12,579 $0 $0 $0 $0 $0 $0 $0 $98,427 Jun-12 337.0 21.5 0.0 386.0

    $1,455,879 $1,820,727 $213,324 $266,784 $152,381 $163,311 $48,495 $48,875 $0 $0 $1,870,079 $2,299,697 5,660.5 4,221.0 1,204.0 2,004.5

    Y-T-D $1,442,671 $1,580,958 $211,389 $231,652 $152,381 $163,311 $48,495 $48,875 $0 $0 $1,854,936 $2,024,796 Y-T-D 4,844.5 3,959.0 1,088.5 1,369.5

    Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Estimated Actual Estimated Actual

    Jul-12 $1,081,221 $944,243 $158,427 $138,356 $130,361 $118,820 $38,389 $37,814 $0 $0 $1,408,398 $1,239,233 Jul-12 0.0 0.0 657.5 630.0

    Aug-12 $13,208 $19,793 $1,935 $2,900 $0 $0 $0 $0 $0 $0 $15,144 $22,693 Aug-12 0.0 0.5 480.5 339.0

    Sep-12 $85,848 $85,848 $12,579 $12,579 $0 $0 $0 $0 $0 $0 $98,427 $98,427 Sep-12 85.0 73.5 137.5 139.5

    Oct-12 $0 $114,173 $0 $16,729 $0 $0 $0 $0 $0 $0 $0 $130,903 Oct-12 259.5 340.5 48.0 21.0

    Nov-12 $13,208 $13,627 $1,935 $1,997 $0 $0 $0 $0 $0 $0 $15,144 $15,624 Nov-12 635.0 571.5 0.0 0.0

    Dec-12 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Dec-12 948.0 960.0 0.0 0.0

    Jan-13 $347,693 $271,710 $50,946 $39,813 $32,950 $20,971 $10,486 $7,367 $0 $0 $442,075 $339,861 Jan-13 928.5 1,011.0 0.0 0.0

    Feb-13 $39,779 $14,059 $5,829 $2,060 $0 $0 $0 $0 $0 $0 $45,608 $16,119 Feb-13 820.0 916.0 0.0 0.0

    Mar-13 $0 $85,848 $0 $12,579 $0 $0 $0 $0 $0 $0 $0 $98,427 Mar-13 283.0 847.0 46.0 0.0

    Apr-13 $140,293 $20,557 $0 $0 $0 $160,850 Apr-13 205.5 43.0

    May-13 $13,627 $1,997 $0 $0 $0 $15,624 May-13 35.0 206.0

    Jun-13 $85,848 $12,579 $0 $0 $0 $98,427 Jun-13 21.5 386.0

    $1,820,727 $1,549,302 $266,784 $227,013 $163,311 $139,792 $48,875 $45,181 $0 $0 $2,299,697 $1,961,288 4,221.0 4,720.0 2,004.5 1,129.5

    SALINA

    KSU UTILITY SUMMARY

    HeatingVETMED LAFENE HEALTH TOTALSESARP CoolingMAIN

    Printed4/16/2013

  • Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    PROJECTED $148,183 $153,144 $190,711 $164,992 $204,281 $171,289 $193,443 $238,556 $196,242 $193,411 $150,308 $159,835 151,257$ 165,290$ 213,219$ 170,034$ 220,447$ 134,968$ 144,432$ 225,278$ 182,812$ 201,345$ 176,093$ 156,715$

    ACTUAL $151,257 $165,290 $213,219 $170,034 $220,447 $134,968 $144,432 $225,278 $182,812 $201,345 $176,093 $156,715 206,358$ 229,779$ 252,164$ 265,079$ 245,092$ 193,837$ 216,634$ 247,976$ 239,924$ -$ -$ -$

    ($3,074) ($12,146) ($22,508) ($5,042) ($16,166) $36,321 $49,011 $13,278 $13,430 ($7,935) ($25,785) $3,120 ($55,102) ($64,490) ($38,945) ($95,046) ($24,645) ($58,869) ($72,202) ($22,698) ($57,112) $201,345 $176,093 $156,715

    Annual Projected Receipts Annual Projected Receipts

    Actual Receipts

    KANSAS STATE UNIVERSITY FACILITIES CHARGE OUTMarch 2013

    FY12 FY13

    $2,164,396 $2,141,890

    $2,141,890 Y-T-D Actual Receipts $2,096,844

    (Above)/Below Annual Projection $22,506 (Above)/Below Annual Projection $45,046

    $0

    $50,000

    $100,000

    $150,000

    $200,000

    $250,000

    $300,000

    Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Projected Actual

    Printed4/16/2013

  • OTHER (Charge-out)Projected Actual Under/

    FY12 Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Total Total (Over)

    Jul-11 1,418,297 1,273,890 98,435$ 92,296$ 3,223 3,365 26,836$ 24,836$ 6,725 8,818 9,014$ 13,361$ 6,500 8,236 13,899$ 20,764$ $148,183 $151,257 ($3,074)

    Aug-11 1,459,671 1,232,221 103,906$ 94,062$ 2,955 3,956 25,424$ 34,087$ 7,168 9,320 9,634$ 14,108$ 6,646 9,106 14,180$ 23,033$ $153,144 $165,290 ($12,146)

    Sep-11 1,701,571 1,785,626 127,958$ 139,422$ 3,720 3,089 27,286$ 23,773$ 10,460 12,440 13,942$ 18,747$ 10,073 12,359 21,525$ 31,276$ $190,711 $213,219 ($22,508)

    Oct-11 1,375,392 1,385,938 96,877$ 95,314$ 4,836 2,955 35,594$ 22,262$ 9,528 13,049 12,679$ 19,653$ 9,272 12,963 19,841$ 32,804$ $164,992 $170,034 ($5,042)

    Nov-11 1,470,426 1,547,414 102,767$ 107,742$ 8,030 7,527 50,692$ 51,136$ 14,772 15,261 19,531$ 22,911$ 14,604 15,261 31,290$ 38,658$ $204,281 $220,447 ($16,166)

    Dec-11 1,129,305 1,085,852 70,091$ 70,714$ 10,881 8,319 73,760$ 55,811$ 7,893 2,045 10,504$ 3,239$ 7,891 2,045 16,934$ 5,204$ $171,289 $134,968 $36,321

    Jan-12 1,105,966 966,719 72,139$ 66,442$ 15,596 9,156 103,763$ 63,434$ 4,898 3,464 6,722$ 5,521$ 4,897 3,464 10,819$ 9,035$ $193,443 $144,432 $49,011

    Feb-12 1,388,724 1,466,300 93,218$ 96,615$ 15,279 13,231 104,721$ 87,667$ 10,053 8,541 15,143$ 15,925$ 10,051 8,541 25,474$ 25,071$ $238,556 $225,278 $13,278

    Mar-12 1,255,917 1,264,366 83,766$ 88,931$ 10,846 7,452 71,696$ 58,960$ 10,106 7,273 15,212$ 13,585$ 10,102 7,271 25,569$ 21,336$ $196,242 $182,812 $13,430

    Apr-12 1,315,452 1,472,243 92,425$ 111,314$ 8,638 5,180 61,486$ 40,503$ 9,805 10,283 14,707$ 19,143$ 9,739 10,277 24,792$ 30,384$ $193,411 $201,345 ($7,935)

    May-12 1,095,621 1,314,111 81,167$ 101,784$ 4,784 3,324 35,508$ 24,346$ 8,364 10,415 12,598$ 19,430$ 8,294 10,347 21,036$ 30,533$ $150,308 $176,093 ($25,785)

    Jun-12 1,291,495 1,262,035 96,179$ 102,579$ 3,721 2,278 36,592$ 17,754$ 6,739 7,695 10,246$ 14,379$ 6,597 7,436 16,818$ 22,003$ $159,835 $156,715 $3,120

    16,007,837 16,056,715 $1,118,928 $1,167,217 92,509 69,832 $653,359 $504,569 106,511 108,604 $149,932 $180,003 104,666 107,306 $242,176 $290,102 $2,164,396 $2,141,890 $22,506

    Y-T-D 12,305,269 12,008,326 $849,157 851,540$ 75,366 59,050 519,773$ 421,966$ 81,603 80,211 112,381$ 127,050$ 80,036 79,246 179,531$ 207,181$ $1,660,841 $1,607,737

    Projected Actual Under/

    FY13 Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual Total Total (Over)

    Jul-12 1,273,890 1,388,710 92,296$ 109,645$ 3,365 5,161 24,836$ 51,970$ 8,818 9,686 13,361$ 18,104$ 8,236 9,053 20,764$ 26,639$ 151,257$ $206,358 ($55,102)

    Aug-12 1,232,221 1,530,105 94,062$ 121,802$ 3,956 6,280 34,087$ 61,633$ 9,320 10,016 14,108$ 18,680$ 9,106 9,383 23,033$ 27,664$ 165,290$ $229,779 ($64,490)

    Sep-12 1,785,626 1,507,871 139,422$ 118,479$ 3,089 6,694 23,773$ 66,592$ 12,440 14,190 18,747$ 26,369$ 12,359 13,782 31,276$ 40,724$ 213,219$ $252,164 ($38,945)

    Oct-12 1,385,938 1,621,089 95,314$ 119,934$ 2,955 6,936 22,262$ 70,412$ 13,049 15,670 19,653$ 29,105$ 12,963 15,434 32,804$ 45,628$ 170,034$ $265,079 ($95,046)

    Nov-12 1,547,414 1,298,365 107,742$ 95,716$ 7,527 8,673 51,136$ 91,568$ 15,261 12,002 22,911$ 22,320$ 15,261 12,002 38,658$ 35,488$ 220,447$ $245,092 ($24,645)

    Dec-12 1,085,852 1,094,712 70,714$ 79,146$ 8,319 8,026 55,811$ 72,784$ 2,045 8,685 3,239$ 16,206$ 2,045 8,680 5,204$ 25,701$ 134,968$ $193,837 ($58,869)

    Jan-13 966,719 1,046,552 66,442$ 78,326$ 9,156 12,529 63,434$ 116,837$ 3,464 4,386 5,521$ 8,373$ 3,464 4,386 9,035$ 13,099$ 144,432$ $216,634 ($72,202)

    Feb-13 1,466,300 1,221,879 96,615$ 92,838$ 13,231 11,547 87,667$ 102,764$ 8,541 10,309 15,925$ 20,823$ 8,541 10,309 25,071$ 31,550$ 225,278$ $247,976 ($22,698)

    Mar-13 1,264,366 1,180,009 88,931$ 89,470$ 7,452 10,067 58,960$ 96,784$ 7,273 10,567 13,585$ 21,332$ 7,271 10,567 21,336$ 32,338$ 182,812$ $239,924 ($57,112)

    Apr-13 1,472,243 111,314$ 5,180 40,503$ 10,283 19,143$ 10,277 30,384$ 201,345$ $201,345

    May-13 1,314,111 101,784$ 3,324 24,346$ 10,415 19,430$ 10,347 30,533$ 176,093$ $176,093

    Jun-13 1,262,035 102,579$ 2,278 17,754$ 7,695 14,379$ 7,436 22,003$ 156,715$ $156,715

    16,056,715 11,889,292 $1,167,217 $905,355 69,832 75,913 $504,569 $731,345 108,604 95,511 $180,003 $181,313 107,306 93,596 $290,102 $278,831 $2,141,890 $2,096,844 $45,046

    Electricity Gas Water Sewer

    KSU UTILITY CHARGE-OUT SUMMARY

    Electricity Gas Water Sewer

    Printed4/16/2013