K6000010 RevB
-
Upload
baskar-kannaiah -
Category
Documents
-
view
76 -
download
1
description
Transcript of K6000010 RevB
TOTAL NO. OF SHEET ( 1 ) 1/26
2 TPOT DAMIR GLAVANTPOT
4
CHOPRA
ITEM DWG. NO. REV NO
B SC LEE 15/03/2008A PJ DING 04/03/2008
REV. NO REVISED BY REV. DATE
QA/QC
1 ZULAIHA
BD 1 SC LEEHC JC CHEN
HFP
MF MV RAOEF CH LER
9 SECTION
ABSCLASS :
REV. BSCALE: N/A
JSPL DWG NO.
K6000010
SECTION MANAGER
TPOT DWG NO.
QUANTITY : ONE VESSEL
METERING SKID LIFTING PROCEDURE
QUEENSWAY FSO
15/03/2008
DRAWER
CHARG. ENG
PROJECT:
TPO17-JSPL-NA-PR-0004
LIST OF REFERENCED DRAWINGS AND DOCUMENTS USED FOR DRAWINGS
PROJECT MANAGER
DESCRIPTION OF REVISION
DRAWING NO. OR DOCUMENTS TITLE
JOB NO.
21-9381
RE-ISSUED FOR APPROVALHP MGR
EST
SALES
1
GENERAL MANAGER
CHECKER
DATE ISSUED
DATE DRAWN
EN
GIN
EE
RIN
GD
EP
AR
TME
NT
PJM
HFF
BIBLIOGRAPHY
CLASS
OWNER
ME MGR
HP
ME
HS
CENT. FILES
ENGINEERING DEPARTMENT
JURONG SHIPYARD PTE LTDSINGAPORE
DISTRIBUTIONTOTAL
BH LEE
ANAND
HS MGR
ISSUE FOR APPROVAL
PJM
PF
PF MGR
SEATECH
PREPARED BY JSPL'S ENGINEERING DEPARTMENT.FOR HULL NO : 21-9381
IFC
BF/HC
(A Subsidiary of SembCorp Marine Ltd)
Certificate Number: 31453
m
lytilauQSBA
avE
Management Syste
.
noitacifitreC
cnI
snoitau
,
1 GENERAL 3
2 CONDITION OF THE EQUIPMENTS TO BE LIFTED 3
3 INSPECTION 3
4 CHAIN OF COMMAND 4
5 ENVIRONMENTAL CRITERIA 5
6 LIFTING OPERATION 5
7 LIFTING CAPACITY 6
8 RIGGING ARRANGEMENT 7
9 MOORING PLAN 7
10 APPENDIX 1 LIFTING PLAN 8
11 APPENDIX 2 RIGGING ARRANGEMENT 11& CG LOCATION
12 APPENDIX 3 SPREADER BEAM STRESS ANALYSIS & 13SLING AND SHACKLES STRENGTH CALCULATION
13 CERTIFICATES 22
TABLE OF CONTENT
2/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
1. GENERAL
1.1 Lifting of Metering Skid to be carried out according to this procedure so as to
ensure that all safety aspects have been met.
1.2 Yard’s project manager to inform all parties concerned two days before the lift.
1.3 Job Safety Analysis (JSA) shall be performed by the yard to all yard personnel
that involved in this lifting before lift.
2. CONDITIONS OF THE EQUIPMENTS TO BE LIFTED
2.1 Metering Skid shall be as near to planned condition as possible. All primary
welding are to be completed, inspected, ndt’d and signed.
2.2 All spare parts or components and loose items installed during the erection
process are to be firmly secured in their positions, and care to be taken when
welding to secure external structure so no damage occurs. Tack welding shall be
avoided. All hinged, swinging and movable items shall be secured in their normal
positions.
2.3 The area where the Metering Skid is going to be set is also to be inspected in the
same manner. Guide pieces for setting are also to be fitted.
2.4 All area on the Metering Skid shall be free of any standing liquid prior to lifting.
3. INSPECTION
3.1 Prior to lifting, Owner, Yard and crane barge operator / lifter are to verify all lifting
gears used tally with submitted certificates. Crane operators / lifter are allowed
to substitute or add shackles and slings provided if it does not jeopardize the
safety of the operation and the lifting gears must come with a valid certificate.
Crane barge operators/ lifter must obtain approval from owner, project manager
and LOC surveyor for changes prior to lifting.
3.2 Owner, Marine Warranty Surveyor (MWS) and Yard are to conduct a joint
inspection of the metering skid before the lifting operation to identify & clarify
weights, loose items to be removed, checking that items are secured as well as
general condition of the equipments. Any fitting which may cause delay to the
3/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
operations is to be removed. Before inspection a joint J.S.A./tool box meeting is
to be organized.
3.3 Carry out MPI for lifting lug before lifting, NDT & visual records of the lifting points
are to be submitted by FMC (QA) to the owner for inspection prior to
commencement of lifting operation. This should be done by FMC.
3.4 Check that all sea fastening have been removed before lift.
3.5 Before the lift, MWS, Owner, Yard and Crane operator are to check whether the
lifting gears are correctly rigged.
3.5 Safety officer from yard will monitor the whole process and barricade will be set
up. A heavy lifting permit will be approved by the safety officer before lift.
4. CHAIN OF COMMAND
Before starting the lifting procedure, the chief-in-command responsible for the decision
to proceed with the operation should be satisfied that the following conditions are
complied with:
4.1 The environmental conditions including the weather forecasts are such that the
operations can be completed in a well controlled manner and in accordance with
the design assumptions of this procedure.
4.2 All personnel should be properly brief and are standing by.
4.3 The crane and all equipment for the operation are correctly rigged and ready to
be used.
4.4 Obstacles which may unduly delay the operations have been removed.
Chief –In CommandYard Project Manager
Owner Representative
Yard Operation Personnel
Qualified lifter & Shore Crane
Operators
EngineeringBH LEE
MWS
4/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
Communication between Yard operation team, Shore crane operators and lifter is
via mobi-talk or walkie- talkie.
5. ENVIRONMENTAL CRITERIA REV B
The condition of wind, wave and current must be favorable to ensure a safe lift. The
operation may be delayed or postponed if conditions exist are likely to preclude safety.
All passing vessel are to be warned and slowed down to minimize the wave and swell.
This will be done using alarm horns.
Tide The lifitng operation can be conducted any time during the day.
Consensus Lifting operation shall not be initiated unless the floating crane Master, lifter, owner,
JSPL representative, MWS, all parties agree that the lifting conditions are safe.
6. LIFTING OPERATION
6.1 Rig up slings and shackles
6.2 Metering Skid is lifted from original position (transportation barge with size 46m
(L) x 15m (B) x 3.5m (H) by floating crane barge PWL 1501. REV B
6.3 At the beginning of lifting, the crane load should be gradually increased until the
metering skid is free from the supporting point, check and confirm the load status
is in order.
6.4 When the skid is lifted up 300MM from the supporting level, check the balancing
of the skid and determine if the level should be adjusted.
6.5 Continue the lifting process.
6.6 Raise the crane hook; adjust the height of the hooks to achieve designed height.
Metering skid (hanging) moved towards to the installed location (lifting plan see
appendix 1).
5/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
6.7 The skid is slowly lowered to its installed location. All guide piece and marking
shall be properly aligned. The skid is held by slings in final position and secured
in position.
6.8 Release the crane’s hook when installation process is done and inspected by
both owner representative and yard project manager.
7. LIFTING CAPACITY REV B
Metering Skid Particulars:
Weight = 59.528 mt
Size 17.8m x 6.25m x 9.6m
CG Location: Refer to Appendix 2 Rigging arrangement & CG location
Transportation Barge:
Barge dimensions are 46m x 15m x 3.5m Floating Crane:
PWL-1501 1500mt Floating sheer leg crane
Crane boom: 80m A-frame
Hook: 2 x 750mt main hooks and 1 x 200mt auxiliary hook
Crane Capacity (Aux hook):
Outreach 45 m
Lifting Capacity @ 45m 200 mt
Maximum hook height (from floating
crane main deck) @ 45m 73 m
Boom Angle 58 deg
Refer to Appendix 1 Lifting Plan for details.
6/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
8. RIGGING ARRANGEMENT REV B
The detail of the rigging arrangement is shown in Appendix 2. The conceptual of the
arrangement is based on rigging arrangement that proposed by FMC. Spreader bar
stress calculation (by FMC), sling and shackle strength calculation (by JSPL) are shown
in appendix 3. All slings and shackles certificates are attached in Appendix 4.
Spreader beam
1 set of Steel 80mt spreader beam 6m (L) x 400mm x 32MM I section with two lifting pad
eyes on top and bottom (by FMC).
Slings
• Ø 64mm x 8m , Steel wire sling c/w soft eye both ends both ends, Proof load
109.6mt (by Pacific Workboat, PWL).
• Ø 78mm x 12m, Cable Laid Grommet, Maximum Test Load 478mt, (by Pacific
Workboat, PWL).
Shackle
• Crosby G-2130 SWL 85mt x 2 sets (by PWL)
• SWL 55mt x 4 sets (by PWL)
• Green Pin SWL 85mt x 4 sets (by PWL)
9. MOORING PLAN REV B
Refer to Appendix 1 Lifting Plan for floating crane and barge mooring plan.
In general, the mooring lines are pre-set prior to lifting so as to ensure a smooth
maneuvering from transport barge to vessel. Detail mooring arrangement to be decided
on site based on crane barge’s Captain’s requirement and to the satisfaction of MWS
site surveyor.
Two tug boats should be available for the lifting operation.
7/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
APPENDIX 1
LIFTING PLAN
8/26
9/26
10/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
APPENDIX 2
RIGGING ARRANGEMENT & CG LOCATION OF METERING SKID
11/26
12/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
APPENDIX 3
SPREADER BEAM STRESS ANALYSIS, SLINGS AND SHACKLES
STRENGHT CALCULATION
13/26
14/26
15/26
16/26
17/26
18/26
19/26
METERING SKID RIGGING CALCULATION
CALCULATED WEIGHT 59.60 L1 5329CONTINGENCY FACTOR 1.10 10% of 59.6mt L2 6277GROSS WEIGHT 65.56 L3 2910DYNAMIC FACTOR 1.00 lift from quay side L4 3183LIFT WEIGHT 65.56RIGGING WEIGHT 4.20 7% of 59.6mtHOOK LOAD 69.76
RIGGING WEIGHTT1 T2 T3 T4 SPREADE
R UPPER TOTAL
0.75 0.75 0.75 0.75 1.2 4.2
SLING FORCEPLANE T1 T2 T3 T4ANGLE 60 64 60 64
PADEYE RESOLVED LIFT WEIGHT ( VERTICAL LOAD AT EACH PADEYE )T1 + T2 = 34.25
T3 + T4 = 31.31
T1 T2 T3 T4 TOTAL
18.52 15.73 16.93 14.38 65.56
VERTICAL PADEYE LOAD = PADEYE RESOLVED LIFT WEIGHT X SKLT1 T2 T3 T4
23.15 19.66 21.17 17.97
RESOLVED PADEYE LOAD = VERTICAL PADEYE LOAD / SIN ( SLING ANGLE )
T1 T2 T3 T4 SKEW LOAD FACTOR 1.25
26.74 21.87 24.44 19.99
SLING FORCE = (VERTICAL LOAD + SLING WEIGHT)/ SIN ( SLING ANGLE )T1 T2 T3 T4
27.60 22.70 25.31 20.83
L1L2 300 mm
COG SHIFTING L3L4 150 mmCG SHIFT TO T1 CG SHIFT TO T3L1 5029 L1 5029L2 6577 L2 6577L3 2760 L3 3060L4 3333 L4 3033T1 + T2 = 35.86 T1 + T2 = 32.63T3 + T4 = 29.70 T3 + T4 = 32.93T1 T2 T3 T4 T1 T2 T3 T4
20.32 15.54 16.83 12.87 18.49 14.14 18.66 14.27
CG SHIFT TO T2 CG SHIFT TO T4L1 5629 L1 5629L2 5977 L2 5977L3 2760 L3 3060L4 3333 L4 3033T1 + T2 = 35.86 T1 + T2 = 32.63T3 + T4 = 29.70 T3 + T4 = 32.93T1 T2 T3 T4 T1 T2 T3 T4
19.62 16.25 15.29 14.40 16.81 15.83 16.96 15.97
SUMMARY OF SLING VERTICAL LOAD T1 T2 T3 T4
BASE CASE 18.52 15.73 16.93 14.38
CG SHIFT TO T1 20.32 15.54 16.83 12.87
CG SHIFT TO T3 18.49 14.14 18.66 14.27
CG SHIFT TO T2 19.62 16.25 15.29 14.40
CG SHIFT TO T4 16.81 15.83 16.96 15.97MAX VERTICAL UPPER SLING LOAD 20.32 16.25 18.66 15.97
20/26
SHACKLE CHECK
Max Expected load = Max. Vertical Upper Sling Load x Skew Load Factor
LIFT POINT SHACKLE SWL MAX
EXPECTED LOAD
SLING FORCE
SLING FORCE/
DYNAMIC FACTOR
FACTOR OF SAFETY COMMENTS
T1 SWL 55T CROSBY G-2130 55 25.40 30.20 30.20 1.82 OK
T2 SWL 55T CROSBY G-2130 55 20.31 23.43 23.43 2.35 OK
T3 SWL 55T CROSBY G-2130 55 23.32 27.80 27.80 1.98 OK
T4 SWL 55T CROSBY G-2130 55 19.96 23.04 23.04 2.39 OK
SLING CHECKMIN REQUIRED MBL = SLING LOAD X 2.25 / MIN(TERMINATION EFF., BENDING EFF)
FACTOR OF SAFETY = SLING MBL X MIN ( TERMINATION EFF., BENDING EFF) / SLING LOAD
LIFTING POINT SLING SLING Φ PIN Φ PIN/SLING BENDING FACTOR
TERMINATION EFF
GOVERNING FACTOR
T1 64mm X 8m 64 65 1.02 0.50 0.75 0.50
T2 64mm X 8m 64 65 1.02 0.50 0.75 0.50
T3 64mm X 8m 64 65 1.02 0.50 0.75 0.50
T4 64mm X 8m 64 65 1.02 0.50 0.75 0.50
LIFTING POINT LOAD GOV. FACTOR
MIN REQD MBL
USED MBL
FACTOR OF SAFETY COMMENTS
T1 30.20 0.50 134.86 219.20 3.66 OK
T2 23.43 0.50 104.61 219.20 4.71 OK
T3 27.80 0.50 124.13 219.20 3.97 OK
T4 23.04 0.50 102.90 219.20 4.79 OK
21/26
21-9381 FSO QUEENSWAY METERING SKID INSTALLATION PROCEDURE
PREPARED BY ENGINEERING DEPARTMENT
APPENDIX 4
CERTIFICATES
(FOR THOSE CERTIFICATES ARE NOT ATTACHED IN THIS REVISION
WILL BE PROVIDED ONE DAY BEFORE LIFT i.e 17 MARCH 2008)
23/26
€ngsGonsultlng 438 Alexandra Road#09-01 Alexandra Point
Singapore 1t9958Tel: (65) 6270 8663 / Fax: (65) 6270 9987
Page l of I
sG-1704572-132Project lD Number: Repo.t Number: Office Location:
WITNESS INSPECTION & TESTINGof
USED GREEN PIN SHACKLES
rhis is fo certify thatthe undersigned representative of ABS consulting, did at the requestof Messrs.
FRANKLIN OFFSHORE INTERNATIONAL PTE LTD
attend at the yard premises of 11, Pandan Road, Yard Premises, Singapore, on the 04thApril 2007 and dates thereafter, to witness and inspect the captioned equipment.We report as follows :
L-1501-GP55T-1L-1501-GP55T-2L-150't-55T-3L-1501-55T-4
4 pcs Used Green PinNut Shackles.s.w.L. :Proof Load Applied :
Bow Bolt and
55.0 m.ton110.0 m.ton
Upon completion of tension test, above shackles were laid on workshop and visuallyexamined on body, pin and nut assemblies. All shackles were visually inspected with novisible defects found.
Calibration of the testing machine traceable to DNV certificate DNV/SUC2OO61974 dated18 Oct 2006.
This factual statement of the visual inspection and test carried out andis issued
LeongSurveyor,ABS
Thiscert i fcalsorreport is9rantedol issUsdsUbj€ct lot . tecondi t ionl ,hat i t isUnde6tood€ndagredlhatnohinghe� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �sUpp| .sr ' rep6ireroroPeratolofanywafanty 'expressor imp| i€dandABsGconsU|t jn9lnc ' l lsbi | i tysh6| |bel imi tedtotheactsandornissionsof i tsemp|oyees'agenF'andsUbcon|rac|oG.lJndernocircums|ancewhalso€v€.sha||ABsGconsU|tiag|nc'be|iab|efolanyiniUrordamageto€nype6onolprope'tyoccUlringbyrea5ond���������������misuseofolanydefecl inmateda|s 'macniner,eqUipmentoroth€. i t€msothel lhandefec|s in. tsrnsactUa| |y inspectedbyAasGconsu| l ing|nc-anda� |nab|gbynoma||yac6p|gdlssting3|andards.ordsisctsrfectedindocumenlsrsvi€w€dbyABsGconsU|tin9|nc,andssced,ainab|€bynona|lyacceptedtestingstandal(ts'oldefectsrefddiid�menisreviewed by ABSG Consulting Inc. and which are covered by this cedificate or rsporr.
Conditioi, Damage, P&t, Machinery, & Cargo Surveys / Owner's Rep. / Ctass Record Reviews
24/26
25/26
26/26