FACTORS AFFECTING IN THE PREPARATION OF CONSTRUCTION WORK SCHEDULE JUSTIN BONG CHUNN TAT UNIVERSITI TEKNOLOGI MALAYSIA

Transcript of justinbongchunntatma081181ttt

Page 1: justinbongchunntatma081181ttt

FACTORS AFFECTING IN THE PREPARATION OF CONSTRUCTION

WORK SCHEDULE

JUSTIN BONG CHUNN TAT

UNIVERSITI TEKNOLOGI MALAYSIA

Page 2: justinbongchunntatma081181ttt

PSZ 19:16 (Pind. 1/07)

DECLARATION OF THESIS / POSTGRADUATE PROJECT PAPER AND COPYRIGHT

Author’s full name :

Date of birth : Title : Academic Session :

I declare that this thesis is classified as: I acknowledged that Universiti Teknologi Malaysia reserves the right as follows :

1. The thesis is the property of Universiti Teknologi Malaysia. 2. The Library of Universiti Teknologi Malaysia has the right to make copies for the purpose

of research only. 3. The Library has the right to make copies of the thesis for academic exchange.

Certified by:

SIGNATURE SIGNATURE OF SUPERVISOR

(NEW IC NO. /PASSPORT NO.) NAME OF SUPERVISOR Date : Date :

NOTES : * If the thesis is CONFIDENTIAL or RESTRICTED, please attach with the letter from the organisation with period and reasons for confidentiality or restriction.

UNIVERSITI TEKNOLOGI MALAYSIA

CONFIDENTIAL (Contains confidential information under the Official Secret Act 1972)*

RESTRICTED (Contains restricted information as specified by the

organisation where research was done)* OPEN ACCESS I agree that my thesis to be published as online open access

(full text)

JUSTIN BONG CHUNN TAT

10 NOVEMBER 1985

FACTORS AFFECTING IN THE PREPARATION OF CONSTRUCTION WORK SCHEDULE

2008/2009

851110-13-6327

25 JUNE 2009 25 JUNE 2009

PROF DR MUHD ZAIMI ABD MAJID

Page 3: justinbongchunntatma081181ttt

“I hereby declare that I have read this thesis and in my opinion this thesis is sufficient

in terms of scope and quality for the award of the degree of Master of Science

(Construction Management)”

Signature : ……………………………………

Name of Supervisor : Prof. Dr. Muhd Zaimi Abdul Majid

Date : 30 JUNE 2009

Page 4: justinbongchunntatma081181ttt

FACTORS AFFECTING IN THE PREPARATION OF CONSTRUCTION

WORK SCHEDULE

JUSTIN BONG CHUNN TAT

A project report submitted in partial fulfillment of the requirements for the award of

the degree of Master of Science (Construction Management)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

30 JUNE 2009

Page 5: justinbongchunntatma081181ttt

ii

“I declare that this project report entitled “Factors Affecting in the Preparation of

Construction Work Schedule” is the result of my own research except as cited in the

references. The report has not been accepted by any degree and is not concurrently

submitted by any candidature of any other degree.”

Signature : ……………………………….....

Name : JUSTIN BONG CHUNN TAT

Date : 30 JUNE 2009

Page 6: justinbongchunntatma081181ttt

iii

DEDICATION

Especially to my beloved father, mother, brother,

and all my friends.

Page 7: justinbongchunntatma081181ttt

iv

ACKNOWLEDGEMENT

I wish to express my sincere appreciation to my supervisor Professor Dr.

Muhd Zaimi Abdul Majid for his effort, encouragement and guidance.

In preparing this project, I was in contact with many industry practitioners.

They have given me tips and useful information in order for me to complete the data

sourcing. I am very thankful for them.

Last but not least, I am grateful to all my family members and friends for their

support and understanding and providing me the fundamentals of character and work

ethics to complete this task. Moreover, for their prayers, courage and understanding

for me in my endurance to complete this mission.

Page 8: justinbongchunntatma081181ttt

v

ABSTRACT

Construction scheduling is widely used in many construction projects today

but there still exists a large disparity in the proper use of this tool. Many projects

schedule is created at the beginning of the project and never reviewed or revised until

a problem arises. Besides, contractors lack the skills necessary for preparing good

construction schedule. Therefore, the objectives of this study are to investigate the

factors affecting the preparation of better construction schedule; establish the severity

of these factors; and the methods of improvements for preparing better construction

schedule. Comprehensive literature review has been conducted to gather the

information on the factors affecting the preparation of construction work schedule

followed by structured questionnaire distribution as a main tool to gain data to

establish the severity of these factors. The data attained were analyzed using average

index and frequency analysis. From the analysis highlighted, there were thirty-five

(35) factors where these factors were divided into four (4) main categories which

were project specific factors, project management, working condition and external

environment related factors. Hence, the results showed the top three factors that have

the highest rank were complexity of project, identification of critical activities and

type of project involved. In conclusion, the study also identified recommendations

that can be used by the project participants in order to prepare effective and good

construction work schedule in the local construction industry.

Page 9: justinbongchunntatma081181ttt

vi

ABSTRAK

Penjadualan kerja pembinaan digunakan secara meluas dalam banyak projek-

projek pembinaan hari ini tetapi cara penggunaannya masih tidak betul dan tepat.

Kebanyakan penjadualan projek dihasilkan pada permulaan projek tidak pernah dikaji

atau disemak semula sehingga sesuatu masalah muncul. Selain itu, ramai kontraktor

tidak mempunyai kemahiran yang mencukupi dalam penjadualan kerja pembinaan.

Oleh demikian, objektif kajian merangkumi penyiasatan factor-faktor dalam

mempengaruhi persediaan penjadualan kerja pembinaan yang lebih baik,

mengenalpasti tahap kritikal setiap faktor dan pengenalpastian kaedah peningkatan

penyediaan jadual kerja pembinaan yang lebih berkesan. Kajian literatur secara

komprehensif telah dilakukan untuk mengumpul maklumat mengenai faktor-faktor

yang menyebabkan kelemahan prestasi projek prmbinaan melalui kajian sebelum ini.

Seterusnya, kajian soal selidik telah dilakukan untuk mengumpul data bagi

mengenalpasti tahap kritikal setiap faktor. Data-data yang diperolehi dianalisis

menggunakan index purata dan analisis frequensi. Keputusan kajian menunjukkan

terdapt 35 faktor penyebab dikenalpasti dimana faktor-faktor itu dibahagikan kepada

4 kategori utama iaitu faktor khusus projek; pengurusan projek; keadaan kerja dan

faktor luaran. Dari analisis, 3 faktor utama yang mempunyai tahap kritikal tertinggi

adalah kerumitan projek, pengenalpastian aktiviti-aktiviti genting dan jenis projek

yang terlibat. Kajian ini juga memberi cadangan-cadangan yang boleh digunakan

oleh pihak-pihak yang terlibat dalam projek untuk menyediakan jadual kerja

pembinaan yang lebih efektif dan berkesan dalam ndustri pembinan tempatan.

Page 10: justinbongchunntatma081181ttt

vii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v

ABSTRAK vi

TABLE OF CONTENTS vii

LIST OF TABLES xii

LIST OF FIGURES xiii

LIST OF APPENDIXES xiv

1 INTRODUCTION

1.1 Introduction 1

1.2 Background of Study 2

1.3 Problem Statement 4

1.4 Aim and Objectives of the Study 6

1.5 Scope of the Study 7

1.6 Significance of the Study 7

1.7 Research Methodology 8

1.8 Summary 8

Page 11: justinbongchunntatma081181ttt

viii

CHAPTER TITLE PAGE

2 LITERATURE REVIEW

2.1 Introduction 10

2.2 Importance of Construction

Work Scheduling 10

2.2.1 Benefits of Construction Work Schedule 12

2.2.2 Developing a Construction Work Schedule 13

2.3 Construction Work Scheduling Techniques 14

2.3.1 Bar Charts 15

2.3.2 Critical Path Method 15

2.3.3 Choosing the Right Scheduling

Method 18

2.4 Developing Scheduling Specifications 19

2.5 Responsibility of Schedule Preparation 20

2.5.1 The Clients / Owners 22

2.5.2 The Construction Manager 22

2.5.3 The Designers 24

2.5.4 The Contractor and Subcontractors 24

2.5.5 The Design-Build Firm 25

2.5.6 Fabricators and Vendors 25

2.6 Sources of Planning Work Schedule 26

2.6.1 Construction Materials 26

2.6.2 Machineries and Equipments 26

2.6.3 Labours and Manpower 27

2.6.4 Finance 27

2.6.5 Time 28

2.7 Control and Monitor Construction Work

Schedule 28

2.8 Characteristics of Good Construction Work

Schedule 29

2.8.1 The Plan 29

2.8.2 Subcontractor Input 30

2.8.3 Schedule Card Trick 30

Page 12: justinbongchunntatma081181ttt

ix

CHAPTER TITLE PAGE

2.8.4 Explicit Activities Name 31

2.8.5 The Right Level of Detail 32

2.8.6 Well Organized Activities

Groupings 33

2.8.7 Proper Consideration of Weather 33

2.9 Requirements of Successful Construction

Work Schedule 34

2.10 Factors Affecting Preparation of Better

Construction Work Schedule 36

2.10.1 Project Specific Factors 39

2.10.2 Project Management 40

2.10.3 Working Condition 41

2.10.4 External Environment 41

2.11 Summary 42

3 RESEARCH METHODOLOGY

3.1 Introduction 43

3.2 Literature Review 43

3.3 Methods of Data Collection 44

3.3.1 Primary Data Collection 45

3.3.2 Secondary Data Collection 45

3.4 Analysis Method 47

3.5 Reporting Results 48

3.6 Summary 49

4 DATA ANALYSIS AND FINDINGS

4.1 Introduction 50

4.2 Data Collection 50

4.3 Demographic Profile of Respondents 51

4.3.1 Respondent’s Highest Qualification 51

Page 13: justinbongchunntatma081181ttt

x

CHAPTER TITLE PAGE

4.3.2 Respondent’s Experience 52

4.3.3 Current Working Position 53

4.4 The Analysis of the Factors 53

4.4.1 Analysis of Projects Specific Factors

Considered 54

4.4.1.1 Average Index Analysis 54

4.4.1.2 Frequency Analysis 55

4.4.2 Analysis for Project Management Factors

Considered 57

4.4.2.1 Average Index Analysis 57

4.4.2.2 Frequency Analysis 59

4.4.3 Analysis for Working Condition Factors 63

4.4.3.1 Average Index Analysis 63

4.4.3.2 Frequency Analysis 64

4.4.4 Analysis for External Environment Factors 66

4.4.4.1 Average Index Analysis 66

4.4.4.2 Frequency Analysis 67

4.5 Analysis on Improvement Methods in

Preparing Better Construction

Work Schedule 68

4.6 Additional Suggested Factors Affecting

In the Preparation of Construction

Work Schedule 70

4.7 Discussion of Findings 70

4.8 Summary 73

5 CONCLUSION AND RECOMMENDATION

5.1 Introduction 75

5.2 Conclusion 75

5.3 Recommendations for future Study 79

5.4 Summary 80

Page 14: justinbongchunntatma081181ttt

xi

CHAPTER TITLE PAGE

REFERENCES AND BIBLIOGRAPHY 81

APPENDIXES 84

Page 15: justinbongchunntatma081181ttt

xii

LIST OF TABLES

CHAPTER TITLE PAGE

4.1 Project Specific Factors Considered in Preparing

Better Construction Work Schedule 56

4.2 Project Management Factors Considered in Preparing

Better Consruction Schedule 61

4.3 Working Condition Factors Considered in Preparing

Better Construction Work Schedule 65

4.4 External Environment Factors Considered in Preparing

Better Construction Work Schedule 65

4.5 Improement Methods in Preparing Better Construction

Schedule 69

5.1 Factors Affecting the Preparation of Better Construction

Work Schedule 76

5.2 Severity of Factors Affecting Preparation of Better

Construction Work Schedule 77

Page 16: justinbongchunntatma081181ttt

xiii

LIST OF FIGURES

CHAPTER TITLE PAGE

1.1 Research Framwork Flow Chart 9

4.1 Highest Qualification of Respondents 52

4.2 Working Experience of Respondents 52

4.3 Working Position of Respondents 53

4.4 Project Specific Factors 54

4.5 Tabulatin of Project Specific Factors 56

4.6 Project Management Factors 58

4.7 Tabulation of Project Management Factors 60

4.8 Working Condition Factors 63

4.9 Tabulation of Working Condition Factors 64

4.10 External Environment Factors 66

4.11 Tabulation of External Environment Factors 67

4.12 Tabulation of Improvement Methods 68

Page 17: justinbongchunntatma081181ttt

xiv

LIST OF APENDIXES

CHAPTER TITLE PAGE

APPENDIX A QUESTIONNAIRE FORM 84

Page 18: justinbongchunntatma081181ttt

INTRODUCTION

CHAPTER 1

Page 19: justinbongchunntatma081181ttt

CHAPTER 1

INTRODUCTION

1.1 Introduction

The construction development projects are vastly increasing in Malaysia as

the Government is taking the initiative towards making Malaysia a developed

country by 2020. In association to that, the construction arena became the catalyst

for this development purpose. Malaysian today is mesmerized by the unique

development today namely the Kuala Lumpur Tower, The Petronas Twin Tower,

Kuala Lumpur International Airport in Sepang and The North-South Light-Way-

Transit. These have become the Malaysian’s pride.

Nevertheless, in ensuring these massive projects to be completed and utilized,

some important elements must be considered, such as cost, time period and design

quality. Thus, in this research, time factor for the completion of a project is crucial.

The construction development projects in Malaysia have adopted several

scheduling and monitoring techniques to handle similar projects using manual or

computer software operations. The clients monitor and check progress evaluations

of work at site through his representative, the Superintending Officer or nominate

other consultants.

Page 20: justinbongchunntatma081181ttt

2

Generally, the site supervisor will prepare scheduling reports to be evaluated

and recommended by the client. The scheduling technique used will be the

Precedence Diagram presented in the form of Microsoft Project or Primavera

computer software.

This methods of scheduling is becoming more widely used in most of the

construction projects especially Government projects. Thus, with this new

technique, the process of construction in future can be identified and understood.

Therefore, research is done to identify factors affecting the preparation of a

workable schedule of using Gantt chart, critical path method and other elements in

the development projects in Malaysia. The usage of this method is predicted to

reduce the problem of late possession of site and ensure that optimum cost,

completion time and highest quality throughout the project.

1.2 Background of Study

Construction scheduling has come a long way in the last 25 years.

Unfortunately, despite the widespread use of computerized scheduling on

construction projects today, there still exists a large disparity in the level of

understanding in the proper use of this powerful tool. According to Frank (2004),

some even say there is a crisis in the construction industry because they believe

scheduling software is being misused to assert delay claims and there is, in their

view, a predominance of poor quality schedules.

The monitoring and control for construction projects sometimes cannot be

seen on the whole and it takes a long time to reach a solution for any problem. The

planning which is drafted together with current needs at that time will also give rise

to late possession of sites and other problems regarding to site possession.

Page 21: justinbongchunntatma081181ttt

3

In association to that, the clients and contractors should be exposed to the

importance and benefits of using work scheduling as an effective way to plan future

work. The concept of work scheduling technique using critical path and Gantt chart

gives a great impact on a project by assimilating every party involved in the

construction project in reducing cost, shorten the time period and increase the

quality of construction productivity.

Glenwright (2008) also stated that a characteristic of contemporary project

scheduling is the over-simplification which stems from the inability of unaided

human beings to cope with sheer complexity. Even though a detailed plan is

necessary, the management also need only act when deviations from the plan occur.

A technique can be developed to resolve this situation that would be very simple but

yet rigorous in application. One of the difficulties in the traditional approach is that

planning and scheduling are carried on simultaneously.

Besides that, according to Twomey (2006), delivering a project on time

relies on managing the development process, choosing experienced professionals,

assessing timeframes realistically, and anticipating that some unforeseen problems

are likely to come up. Aggressive management of typical scheduling issues that

occur throughout construction can help ensure that projects are completed within the

intended timeframe.

Hendrikson (2008) mentioned that in developing a construction plan, it is

common to adopt a primary emphasis on either cost control or on schedule control.

Some projects are primarily divided into expense categories with associated costs. In

these cases, construction planning is cost or expense oriented. Within the categories

of expenditure, a distinction is made between costs incurred directly in the

performance of an activity and indirectly for the accomplishment of the project. For

other projects, scheduling of work activities over time is critical and is emphasized

in the planning process.

Traditional scheduling procedures emphasize the maintenance of task

precedences (resulting in critical path scheduling procedures) or efficient use of

Page 22: justinbongchunntatma081181ttt

4

resources over time (resulting in job shop scheduling procedures). Finally, most

complex projects require consideration of both, cost and scheduling over time, so

that planning, monitoring and record keeping must consider both dimensions. In

these cases, the integration of schedule and budget information is a major concern.

According to Glenwright (2008), the first step was to separate the functions

of planning from scheduling. The basic elements of a project are activities and

resource expenditures and execution times are associated with each activity in the

project. These factors, combined with technological relations, produce schedules

proposing varying completion dates. Management comes into possession of a

spectrum of possible schedules, each having an engineered sequence, a known

elapsed time span, a known expenditure function, and a calendar fit.

In fact, Twomey (2006) stated that the key factors in keeping a project on

track are to understand what causes delays and then to properly plan and manage

schedule issues before they become problems. Delays of individual construction

tasks may not be preventable. However, those that can’t be avoided do not

necessarily have to hold up the entire project. The success of any construction

project is based on balancing the resources of cost, quality, and schedule. All three

of these issues are important. On many projects, however, time is the most critical

issue for the overall success of the plan.

1.3 Problem Statement

Some project participants care more about their schedules than others. Some

contractors prepare schedules only because it is a contract requirement. On far too

many projects schedule is created at the beginning of the project and never reviewed

or revised until a problem develops. The best approach is for all project participants

to join in the scheduling process and develop a meaningful schedule, and then use it

Page 23: justinbongchunntatma081181ttt

5

throughout the duration of the project. This is most likely to happen when the

schedule is realistic, useable, and understood by all of the project participants.

Besides, Harban Singh (2004) mentioned that work schedule submitted by

the contractor should contain the main activities, sequence of activities, timing of

activities, critical activities and critical path, and important milestones. Since there

are no clear guidelines for the application of project scheduling in project

management the current practice is entirely depending on the experience of the

project manager. This has resulted in a lot of time wasting effort before parties

involved in the project accept any work schedule.

Nevertheless, there are still weaknesses in term of formal guidelines for the

preparation and submission of work schedule. Several problems associated with

project scheduling are the inability to fully utilize the schedule, lack of

understanding of scheduling techniques, and unable to see the importance of work

schedule as stated by Mohamad Ibrahim et al (2006).

Furthermore, Jon et. al.(2002) said that as many contractors lack the skills

necessary for successful scheduling, an owner may choose instead to provide to the

contractor for successful scheduling consultant and may even pay for this service.

The participation of key subcontractors and suppliers to the development of a

workable plan (detailed activity plans) is emphasized by Claugh and Sears (2000)

and Walker (1996) who argues that construction planning and scheduling must be

done by participation of people who are experienced in and familiar with the type of

field work involved.

A similar idea is advocated by Ballard (1997) who emphasizes the idea of

enabling what he calls the ‘‘Last Planner’’ participation in producing directives to

drive direct work processes ‘‘assignments’’. He thinks that failing to prepare good

assignments by planning at crew level, will prevent plans from being realized even if

the upstream planning was good. The ‘‘last planner’’ principle requires selecting

assignments from activities that are known to can be done. Without this has caused

the uncertainty and variation of work flow, which results in less percentage of non-

Page 24: justinbongchunntatma081181ttt

6

productive time. Problems will arise in sequencing decisions which was made by

last planners based on their knowledge of working conditions and constructability

issues, as well as, selecting the right amount of work which will use the labor and

equipment capacity as directed by the schedule.

However, it appears that it is not how often the network is recalculated or

updated but instead it is how well the plan and schedule continue to fit the actual

conduct of the work. As many of the key problems of implementation lie in the

general environment of the project and not under the direct control of the project,

project managers must look outside the project and ahead to anticipate problems and

develop contingency plans. Kiiras (2001) stated that this can only be achieved by

means of continuous planning and steering during project life instead of the

traditional detailed project planning before the start and reporting during execution.

1.4 Aim and Objectives of the Study

The aim of this study is to identify the factors affecting in the preparation of

construction work schedule.

To achieve the aim, the main objectives of this study are outlined as follows:

(1) To investigate the factors affecting in the preparation of better

construction work schedule;

(2) To establish the severity of these factors; and

(3) To identify improvement methods in preparing better construction work

schedule.

Page 25: justinbongchunntatma081181ttt

7

1.5 Scope of the Study

The scope of study is confined to building projects undertaken by contractors

registered with class G5 to G7 under Construction Industry Development Board

(CIDB) in the locality of Johor.

1.6 Significance of the Study

The study intends to analyze and promote a better understanding and

recognition of the complexities of the performance of contractors in completing

projects. This study will offer some practical ideas, based on actual construction

experience, to assist contractors in developing realistic construction schedules. It is

intended to make the reader aware of certain aspects that frequently seem to be

ignored and to alert owners to potential problems as well as possible courses of

action to avert problems. The points outlined in the paper will also assist owners in

evaluating the qualifications of potential contractors who may propose on building

development projects.

Page 26: justinbongchunntatma081181ttt

8

1.7 Research Methodology

In achieving the results of this study, a pilot study is done to obtain opinion

from various parties involved in the construction projects. From this study, a

hypothesis shows that the schedules normally given to clients from the contractors

are done using the critical path method or precedence diagram method rather than

bar charts.

The approach for implementing this research is divided into a few categories.

The purpose of this methodology is to simplify the process of data collection and

other relevant information which is obtained throughout this research. The research

framework flow chart is illustrated as show in Figure 1.1.

1.8 Summary

This research is a descriptive research and the type of research method used

is questionnaire survey. The method of data collection is through questionnaire

forms. The respondents are randomly selected from Classes G5 to G7 registered

under the CIDB. After the primary data are sufficiently obtained, the data will then

be collected to achieve the objective of this study.

Page 27: justinbongchunntatma081181ttt

9

Figure 1.1: Research Framework Flow Chart

Initial Study

Identify Problem of Statement

Importance of Study

Objectives Research Scope

Literature Review

Factors Affecting in the preparation of Construction Work Schedule

Research Methodology

Results

Discussion

Conclusions and Recommendations

Data Collection:

Questionnaire Survey

Data Analysis:

1. Average Index

2. Frequency Analysis

Page 28: justinbongchunntatma081181ttt

LITERATURE REVIEW

CHAPTER 2

Page 29: justinbongchunntatma081181ttt

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

This chapter covers the introductory of construction work schedule. The last

part of this chapter will focus on the factors affecting in the preparation of

construction work schedule with listing of all the possible factors adopted according

to the suitability of the local construction industry.

2.2 Importance of Construction Work Scheduling

The importance of planning and scheduling in construction cannot be

overestimated. The US Department of Labor, Bureau of Statistics, includes an

industry definition of a Construction Manager (CM) that states they will typically

schedule and coordinate all design and construction processes (USDL, 2005). In a

study entitled “What does a Construction Manager really do?” performed by the

Construction Management Association of America, it was found that one of the

Page 30: justinbongchunntatma081181ttt

11

most important general areas was time management, in which CMs reported their

most important function is to develop a construction schedule, followed by

developing and managing a critical path schedule for the job (CMAA, 2005).

Glavinich (2004) answers the question, “Why Schedule the Construction Project?”

with the following: to communicate the construction plan, establish production goals,

monitor and establish progress, and to manage change.

The construction schedule is one of the most powerful management tools at

the service of the construction manager. A well-planned and realistic schedule that

takes into account as many variables as possible will help keep a construction

project moving along smoothly, alert the construction manager when the project is

about to run into snags, and help make needed adjustments when unforeseen

circumstances arise. In order to do all that, though, the plan must have the input and

some degree of ownership from everyone who will have to live by it. Otherwise,

there is risk of having workers and subcontractors who are working against the

construction schedule rather than with it.

The schedule is prepared by the scheduler and/or planner. In preparing a

schedule, the scheduler or planner may meet or discuss with some people for crucial

information, e.g. estimator, manager, superintendent, sub-contractor, architect,

engineer, owner, and materials' suppliers. They may need to study the contract,

drawings, specification, and perhaps, conduct site reconnaissance. Further, they need

to know about manpower and productivity. Apart from the schedule, it is also

necessary to prepare systematic monitoring to provide early warning of restraints as

well as imaginative action to overcome them.

According to Jon et. al. (2002), the scheduling consultant should strive to

develop a trusting relationship with the different participants to develop a workable

plan and project schedule. Proper scheduling provides the best opportunity for a well-

coordinated and well-sequenced project that is delivered on time and within all

participants’ budget. This is because a well-coordinated and well-sequenced project is

often difficult to achieve. He must work diligently with the project stakeholders who

are the general contractor, the subcontractors, the construction manager, and the owner,

to ensure the construction process participants are working collectively toward agreed-

Page 31: justinbongchunntatma081181ttt

12

on objectives. These objectives usually involve completion of performance in the time

allotted and delegated responsibility for maintaining the schedule utilizing the

methodology reflected in the project schedule.

2.2.1 Benefits of Construction Work Schedule

The Construction schedule major purpose is to map out the progress

expected on a construction project in a timeline that is the most efficient and cost

effective possible. It does this through various means, and serves a number of

subsidiary purposes as well. These include:

(1) The original conceptual plan can help determine the feasibility of the project

and give an idea of the estimated cost of the project;

(2) It serves as a reasonable, understandable document upon which contractors

and subcontractors can make realistic bids on the project;

(3) It makes binding agreements with subcontractors. When a subcontractor

signs the agreed-upon construction schedule, they are committing to meeting

its terms;

(4) It gives the owner of the project a realistic timeline by which he can expect

his project to be completed. It lays out the sequence of events and the

process that will be followed by the construction company and

subcontractors, making it easier for him to monitor;

(5) It serves as a map and scheduling tool for the project manager, who can use

it to schedule work crews, time deliveries and equipment rentals and monitor

the progress in case of needed changes;

(6) It becomes a daily, weekly and monthly benchmark of the actual progress on

the project as the construction subcontractors and crew leaders enter finished

jobs and concerns;

Page 32: justinbongchunntatma081181ttt

13

(7) It serves as a base plan for any changes that might have to be made due to

unforeseen circumstances, unexpected delays (or completion ahead of

schedule – it can happen!), or owner changes and additions;

(8) When coupled with communication and project management software, it is

an effective, efficient way to track progress, and flag trouble spots before

they become critical.;

(9) It serves as documentation of work completed as the concerned parties sign

off on agreed upon completion;

(10) In the event of dispute or questions, it can serve as legal documentation of

the actual history and events of the construction; and

(11) After project completion, it can serve as a guide in future projects through

post-completion analysis.

2.2.2 Developing a Construction Work Schedule

Construction schedule specifications are all over the map. According to the

committees of the Association for the Advancement of Cost Engineering (AACEI)

and the Project Management Institute College of Scheduling (PMICoS) (2005),

there is no consistency in arrangement, focus or language. Some specifications start

right off with the software to be used along with the requirements for reports and

updates. Others start with scheduler qualifications while still others introduce the

purpose of the schedule and the schedule scope of work. Frequently, however, these

procedures, processes and technical details are completely intermingled. At the

same time, there are variances in common details, such as determination of lost

weather days and the maximum duration of an activity. Some specs specifically

require the qualification of the scheduler, while one owner offers to fund the

scheduling services for the contractor.

Page 33: justinbongchunntatma081181ttt

14

The idea is that processes and procedures that are common to many

specifications will be independent of the technical portions of the specifications.

The mechanical details of the schedule and specific software requirements can

reside in a technical section of the specification. Time extension requirements

should be separate as well. Having a common framework of schedule specifications

will lead to more consistency across contracts and will reduce confusion among the

contractor community. Accomplishing general industry agreement on the

procedures and process should be more achievable. Having a separate technical

section may not necessarily lead to agreement on many details, but will at least lead

to development of a checklist for owners to consider in their schedule specifications.

If today’s construction schedules are properly prepared, construction

managers, owners, suppliers, and sub-contractors have an efficient and effective

management tool to control complex construction projects accomplished by a

diverse array of designers, engineers, suppliers, and specialty subcontractors.

Planning, coordination, and communication of the work plan, schedule, performance,

and control are then greatly facilitated in the efforts to achieve projects successfully

and profitably. However, the ‘if’ needs to become ‘when’. And this means all of

the underlying aspects need to be checked by an independent, qualified and

experienced master construction scheduler and the validation-auditing team as stated

by Glenwright (2008).

2.3 Construction Work Scheduling Techniques

The advantages to using a complete construction scheduling package include:

immediate field updates; realistic revisions; input from those actually completing the

work; and a stronger investment in completing the work according to schedule and

on time. Onsite internet access to the construction schedule and communication

capabilities give the project leadership the tools they need to provide onsite

supervision that is responsive and decisive.

Page 34: justinbongchunntatma081181ttt

15

The nature of the project schedule will normally depend on the cost of the

project. A bar chart is usually used on smaller projects. As the cost of the project

increases owner’s start to demand a schedule that is based on a critical path method

network.

2.3.1 Bar Charts

A bar chart simply indicates when specific activities will start date, their

duration and finish date. The activities are plotted on a time scale. Since each

specific activity on a bar chart is depicted as a straight line on the schedule, a bar

chart is easy to understand. A bar chart does not indicate the interrelationship

between different activities nor does indicate that the commencement of one activity

is dependent on the completion of a predecessor activity.

2.3.2 Critical Path Method

It is important to understand the relationship between the commencement

and completion of the various activities which comprise a construction project.

Critical path method (CPM) network and Program Evaluation Review Technique

(PERT) are the two scheduling devices which indicate the dependencies and

interrelationships between different activities. Those interrelationships between

activities are indicated as a network.

Over the years, the CPM has become the common construction network

schedule. A CPM shows the sequence of each activity, the start of each activity, the

Page 35: justinbongchunntatma081181ttt

16

dependence of that activity on the completion of a preceding activity, and how the

completion of that activity will restrict the commencement of subsequent activities.

The CPM is graphical model of a project. The basic components of the

network are individual arrows which represent specific activities. The activity can

be any aspect of the project that requires either time or resources. The project

activities are indicated by a logical flow of the work from the left hand side of the

schedule to the right hand side. At each end of the arrow are activity numbers. The

numbers are referred to as “i-j” designations. The letter “i” represents the start of

the activity and the letter “j” represents the finish of the activity. At some place

along the arrow and between the “i-j” designations is a number which represents the

number of days that activity will require. The schedule also has a time scale. Finally,

the critical path is shown as darker or different colored line that runs through the

critical activities.

According to William (2009), the basic steps in creating a CPM schedule

include: (1) identification of the basic tasks or activities that must be performed to

complete the project; (2) estimation of the duration of the specific activities; (3)

making a determination of the logical flow of the work, which includes a

determination of which activities must be completed before the subsequent ones can

commence; and (4) inputting the information into the computer so that it can make

the numeric calculations that lead to the formulation of the schedule.

Terms that are used in context of a CPM network include:

(1) An Arrow or line is used to represent one activity;

(2) A Node or Event which represents the beginning and ending point of

an activity;

(3) A Milestone is typically a significant event that the owner or

contractor wants to track;

(4) A Link which represents the path between two Nodes;

(5) A Dependency is the relationship between two different activities as

they related to the commencement and completion of those activities;

Page 36: justinbongchunntatma081181ttt

17

(6) A Predecessor activity is an activity that restrains ( refer to as a

restrain) a subsequent depend activity;

(7) A the restrained activity that follows a Predecessor activity is a

Successor activity;

(8) Job logic refers to the necessary time and order of specific activities

in relationship to the whole project; and

(9) Float represents the number of days an activity can be delayed

without delaying the project, with a critical activity having no float.

The critical path is computed in two steps. The first step involves a forward

pass calculation of the activities; starting with the first activity on day one of the

project. During the forward pass calculation the early start and early finish for that

activity is calculated. The early start is the earliest time an activity can start and is

based on the completion of predecessor activities. The early finish is the earliest

time an activity can finish, assuming it starts on time and takes no longer than was

planned. The second step is the backward pass calculation. It involves calculating

the late start dates and late finish dates for each activity. While the late start date is

the latest date an activity can start without delaying the project completion, the late

finish date is the latest date an activity can finish without delaying the project.

Scheduling software automatically completes these two calculation passes then

prepares a report with the dates and a graphic network portrayal of the schedule.

The Critical Path is the longest continuous chain or series of activities

through the CPM network. In essence, the critical path is the shortest period of time

it will take to complete all the activities that comprise the project. The completion

of project is delayed when one of the critical path activities is not started on time,

not finished within the allotted time, or not finished on time. If a non-critical

activity exceeds its float time, that activity will become critical.

Page 37: justinbongchunntatma081181ttt

18

2.3.3 Choosing the Right Scheduling Method

Jon et. al. (2002) mentioned that one of the key decisions to be made before

a project begins is which scheduling method is best suited to the project.

Frequently, the owner and the designer decide on scheduling requirements as a part

of the planning process for a project and the process of drafting specifications for

bidding or negotiating. In making this decision, considerations were given to;

(1) The size, complexity, and location of the project;

(2) Project phases and timing;

(3) The number of parties that will act as prime contractors;

(4) The need date for completion of certain milestones and of the project;

(5) The experience of the owner, the architect/engineer, or the construction

manager in the use of specific scheduling techniques;

(6) The capabilities and experience of the prime contractor(s) in preparing

and implementing the project schedule required;

(7) The type and quality of data desired by the owner, architect/engineer,

construction manager, or contractor to effectively plan, schedule,

coordinate, monitor, appraise, and document the progress of the project;

and

(8) The amount of owner-furnished or third-party-furnished material and

equipment involved.

Regardless of the scheduling system chosen, the owner or the owner’s agent

responsible for managing the project should have experience with the scheduling

method selected.

Page 38: justinbongchunntatma081181ttt

19

2.4 Developing Schedule Specifications

After an owner or agent has chosen the proper scheduling technique, either

the critical path method (CPM) or the bar chart method, it is important to the success

of the project that specifications outlining the scheduling requirements be carefully

prepared and incorporated into the contract. Including such requirements enables

an owner to more effectively control and enforce the scheduling obligations of the

parties involved.

Schedule specifications should be clear and concise, avoiding ambiguities

and potential misunderstanding. Unfortunately, this is not often the case.

Frequently, specifiers have little knowledge of the scheduling technique being

specified and the responsibilities and liabilities they can incur.

Experience has shown that it is very difficult to establish standard schedule

specifications for use by the construction industry today. For example,

specifications may range from one paragraph to five or ten pages. The short

specifications are dangerous, and the long ones are expensive. However, experience

has shown that the more detail included in the specifications, the better chance there

is to eliminate misunderstandings.

Hence, Jon et. al. (2002) stated that good Construction work schedule

specifications set forth the type of schedule that will be in effect for the project.

Specifically, they address:

(1) The scheduling method and techniques to be used;

(2) Which party has the responsibility for preparing the schedule;

(3) Coordination of any multiple-contract situations that will exist on the

project;

(4) The amount or level of schedule detail required by the specification;

(5) The need to incorporate all contractually specified milestones. This may

include completion dates for critical components of work, deliveries of

equipment, dates for promised information (such as owner-tenant

Page 39: justinbongchunntatma081181ttt

20

layouts), dates for access to the prject, and availability dates for key work

areas (where renovbation proceed in existing facilities);

(6) The need for the contractor to identify dependencies that will restrain

performance;

(7) Processing procedures for shop drawings (preparation, submission, and

approval);

(8) Processing procedures for submittals (initial and updates, plus frequency);

(9) Procedures for review and approval of the schedule;

(10) Remedies for noncompliance (for initial schedule as well as updates);

(11) Updating procedures (specifying frequency, requirements for joint

updating meetings between parties, the keeping of meeting minutes, data

requirements and methods for incorporating time-impact analyses and

time extensions as part of the updating process);

(12) Progress reports;

(13) Whether or not the schedule will be used for determining progress

payments;

(14) Procedures for justification of time extensions (using time impact

analysis);

(15) Float utilization and availability to project and parties; and

(16) Involvement of subcontractors in the scheduling process.

2.5 Responsibility for Schedule Preparation

In order for the construction plan to meet all these requirements, though, it

must have the willing cooperation and buy-in of the owner, construction manager,

sub-contractors and designers. In short, everyone needs to have some degree of

ownership in the plan. For that reason, it’s important that the owner or construction

manager to have the input of every major player in the project during the design

stages of the construction schedule.

Page 40: justinbongchunntatma081181ttt

21

As early as the bidding stage, it pays to be open to suggestions and

communication. Being open to input from bidding subcontractors allows the plan to

be refined based on the experience and capabilities of those who have tackled

similar work in the past. If those lines of communication are open from the very

start, every subcontractor who makes a successful bid has a realistic stake in the

project because they feel they helped define the tasks and timetable. Without it,

updating the schedule regularly becomes a time-wasting chore in their minds. When

a contractor and his crew have an investment in the plan, they feel they are helping

to manage it rather than being a slave to it.

As quoted by Willis (1986), most of the following parties will be participants

in a typical construction project. Women now play significant roles in all sectors of

the construction industry, and it is expected that their participation in the industry

will continue to increase.

Once the project delivery system and scheduling methods have been selected,

the party responsible for preparing the project schedule must be designated. In the

traditional approach, for example, an owner requires a general contractor to prepare

the schedule. In addition, the owner has the option to require the general contractor

to submit the schedule either for formal approval or for informational purposes only.

Under such circumstances, the general contractor also had options. For

example, the general contractor may choose to prepare the schedule in-house or may

contract the services of a scheduling consultant to provide technical assistance if the

required skills and experience are not available in the general contractor’s

organization. On occasion, an owner may specify that the general contractor hire a

scheduling consultant and may even insist on approving the use of any consultant

selected by the contractor.

As many contractors lack the skills necessary for successful scheduling, an

owner may choose instead to provide to the contractor for successful scheduling

consultant and may even pay for this service as referred by Jon et. al. (2002). This

option also offers alternatives. For example, the scheduling consultant can work

with the contracted party or parties and assist in developing a schedule for all work

Page 41: justinbongchunntatma081181ttt

22

contracted; the resultant schedule can then be submitted by the contractors to the

owner for formal approval or informally agreed to by the owner. The scheduling

specifications should include information on whether the schedule submittal

required formal approval by the owner.

2.5.1 The Clients / Owners

This is the individual, the firm, or the organization that funds the construction

project and will own the completed facilities. The owner, perhaps assisted by

consultants, specifies the scope of the construction project.

In some instances, the owner may specify the detailed layout of the facility,

the type of materials to be used, and so forth. The owner, perhaps assisted by some

of the parties described below, and depending on the technical expertise of his or her

own staff, may inspect the project work as it is being performed and on its completion.

The golden rule in the construction process is: "He who has the gold makes the

rules." Because the owner controls the purse strings, he or she dictates the kind of

contract that will be used and selects the other parties to the project.

2.5.2 The Construction Manager

He or she is an employee of a professional construction management firm that

may be retained by the owner to perform predesigned planning, to help select the

designer, to help select contractors, and to perform post-contract award functions. The

construction management firm may perform all or some of these functions in return

for a fee. When capitalized, the term Construction Manager (CM) means an

Page 42: justinbongchunntatma081181ttt

23

employee of such a firm. The term construction manager can also be applied to

many other management level personnel within the construction industry.

When an owner contracts the services of a construction manager as his agent,

the construction manager is frequently responsible for overall scheduling and

coordination when multiple trade or multiple prime contracts are used. As a result,

the construction manager has several options schedule development and

implementation.

The construction manager may prepare an overall detailed master schedule

for the project. This type of schedule usually be supported by milestone schedules

and/or prebid integrated schedules for each of the key multiple prime or trade

contracts that are anticipated to be let with this method of the project delivery.

As trade contractors are let, the construction manager has the option to

require each trade contractor to participate jointly in the development of the trade

contract schedule. The objective is to reflect the trade in the development of the

trade contract schedule. The objective is to reflect the trade contractors’ plans and

intentions to execute their work and to coordinate their dependencies with others.

The alternative to this procedure is to require trade contractors to prepare

their own schedules, based on certain basic information provided by the construction

manager, and submit them to the construction manager for approval. After approval,

the construction manager has the option to incorporate the trade contractors’

schedulers into the detailed master schedule or to maintain them separately. From

the detailed information, a time-scaled master summary control schedule may be

developed by the construction manager to provide management with overall project

visibility and a management tool for use in periodic briefings and reports.

When design-build construction manager project delivery systems are used,

the scheduling options available to the design-build contractor construction manager

are basically the same as with the agency construction manager.

Page 43: justinbongchunntatma081181ttt

24

2.5.3 The Designers

They may be employees of the owner, but are more often the employees of

an architect-engineer (AE) firm. In addition to designing a facility that meets the

expressed needs of the owner and that complies with applicable building codes, the

AE may be retained by the owner to act as his or her representative in

inspecting the project work, to review and approve materials that the contractor

proposes to use in the work, to review and recommend contractor requests for progress

payments, and to perform other functions on behalf of the owner.

2.5.4 The Contractor and Sub-contractors

These are individuals or firms that undertake to perform required

construction work in return for a contract price. Contractors may be categorized

as prime contractors and subcontractors. Prime contractors have a contractual

relationship with the owner, whereas subcontractors have a contractual relationship

with the prime contractor or with another subcontractor. General contractors are

prime contractors who contract to perform ail of the required work, possibly

excluding some specialty items such as electrical and mechanical work that the

owners desire to contract directly with the specialty contractors. Subcontractors

are sometimes referred to as first-tier subcontractors, second-tier subcontractors, and

so on. A first-tier subcontractor has a contractual relationship with a prime

contractor. A second-tier subcontractor has a contractual relationship with a

first-tier subcontractor, and so forth. A typical construction contractor, regardless of

whether a prime contractor or a subcontractor, will perform certain functions, either

personally or by use of his staff. These functions include the following:

A. Home Office Functions. These include the selection of potential

projects, estimating the costs of such projects, the preparation of

Page 44: justinbongchunntatma081181ttt

25

bids or negotiating construction contracts, the procurement of

construction materials, the management and maintenance of

contractor-owned equipment, and personnel and financial

management. The titles of home office contractor staff members

might include: estimators, schedulers, procurement specialists,

accountants, counsel, project managers, fleet managers, safety

officer, quality control officer, and others.

B. Field Functions. The contractor's principal field function is project

management. The contractor may have a project manager, a

project superintendent, or both as his field supervisors at the project

site. Other contractor field personnel may include office engineers,

office clerks, time-keepers, clerks, inspectors, and foremen.

2.5.5 The Design-Build Firm

The term is usually reserved for firms that perform both design and

construction functions, but such a firm may also perform planning functions.

2.5.6 Fabricators and Vendors

These terms apply to firms that contract with the owner or with the

contractor, to fabricate and deliver fabricated or off-the-shelf construction

materials to be used in the project. The construction contract may call for the

contractor to purchase and install all of the material, or it may call for the owner to

purchase some of the material for installation by the contractor. Material that has

been procured by the owner is termed owner-furnished material (OFM). If the owner

is the federal government, the material is termed GFM.

Page 45: justinbongchunntatma081181ttt

26

2.6 Sources of Planning Work Schedule

When everyone is together, it is more possible to identify needs for

additional manpower, added equipment, and potential time loss and gain. If a delay

has caused the loss of time, the entire team can work on recovering the lost time. If

there is a gain, the team can come up with the best way to use the gain.

There are many method employed in project planning. Many project

planners were used to table form which comprises from a date list, starting or

completed information, which are provided by the management. Regardless of the

methods employed, the decisions made will require the collection of data on

materials, machineries, equipments, manpower, finance and time.

2.6.1 Construction Materials

The measurement of quantities by the quantity surveyors from building plans

and specifications can be summarized to determine the particular quantity and types

of materials to be used to perform a work. The availability and delivery period for

these materials should be obtained and from suppliers or according to experience.

2.6.2 Machineries and Equipments

The machineries and equipment which are required to complete a

construction project will definitely depend on the suitable types and the method of

which there are place or keep safely. After the selection on the particular

Page 46: justinbongchunntatma081181ttt

27

machineries or equipments is made, the availability and delivery time must be

determined.

Heavy machineries such as cranes, cement mixers, steel bar cutter and steel

bar bending machines for structural works are required during the execution of the

work scheduling. These matters are important to prevent machineries from idling

which induce will induce a high cost.

2.6.3 Labours and Manpower

Labours and manpower are important assets in construction projects.

Without labours, a project can become abandoned and the contractor will need to

terminate the contract. Thus, labours should be taken into account when scheduling

work to ensure that the participation of the labours is at the maximum standard.

The numbers of skilled workers should also be considered in the work

performed. It should be adequately sufficient to meet expected workload and work

tasks. A mistake in this planning will result in late submission of works.

2.6.4 Finance

The allocation of finance must be scrutinized to reimburse for the cost of the

supply of construction materials, labours and machineries. Any financial difficulties

must be solve to ensure that the construction project can be carried out smoothly.

Page 47: justinbongchunntatma081181ttt

28

2.6.5 Time

The most crucial element which must be carefully monitored is time. The

owners will normally check for starting dates, completed dates and other relevant

yet important dates in contract submissions by the contractors. Besides, there are

also time limits which must be obeyed by construction organizations during

planning stage.

The time require for the construction materials to be delivered to site should

follow a specified schedule. This is to fulfill worker’s demand and reduce wastage.

A proper understanding of the project requirements will enable a more effective and

efficient materials handling at site.

2.7 Control and Monitor Construction Work Schedule

Communication remains vital once construction begins. Keeping the lines of

communication open involves making regular updates on progress both ways. It’s

up to the crew leaders to be sure that progress is tracked regularly in the scheduling

software. Any possible delays need to be noted, as well as finished work flagged.

Making the means to communicate instantly available on site provides both

incentive and opportunity to keep the schedule properly maintained.

In addition to daily updates, regular weekly meetings of the team leaders are

vital as well. These meetings should include the project manager, an owner

representative, and representatives of the subcontractors. Update meetings can

provide a look-ahead on the project’s progress and possible difficulties or gains. By

breaking down the schedule into smaller blocks, weekly meetings can help make the

transition from the big picture to a more detailed look at the tasks needed in the

Page 48: justinbongchunntatma081181ttt

29

upcoming week. Again, including all interested parties makes use of the expertise

of everyone concerned, and fosters the team attitude that keeps the project on track.

2.8 Characteristics of a Good Construction Schedule

According to Frank (2204), the best approach is for all project participants to

join in the scheduling process and develop a meaningful schedule, and then use it

throughout the duration of the project. This is most likely to happen when the

schedule is realistic, useable, and understood by all of the project participants.

2.8.1 The Plan

All good schedules start with a well thought out planned work sequence.

The plan should consider factors that could impact the timing of the work such as

site access, access to work areas, long lead time equipment and materials, labor

availability, and which areas of the work will take the longest. Once this plan has

been established, it should be clearly communicated to all project participants. It is

important to make sure that those not working on site, such as the engineer

reviewing shop drawings or material fabricators, understand the priorities and

planned work sequence.

Page 49: justinbongchunntatma081181ttt

30

2.8.2 Subcontractor Input

Generally, construction managers and general contractors are capable of

putting together a schedule without subcontractor input. However, it is the

subcontractors who are in the best position to know their durations and plan their

work sequences. For this reason, I have found that a detailed schedule planning

meeting with the major or early subcontractors is one of the best ways to ensure the

schedule has appropriate work activity durations and sequencing.

Subcontractor input will also confirm durations for shop drawing submittals

and material deliveries. How long will shop drawings take? What time has the

manufacturer indicated for fabrication of materials? The initial schedule will

include these activities, but the subcontractor can help "tune up" the schedule with

more accurate information. Subcontractors can also assist in the schedule updating

process, since they are closest to the actual work. Often they can suggest "work-

arounds" or alternate sequences to mitigate delays or other field problems.

2.8.3 Schedule Card Trick

One method for coordinating the schedule input of large groups of

contractors is a meeting called the "Schedule Card Trick." The contractors prepare

their activities and durations in advance of the meeting on different colored 3 x 5

cards. Several large calendar sheets with weekly time increments are also prepared

before the meeting. During the "card trick" meeting, you "build the building,"

starting with the earliest work areas. The activities for each work area are sequenced

and arranged by placing the cards on the calendar sheets and connecting related

activities.

Page 50: justinbongchunntatma081181ttt

31

In this way, the construction schedule is created in front of the

subcontractors. This is a great opportunity to hash out key sequencing and planning

issues. For example, which subcontractor goes first inside the building, ductwork,

or masonry? Will the finishes go from the bottom floor up or the top floor down?

The "Schedule Card Trick" gives all the subcontractors a chance to see the big

picture, as well as where and when their work fits in the schedule. There is also the

added benefit of "buy in" of the schedule by the subcontractors because they helped

put it together.

2.8.4 Explicit Activity Names

Work activities in the schedule should have names that are clear and specific.

Explicit work activity names make it easy to understand what is included (and not

included) in the work activity and when they start and finish. In order to properly

track work progress, the schedule needs separate activities for each trade contractor

even if the activities are scheduled to occur at the same time. The plan may be for

them to start and finish together, but you will never be able to identify the contractor

responsible for delaying the activity if they are combined in a single activity in the

schedule. Similarly, it is good practice to separate activities that a certain trade

contractor may do in different time periods or with different crews, such as "framing

walls" and "drywall and tape."

Page 51: justinbongchunntatma081181ttt

32

2.8.5 The Right Level of Detail

When construction is just getting started on a project, it is not unusual to find

the project team focused on the earlier parts of the work. As a result, they may not

want to take the time to develop a detailed schedule for work that is a year or more

in the future. On many projects, a detailed schedule will be developed for the site

work, structure and enclosure, and a single long duration activity will be allocated

for "interior finish work." This will work, as long as enough time is allocated in the

schedule for the later work and a future schedule details this work.

A schedule may not be used if it is cluttered with too much detail. Generally,

activity durations should range between one and four weeks. How much to "break

down" individual work activities also depends on how large the work areas are and

if a set of activities will always be done in sequence. It may be all right to combine

"form/reinforce/place footing - east side" if the duration is one or two weeks. One

day activities or milestones signifying the completing of key project activities (i.e.

permanent power available, roof tight, completion of a work stage) are also useful.

Even a large, detailed schedule may not provide all the specific activities needed in

the field or may be too cumbersome to use on a daily basis. For these reasons, field

staff often develops short-term, hand drawn schedules to coordinate day to day

activities among subcontractors. This is an acceptable practice if the durations and

sequencing in these short-term schedules are consistent with the "official" project

schedule. Significant differences between the two schedules are indications that

there may be a problem with the overall schedule because it is not accurately

reflecting the work being performed in the field.

Page 52: justinbongchunntatma081181ttt

33

2.8.6 Well Organized Activity Groupings

The typical construction schedule on a large project will include hundreds or

even thousands of activities. To make the schedule useable, it should be structured

so these activities can be sorted and grouped, making it easy to find desired schedule

information. Generally, activities can be separated by phases, such as bid/award,

shop drawing/fabrication, new construction and renovation. It is helpful if the

activities can be sorted by bid package or specification section within these

categories. It works best if the groupings of activities correspond to the planned

work areas and sequences (i.e. how you are planning to "build the project"). For

example, if the interior work on the floor of a building will be completed all at once

or in two halves, or by specific functional areas (Administration Area, Classrooms,

Library, etc.), it is important to create schedule activities for each work area.

Breaking work into smaller pieces in the schedule also allows better tracking (for

starts and finishes) and better logic (the following activity will probably start sooner).

Areas on bridge and road projects are often sub-divided by survey stations or work

phases.

2.8.7 Proper Consideration of Weather

Once a detailed schedule has been developed and the expected start date for

the work is known, the project team should review the activities in relation to the

time of year in which they are scheduled. In cold weather climates, activities which

fall in the winter months may need to be shifted, or it may be necessary to plan for

temporary enclosure and heating. Similarly, the schedule may need to allow more

time for certain activities or show them being done on a limited basis because of

weather considerations. Similar issues may arise in extremely warm areas or areas

which have a rainy season. If a revised project start date or other delays shift the

work by several months, the schedule should be updated and the activities that have

Page 53: justinbongchunntatma081181ttt

34

shifted into bad or difficult weather periods should be looked at closely and adjusted

as needed to reflect the effect of weather.

This is one of the most often ignored aspects of preparing and updating

project schedules; when not considered and planned for, seasonal effects can

significantly impact the project cost and schedule. Finally, use the schedule. Hang

a large plot on the wall at the jobsite. Write on it, noting actual starts and finishes,

and make notes about changes and new issues. Put the new updates on top of older

versions (which are very likely to be referred to by those who are really watching

the schedule). Refer to it daily with the subcontractors. Formally review current

activities at all regular subcontractor meetings. Awareness of the schedule and

delays will allow for better planning and a smoother job. Throughout the project, be

"schedule conscious." The schedule itself may experience delays, but time will

move on.

2.9 Requirements of Successful Construction Work Schedule

There are advantages and disadvantages to each of the methods of schedule

preparation and implementation. Although success has been achieved using all of

these methods, each has had its own failures, due primarily to various user-oriented

reasons.

According to Jon et. al. (2002), experience has shown that on fixed-price or

lump-sum contracts, the best results have been achieved when the contractor is

responsible for schedule preparation and maintenance, with the owner or the

owner’s agent reserving the right to approve the initial schedule.

This assignment of responsibility makes a good deal of sense, considering

the risks involved. On a fixed-price or lump-sum contract, the general contractor, in

establishing its price, makes a number of assumptions based on the manner by which

Page 54: justinbongchunntatma081181ttt

35

it can perform the required work at a cost lower than the competition. Therefore, the

general contractor is in the best position to plan and schedule its work and the work

of the subcontractors and suppliers. If the general contractor lacks the technical

capability to develop this information, there is always the option of hiring a

scheduling consultant to convert the plans and intentions to the scheduling technique

specified in the contract.

When multiple prime contracts are involved in project delivery, the

responsibility for overall schedule preparation is best left to the owner or the

owner’s agent. The owner is the only party with the authority and economic power

to schedule and coordinate the multiple prime contractors involved. This does not,

of course, preclude specifying and allowing the prime contractors to develop their

own schedules for their own portions of the work and then monitoring them

separately or on an integrated basis, throughout the life of the project.

When a design-build contractor is involved, the contractor or construction

manager should be directly responsible for scheduling and coordination of the work.

Regardless of the schedule preparation method chosen, the degree of success will

depend on five conditions (Jon M. W. et. al., 2002):

(1) All parties need to commit to making the schedule work;

(2) A good scheduling specification must be prepared to properly

communicate to all parties their contractually required responsibilities,

methods, and procedures for scheduling;

(3) Once the schedule is agreed on, it must be implemented and periodically

updated to reflect current status and how the remaining work is to be

completed;

(4) Timely and accurate submissions of delay analyses by all parties

involved are a must to keep the schedule properly adjusted for excusable

delay. Each party should strive to maintain a correct posture for the time

of performance; and

(5) The owner, or the party having the responsibility for overall schedule and

coordination and the economic power to enforce the schedule, must

Page 55: justinbongchunntatma081181ttt

36

ensure schedule compliance by the various parties involved so as not to

delay another party.

2.10 Factors Affecting in the Preparation of Better Construction Work

Schedule

According to Mohamad Ibrahim et. al. (2006), they believed that four areas

should be properly investigated prior to the development of the project scheduling

procedures. The critical areas that have been identified are process of acceptance,

responsibilities of contracting parties, application of work schedule, and

implications of work schedule.

According to Jon et. al. (2002), clear and concise schedule specifications

outlining the responsibilities for scheduling and the requirements for preparation,

approval, participation, use, maintenance, and reporting are essential for timely and

successful completion of most projects. Unfortunately, poor scheduling especially in

terms of its specifications, have contributed to the downfall of many projects. Some of

the common problems associated with the poor construction work schedule include:

(1) Not being specific about the method of scheduling required.

Whatever the scheduling method chosen, it should be stated clearly and

eliminate any opinions or ambiguities;

(2) Not requiring contractors to involve subcontractors in schedule

development and implementation.

This is compounded by the problem of prime contractors;

(3) Specifying only a maximum number of activities required.

The level of detail required should be based on specific criteria. Based

on experience, a minimum number of activities should be specified to

ensure a sufficient level of detail;

Page 56: justinbongchunntatma081181ttt

37

(4) Owners not approving or rejecting a contractor’s schedule in a timely

manner and not stating reasons for rejecting when formal approval of a

schedule is required.

Owner should state clearly in the specification how long he intends to

take to review and approve the contractor’s schedule or reject it as

unreasonable or not feasible;

(5) Stating that the schedule will be periodiacally updated, but not being

specific about the frequency of such updates.

The frequency of updating should be clearly stated, such as mothly or

bi-weekly. If the specified freuquency becomes unnecessary, the

requirement can always be reduced to a lesser frequency, either

temporarily or permanently;

(6) Not requiring joint updates.

Joint updates involving all key parties are encouraged to maximize

communication abouyt schedule, performace, problems, actions reuired,

and intended plans for completion. The objective is to eliminate the

surprises that can result when a single party independently prepares an

update and distributes the updated version of the schedule to all other

project participants;

(7) Not requiring that all physical access and availability restraints be

incorporated into the project schedule.

The party responsible for preparing the schedule should include this

information in the schedule and define the relationship of each restraint

to the sequence of work planned to accomplish the required scope of

work within the time period specified;

(8) Not specifying an explicit period for review and approval of shop

drawings and other contractual submittals.

Many contracts simply state that shop drawings will be submitted

within a reasonable period of time. Define reasonable by stating

specifically when submittals are to be made at the duration of their

review and submittal periods;

(9) Not requiring owner-furnished equipment to be incorporated into a

construction schedule.

Page 57: justinbongchunntatma081181ttt

38

This is essential for identifying proper dependency and time impact

when delivery delays occur;

(10) Not specifying in the contract all contractual dependencies with

proceeding, concurrent, and follow-on contractors in a multi-prime

contractor project.

Additionally, not requiring prime contractors to define other key points

of interface, particularly with the subcontractors and suppliers on which

they are dependent;

(11) Allowing manpower and equipment restraints to create critical and

near-critical paths.

These situations may be the result of float abuses, which attempt to hide

float that normally exists. Critical or near-critical paths are those with

less than two weeks of contingency;

(12) Not giving specific instructions for graphic techniques to be used for

network or bar-chart construction.

The failure to require readable time-scaled diagrams for the original

plan and updates can result in schedules that are useless and effectively

unintelligence to the owner, subcontractors, architect/engineer, and

contractor;

(13) Not including in the specifications remedies for noncompliance of

initial schedule submittal and subsequent update information;

(14) Not including a narrative reporting requirement as part of the update

process;

(15) Not including a remedy for schedule-specification discrepancies.

Most specifications include a statement that, in the event of

discrepancies, the specifications shall govern the development and

utilization of the project schedule;

(16) Stating a maximum duration requirement for activities.

Keeping durations to a minimum, along with criteria for levels of

indenture, is appropriate;

(17) Not requiring time extensions to be justified by proper documentation

(such as the use of time-impact analyses and fragnets) and not

requiring that they be submitted to illustrate the impact of various types

of delays.

Page 58: justinbongchunntatma081181ttt

39

(18) Restricting network changes until the contractor submits details in

writing and the owner formally approves;

(19) Preparing an integrated schedule for a project involving numerous

prime contractors, subcontractors, and suppliers, and then not allowing

their direct participation; and

(20) Completely restricting any schedule changes involving change orders

and/or delays until an agreement on cost is reached.

Furthermore, to study the factors affecting the preparation of construction

work schedule, a throughout analysis is done on the factors affecting the schedule

performance of a project. Previous studies were done by Iyer et. al. (2006) on

critical factors affecting the schedule performance, an evidence from the Indian

Construction Projects. From this study, the critical factors were being analyzed and

a new list of factors was being developed. They were divided into 4 categories,

namely project specific factors, project management, working condition and external

environment.

2.10.1 Project Specific Factors

Project Specific factors which were affecting the preparation of better

construction work schedule was the type of project which is undertaken, the nature

of the project, complexity of the project and size of the project.

Page 59: justinbongchunntatma081181ttt

40

2.10.2 Project Management

According to Chua et. al. (1999), project management action is a key for

project success. By using management tools, the project managers would be able to

plan and execute their construction projects to maximize the project’s chances of

success. Thus, the variable in the project management include inadequate

communication, control mechanism, feedback capabilities, troubleshooting,

coordination effectiveness, decision making effectiveness, monitoring, project

organization structure, planning of schedule, and related previous management

experience.

A number of attributes which will affect the preparation of better

construction work schedule includes, communication system, planning effort, safety

and quality assurance program and overall managerial actions. The list of attributes

under this factor is as follows:

(1) Coordination with other team members;

(2) Leadership quality;

(3) Technical capability;

(4) Authority to make decisions;

(5) Ability to delegate authority to team members;

(6) Understanding responsibilities of team Members;

(7) Commitment of all parties;

(8) Backing up plan;

(9) Identifying critical activities;

(10) Availability f resources;

(11) Human resource training;

(12) Monitoring and feedback by client;

(13) Project completion date specified but not yet planned;

(14) Mismatch in capabilities of client and architect;

(15) Tendency to pass on the blame to others;

(16) Conflicts among team members;

Page 60: justinbongchunntatma081181ttt

41

(17) Ignorance of appropriate planning tools and techniques;

(18) Reluctance in timely decision;

(19) Lack of understanding of operating procedures;

(20) Inadequate project formulation in the beginning;

(21) Negative attitude;

(22) Aggressive competition at tender stage; and

(23) Uniqueness of the project activities requiring high technical know-how.

2.10.3 Working Condition

This factor comprises attributes like scope and nature of work and also the

climatic condition at site.

2.10.4 External Environment

The attributes under this factors includes the economic environment, social

environment, political environment, physical environment, industry relation

environment and technical advancement.

Page 61: justinbongchunntatma081181ttt

42

2.11 Summary

Today’s available technology can allow everything from instant

communication to actual web camera supervision of the job site. The ability to

update and make changes as soon as new information is available reduces delays

and allows everyone to make the best use of their time. Take full advantage of the

capabilities of construction schedule and project planning software by fostering a

team attitude that encourages everyone involved to take ownership of the plan. The

end result will be a construction schedule and plan that is useful throughout every

stage of construction from conception to post-construction analysis.

Moreover, it is difficult to establish standard specifications for use in the

construction industry. Despite advances, more effort is needed to shift preferences

towards employing scheduling technology. Scheduling software aids in the

effective daily decision-making on projects, predicting time problems encountered

when altering the scope of work. No single industry scheduling procedure is

applicable for all projects. However, the procedure for reaching timely scheduling

decisions should be established prior to its demand. Contractor preferences for

updating, cost loading, and formatted reports effect the success of the project.

Specifications for these scheduling issues should be agreed upon by all parties prior

to construction and included in the contract’s supplemental conditions.

Page 62: justinbongchunntatma081181ttt

RESEARCH

CHAPTER 3

METHODOLOGY

Page 63: justinbongchunntatma081181ttt

CHAPTER 3

RESEARCH METHODOLOGY

3.1 Introduction

This chapter describes the methodology and procedures applied in achieving

the objectives of this research. Method of data collection described in orderly manner

in the aspects of how the data were collected, where the data is to be source and how

the design till implementation of the questionnaire.

3.2 Literature Review

A comprehensive literature review had been carried out through variety

information sources, which included library reference books, journal, articles and

researches papers and reports from Internet. These reviews help the writer having

more understanding in:

Page 64: justinbongchunntatma081181ttt

44

(1) Factors that affect in the preparation of construction work schedule

(2) Project team layers roles and responsibility throughout the course of

construction period.

(3) The severity of these factors from previous study for local and

international condition.

3.3 Methods of Data Collection

Data collection is considers as the crucial stage in gathering all required

information form the fundamental in achieving main objectives of the study. Basically,

the main or primary data were collected from literature review. Data collected from

studies regarding the preparation of good construction work schedule. All factors

obtained from previous from previous study were listed. The primary data was as a

platform for the formulation of questionnaire.

Secondary data is the finalize questionnaire as the main data to be used for the

analysis for the study. Secondary data are collected form questionnaire survey. The

data collect through questionnaire survey delegated to contractors that involve in

management of construction project.

Page 65: justinbongchunntatma081181ttt

45

3.3.1 Primary Data Collection

The primary data in this study were gathered through literature review of

journals by on preparation of good construction work schedule in construction project.

A list of factors were identified and listed as a guideline to develop the questionnaire

for study. Besides factors causes, identification of factors improvement to minimize

the problem was also identified. From the factors identified, selection was done to

suit the suitability for local industry as the previous study was for international

condition.

The selection of the factors affects was alone also done by studying from

surveys with the selected project team players. From their past experience not all of

these factors seem to be suitable for local condition and some of these factors also

seem to be repeated (same factor meaning but different statement). The project team

players selected were also asked about their opinion on improvement factors in order

to minimize the poor performance problem.

The purpose of this primary data was as a guideline to develop the final

questionnaire. Selection on factors suitability was important to produced short and

simple yet compact and informative questionnaire.

3.3.2 Secondary Data Collection

The questionnaires structure framed based on three types of answering

techniques, namely rating-based, selective based and open-ended format. Rating-

based format, respondents were instructed to rate their opinion for a specific fact by

making a 5-point scale ranging from Strongly Disagree to Strongly Agree. Secondly,

selective-based questions only required respondents to tick in the appropriate box or

boxes.

Page 66: justinbongchunntatma081181ttt

46

The structured questionnaires for this study would cover 3 sections,

(1) Section 1: The background of the respondents such numbers of years

of experience, qualification, his/or position in the company. The

company profile where he/she currently employed, such as business

activity and nature of the company.

(2) Section 2: The second part comprises the questions the indicating the

possible factors that could affect in the preparation of construction

work schedule in a construction project.

(3) Section 3: Third part would be the proposed methods of improvement

when preparing better construction work schedule.

In this study, there were 100 questionnaire being distributed to randomly

selected respondents which are contractor from Johor of classes G5 to G7 registered

under CIDB, with various ages group, level of experience, organizations, working

nature and responsibilities as their involved in managing construction project.

The chosen respondents for the study are involve themselves in the

construction project running and in particular had encounter experience during

construction phase. In addition to that, the selected organizations are ranging from

medium to large scale organization only. The frameworks of categories of the

respondents are from executive level and managerial level and having responsibility

in running respective construction project representing the contractors.

Page 67: justinbongchunntatma081181ttt

47

3.4 Analysis Method

The data are processed and analyzed partly by the researcher examination and

partly using the Statistical Package Social Science (SPSS). The analysis of the data

from the receivable feedback from the questionnaire quantitative stimulation for

instance in average index calculation. Average index was calculated to reflect the

effectiveness of aforementioned criteria. The analysis will rank the factors based on

the frequency analysis and the average index. This index was calculated as follows

(Abd Majid and McCaffer, 1997):

Average Index Formula:

Average Index =

μ = Weighting given to each factor by respondents (1 to 5);

n = Frequency of the respondents;

N = Total number of respondents

Whereby the application of Average index in questionnaire for instance would be:

μ1

μ

= 1, frequency of “Strongly Disagree” response

2

μ

= 2, frequency of “Disagree” response

3

μ

= 3, frequency of “Neutral” response

4

μ

= 4, frequency of “Agree” response

5

= 5, frequency of “Strongly Agree” response

∑ μ X n

N

Page 68: justinbongchunntatma081181ttt

48

Besides, they can be represented by:

1 = Very High Degree of Consideration

2 = High Degree of Consideration

3 = Neutral Consideration

4 = Low Degree of Consideration

5 = Very Low Degree of Consideration

With the rating scale as below: (Abd Majid and McCaffer, 1997)

1 = Strongly Disagree (1.00 ≤ Average index < 1.5)

2 = Disagree (1.50 ≤ Average index < 2.5)

3 = Neutral (2.50 ≤ Average index < 3.5)

4 = Agree (3.5 ≤ Average index < 4.50)

5 = Strongly Agree (4.5 ≤ Average index < 5.00)

3.6 Reporting Results

All possible factors that affect the preparation of better construction work

schedule were listed and ranked according to the rating scale by respondents. These

factors were divided into 8 categories:

(1) Project specific factors;

(2) Project management;

(3) Working Condition;

(4) External Environment

Besides factors affecting, the improvements methods to prepare better

construction work schedule were also identified and reported to project team

member’s responsibilities.

Page 69: justinbongchunntatma081181ttt

49

3.7 Summary

The data collection for this study was obtained from literature review and

questionnaire. Through literature review, factors affecting the preparation of better

construction work schedule were obtained from previous researchers. The pin-pose of

questionnaire was to gain more information on the possible factors from the

respondents’ opinion and past experience. Besides that, there were questions for

the respondents to rank the severity of these factors. Questionnaire survey was

conducted in to gain information for this study. The questionnaire consist of three (3)

section, where the first section was about the background of the respondents, the

second section indicated possible factors affecting the preparation of better

construction work schedule and the third section was the proposed improvement

methods to prepare better construction work schedule of the construction

projects.

Page 70: justinbongchunntatma081181ttt

DATA ANALYSIS

CHAPTER 4

AND FINDINGS

Page 71: justinbongchunntatma081181ttt

CHAPTER 4

DATA ANALYSIS AND FINDINGS

4.1 Introduction

This chapter presents the research analysis and discussions. Based on the

questionnaire survey done earlier, the data will then be processed and analyzed. This

is done in order to generate the results which will then be tabulated and used for

further discussion. The first section explains the respondents’ demographic profile.

The next two sections display results on the factors affecting the preparation of better

construction work schedule.

4.2 Data Collection

The qualitative data generated from the questionnaire survey was analyzed

using the frequency analysis and relative index technique as explained before. The

Page 72: justinbongchunntatma081181ttt

51

summary of data analysis for questionnaire survey will be tabulated in the next section.

The result will be used as the basis for further discussion in the next chapter.

The developed questionnaire was distributed one-hundred (100) sets to targeted

respondents within the locality of Johor contractors. Out of one-hundred (100) sets

distributed, thirty (30) sets that are 30% were managed to be returned and hence will

be used as the basis of the analysis of this research.

4.3 Demographic Profile of Respondents

The demographic profile of respondents through the questionnaire shows that

majority of the respondents were from top management of the company. The positions

held were project managers, site supervisors or site engineers, quantity surveyors,

executives and civil engineers. This shoes and proves that the data gained for the

purpose of this analysis is deemed to be strong and appropriate, as they comes from the

top management of most of the organizations. Opinions given were from diverse

perspective with professional insight.

4.3.1 Respondent’s Highest Qualifications

According to the study, Figure 4.1 showed half of the respondents hold a

Degree in Civil Engineering. 26.7% were graduated with a Degree in Science

Building. Besides, 13.3% of the respondents have the highest qualification of Degree

in Quantity Surveying. A minority holds Diploma in Quantity Surveying and LCCI

Higher Diploma with 6.7% and 3.3% each.

Page 73: justinbongchunntatma081181ttt

52

Figure 4.1: Highest Qualification of Respondents

4.3.2 Respondent’s Experience

Figure 4.2 showed the respondents’ working experience in the construction

industry. A majority of them, 36.7% have 2 to 3 years of experience. 30.0% of the

respondents have 4 to 5 years of working experience in the field. A minimum of them,

only 20.0% have less than 2 year of experience follow by 13.3% having 6 to 7 years of

experience. However, none of them have more than 8 years of experience in the field.

This proves that there were many junior level executives in the construction industry.

Figure 4.2: Working Experience of Respondents

Page 74: justinbongchunntatma081181ttt

53

4.3.3 Current Working Position

Based on the study, Figure 4.3 showed a majority of the respondents, 36.7%

hold positions as site engineer or site supervisors. Project managers and quantity

surveyors have equal percentage which is 23.3%. Next, 10.0% were of executive

levels and 6.7% were civil engineers. This is due to the fact that many respondents

graduated with a degree in civil engineering work as site engineers or site supervisors

instead of civil engineers.

Figure 4.3: Working Position of Respondents

4.4 The Analaysis of the Factors

The analysis for this section will cover the evaluation of critical factors that

have been asked in the questionnaire. In addition to that, these factors have been

discussed earlier in the literature review. Through the SPSS software, analysis is

automatically done by inserting the data, and hence the analysis is then tabulated. All

Page 75: justinbongchunntatma081181ttt

54

the factors discussed will be referred to as in short form term for instance B1, C2 and

D3 for easy identification of the factors that has been discused. The factors were

divided into four parts which is, project specific factors, project management, working

condition and external environment.

4.4.1 Analysis of Projects Specific Factors Considered

Four (4) main factors were highlighted in this section. The results of the study

were shown in Table 4.1. All (4) of this factors were ranked and anlazed using

average index and frequancy analsysis as stated before.

4.4.1.1 Average Index Analysis

Figure 4.4: Project Specific Factors

Page 76: justinbongchunntatma081181ttt

55

Based on Figure 4.4 shown, the factors of this category have the highest scale

of degree of consideration ranging from 4.50 to 5.00. The factor A3 has an average

index of 4.73 followed by factor A1 with scale of 4.70. Then, factor A4 comes next on

having a scale of 4.57. The last factor was A2 with a scale of 4.50. All of these factors

were stongly agreed by the respondents and therefore these were very imporant factors

affecting the preparation of construction work schedule.

4.4.1.2 Frequency Analysis

Table 4.1 showed the tabulation of the project specific factors in terms of its

frequancy. Based on this survey it can be seen clearly that the majority of the

respondents have a very high degree of consideration that these factors were equally

important to be considered to prepare better construction work schedule. The factor of

A3 shows 73.3% of respondents have very high degree of consideration on this factor.

This is followed by 26.7% with high degree. The factor of A1 shows that 70.0% of the

respondents have very high degree of consideration while 30.0% with high degree.

The factor A4 shows 60.0% have very high degree of consideration, 36.7% high

degree and 3.3% in neutral position. On the other hand, factor A2 shows fairly half of

all respondents who choses this factor has highest consideration, 43.3% with high

consideration and 3.3% in neutral position.

Page 77: justinbongchunntatma081181ttt

56

Table 4.1: Project Specific Factors Considered in Preparing Better Construction Work Schedule

Figure 4.5: Tabulation of Project Specific Factors

Level of Consideration 1 2 3 4 5 Average Index Rating Description

Respondent's Frequency f % f % f % f % f % A3 Complexity of Project 0 0.0 0 0.0 0 0.0 8 26.7 22 73.3 4.73 5 Strongly Agree A1 Type of Project 0 0.0 0 0.0 0 0.0 9 30.0 21 70.0 4.70 5 Strongly Agree A4 Size of Project 0 0.0 0 0.0 1 3.3 11 36.7 18 60.0 4.57 5 Strongly Agree A2 Nature of Project 0 0.0 0 0.0 1 3.3 13 43.3 16 53.3 4.50 5 Strongly Agree

Page 78: justinbongchunntatma081181ttt

57

4.4.2 Analysis for Project Management Factors Considered

Twenty-Three (23) main factors were highlighted in this section. The results of

the study were shown in Table 4.2. All (23) of this factors were ranked and anlazed

using average index and frequancy analsysis as stated before.

4.4.2.1 Average Index Analysis

Based on the Figure 4.6, first fifteen (15) factors shows above figure of scale

four (4). However, the remaining five (5) factors show below 4.00 scales. The factor

of identifying critical activities (B9) shows the scale 4.73 that is between 4.50 and 5.00

which shows that it has a very high degree of consideration. Factor B1 have average

index at 4.67. Factor B6 having a scale of 4.57 whish is also considering high degree

of consideration by the respondents. For factor B7, it shows the scale of 4.53. These

factors were considered as very imporant factors as the rating was at a scale of 5

overall. Besides, these factor were the most severe under this categoty and were

considered as top priority in any case.

Next, many factors fall under the scale between 3.50 to 4.49 which have high

degree of consideration, starting from factor B5 which has a scale of 4.43. The factor

B4 comes next having scale of 4.40. Next, factor B2 having a scale of 4.37. Factor

B19 have scale of 4.33, followed by factor B20 with scale 4.30. Then, factor B23 have

a scale of 4.23. The Factor B12 have a scale of degree of consideration 4.20. This is

followed by factor B17 having a scale of 4.17 and factor B14 with scale 4.13. Factor

B10 and B18 shows the same degree of consideration, 4.10. For the factor B16, it

shows the scale 4.00. Next, factor B13 shows a scale of 3.93 and factor B21 shows a

scale of 3.77. The factor B22 and B15 have average index of 3.73 and 3.67

respectively. These factors were fairly important as they score an overall of rating

scale 4.

Page 79: justinbongchunntatma081181ttt

58

The last factor is B11 which shows a degree of consideration of 3.40 is

considerede as not quite important. This is due to the fact that respondents believed

that human resource training may not be an important factor to be considered is this

category to prepare better construction work schedule.

Figure 4.6: Project Management Factors

Page 80: justinbongchunntatma081181ttt

59

4.4.2.2 Frequency Analysis

Figure 4.7 showed the factors identified by respondents under the category of

project management factors. Factor B9 has the highest degree of consideration with

73.3% of respondents believe that it has strong influence while 26.7% of them have

high degree of consideration. Factor B1 have 66.7% respondents who have highest

degree of consideration and 33.3% who only agree. Factor B6 shows 60.0% who

have highest degree of consideration but 36.7% who have high degree of consideration.

3.3% respondents stands neutral same as factor B3 and B7. Factor B7 has same

percentage of highest degree of consideration which is same as factor B5. Half of the

respondetns who choses factor B4 have highest degree of consideration while half of

respondents who choses factor B2 only have high degree of consideration. This case

was the same for factor B20, B23, B16 and B13 having 50.0% of high degree of

consideration. 40.0% of respondents have highest degree of consideration for factor

B19, B20, B17 and B14. Factor B17 have equal percentage (40.0%) of respondents

having very high and high degree of consideration. 16.7% stands neutral but 3.3%

have low degree of consideration on factor B17. The same case also applies to factor

B10, B16 and B13 having 3.3% with low consideration. Factor B18 has 70.0%

respondents who agree but only 20.0% strongly agree and 10.0% stands neutral.

On the other hand, factor B21, B22, B15 and B11 have equal respondents of

20.0% having highest degree of consideration for each factor respectively. Factor B21

has 43.3% who have high degree of consideration, 30.0% neutral and 6.7% with low

degree of consideration. Factor B22 have 46.7% respondents having high degree of

consideration which is same as factor B15. 13.3% of respondents stands neutral and

20.0% have ow degree of consideration for factor B15. Then, factor B11 have equal

percentage (23.3%) of respondents having high and low degree of consideration while

its neutral stand is about 33.3%.

Page 81: justinbongchunntatma081181ttt

60

Figure 4.7: Tabulation of Project Management Factors

Page 82: justinbongchunntatma081181ttt

61

Table 4.2: Project Management Factors Considered in Preparing Better Consruction Schedule

Level of Consideration 1 2 3 4 5 Average Index Rating Description

Respondent's frequency f % f % f % f % f % B9 Identifying critical activities 0 0.0 0 0.0 0 0.0 8 26.7 22 73.3 4.73 5 Strongly Agree

B1 Coordination with other team members 0 0.0 0 0.0 0 0.0 10 33.3 20 66.7 4.67 5 Strongly Agree

B6 Understanding responsibilities of team members 0 0.0 0 0.0 1 3.3 11 36.7 18 60.0 4.57 5

Strongly Agree

B3 Technical capability 0 0.0 0 0.0 1 3.3 12 40.0 17 56.7 4.53 5 Strongly Agree B7 Commitment of all parties 0 0.0 0 0.0 1 3.3 12 40.0 17 56.7 4.53 5 Strongly Agree

B5 Ability to delegate authority to team members 0 0.0 0 0.0 4 13.3 9 30.0 17 56.7 4.43 4

Agree

B4 Authority to make decisions 0 0.0 0 0.0 3 10.0 12 40.0 15 50.0 4.40 4 Agree B2 Leadership quality 0 0.0 0 0.0 2 6.7 15 50.0 13 43.3 4.37 4 Agree

B19 Lack of understanding of operating procedures 0 0.0 0 0.0 2 6.7 16 53.3 12 40.0 4.33 4

Agree

B20 Inadequate project formulation in the beginning 0 0.0 0 0.0 3 10.0 15 50.0 12 40.0 4.30 4

Agree

B23 Uniqueness of the project activities requiring high technical know-how 0 0.0 0 0.0 4 13.3 15 50.0 11 36.7 4.23 4

Agree

B12 Monitoring and feedback by client 0 0.0 0 0.0 5 16.7 14 46.7 11 36.7 4.20 4 Agree

B17 Ignorance of appropriate planning tools and techniques 0 0.0 1 3.3 5 16.7 12 40.0 12 40.0 4.17 4

Agree

B14 Mismatch in capabilities of client and architect 0 0.0 0 0.0 8 26.7 10 33.3 12 40.0 4.13 4

Agree

B10 Availability of resources 0 0.0 1 3.3 6 20.0 12 40.0 11 36.7 4.10 4 Agree

Page 83: justinbongchunntatma081181ttt

62

Table 4.2: Project Management Factors Considered in Preparing Better Consruction Schedule (Cont’d)

Level of Consideration 1 2 3 4 5 Average Index Ranking Description

Respondent's frequency f % f % f % f % f % B18 Reluctance in timely decision 0 0.0 0 0.0 3 10.0 21 70.0 6 20.0 4.10 4 Agree B16 Conflicts among team members 0 0.0 1 3.3 6 20.0 15 50.0 8 26.7 4.00 4 Agree B8 Backing up plan 0 0.0 1 3.3 8 26.7 13 43.3 8 26.7 3.93 4 Agree

B13 Project completion date specified but not yet planned 0 0.0 1 3.3 7 23.3 15 50.0 7 23.3 3.93 4

Agree

B21 Negative attitude 0 0.0 2 6.7 9 30.0 13 43.3 6 20.0 3.77 4 Agree

B22 Aggressive competition at tender stage 0 0.0 4 13.3 6 20.0 14 46.7 6 20.0 3.73 4 Agree

B15 Tendency to pass on the blame to others 0 0.0 6 20.0 4 13.3 14 46.7 6 20.0 3.67 4 Agree

B11 Human resource training 0 0.0 7 23.3 10 33.3 7 23.3 6 20.0 3.40 3 Neutral

Page 84: justinbongchunntatma081181ttt

63

4.4.3 Analysis for Working Condition Factors Considered

Two (2) main factors were highlighted in this section. The results of the study

were shown in Table 4.3. All (2) of this factors were ranked and anlyzed using

average index and frequency analysis as stated before.

Figure 4.8: Working Condition Factors

4.4.3.1 Average Index Analysis

Based on Figure 4.8, factor C1 and C2 shows they have very high degree of

consideration of a scale between 4.50 to 5.00. Factor C1 has a scale of 4.6 while factor

C2 has a scale of 4.5. Both factor C1 (scope and nature of work) and C2 (climatic

condition at site) were considerably very important factors which affects the

preparation of construction work schedule.

Page 85: justinbongchunntatma081181ttt

64

4.4.3.2 Frequancy Analysis

Figure 4.9: Tabulation of Working Condition Factors

Figure 4.9 showed the frequancy analysis of both C1 and C2 factors. Factor

C1 has 63.3% of respondents having highest degree of consideration, 33.3% have high

degree of consideration while only 3.3% stands neutral. However, factor C2 has

60.0% of respondents having highest degree of consideration. It has the same

percentage (33.3%) for high degree of consideration same as factor C1. Besides, the

percentage for respondents having neutral and low degreeof consideration is equal to

the respondents who chose neutral on factor C1 which is 3.3%.

Page 86: justinbongchunntatma081181ttt

65

Table 4.3: Working Condition Factors Considered in Preparing Better Construction Work Schedule

Level of Consideration 1 2 3 4 5 Average Index Rating Description

Respondent's Frequency f % f % f % f % f % C1 Scope and nature of work 0 0.0 0 0.0 1 3.3 10 33.3 19 63.3 4.60 5 Strongly Agree C2 Climatic condition at site 0 0.0 1 3.3 1 3.3 10 33.3 18 60.0 4.50 5 Strongly Agree

Table 4.4: External Environment Factors Considered in Preparing Better Construction Work Schedule

Level of Consideration 1 2 3 4 5 Average Index Rating Description Respondent's frequency f % f % f % f % f %

D1 Economic Environment 0 0.0 2 6.7 2 6.7 12 40.0 14 46.7 4.27 4 Agree

D6 Technological Environment 0 0.0 0 0.0 7 23.3 11 36.7 12 40.0 4.17 4 Agree

D5 Industrial Relation Environment 0 0.0 1 3.3 9 30.0 14 46.7 6 20.0 3.83 4 Agree

D2 Social Environment 0 0.0 1 3.3 10 33.3 14 46.7 5 16.7 3.77 4 Agree

D4 Physical Environment 0 0.0 3 10.0 12 40.0 11 36.7 4 13.3 3.53 4 Agree

D3 Political Environment 0 0.0 10 33.3 11 36.7 6 20.0 3 10.0 3.07 3 Neutral

Page 87: justinbongchunntatma081181ttt

66

4.4.4 Analysis for External Enviornment Factors

Two (6) main factors were highlighted in this section. The results of the study

were shown in Table 4.4. All (6) of this factors were ranked and anlazed using

average index and frequancy analsysis as stated before.

4.4.4.1 Average Index Analysis

Figure 4.10: External Environment Factors

According to Figure 4.10 shown, the factors for this category has high and

neutral degree of consideration. Factor D1 has a scale of 4.27 for the average index.

Next is factor D6 which has a scale of 4.17. Factor D5 has a scale of 3.83 while factor

D2 have a scale of 3.77. Factor D4 have average index with a scale of 3.53. These

factors were very important factors affecting the preparation of construction work

schedule. However, the final factor D3 has a scale of 3.07 is considered as not quite

important factor.

Page 88: justinbongchunntatma081181ttt

67

4.4.4.2 Frequancy Analysis

Figure 4.11: Tabulation of External Environment Factors

Figure 4.11 showed the tabulation of the factors in external environment

category in terms of its frequancy. The factor D1 has 46.7% of respondents having the

highest degree of consideration and 40.0% who have high consideration. 6.7% of the

respondents stands neutral and have low degree of consideration. On the other hand,

factor D6 have 40% of respondents having very high degree of consideration but only

36.7% have high consideration and 23.3 stands neutral. Factor D5 have larger group

of respondents (46.7%) who have high degree of consideration if compared to very

high degree (20.0%, neutral (30.0%) and low degree (3.3%). The same case happens

to factor D2 where its percentage of respondents is the same for both having high

degree of consideration and neutral. As for factor D4, 40.0% of respondents stands

neutral and followed by 36.7% who agree, 13.3% strongly agree and 10.0% disagree.

Then, factor D3 has 36.7% whostands neutral, 33.3% with low degree of consideration,

20.0% high degree of consideration and only 10.0% who strongly agree.

Page 89: justinbongchunntatma081181ttt

68

4.5 Analysis on Improvement Methods in Preparing Better Construction

Work Schedule

Table 4.5 showed the list of methods of improvement that could be considered

in preparing better construction work schedule in the construction industry.

Respondents show different opinion towards these methods of improvement.

Figure 4.12: Tabulation of Improvement Methods

From Figure 4.12, only three (3) methods were agreed totally by all

respondents which were IM3, IM5 and IM8. The other five (5) methods suggested

were not agreed by all respondents. However, the percentage of respondents who

agree that these methods will prove improvement is more than those who think

otherwise. IM1 and IM4 both have 97% of respondents who agree that these methods

were important while 80% of respondents agree on IM2 and IM6. Only 70% of

respondents agree on IM7 which proves that IM7, upgrading communication system

used or using more technology when giving information for efficiency and more

effectiveness such as email, PDA, and GPRS is not a good idea in improving the

preparation of construction work schedule. Nevertheless, these improvement methods

Page 90: justinbongchunntatma081181ttt

69

should be consider as an important actions to be taken by all project team players to

improve the preparation of construction work schedule.

Table 4.5: Improvement Methods in Preparing Better Construction Schedule

Improvement Methods Yes No

Frequency (f)

Percentage (%)

Frequency (f)

Percentage (%)

IM3 Project team members must be committed to their responsibilities.

30 100 0 0

IM5

Continuous and proper planning before construction, so that resources and time are sufficient.

30 100 0 0

IM8 Give prompt feedback/action when any matter arises.

30 100 0 0

IM1

Project team leaders should keep good relationship with all project participants.

29 97 1 3

IM4 Contractor should manage his financial resources and plan cash flow.

29 97 1 3

IM2

Learn more on managing human, because with good skill on human management and good motivating skill, motivated workers could improve productivity.

24 80 6 20

IM6

Material supply should be readily preserved to avoid insufficient or depleted resources.

24 80 6 20

IM7

Upgrade communication system used. Use more technology when giving information for efficiency and more effectiveness such as email, PDA, and GPRS. It is better to give information in written form rather than verbal instruction or information.

21 70 9 30

Page 91: justinbongchunntatma081181ttt

70

4.6 Additional Suggested Factors Affecting in the Preparation of Construction

Work Schedule

Out of the thirth (30) respondents, one respondents suggested that transparency

in sharing data among involved parties is also a factor which should be considered

when preparing the construction work schedule. Besides he also suggested that team

players should have good communication skill as a method of improvement.

4.7 Discussion of Findings

The information obtained through earlier literature study in Chapter 2,

literature review and the results from the questionnaire distribution for questionnaire

survey of the local contractors have fulfilled the objective of this study.

In general, this thesis was conducting an exploratory study on the preparation

of construction work schedule to determine the factors which were affecting this

mater in the construction industry. Therefore, the objectives of the study and findings

will be reviewed as a resolution of the objectives. There were three (3) objectives

posted in this study and further details on the individual findings and an overall

outcome as the general conclusion summarized the entire study.

In this study, thirty-five (35) possible factors affecting the preparation of better

construction work schedule were investigated. These factors were divided into four

(4) main categories namely project specific factors, project management factors,

working condition factors and external environment related factors. From the factors

listed, eleven (11) factors scored an average index between 4.50 to 5.00 rating scale,

twenty-two (22) factors has average index between 3.50 to 4.5 rating scale, whereas

only 2 factors were have average index between 2.00 to 3.49 rating scale. This means

Page 92: justinbongchunntatma081181ttt

71

that most of the respondents have fairly high degree of consideration of most of the

factors discussed.

Besides, this study has also identified the importance of these factors that

affect the preparation of better construction work schedule. The factors which were

very important were complexity of project, type of project, size of project and nature

of project under the project specific factors.

Complexity of project is important as the activities and procedures involved

will need a different approach from conventional. A more complex the construction

project, the more complex the construction project, the greater the complication in

preparing the construction work schedule. Besides, the type of project must be

determined first whether it is a commercial building, housing estates, schools or

others. Each building project requires different construction work schedule. Size and

nature of project should be taken into consideration seriously before preparing the

construction schedule. Large construction projects, such as an office building or

industrial complex, are often too complicated. These projects are divided into many

segments such as site preparation, landscaping and the building construction which

require schedulers to determine the best way to get materials to the building site and

the most cost-effective plan and schedule for completing the project. all required

construction site activities are divided into logical steps, budgeting the time required

to meet established deadlines which will require sophisticated estimating and

scheduling techniques and use of computers with specialized software.

On the other hand, all the project management related factors was also

important except for human resource training. The factor, identification of the critical

activities, coordination with other team members, understanding responsibilities of

team members, technical capability and commitment of all parties were very

important. Every activities involved in the whole construction process should be

carefully listed and planned systematically to avoid missing tasks and delay. This is

also to smooth the construction process with a clear direction of process to follow.

Every members participating in a construction project should keep a god relationship

between each other in order to ensure that works carry out is according to plan.

Without good relationship, problems may arise and team members, authority to make

Page 93: justinbongchunntatma081181ttt

72

decisions, leadership quality difficult to solve jeopardizing the work and causing the

project to be in chaos.

Nevertheless, the other project management related factors which were the

ability to delegate authority to team members, authority to make decisions, leadership

quality, technical capability, lack of understanding of operating procedures,

inadequate project formulation in the beginning, uniqueness of the project activities

requiring high technical know-how, monitoring and feedback by client, ignorance of

appropriate planning tools and techniques, reluctance in timely decision, mismatch in

capabilities of client and architect, availability of resources, reluctance in timely

decision, conflicts among team members, project completion date specified but not

yet planned, negative attitude, aggressive competition at tender stage, and tendency to

pass on the blame to others are quite important. Thus, the construction team members

should always pay attention to these factors to prepare a good construction work

schedule so that construction work can be carried out smoothly and effectively.

Factors with the lowest average index were human resource training and

political environment. The construction players believed that human resource training

affect the preparation of construction work schedule less. However, it can educate

team members to learn more on managing human and projects which improve

productivity.

Furthermore, working condition related factors were also very important. The

scope and nature of work was considered as very important because the scope and

nature of work will be the base for preparing the construction work schedule.

Inaccurate scope and nature of work will result in misleading deceptive or false

statement or even claims in the construction projects.

External environment related factors were fairly important affecting in the

preparation of construction work schedule. These factors refer to economic

environment, technological environment, industrial relation environment, social

environment and physical environment. These factors were inter-related to all the

other factors mentioned above. Economic environment seem to be important due to the

importance of the country economic situation.

Page 94: justinbongchunntatma081181ttt

73

Methods of improvement in preparing construction work schedule were also

identified in order to help the project team members produce a more effective and

good construction work schedule. Any improvement methods will help in the

preparation but only a few will drastically enhance the development of the

construction work schedule namely project team leaders should keep good

relationship with all project participants, continuous and proper planning before

construction so that resources and time were sufficient and give prompt

feedback/action when any matter arises.

4.8 Summary

Based on the survey done above, it can clearly be seen that there were some

factors that were in theory which might not be as important as everyone thinks.

However, when it comes to practical, it plays such an important role in determining the

success of a project. This can be seen from the responses given by the respondents.

Quantitative and qualitative judgements were employed in data analysis. Statistics

were used to analyze the background of the respondents and Likert scaling system was

used to analyze the factors that were presented in the questionnaire form.

According to the result of the analysis, the factors vary from one situation to

another. The analysis indicated that thirty-five (35) possible factors that should be

considered in preparation of consruction work schedule were divided into four (4)

catagories namely, project specific factors, projectmanagemtn, working condition and

external environment. The factors listed have achieved the average index ranging from

3.07 to 4.73 rating scale. Ten (11) factors have scale from 4.50 to 5.00 average index

as very high degree of consideration. However, most of the factors, twety-one (22)

have average index between 3.50 to 4.50 rating scale The remaining factors which is

only two (2) have average index between 2.00 to 3.5 rating scale. This shows that

most of the factors agreed by the respondents to be considered in preparing better

construction work schedule.

Page 95: justinbongchunntatma081181ttt

74

The most critical factors with the highest average index overall would be the

complexity of the project and identifying critical factors with average index of 4.73

and type of project with average index of 4.70 rating scale respectively. Generally,

project specific factors is considerably most important when preparing construction

work schedule. Then, it is followed by the project management and working condition

factors which is also quite significant. In fact, from the study it was revealed that the

external environment factors were less vital compared to the other factors in this matter.

Page 96: justinbongchunntatma081181ttt

CONCLUSION

CHAPTER 5

AND

RECOMMENDATIONS

Page 97: justinbongchunntatma081181ttt

CHAPTER 5

CONCLUSION AND RECOMMENDATIONS

5.1 Introduction

This chapter concludes the study by the discussion of the results of the data

analysis done on Chapter 4 on data analysis and findings. This study basically aimed

to reveal the main factors that normally being considered in the preparation of the

construction work schedule. From the extensive literature review, those factors are

discussed with a sound knowledge of the factors in various angles were achieved.

5.2 Conclusion

As a conclusion to the study, the objectives of the study and findings will be

reviewed as a resolution of the objectives. There were three (3) objectives posted in

this study and further details on the individual findings and an overall outcome as the

general conclusion to summarize the entire study.

Page 98: justinbongchunntatma081181ttt

76

Objective 1:

To investigate the factors affecting the preparation of a better construction work

schedule.

Table 5.1 below showed the summary of the 33 factors which affects the preparation

of construction work schedule in the construction industry according to category.

Table 5.1: Factors Affecting the Preparation of Better Construction Work Schedule

No Factors Affecting the Preparation of Construction Work Schedule Factors Category

1 Complexity of Project Project Specific Factors 2 Type of Project Project Specific Factors 3 Size of Project Project Specific Factors 4 Nature of Project Project Specific Factors 5 Identifying critical activities Project Management Factors 6 Coordination with other team members Project Management Factors 7 Understanding responsibilities of team members Project Management Factors 8 Commitment of all parties Project Management Factors 9 Ability to delegate authority to team members Project Management Factors

10 Authority to make decisions Project Management Factors 11 Leadership quality Project Management Factors 12 Technical capability Project Management Factors 13 Lack of understanding of operating procedures Project Management Factors 14 Inadequate project formulation in the beginning Project Management Factors

15 Uniqueness of the project activities requiring high technical know-how Project Management Factors

16 Monitoring and feedback by client Project Management Factors

17 Ignorance of appropriate planning tools and techniques Project Management Factors

18 Reluctance in timely decision 19 Mismatch in capabilities of client and architect Project Management Factors 20 Availability f resources Project Management Factors 21 Reluctance in timely decision Project Management Factors 22 Conflicts among team members Project Management Factors

23 Project completion date specified but not yet planned Project Management Factors

24 Negative attitude Project Management Factors 25 Aggressive competition at tender stage Project Management Factors 26 Tendency to pass on the blame to others Project Management Factors 27 Human resource training Project Management Factors 28 Scope and nature of work Working Condition Factors 29 Climatic condition at site Working Condition Factors 30 Economic Environment External Environment Factors

Page 99: justinbongchunntatma081181ttt

77

Table 5.1: Factors Affecting the Preparation of Better Construction Work Schedule

(Cont’d)

No Factors Affecting the Preparation of Construction Work Schedule Factors Category

31 Technological Environment External Environment Factors 32 Industrial Relation Environment External Environment Factors 33 Social Environment External Environment Factors 34 Physical Environment External Environment Factors 35 Political Environment External Environment Factors

Objective 2:

To establish the severity of these factors.

Table 5.2showed the severity of the factors affecting the preparation of construction

work schedule in terms of average index from the highest to the lowest index.

Table 5.2: Severity of Factors Affecting Preparation of Better Construction Work

Schedule

No Factors Affecting the Preparation of Construction Work Schedule

Average Index Factors Category

1 Complexity of Project 4.73 Project Specific Factors 2 Identifying critical activities 4.73 Project Management Factors 3 Type of Project 4.70 Project Specific Factors

4 Coordination with other team members 4.67 Project Management Factors

5 Scope and nature of work 4.60 Working Condition Factors 6 Size of Project 4.57 Project Specific Factors

7 Understanding responsibilities of team members 4.57 Project Management Factors

8 Technical capability 4.53 Project Management Factors 9 Commitment of all parties 4.53 Project Management Factors

10 Nature of Project 4.50 Project Specific Factors 11 Climatic condition at site 4.50 Working Condition Factors

12 Ability to delegate authority to team members 4.43 Project Management Factors

13 Authority to make decisions 4.40 Project Management Factors 14 Leadership quality 4.37 Project Management Factors

15 Lack of understanding of operating procedures 4.33 Project Management Factors

16 Inadequate project formulation in the beginning 4.30 Project Management Factors

17 Economic Environment 4.27 External Environment Factors

Page 100: justinbongchunntatma081181ttt

78

Table 5.2: Severity of Factors Affecting Preparation of Better Construction Work

Schedule (Cont’d)

No Factors Affecting the Preparation of Construction Work Schedule

Average Index Factors Category

18 Uniqueness of the project activities requiring high technical know-how 4.23 Project Management Factors

19 Monitoring and feedback by client 4.20 Project Management Factors

20 Ignorance of appropriate planning tools and techniques 4.17 Project Management Factors

21 Technological Environment 4.17 External Environment Factors

22 Mismatch in capabilities of client and architect 4.13 Project Management Factors

23 Availability of resources 4.10 Project Management Factors 24 Reluctance in timely decision 4.10 Project Management Factors 25 Reluctance in timely decision 4.10 Project Management Factors 26 Conflicts among team members 4.00 Project Management Factors

27 Project completion date specified but not yet planned 3.93 Project Management Factors

28 Industrial Relation Environment 3.83 External Environment Factors 29 Social Environment 3.77 External Environment Factors 30 Negative attitude 3.77 Project Management Factors 31 Aggressive competition at tender stage 3.73 Project Management Factors

32 Tendency to pass on the blame to others 3.67 Project Management Factors

33 Physical Environment 3.53 External Environment Factors 34 Human resource training 3.40 Project Management Factors 35 Political Environment 3.07 External Environment Factors

Objective 3:

To identify the methods of improvement in preparing better construction work

schedule.

In order to improve and prepare better and good construction work schedule, some

recommendations are listed below as a guideline for the project team members:

1. Project team leaders should keep good relationship with all project participants.

2. Continuous and proper planning before construction, so that resources and

time are sufficient.

3. Give prompt feedback/action when any matter arises.

4. Project team leaders should keep good relationship with all project participants.

Page 101: justinbongchunntatma081181ttt

79

5. Contractor should manage his financial resources and plan cash flow.

6. Learn more on managing human, because with good skill on human

management and good motivating skill, motivated workers could improve

productivity

7. Material supply should be readily preserved to avoid insufficient or depleted

resources.

8. Upgrade communication system used. Use more technology when giving

information for efficiency and more effectiveness such as email, PDA, and

GPRS. It is better to give information in written form rather than verbal

instruction or information.

5.4 Recommendation for Future Study

Another study can be done for other specific type of projects, such as housing

projects, utility projects, highway projects, dam construction projects, etc. Detail

studies can be done to evaluate the effectiveness of the construction work schedule on

the particular project in the construction industry.

In fact, the limitation regarding this study was that study was done at the

respondents own point of view. Thus, a case study can be employ to study on various

types of projects to determine the influence of these factors on the scheduling works

of these projects.

Page 102: justinbongchunntatma081181ttt

80

5.5 Summary

The objectives of this study were achieved by investigation of the important

factors affecting the preparation of better construction work schedule of a

construction project. The three most critical factors affecting in the preparation of

construction work schedule identified were complexity of the project, identifying

critical factors and type of project. In fact, project specific factors was considerably

most important affecting in the preparation of construction work schedule followed by

the project management and working condition factors. However, external

environment factors are less vital. Recommendations on the improvement of the

problem faced were also discussed after the analysis of the findings was done. More

effective and good construction work schedule can be produced if project team

players consider the methods of improvements identified in this study seriously in

their construction work.

Page 103: justinbongchunntatma081181ttt

REFERENCES

AND

BIBLIOGRAPHY

Page 104: justinbongchunntatma081181ttt

81

REFERENCES AND BIBLIOGRAPHY

Abd. Majid, M.Z., and Mc Caffer, R. (1997). Assessment of Work Performance of

Maintenance Contractors in Saudi Arabia Journal of Management in Engineering,

ASCE, Vol. 17 No. 1:91

Ballard Glenn. (1997). Lean construction and EPC performance improvement. Luis

Alarcon: Lean Construction.

Callixtus Tamin. (2005). Factors Affecting the ‘S’ Curve in Determining Project

Completion. UTM.

Che Wan Fadhil Che Wan Putra. (2001). Basic Review of Construction Work Scheduling

Approaches. Faculty of Civil Engineering. UTM.

Chua D.K.H., Kog Y.C. and Loh P.K. (1999). Critical Success Factors for Different

Proect Objectives. Journal of Construction Engineering and Management,

May/June.

Claugh RH, Sears GA, Sears SK. (2000). Construction project management. 4th ed.

Walker A. Project management in construction. 3rd ed. Blackwell Science; 1996.

CMAA. (2005). Construction Management Association of America: What does a

Construction Manager really do? Retrieved December 6, 2005.

http://cmaanet.org/job_analysis.php

Committees of the Association for the Advancement of Cost Engineering (AACEI) and

the Project Management Institute College of Scheduling (PMICoS). 2005.

Approach. http://www.constructionschedule.net/

Page 105: justinbongchunntatma081181ttt

82

Frank J, P.E. (2004). Construction Scheduling 101: Characteristic of a Good

Construction Schedule. Article 3 of 4. Pinnacleone. The conrnerstone of

confidence. http://www.pinnacleone.com/assets/files/PinnacleOne_Characteristics

_Good_Construction_Schedule.pdf

Glavinich, T. E. (2004). Construction Planning and Scheduling, 2nd Edition. Arlington,

VA, Associated General Contractors of America.

Glenwright E. (2008). Contemporary Aspects of Critical-Path Planning and Scheduling.

Part1. PM World Today. Volume X. Issue

III. http://www.pmforum.org/library/papers/2008/PDFs/Glenwright-3-08.pdf

Harban Singh, K.S. (2004). Work Programme - A Contractual Perspective. Buletin

Ingenieur Volume 21.

Hendrickson C. (1998). Project Management for Construction. First Edition. Prentice

Hall.

Iyer K.C. and Jha K. N. (2006). Critical Factors Affecting Schedule Performance:

Evidence from Indian Construction Projects. Journal of Construction Engineering

and Management, August.

Kiiras J. Project Management in Chaos. No. 2, 2001.

Mohamad Ibrahim Mohamad, Rosli Mohamad Zin

Guidelines for the Preparation and Submission of Work Schedule for

Construction Project. Faculty of Civil Engineering, UTM. Malaysian Journal of

Civil Engineering, 20 (2). pp. 145-159.

and Donald Chan B. T. (2006).

Tatiana Rina Puspasari. (2005). Factors Causing the Poor Performance of Construction

Page 106: justinbongchunntatma081181ttt

83

Project. UTM.

Twomey M. (2006). Keeping Construction on Schedule.

http://www.areadevelopment.com/assetManagement/june06/constructionProjects.

shtml

USDL (2005). United States Department of Labor, Bureau of Labor Statistics.

Construction Managers. Retrieved December 6, 2005.

http://www.bls.gov/oco/ocos005.htm

Wickwire Jon M., Jones Allen M., Wickwire Esq, Driscoll Thomas J., Hurlbut Stephen B.

(2002). Construction Scheduling: Preparation, Liability, and Claims. Edition 2.

Aspen Publishers Online.

Willis E. M. (1986). Scheduling Construction Projects. John Wiley and Sons, Inc.

United States of America.

William C. Last, Jr. 2009. The Use of a Construction Schedule to Analyze a Delay.

http://www.lhfconstructlaw.com/CM/Articles/Articles104.asp

Page 107: justinbongchunntatma081181ttt

APPENDIX

Page 108: justinbongchunntatma081181ttt

APPENDIX A

QUESTIONNAIRE FORM

Page 109: justinbongchunntatma081181ttt

84

APPENDIX A

QUESTIONNAIRE FORM

Section A: Respondent’s Background

(Please and answer in given spaces)

1. Name : _______________________________________

2. Highest Qualification : _______________________________________

3. Working experience in the construction Industry

less than 2 years 6 to 7 years

2 to 3 years more than 8 years

4 to 5 years

4. Current Position : _______________________________________

5. Contact No. : _______________________________________

6. Company’s Name : _______________________________________

_______________________________________

7. Company’s Address : _______________________________________

_______________________________________

_______________________________________

8. Company’s Stamp:

Page 110: justinbongchunntatma081181ttt

85

SECTION B: Factors Affecting in the Preparation of Better Construction Work

Schedule

This section aims to evaluate the critical factors contributed to the preparation of better

construction work schedule.

Please use the scale below to rate the degree of consent of the following statement based

on your experience. (Please and answer in given spaces)

Strongly Agree Neutral Disagree Strongly

Agree Disagree

A. Project Specific Factors

1. Type of project

2. Nature of Project

3. Complexity of Project

4. Size of Project

B. Project Management

1. Coordination with other team members

2. Leadership quality

3. Technical capability

4. Authority to make decisions

5. Ability to delegate authority to team

members

6. Understanding responsibilities of team

Members

7. Commitment of all parties

8. Backing up plan

9. Identifying critical activities

10. Availability of resources

11. Human resource training

12. Monitoring and feedback by client

Page 111: justinbongchunntatma081181ttt

86

Strongly Agree Neutral Disagree Strongly

Agree Disagree

13. Project completion date specified but

not yet planned

14. Mismatch in capabilities of client and

architect

15. Tendency to pass on the blame to others

16. Conflicts among team members

17. Ignorance of appropriate planning tools

and techniques

18. Reluctance in timely decision

19. Lack of understanding of operating

procedures

20. Inadequate project formulation in the

beginning

21. Negative attitude

22. Aggressive competition at tender stage

23. Uniqueness of the project activities

requiring high technical know-how

C. Working Condition

1. Scope and nature of Work

3. Climatic condition at site

D. External Environment

1. Economic Environment

2. Social Environment

3. Political Environment

4. Physical Environment

5. Industrial Relation Environment

Page 112: justinbongchunntatma081181ttt

87

6. Technological advancement

Besides the factors mentioned above, is there any other factors which may contribute to

the poor preparation of construction work schedule?

________________________________________________________________________

________________________________________________________________________

________________________________________________________________________

Page 113: justinbongchunntatma081181ttt

88

SECTION C: Improvement Methods in Preparing Better Construction Work

Schedule

This section aims to identify improvement methods in preparing better construction work

schedule.

Please thick () Yes / No for the methods which can help improve preparation of better

construction work schedule.

Yes No

1. Project team leaders should keep good

relationship with all project participants.

2. Learn more on managing human, because

with good skill on human management and

good motivating skill, motivated workers

could improve productivity .

3. Project team members must be committed to

their responsibilities.

4. Contractor should manage his financial resources

and plan cash flow.

5. Continuous and proper planning before construction,

so that resources and time are sufficient.

6. Material supply should be readily preserved to

avoid insufficient or depleted resources.

Page 114: justinbongchunntatma081181ttt

89

Yes No

7. Upgrade communication system used. Use more

technology when giving information for efficiency

and more effectiveness such as email, PDA, and GPRS.

It is better to give information in written form rather

than verbal instruction or information.

8. Give prompt feedback/action when any matter arises.

Is there any other solutions to which can be used to improve the preparation of the

construction work schedule?

________________________________________________________________________

________________________________________________________________________

________________________________________________________________________

End of Questionnaire

Your Kind Co-Operation is Highly Appreciated. Thank You.