Activity ID Activity Name Original Duration Start Finish Predecessors Successors CONTRACT 2 : ORBITAL HIGHWAY: EXCO PROGRAM 911 01-Jul-14 01-Jul-17 DESIGN 449 01-Mar-15 17-Aug-16 JUNCTION 4 141 01-Mar-15 17-Aug-15 DESIGN APPROVAL 141 01-Mar-15 17-Aug-15 SHARED UNDERPASS 45 03-Mar-15 25-Apr-15 SHARED UNDERPASS A 18 03-Mar-15 24-Mar-15 M7J4-UPDA-100 Prelim Design Approval 0 03-Mar-15* M7J4-EW-100 M7J4-UPDA-110 Detail Design Approval 0 24-Mar-15* M7J4-SU-F-1330 SHARED UNDERPASS B 32 03-Mar-15 09-Apr-15 M7J4-UPDA-350 Detail Design Approval 0 09-Apr-15* M7J4-SU-F-1930 M7J4-UPDA-340 Prelim Design Approval 0 03-Mar-15* SHARED UNDERPASS C 45 03-Mar-15 25-Apr-15 M7J4-UPDA-360 Prelim Design Approval 0 03-Mar-15* M7J4-UPDA-370 Detail Design Approval 0 25-Apr-15* SHARED UNDERPASS D 45 03-Mar-15 25-Apr-15 M7J4-UPDA-380 Prelim Design Approval 0 03-Mar-15* M7J4-UPDA-390 Detail Design Approval 0 25-Apr-15* MIAN BRIDGE 65 01-Mar-15 16-May-15 M7J4-MBDA-100 Foundation DD submission to AECOM (D01) 0 01-Mar-15* M7J4S-A1MB4F100, M7J4S-A2MB4F150, M7J M7J4-MBDA-110 Abutment & Pier DD submission to AECOM (D01) 0 16-Mar-15* M7J4S-A2MB4F160, M7J4S-A2MB4F150, M7J M7J4-MBDA-120 Beams DD submission to AECOM (D01) 0 30-Apr-15* M7J4-MBDA-130 Deck DD submission to AECOM (D01) 0 16-May-15* BRAIDING 33 06-Jul-15 17-Aug-15 M7J4-UPDA-150 Prelim Design Approval 0 06-Jul-15* M8J4S-BA-EW-100 M7J4-UPDA-170 Detail Design Approval 0 17-Aug-15* JUNCTION 5 18 24-Mar-15 14-Apr-15 DESIGN APPROVAL 18 24-Mar-15 14-Apr-15 M7J5-MBDA-100 Tunnel Prelim Design 0 24-Mar-15* M7P5-MBDA-105 Detail Design Approval 0 14-Apr-15* JUNCTION 6 201 01-Apr-15 28-Nov-15 DESIGN APPROVAL 201 01-Apr-15 28-Nov-15 MIAN BRIDGE 59 21-Jul-15 30-Sep-15 PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) - CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROAD INTERNAL TARGET PROGRAMME OF WORKS JUNCTION -04 CONSTRUCTION PROGRAMME Page 1 of 582 Rev Date Checked Approved C5 310315

description

Program

Transcript of Junction 5 Program -Checking

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    CONTRACT 2 : ORBITAL HIGHCONTRACT 2 : ORBITAL HIGHWAY: EXCO PROGRAM 911 01-Jul-14 01-Jul-17

    DESIGNDESIGN 449 01-Mar-15 17-Aug-16

    JUNCTION 4JUNCTION 4 141 01-Mar-15 17-Aug-15

    DESIGN APPROVALDESIGN APPROVAL 141 01-Mar-15 17-Aug-15

    SHARED UNDERPASSSHARED UNDERPASS 45 03-Mar-15 25-Apr-15

    SHARED UNDERPASS ASHARED UNDERPASS A 18 03-Mar-15 24-Mar-15

    M7J4-UPDA-100 Prelim Design Approval 0 03-Mar-15* M7J4-EW-100

    M7J4-UPDA-110 Detail Design Approval 0 24-Mar-15* M7J4-SU-F-1330

    SHARED UNDERPASS BSHARED UNDERPASS B 32 03-Mar-15 09-Apr-15

    M7J4-UPDA-350 Detail Design Approval 0 09-Apr-15* M7J4-SU-F-1930

    M7J4-UPDA-340 Prelim Design Approval 0 03-Mar-15*

    SHARED UNDERPASS CSHARED UNDERPASS C 45 03-Mar-15 25-Apr-15

    M7J4-UPDA-360 Prelim Design Approval 0 03-Mar-15*

    M7J4-UPDA-370 Detail Design Approval 0 25-Apr-15*

    SHARED UNDERPASS DSHARED UNDERPASS D 45 03-Mar-15 25-Apr-15

    M7J4-UPDA-380 Prelim Design Approval 0 03-Mar-15*

    M7J4-UPDA-390 Detail Design Approval 0 25-Apr-15*

    MIAN BRIDGEMIAN BRIDGE 65 01-Mar-15 16-May-15

    M7J4-MBDA-100 Foundation DD submission to AECOM (D01) 0 01-Mar-15* M7J4S-A1MB4F100, M7J4S-A2MB4F150, M7J

    M7J4-MBDA-110 Abutment & Pier DD submission to AECOM (D01) 0 16-Mar-15* M7J4S-A2MB4F160, M7J4S-A2MB4F150, M7J

    M7J4-MBDA-120 Beams DD submission to AECOM (D01) 0 30-Apr-15*

    M7J4-MBDA-130 Deck DD submission to AECOM (D01) 0 16-May-15*

    BRAIDINGBRAIDING 33 06-Jul-15 17-Aug-15

    M7J4-UPDA-150 Prelim Design Approval 0 06-Jul-15* M8J4S-BA-EW-100

    M7J4-UPDA-170 Detail Design Approval 0 17-Aug-15*

    JUNCTION 5JUNCTION 5 18 24-Mar-15 14-Apr-15

    DESIGN APPROVALDESIGN APPROVAL 18 24-Mar-15 14-Apr-15

    M7J5-MBDA-100 Tunnel Prelim Design 0 24-Mar-15*

    M7P5-MBDA-105 Detail Design Approval 0 14-Apr-15*

    JUNCTION 6JUNCTION 6 201 01-Apr-15 28-Nov-15

    DESIGN APPROVALDESIGN APPROVAL 201 01-Apr-15 28-Nov-15

    MIAN BRIDGEMIAN BRIDGE 59 21-Jul-15 30-Sep-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 1 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    RAMP A AND BRAMP A AND B 35 21-Jul-15 31-Aug-15

    M7J6-MBDA-110 Detail Design Approval 0 31-Aug-15* M7J6S-RB1SC100

    M7J6-MBDA-100 Preliminary Design Approval 0 21-Jul-15*

    RAMP CRAMP C 34 19-Aug-15 30-Sep-15

    M7J6-MBDA-120 Preliminary Design Approval 0 19-Aug-15*

    M7J6-MBDA-130 Detail Design Approval 0 30-Sep-15*

    UNDERPASSUNDERPASS 165 01-Apr-15 17-Oct-15

    SHARED UNDERPASS A ON ORSHARED UNDERPASS A ON ORBITAL HIGHWAY 37 01-Apr-15 14-May-15

    M7J6-SUDA-110 Detail Design Approval 0 14-May-15* M7J6S-EW-370, M7J6S-SU-F-3050

    M7J6-SUDA-100 Preliminary Design Approval 0 01-Apr-15*

    SHARED UNDERPASS B ON SASHARED UNDERPASS B ON SALIYA STREET 34 05-Sep-15 17-Oct-15

    M7J6-SUDA-120 Preliminary Design Approval 0 05-Sep-15*

    M7J6-SUDA-130 Detail Design Approval 0 17-Oct-15*

    BRAIDINGBRAIDING 160 19-May-15 28-Nov-15

    BRAIDING ABRAIDING A 36 19-May-15 30-Jun-15

    M7J6-BDDA-100 Preliminary Design Approval 0 19-May-15* M8J6S-BA-EW-100

    M7J6-BDDA-110 Detail Design Approval 0 30-Jun-15* M8J6S-BA-RT-S1-130

    BRAIDING BBRAIDING B 36 05-Aug-15 16-Sep-15

    M7J6-BDDA-120 Preliminary Design Approval 0 05-Aug-15* M8J6S-BBEW-100

    M7J6-BDDA-130 Detail Design Approval 0 16-Sep-15*

    BRAIDING CBRAIDING C 36 17-Oct-15 28-Nov-15

    M7J6-BDDA-140 Preliminary Design Approval 0 17-Oct-15* M8J6S-BCEW-100

    M7J6-BDDA-150 Detail Design Approval 0 28-Nov-15* M8J6S-BCEW-100

    JUNCTION 12JUNCTION 12 266 05-May-15 17-Mar-16

    DESIGN APPROVALDESIGN APPROVAL 266 05-May-15 17-Mar-16

    MIAN BRIDGEMIAN BRIDGE 18 09-Jun-15 30-Jun-15

    M8J12-MBDA-110 Detail Design Approval 0 30-Jun-15* M8J12S1-A1CDF-130

    M8J12-MBDA-100 Prelim Design Approval 0 09-Jun-15* M8J12S1-A1CDS-100

    SHARED UNDERPASSSHARED UNDERPASS 34 19-Sep-15 31-Oct-15

    SHARED UNDERPASS ASHARED UNDERPASS A 34 19-Sep-15 31-Oct-15

    M8J12-SUDA-110 Detail Design Approval 0 31-Oct-15* M8J12S-SU-F-3770

    M8J12-SUDA-100 Prelim Design Approval 0 19-Sep-15*

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 2 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    SHARED UNDERPASS BSHARED UNDERPASS B 34 19-Sep-15 31-Oct-15

    M8J12-SUDA-120 Prelim Design Approval 0 19-Sep-15*

    M8J12-SUDA-130 Detail Design Approval 0 31-Oct-15*

    SHARED UNDERPASS CSHARED UNDERPASS C 34 19-Sep-15 31-Oct-15

    M8J12-SUDA-140 Prelim Design Approval 0 19-Sep-15*

    M8J12-SUDA-150 Detail Design Approval 0 31-Oct-15*

    CAMEL UNDERPASSCAMEL UNDERPASS 36 05-May-15 16-Jun-15

    CAMEL UNDERPASS- JCAMEL UNDERPASS- J 36 05-May-15 16-Jun-15

    M8J12-SUDA-160 Prelim Design Approval 0 05-May-15*

    M8J12-SUDA-170 Detail Design Approval 0 16-Jun-15*

    CAMEL UNDERPASS- KCAMEL UNDERPASS- K 36 05-May-15 16-Jun-15

    M8J12-SUDA-180 Prelim Design Approval 0 05-May-15*

    M8J12-SUDA-190 Detail Design Approval 0 16-Jun-15*

    BRAIDINGBRAIDING 263 09-May-15 17-Mar-16

    BRAIDING - ABRAIDING - A 36 05-Oct-15 16-Nov-15

    M8J12-BDDA-100 Prelim Design Approval 0 05-Oct-15*

    M8J12-BDDA-110 Detail Design Approval 0 16-Nov-15*

    BRAIDING - BBRAIDING - B 35 04-Feb-16 17-Mar-16

    M8J12-BDDA-120 Prelim Design Approval 0 04-Feb-16*

    M8J12-BDDA-130 Detail Design Approval 0 17-Mar-16*

    BRAIDING - CBRAIDING - C 17 09-May-15 28-May-15

    M8J12-BDDA-140 Prelim Design Approval 0 09-May-15* M8J12S-BC-EW-100

    M8J12-BDDA-150 Detail Design Approval 0 28-May-15* M8J12S-BC-RT-S1-130

    BRAIDING - DBRAIDING - D 36 06-Jun-15 21-Jul-15

    M8J12-BDDA-160 Prelim Design Approval 0 06-Jun-15*

    M8J12-BDDA-170 Detail Design Approval 0 21-Jul-15*

    JUNCTION 1JUNCTION 1 60 05-Aug-15 17-Oct-15

    MAIN BRIDGEMAIN BRIDGE 36 05-Aug-15 16-Sep-15

    M8J1S-MBDA-110 Detail Design Approval 0 16-Sep-15* M8J1S-MB1A1E100

    M8J1S-MBDA-100 Prelim Design Approval 0 05-Aug-15* M8J1S-MB1AEW100

    RAMP BRIDGERAMP BRIDGE 34 05-Sep-15 17-Oct-15

    M8J1S-MBDA-120 Prelim Design Approval 0 05-Sep-15*

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 3 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M8J1S-MBDA-130 Detail Design Approval 0 17-Oct-15*

    JUNCTION 2JUNCTION 2 190 04-Jan-16 17-Aug-16

    MAIN BRIDGEMAIN BRIDGE 35 04-Jan-16 15-Feb-16

    M8J2-MBDA-100 Prelim Design Approval 0 04-Jan-16*

    M8J2-MBDA-110 Detail Design Approval 0 15-Feb-16*

    SHARED UNDERPASS ASHARED UNDERPASS A 36 05-Apr-16 17-May-16

    M8J2-SUDA-100 Prelim Design Approval 0 05-Apr-16*

    M8J2-SUDA-110 Detail Design Approval 0 17-May-16*

    SHARED UNDERPASS BSHARED UNDERPASS B 34 09-Jul-16 17-Aug-16

    M8J2-SUDA-120 Prelim Design Approval 0 09-Jul-16*

    M8J2-SUDA-130 Detail Design Approval 0 17-Aug-16*

    JUNCTION 3JUNCTION 3 60 06-Dec-15 15-Feb-16

    RAMP BRIDGE ARAMP BRIDGE A 36 06-Dec-15 17-Jan-16

    M8J3S-R3DA-110 Detail Design Approval 0 17-Jan-16* M8J3AS-3AA1F-130

    M8J3S-R3DA-100 Prelim Design Approval 0 06-Dec-15*

    RAMP BRIDGE BRAMP BRIDGE B 36 06-Dec-15 17-Jan-16

    M8J3S-R3DA-130 Detail Design Approval 0 17-Jan-16* M8J3S-R3AA1F-110

    M8J3S-R3DA-120 Prelim Design Approval 0 06-Dec-15* M8J3S-R3ADIV100

    SHARED UNDERPASS ASHARED UNDERPASS A 35 04-Jan-16 15-Feb-16

    M8J3-SUDA-100 Prelim Design Approval 0 04-Jan-16*

    M8J3-SUDA-110 Detail Design Approval 0 15-Feb-16*

    JUNCTION 3AJUNCTION 3A 86 05-Nov-15 15-Feb-16

    MAIN BRIDGEMAIN BRIDGE 36 05-Nov-15 17-Dec-15

    M8J3A-MBDA-100 Prelim Design Approval 0 05-Nov-15*

    M8J3A-MBDA-110 Detail Design Approval 0 17-Dec-15*

    RAMP BRIDGERAMP BRIDGE 36 06-Dec-15 17-Jan-16

    M8J3A-MBDA-120 Prelim Design Approval 0 06-Dec-15*

    M8J3A-MBDA-130 Detail Design Approval 0 17-Jan-16*

    SHARED UNDERPASS ASHARED UNDERPASS A 35 04-Jan-16 15-Feb-16

    M8J3A-SUDA-100 Prelim Design Approval 0 04-Jan-16*

    M8J3A-SUDA-110 Detail Design Approval 0 15-Feb-16*

    SHARED UNDERPASS BSHARED UNDERPASS B 35 04-Jan-16 15-Feb-16

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 4 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M8J3A-SUDA-120 Prelim Design Approval 0 04-Jan-16*

    M8J3A-SUDA-130 Detail Design Approval 0 15-Feb-16*

    QP PROTECTIONQP PROTECTION 123 20-Jun-15 16-Nov-15

    QP PROTECTION 51+000QP PROTECTION 51+000 33 20-Jun-15 01-Aug-15

    M7QP-DA-100 Prelim Design Approval 0 20-Jun-15*

    M7QP-DA-110 Detail Design Approval 0 01-Aug-15*

    QP PROTECTION 16+690QP PROTECTION 16+690 36 05-Oct-15 16-Nov-15

    M7QP-DA-120 Prelim Design Approval 0 05-Oct-15*

    M7QP-DA-130 Detail Design Approval 0 16-Nov-15*

    QP PROTECTION 16+333QP PROTECTION 16+333 36 05-Oct-15 16-Nov-15

    M7QP-DA-140 Prelim Design Approval 0 05-Oct-15*

    M7QP-DA-150 Detail Design Approval 0 16-Nov-15*

    QP PROTECTION 16+632QP PROTECTION 16+632 36 05-Oct-15 16-Nov-15

    M7QP-DA-160 Prelim Design Approval 0 05-Oct-15*

    M7QP-DA-170 Detail Design Approval 0 16-Nov-15*

    CONSTRUCTIONCONSTRUCTION 911 01-Jul-14 01-Jul-17

    JUNCTION 4 & SOUTH OF DUKJUNCTION 4 & SOUTH OF DUKHAN ROAD- MILESTONE 7 WORKS 723 01-Jul-14 16-Nov-16

    BENEFICIAL COMPLETION OF M7BENEFICIAL COMPLETION OF M7 527 01-Jul-14 24-Mar-16

    INTERFACE ISSUEINTERFACE ISSUE 527 01-Jul-14 24-Mar-16

    11KV Overhead Cables11KV Overhead Cables 349 15-Jan-15 05-Mar-16

    Option 1 40+800 to 45+250 NOOption 1 40+800 to 45+250 NOH 349 15-Jan-15 05-Mar-16

    M7-BC-IFI-100 Concept Design Submittal 21 15-Jan-15* 08-Feb-15 M7-BC-IFI-110

    M7-BC-IFI-110 Concept Design Approval 14 09-Feb-15 25-Feb-15 M7-BC-IFI-100 M7-BC-IFI-120

    M7-BC-IFI-120 Detail Design Submittal 45 26-Feb-15 19-Apr-15 M7-BC-IFI-110 M7-BC-IFI-130

    M7-BC-IFI-130 Detail Design Approval 45 20-Apr-15 10-Jun-15 M7-BC-IFI-120 M7-BC-IFI-140

    M7-BC-IFI-140 Material Submittal 14 11-Jun-15 27-Jun-15 M7-BC-IFI-130 M7-BC-IFI-150

    M7-BC-IFI-150 Material Approval 45 28-Jun-15 22-Aug-15 M7-BC-IFI-140 M7-BC-IFI-160

    M7-BC-IFI-160 Material Procurement 120 23-Aug-15 11-Jan-16 M7-BC-IFI-150 M7-BC-IFI-170

    M7-BC-IFI-170 Work 45 12-Jan-16 05-Mar-16 M7-BC-IFI-160

    Option 2 40+800 to 45+250 CWOption 2 40+800 to 45+250 CW 151 15-Jan-15 11-Jul-15

    M7-BC-IFI-180 Concept Design Submittal 21 15-Jan-15* 08-Feb-15 M7-BC-IFI-190

    M7-BC-IFI-190 Concept Design Approval 14 09-Feb-15 25-Feb-15 M7-BC-IFI-180 M7-BC-IFI-200

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 5 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7-BC-IFI-200 Detail Design Submittal 30 26-Feb-15 01-Apr-15 M7-BC-IFI-190 M7-BC-IFI-210

    M7-BC-IFI-210 Detail Design Approval 30 02-Apr-15 06-May-15 M7-BC-IFI-200 M7-BC-IFI-220, M7-BC-IFI-240

    M7-BC-IFI-220 Material Submittal 14 07-May-15 23-May-15 M7-BC-IFI-210 M7-BC-IFI-230

    M7-BC-IFI-230 Material Approval 28 24-May-15 24-Jun-15 M7-BC-IFI-220 M7-BC-IFI-250

    M7-BC-IFI-240 Material Procurement 56 11-Apr-15 14-Jun-15 M7-BC-IFI-210

    M7-BC-IFI-250 Work 28 09-Jun-15 11-Jul-15 M7-BC-IFI-230

    Overhead Cables 400 KV (BetwOverhead Cables 400 KV (Between Junction 5 - 6) 404 29-Nov-14 24-Mar-16

    M7-BC-IFI-260 Concept Design Submittal 45 29-Nov-14* 22-Jan-15 M7-BC-IFI-270

    M7-BC-IFI-270 Concept Design Approval 45 24-Jan-15 17-Mar-15 M7-BC-IFI-260 M7-BC-IFI-280

    M7-BC-IFI-280 Detail Design Submittal 60 18-Mar-15 26-May-15 M7-BC-IFI-270 M7-BC-IFI-290, M7-BC-IFI-320

    M7-BC-IFI-290 Detail Design Approval 30 27-May-15 30-Jun-15 M7-BC-IFI-280 M7-BC-IFI-300

    M7-BC-IFI-300 Material Submittal 14 01-Jul-15 16-Jul-15 M7-BC-IFI-290 M7-BC-IFI-310

    M7-BC-IFI-320 Material Procurement 150 13-Jun-15 09-Dec-15 M7-BC-IFI-280 M7-BC-IFI-330

    M7-BC-IFI-310 Material Approval 30 21-Jul-15 24-Aug-15 M7-BC-IFI-300

    M7-BC-IFI-330 Work 90 10-Dec-15 24-Mar-16 M7-BC-IFI-320

    Culvert Extension (Between JuCulvert Extension (Between Junction 5 - 6) 346 01-Dec-14 18-Jan-16

    M7-BC-IFI-340 Concept Design Submittal 56 01-Dec-14* 07-Feb-15 M7-BC-IFI-350

    M7-BC-IFI-350 Concept Design Approval 28 08-Feb-15 12-Mar-15 M7-BC-IFI-340 M7-BC-IFI-360

    M7-BC-IFI-360 Detail Design Submittal 28 14-Mar-15 14-Apr-15 M7-BC-IFI-350 M7-BC-IFI-370

    M7-BC-IFI-370 Detail Design Approval 45 15-Apr-15 06-Jun-15 M7-BC-IFI-360 M7-BC-IFI-380

    M7-BC-IFI-380 Material Submittal 7 07-Jun-15 14-Jun-15 M7-BC-IFI-370 M7-BC-IFI-390

    M7-BC-IFI-390 Material Approval 14 15-Jun-15 30-Jun-15 M7-BC-IFI-380 M7-BC-IFI-400

    M7-BC-IFI-400 Material Procurement 28 01-Jul-15 05-Aug-15 M7-BC-IFI-390 M7-BC-IFI-410

    M7-BC-IFI-410 Work 140 06-Aug-15 18-Jan-16 M7-BC-IFI-400

    QP Abundant Pipe Removal at QP Abundant Pipe Removal at 56+100 100 01-Feb-15 28-May-15

    M7-BC-IFI-420 Concept Design Submittal 28 01-Feb-15* 05-Mar-15 M7-BC-IFI-430

    M7-BC-IFI-430 Concept Design Approval 14 07-Mar-15 22-Mar-15 M7-BC-IFI-420 M7-BC-IFI-440

    M7-BC-IFI-440 Detail Design Submittal 14 23-Mar-15 07-Apr-15 M7-BC-IFI-430 M7-BC-IFI-450

    M7-BC-IFI-450 Detail Design Approval 14 08-Apr-15 23-Apr-15 M7-BC-IFI-440 M7-BC-IFI-460

    M7-BC-IFI-460 Work 30 25-Apr-15 28-May-15 M7-BC-IFI-450

    Mega Reservoir (Between 5 & 6)Mega Reservoir (Between 5 & 6) 0 01-Jul-14 01-Jul-14

    M7-BC-IFI-470 Submission of Realignment of Corridor 0 01-Jul-14 01-Jul-14

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 6 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7-BC-IFI-480 Approval of Proposal 0 01-Jul-14 01-Jul-14

    ROAD WORKSROAD WORKS 232 31-Mar-15 31-Dec-15

    A1000 Start 0 31-Mar-15* P023-M7-CW-Z1-P1-100, P023-M7-CW-Z1-P1-0

    A1010 Completion of Milestone 7 Completion 0 31-Dec-15 P023-M7-CW-Z1-P4-060, P023-M7-CW-Z2-

    Constraints to be ResolvedConstraints to be Resolved 231 31-Mar-15 31-Dec-15

    ZONE 1 40+900 To 47+800ZONE 1 40+900 To 47+800 28 15-Apr-15 18-May-15

    P023-M7-CW-Z1-C-120 Detail design for road works and all utilities approval 0 15-Apr-15* A1000 P023-M7-CW-Z1-P1-040, P023-M7-CW-Z1-P1-0

    P023-M7-CW-Z1-C-140 Traffic diversion approval 0 14-May-15* A1000 P023-M7-CW-Z1-P1-100

    P023-M7-CW-Z1-C-150 Warehouse at Junction 6 to be removed 0 30-Apr-15* A1000 P023-M7-CW-Z1-P1-100

    P023-M7-CW-Z1-C-130 Shared underpass at Junction 6 approval 0 14-May-15* A1000 P023-M7-CW-Z1-P1-110

    P023-M7-CW-Z1-C-100 11 kV relocation at Junction 6 approval 0 18-May-15* A1000 P023-M7-CW-Z1-P3-050

    P023-M7-CW-Z1-C-110 TSE line relocation at Junction 6 approval 0 18-May-15* A1000 P023-M7-CW-Z1-P3-050

    ZONE 2 47+800 To 53+200ZONE 2 47+800 To 53+200 231 31-Mar-15 31-Dec-15

    P023-M7-CW-Z2-C-140 Receipt of Pending road opening permits (Junction 5 to 0 31-Mar-15* A1000 P023-M7-CW-Z2-P1-001, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-C-110 Detail design for road works and all utilities approval 0 15-Apr-15* A1000 P023-M7-CW-Z2-P1-020, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-C-100 QP protection detail design at Ch. 50+900 approval 0 01-Jun-15* A1000 P023-M7-CW-Z2-P1-030

    P023-M7-CW-Z2-C-150 Mega reservoir interface issue to be resolved 0 31-Mar-15* A1000 P023-M7-CW-Z2-P1-050, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-C-120 51+000-53+200 Traffic diversion plan Approval 0 01-Jul-15* A1000 P023-M7-CW-Z2-P2-001

    P023-M7-CW-Z2-C-130 47+800-51+000 including the future phases Approval 0 15-Aug-15* A1000 P023-M7-CW-Z2-P3-001

    P023-M7-CW-Z2-C-160 400 kV overhead lines at chainage 51+100 removal 0 31-Dec-15* A1000 P023-M7-CW-Z2-P3-070

    Construction WorksConstruction Works 231 01-Apr-15 31-Dec-15

    Zone 1 CH. 40+900 To 47+800Zone 1 CH. 40+900 To 47+800 231 01-Apr-15 31-Dec-15

    Phase 1Phase 1 52 01-Apr-15 31-May-15

    Prepare Future Diversion (40Prepare Future Diversion (40+800 - 43+500) 51 01-Apr-15 30-May-15

    P023-M7-CW-Z1-P1-100 Prepare Future Diversion 51 01-Apr-15 30-May-15 A1000, P023-M7-CW-Z1-C-140, P023-M7-C P023-M7-CW-Z1-P1-110, P023-M7-CW-Z1-P2-0

    Excavation for the center paExcavation for the center part of Underpass at Junction 6 40 15-Apr-15 31-May-15

    P023-M7-CW-Z1-P1-110 Excavation for the center part of Underpass 40 15-Apr-15 31-May-15 P023-M7-CW-Z1-P1-100, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-010

    Culverts (43+500 - 47+800)Culverts (43+500 - 47+800) 38 01-Apr-15 14-May-15

    P023-M7-CW-Z1-P1-020 Culverts 38 01-Apr-15 14-May-15 A1000 P023-M7-CW-Z1-P1-030, P023-M7-CW-Z1-P2-0

    TSE Crossings (43+500 - 47+TSE Crossings (43+500 - 47+800) 27 09-Apr-15 10-May-15

    P023-M7-CW-Z1-P1-030 TSE Crossings 27 09-Apr-15 10-May-15 P023-M7-CW-Z1-P1-020 P023-M7-CW-Z1-P1-041

    Earthworks (43+500 - 47+800)Earthworks (43+500 - 47+800) 52 01-Apr-15 31-May-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 7 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    P023-M7-CW-Z1-P1-040 Cut 43 01-Apr-15 20-May-15 A1000, P023-M7-CW-Z1-C-120 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1-P1-0

    P023-M7-CW-Z1-P1-041 Fill 43 01-Apr-15 20-May-15 A1000, P023-M7-CW-Z1-P1-030, P023-M7 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1-P1-0

    P023-M7-CW-Z1-P1-042 Subgrade 27 30-Apr-15 31-May-15 P023-M7-CW-Z1-P1-041, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-001, P023-M7-CW-Z1-P2-0

    Phase 2Phase 2 50 30-May-15 30-Jul-15

    Diversion of TTR Traffic (40+Diversion of TTR Traffic (40+900 - 43+500) 0 30-May-15 30-May-15

    P023-M7-CW-Z1-P2-030 Diversion of TTR Traffic on new diversion 0 30-May-15 P023-M7-CW-Z1-P1-100 P023-M7-CW-Z1-P2-040, P023-M7-CW-Z1-P2-0

    Surface Utilities (43+500 - 47Surface Utilities (43+500 - 47+800) 49 01-Jun-15 30-Jul-15

    P023-M7-CW-Z1-P2-002 Drainage Line 41 01-Jun-15 21-Jul-15 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-003, P023-M7-CW-Z1-P2-0

    P023-M7-CW-Z1-P2-003 ITS 37 15-Jun-15 30-Jul-15 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-004, P023-M7-CW-Z1-P2-0

    P023-M7-CW-Z1-P2-006 Street Lighting (Cable, Foundation & Crossing) 49 01-Jun-15 30-Jul-15 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-010, P023-M7-CW-Z1-P3-0

    P023-M7-CW-Z1-P2-004 DSS 37 15-Jun-15 30-Jul-15 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-030

    P023-M7-CW-Z1-P2-005 Electrical 49 01-Jun-15 30-Jul-15 P023-M7-CW-Z1-P1-042, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-030

    P023-M7-CW-Z1-P2-001 Utility Ducts (Ooredoo, QAF, Vodaphone, etc.) 49 01-Jun-15 30-Jul-15 P023-M7-CW-Z1-P1-042 P023-M7-CW-Z1-P3-030, P023-M7-CW-Z1-P2-0

    Underpass Jucntion 6Underpass Jucntion 6 49 01-Jun-15 30-Jul-15

    P023-M7-CW-Z1-P2-010 Civil Works for Center part of Underpass 41 01-Jun-15 21-Jul-15 P023-M7-CW-Z1-P2-006, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-020

    P023-M7-CW-Z1-P2-020 Road Works over the Center part of Underpass 8 22-Jul-15 30-Jul-15 P023-M7-CW-Z1-P2-010 P023-M7-CW-Z1-P3-010

    Culvert Crossings (40+900 - Culvert Crossings (40+900 - 43+500) 35 31-May-15 09-Jul-15

    P023-M7-CW-Z1-P2-040 Culverts Crossings 35 31-May-15 09-Jul-15 P023-M7-CW-Z1-P2-030, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-050

    TSE Crossings (40+900 - 43+TSE Crossings (40+900 - 43+500) 35 31-May-15 09-Jul-15

    P023-M7-CW-Z1-P2-050 TSE Crossings 35 31-May-15 09-Jul-15 P023-M7-CW-Z1-P2-040, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-060

    Earthworks (40+900 - 43+500)Earthworks (40+900 - 43+500) 50 31-May-15 30-Jul-15

    P023-M7-CW-Z1-P2-060 Cut 44 31-May-15 23-Jul-15 P023-M7-CW-Z1-P2-050, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-061, P023-M7-CW-Z1-P2-0

    P023-M7-CW-Z1-P2-061 Fill 44 31-May-15 23-Jul-15 P023-M7-CW-Z1-P2-060, P023-M7-CW-Z1- P023-M7-CW-Z1-P2-062, P023-M7-CW-Z1-P2-0

    P023-M7-CW-Z1-P2-062 Subgrade 22 02-Jul-15 30-Jul-15 P023-M7-CW-Z1-P2-061, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-001, P023-M7-CW-Z1-P3-0

    Phase 3Phase 3 60 21-Jul-15 30-Sep-15

    Surface Utilities (40+900 - 43Surface Utilities (40+900 - 43+500) 51 01-Aug-15 30-Sep-15

    P023-M7-CW-Z1-P3-001 Utility Ducts (Ooredoo, QAF, Vodaphone, etc.) 51 01-Aug-15 30-Sep-15 P023-M7-CW-Z1-P2-062 P023-M7-CW-Z1-P3-002, P023-M7-CW-Z1-P3-0

    P023-M7-CW-Z1-P3-002 Drainage Line 43 01-Aug-15 19-Sep-15 P023-M7-CW-Z1-P3-001, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-003, P023-M7-CW-Z1-P3-0

    P023-M7-CW-Z1-P3-003 ITS 39 15-Aug-15 30-Sep-15 P023-M7-CW-Z1-P3-002, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-004, P023-M7-CW-Z1-P3-0

    P023-M7-CW-Z1-P3-005 Electrical 51 01-Aug-15 30-Sep-15 P023-M7-CW-Z1-P3-001, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-006, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P3-006 Street Lighting (Cable, Foundation & Crossing) 51 01-Aug-15 30-Sep-15 P023-M7-CW-Z1-P3-005, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-010, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P3-004 DSS 39 15-Aug-15 30-Sep-15 P023-M7-CW-Z1-P3-003, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-030

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 8 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    Shift the TTR on center partShift the TTR on center part of Underpass 0 01-Aug-15 01-Aug-15

    P023-M7-CW-Z1-P3-010 Shift the TTR on the center part of the Underpass 0 01-Aug-15 P023-M7-CW-Z1-P3-006, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-020

    Excavation for the RHS of UExcavation for the RHS of Underpass 17 01-Aug-15 19-Aug-15

    P023-M7-CW-Z1-P3-020 Excavation for the RHS of Underpass 17 01-Aug-15 19-Aug-15 P023-M7-CW-Z1-P3-010 P023-M7-CW-Z1-P4-010

    Road Works (43+500 - 47+80Road Works (43+500 - 47+800) 59 21-Jul-15 29-Sep-15

    P023-M7-CW-Z1-P3-030 Road Subbase 33 21-Jul-15 27-Aug-15 P023-M7-CW-Z1-P2-001, P023-M7-CW-Z1- P023-M7-CW-Z1-P3-031, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P3-031 Asphalt Base & Intermediate Course 43 25-Jul-15 12-Sep-15 P023-M7-CW-Z1-P3-030 P023-M7-CW-Z1-P3-032

    P023-M7-CW-Z1-P3-032 Asphalt Wearing Course (7 Lane LHS) 7 13-Sep-15 20-Sep-15 P023-M7-CW-Z1-P3-031 P023-M7-CW-Z1-P3-033, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P3-033 Road Marking 11 15-Sep-15 29-Sep-15 P023-M7-CW-Z1-P3-032 P023-M7-CW-Z1-P3-040

    Traffic Diversion on new LanTraffic Diversion on new Lanes 0 29-Sep-15 29-Sep-15

    P023-M7-CW-Z1-P3-040 Traffic Diversion on new Lanes 0 29-Sep-15 P023-M7-CW-Z1-P3-033 P023-M7-CW-Z1-P4-040

    11kV and TSE to be relocate11kV and TSE to be relocated 43+500 - 47+800) 50 01-Aug-15 29-Sep-15

    P023-M7-CW-Z1-P3-050 11kV and TSE to be relocated 50 01-Aug-15 29-Sep-15 P023-M7-CW-Z1-P2-006, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-030

    Phase 4Phase 4 113 20-Aug-15 31-Dec-15

    Construction of Underpass Construction of Underpass (RHS) 86 20-Aug-15 30-Nov-15

    P023-M7-CW-Z1-P4-010 Construction of Underpass 86 20-Aug-15 30-Nov-15 P023-M7-CW-Z1-P3-020 P023-M7-CW-Z1-P4-020

    Backfill and Asphalt on the Backfill and Asphalt on the Structure 13 01-Dec-15 15-Dec-15

    P023-M7-CW-Z1-P4-020 Backfill and Asphalt on the Structure 13 01-Dec-15 15-Dec-15 P023-M7-CW-Z1-P4-010 P023-M7-CW-Z1-P4-050

    Road Works (40+800 - 43+50Road Works (40+800 - 43+500) 47 15-Sep-15 10-Nov-15

    P023-M7-CW-Z1-P4-030 Road Subbase 20 15-Sep-15 10-Oct-15 P023-M7-CW-Z1-P3-030, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-031, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P4-031 Asphalt Base & Intermediate Course 28 21-Sep-15 25-Oct-15 P023-M7-CW-Z1-P4-030, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-032, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P4-032 Asphalt Wearing Course 7 26-Oct-15 02-Nov-15 P023-M7-CW-Z1-P4-031 P023-M7-CW-Z1-P4-033

    P023-M7-CW-Z1-P4-033 Asphalt Wearing Course (7 Lane LHS) 7 03-Nov-15 10-Nov-15 P023-M7-CW-Z1-P4-032 P023-M7-CW-Z1-P4-050, P023-M7-CW-Z1-P4-0

    Utility Works (40+800 - 47+8Utility Works (40+800 - 47+800) 68 01-Oct-15 19-Dec-15

    P023-M7-CW-Z1-P4-040 Erection of High Mast Pole 68 01-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-031, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-041, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P4-041 Feeder Piller 68 01-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-040 P023-M7-CW-Z1-P4-042, P023-M7-CW-Z1-P4-0

    P023-M7-CW-Z1-P4-042 Ditch Works 60 11-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-041 P023-M7-CW-Z1-P4-050

    P023-M7-CW-Z1-P4-043 Guard Rail 51 21-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-041 P023-M7-CW-Z1-P4-050

    P023-M7-CW-Z1-P4-044 Traffic Signs & Gantries 68 01-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-040 P023-M7-CW-Z1-P4-050

    P023-M7-CW-Z1-P4-045 Traffic Marking 68 01-Oct-15 19-Dec-15 P023-M7-CW-Z1-P4-040, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-050

    Finalizing the Snagging ActFinalizing the Snagging Activities 10 20-Dec-15 30-Dec-15

    P023-M7-CW-Z1-P4-050 Finalizing the Snagging Activities 10 20-Dec-15 30-Dec-15 P023-M7-CW-Z1-P4-045, P023-M7-CW-Z1- P023-M7-CW-Z1-P4-060

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 9 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    Shift Traffic on NOH2 HighwShift Traffic on NOH2 Highway 1 31-Dec-15 31-Dec-15

    P023-M7-CW-Z1-P4-060 Shift Traffic to NOH2 Highway 1 31-Dec-15 31-Dec-15 P023-M7-CW-Z1-P4-050 A1010

    Zone 2 CH. 47+800 To 53+200 Zone 2 CH. 47+800 To 53+200 (5.4 KM) 231 01-Apr-15 31-Dec-15

    Phase 1Phase 1 128 01-Apr-15 31-Aug-15

    Crossing Culverts (47+800 - Crossing Culverts (47+800 - 50+400) 58 01-Apr-15 07-Jun-15

    P023-M7-CW-Z2-P1-001 Crossing Culverts 58 01-Apr-15 07-Jun-15 A1000, P023-M7-CW-Z2-C-140, P023-M7-C P023-M7-CW-Z2-P1-010, P023-M7-CW-Z2-P1-0

    TSE Crossings (if present) (TSE Crossings (if present) (47+800 - 50+400) 58 01-Apr-15 07-Jun-15

    P023-M7-CW-Z2-P1-010 TSE Crossings (if present) 58 01-Apr-15 07-Jun-15 A1000, P023-M7-CW-Z2-P1-001, P023-M7 P023-M7-CW-Z2-P1-050

    Earthworks (47+800 - 50+400)Earthworks (47+800 - 50+400) 72 01-Apr-15 23-Jun-15

    P023-M7-CW-Z2-P1-020 Cut 46 01-Apr-15 24-May-15 A1000, P023-M7-CW-Z2-C-110, P023-M7-C P023-M7-CW-Z2-P1-021, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-021 Fill 54 16-Apr-15 17-Jun-15 P023-M7-CW-Z2-P1-020, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-022, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-022 Subgrade 48 29-Apr-15 23-Jun-15 P023-M7-CW-Z2-P1-020, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-050

    QP Pipes (50+900 - 50+900)QP Pipes (50+900 - 50+900) 128 01-Apr-15 31-Aug-15

    P023-M7-CW-Z2-P1-030 Excavation for QP Culverts 65 01-Apr-15 15-Jun-15 A1000, P023-M7-CW-Z2-C-100, P023-M7-C P023-M7-CW-Z2-P1-93

    P023-M7-CW-Z2-P1-93 Civil Works & Backfilling and Road Works 63 16-Jun-15 31-Aug-15 P023-M7-CW-Z2-P1-030 P023-M7-CW-Z2-P3-001, P023-M7-CW-Z2-P3-0

    Crossing Culverts (free areaCrossing Culverts (free area) (47+800 - 50+400) 27 01-Apr-15 02-May-15

    P023-M7-CW-Z2-P1-040 Crossing Culverts (free area) 27 01-Apr-15 02-May-15 P023-M7-CW-Z2-P1-001, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-060, P023-M7-CW-Z2-P1-0

    TSE Crossings (if present) (TSE Crossings (if present) (free area) (47+800 - 50+400) 27 01-Apr-15 02-May-15

    P023-M7-CW-Z2-P1-050 TSE Crossing (if present) (free area) 27 01-Apr-15 02-May-15 P023-M7-CW-Z2-P1-010, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-060, P023-M7-CW-Z2-P1-0

    Earthworks (free area) (51+0Earthworks (free area) (51+000 - 53+400) 41 01-Apr-15 18-May-15

    P023-M7-CW-Z2-P1-060 Cut 36 01-Apr-15 12-May-15 A1000, P023-M7-CW-Z2-P1-040, P023-M7 P023-M7-CW-Z2-P1-061

    P023-M7-CW-Z2-P1-061 Fill 23 16-Apr-15 12-May-15 P023-M7-CW-Z2-P1-060, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-062, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-062 Subgrade 17 29-Apr-15 18-May-15 P023-M7-CW-Z2-P1-061, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-070, P023-M7-CW-Z2-P1-0

    Surface Utilities (free area) (Surface Utilities (free area) (51+000 - 53+200) 42 09-May-15 25-Jun-15

    P023-M7-CW-Z2-P1-070 Utility Ducts (Ooredoo, QAF, Vodaphone, etc.) 42 09-May-15 25-Jun-15 P023-M7-CW-Z2-P1-062 P023-M7-CW-Z2-P1-071, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-071 Drainage Line 42 09-May-15 25-Jun-15 P023-M7-CW-Z2-P1-070, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-072, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-073 DSS 42 09-May-15 25-Jun-15 P023-M7-CW-Z2-P1-071, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-074, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-074 Electrical 42 09-May-15 25-Jun-15 P023-M7-CW-Z2-P1-073, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-075, P023-M7-CW-Z2-P1-0

    P023-M7-CW-Z2-P1-072 ITS 33 19-May-15 25-Jun-15 P023-M7-CW-Z2-P1-071, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-080

    P023-M7-CW-Z2-P1-075 Street Lighting (Cable, Foundation & Crossing) 42 09-May-15 25-Jun-15 P023-M7-CW-Z2-P1-074, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-080

    Road Works (free area) (51+Road Works (free area) (51+000 - 53+200) 23 20-Jun-15 15-Jul-15

    P023-M7-CW-Z2-P1-080 Road Subbase 8 20-Jun-15 28-Jun-15 P023-M7-CW-Z2-P1-070, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-081, P023-M7-CW-Z2-P1-0

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 10 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    P023-M7-CW-Z2-P1-081 Asphalt Base & Intermediate Course 10 24-Jun-15 05-Jul-15 P023-M7-CW-Z2-P1-080, P023-M7-CW-Z2- P023-M7-CW-Z2-P1-082

    P023-M7-CW-Z2-P1-082 Asphalt Wearing Course (7 Lane LHS) 4 06-Jul-15 09-Jul-15 P023-M7-CW-Z2-P1-081 P023-M7-CW-Z2-P1-083

    P023-M7-CW-Z2-P1-083 Road Marking 8 07-Jul-15 15-Jul-15 P023-M7-CW-Z2-P1-082 P023-M7-CW-Z2-P2-001

    Phase 2Phase 2 37 15-Jul-15 31-Aug-15

    Traffic Diversion on LHS (51Traffic Diversion on LHS (51+000 - 53+200) 0 15-Jul-15 15-Jul-15

    P023-M7-CW-Z2-P2-001 Traffic Diversion on LHS 0 15-Jul-15 P023-M7-CW-Z2-P1-083, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-010, P023-M7-CW-Z2-P2-0

    Embankment in the both sidEmbankment in the both side of QP (RHS) (50+900 - 50+900) 13 16-Jul-15 03-Aug-15

    P023-M7-CW-Z2-P2-010 Embankment in the both side of QP (RHS) 13 16-Jul-15 03-Aug-15 P023-M7-CW-Z2-P2-001 P023-M7-CW-Z2-P2-030, P023-M7-CW-Z2-P2-0

    Crossing Culverts (TTR areaCrossing Culverts (TTR area) (47+800 - 50+400) 23 16-Jul-15 15-Aug-15

    P023-M7-CW-Z2-P2-020 Crossing Culverts (TTR Area) 23 16-Jul-15 15-Aug-15 P023-M7-CW-Z2-P2-010, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-040, P023-M7-CW-Z2-P2-0

    TSE Crossings (if present)(TTSE Crossings (if present)(TTR area) (47+800 - 50+400) 23 16-Jul-15 15-Aug-15

    P023-M7-CW-Z2-P2-030 TSE Crossings (if present) (TTR area) 23 16-Jul-15 15-Aug-15 P023-M7-CW-Z2-P2-001, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-040, P023-M7-CW-Z2-P2-0

    Earthworks on TTR (51+000 Earthworks on TTR (51+000 - 53+200) 37 16-Jul-15 31-Aug-15

    P023-M7-CW-Z2-P2-040 Cut 32 16-Jul-15 25-Aug-15 P023-M7-CW-Z2-P2-001, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-041, P023-M7-CW-Z2-P2-0

    P023-M7-CW-Z2-P2-041 Fill 27 26-Jul-15 25-Aug-15 P023-M7-CW-Z2-P2-040, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2-P2-0

    P023-M7-CW-Z2-P2-042 Subgrade 17 12-Aug-15 31-Aug-15 P023-M7-CW-Z2-P2-041, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-030, P023-M7-CW-Z2-P3-0

    Surface Utilities (47+800 - 50Surface Utilities (47+800 - 50+400) 37 16-Jul-15 31-Aug-15

    P023-M7-CW-Z2-P2-050 Utility Ducts (Ooredoo, QAF, Vodaphone, etc.) 37 16-Jul-15 31-Aug-15 P023-M7-CW-Z2-P1-022, P023-M7-CW-Z2- P023-M7-CW-Z2-P2-051, P023-M7-CW-Z2-P2-0

    P023-M7-CW-Z2-P2-051 Drainage Line 37 16-Jul-15 31-Aug-15 P023-M7-CW-Z2-P2-050 P023-M7-CW-Z2-P2-052, P023-M7-CW-Z2-P2-0

    P023-M7-CW-Z2-P2-054 Electrical 37 16-Jul-15 31-Aug-15 P023-M7-CW-Z2-P2-050 P023-M7-CW-Z2-P2-055, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P2-052 ITS 33 25-Jul-15 31-Aug-15 P023-M7-CW-Z2-P2-051 P023-M7-CW-Z2-P3-020

    P023-M7-CW-Z2-P2-053 DSS 37 16-Jul-15 31-Aug-15 P023-M7-CW-Z2-P2-051 P023-M7-CW-Z2-P3-020

    P023-M7-CW-Z2-P2-055 Street Lighting (Cable, Foundation & Crossing) 37 16-Jul-15 31-Aug-15 P023-M7-CW-Z2-P2-054 P023-M7-CW-Z2-P3-020

    Phase 3Phase 3 103 31-Aug-15 31-Dec-15

    Shift the TTR over QP CulveShift the TTR over QP Culverts (RHS) 0 31-Aug-15 31-Aug-15

    P023-M7-CW-Z2-P3-001 Shift the TTR over QP Culvert (RHS) 0 31-Aug-15 P023-M7-CW-Z2-P1-93, P023-M7-CW-Z2-C P023-M7-CW-Z2-P3-010, P023-M7-CW-Z2-P3-0

    CW to reinforce the center oCW to reinforce the center of the QP culvert 13 01-Sep-15 15-Sep-15

    P023-M7-CW-Z2-P3-010 CW to reinforce the center of the QP Culvert 13 01-Sep-15 15-Sep-15 P023-M7-CW-Z2-P1-93, P023-M7-CW-Z2-P P023-M7-CW-Z2-P3-060, P023-M7-CW-Z2-P3-0

    Road Works (47+800 - 50+40Road Works (47+800 - 50+400) 37 01-Sep-15 15-Oct-15

    P023-M7-CW-Z2-P3-020 Road Subbase 20 01-Sep-15 26-Sep-15 P023-M7-CW-Z2-P2-055, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-021, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-021 Asphalt Base & Intermediate Course 28 05-Sep-15 08-Oct-15 P023-M7-CW-Z2-P3-020, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-022

    P023-M7-CW-Z2-P3-022 Asphalt Wearing Course 6 10-Oct-15 15-Oct-15 P023-M7-CW-Z2-P3-021 P023-M7-CW-Z2-P3-050

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 11 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    Surface Utilities (51+00 - 53+Surface Utilities (51+00 - 53+200) 37 01-Sep-15 15-Oct-15

    P023-M7-CW-Z2-P3-030 Utility Ducts (Ooredoo, QAF, Vodaphone, etc.) 37 01-Sep-15 15-Oct-15 P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-031, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-031 Drainage Line 37 01-Sep-15 15-Oct-15 P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-032, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-033 DSS 37 01-Sep-15 15-Oct-15 P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-034, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-034 Electrical 37 01-Sep-15 15-Oct-15 P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-035, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-032 ITS 29 10-Sep-15 15-Oct-15 P023-M7-CW-Z2-P3-031, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-040

    P023-M7-CW-Z2-P3-035 Street Lighting (Cable, Foundation & Crossing) 37 01-Sep-15 15-Oct-15 P023-M7-CW-Z2-P2-042, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-040

    Road Works (TTR area) (51+Road Works (TTR area) (51+000 - 53+200) 16 17-Oct-15 03-Nov-15

    P023-M7-CW-Z2-P3-040 Road Subbase 8 17-Oct-15 25-Oct-15 P023-M7-CW-Z2-P3-035, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-041, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-041 Asphalt Base & Intermediate Course 9 21-Oct-15 31-Oct-15 P023-M7-CW-Z2-P3-040, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-042

    P023-M7-CW-Z2-P3-042 Asphalt Wearing Course 3 01-Nov-15 03-Nov-15 P023-M7-CW-Z2-P3-041 P023-M7-CW-Z2-P3-054, P023-M7-CW-Z2-P3-0

    Utilities Works (47+800 - 53+Utilities Works (47+800 - 53+200) 61 10-Oct-15 19-Dec-15

    P023-M7-CW-Z2-P3-050 Erection of High Mast Pole 61 10-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-022, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-051, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-052 Ditch Works 52 20-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-050, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-053, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-051 Feeder Piller 61 10-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-050, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-054, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-054 Traffic Signs & Guantries 61 10-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-051, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-055, P023-M7-CW-Z2-P3-0

    P023-M7-CW-Z2-P3-053 Guard Rail 44 29-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-052 P023-M7-CW-Z2-P3-060

    P023-M7-CW-Z2-P3-055 Traffic Marking 61 10-Oct-15 19-Dec-15 P023-M7-CW-Z2-P3-054, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-060

    Finalizing the Snagging ActFinalizing the Snagging Activities 11 20-Dec-15 31-Dec-15

    P023-M7-CW-Z2-P3-060 Finalizing the Snagging Activities 11 20-Dec-15 31-Dec-15 P023-M7-CW-Z2-P3-055, P023-M7-CW-Z2- P023-M7-CW-Z2-P3-070

    Shift Traffic on NOH2 HighwShift Traffic on NOH2 Highway 0 31-Dec-15 31-Dec-15

    P023-M7-CW-Z2-P3-070 Shift Traffic on NOH2 Highway 0 31-Dec-15 P023-M7-CW-Z2-P3-060, P023-M7-CW-Z2- A1010

    STRUCTURAL WORKSSTRUCTURAL WORKS 280 26-Mar-15 22-Feb-16

    SHARED UNDERPASS - J-6 - OSHARED UNDERPASS - J-6 - ON ORBITAL HIGHWAY (116 m) CH. 43+535 267 11-Apr-15 22-Feb-16

    PHASE 1 (6 PANELS)PHASE 1 (6 PANELS) 147 11-Apr-15 04-Oct-15

    EARTHWORKS & BLINDINGEARTHWORKS & BLINDING 26 11-Apr-15 10-May-15

    M7J6S-EW-370 General Ground Clearances / Grubbing 4 11-Apr-15 14-Apr-15 M7J6-SUDA-110 M7J6S-EW-380, M7J6S-EW-380

    M7J6S-EW-380 Protection of Existing underground services 12 15-Apr-15 28-Apr-15 M7J6S-EW-370, M7J6S-EW-370 M7J6S-EW-390, M7J6S-EW-390

    M7J6S-EW-390 General Excavation & Formation Preparation 12 20-Apr-15 03-May-15 M7J6S-EW-380, M7J6S-EW-380 M7J6S-EW-400, M7J6S-EW-420

    M7J6S-EW-400 Blinding & Waterproofing 6 04-May-15 10-May-15 M7J6S-EW-390 M7J6S-SU-F-3050

    FOUNDATIONFOUNDATION 40 28-May-15 13-Jul-15

    SEGMENT 1SEGMENT 1 18 28-May-15 17-Jun-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 12 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    P6-SU-F-WP-450 Water Proofing and Backf illing 5 13-Jun-15 17-Jun-15 M7J6S-SU-F-3105, M7J6S-SU-F-3080 M7J6S-SU-DS-2620

    M7J6S-SU-F-3080 Pouring of Concrete Abutment 1 1 01-Jun-15 01-Jun-15 M7J6S-SU-F-3060 M7J6S-SU-E-3070, P6-SU-F-WP-450

    M7J6S-SU-F-3105 Pouring of Concrete Abutment 2 1 03-Jun-15 03-Jun-15 M7J6S-SU-F-3100 M7J6S-SU-E-3100, P6-SU-F-WP-450

    M7J6S-SU-F-3050 Fixing of Steel Reinforcement Abutment 1 2 28-May-15 30-May-15 M7J6S-EW-400, M7J6-SUDA-110, M7J4-S M7J6S-SU-F-3060, M7J6S-SU-F-3090

    M7J6S-SU-F-3060 Fixing of Formwork Abutment 1 2 31-May-15 01-Jun-15 M7J6S-SU-F-3050 M7J6S-SU-F-3100, M7J6S-SU-F-3080

    M7J6S-SU-F-3090 Fixing of Steel Reinforcement Abutment 2 2 31-May-15 01-Jun-15 M7J6S-SU-F-3050 M7J6S-SU-F-3100, M7J6S-SU-F-3110

    M7J6S-SU-F-3100 Fixing of Formwork Abutment 2 2 02-Jun-15 03-Jun-15 M7J6S-SU-F-3060, M7J6S-SU-F-3090 M7J6S-SU-F-3120, M7J6S-SU-F-3105

    SEGMENT 2SEGMENT 2 18 02-Jun-15 22-Jun-15

    P6-SU-F-WP-460 Water Proofing and Backf illing 5 17-Jun-15 22-Jun-15 M7J6S-SU-F-3160, M7J6S-SU-F-3130 M7J6S-SU-DS-2780

    M7J6S-SU-F-3130 Pouring of Concrete Abutment 1 1 06-Jun-15 06-Jun-15 M7J6S-SU-F-3120 M7J6S-SU-E-3190, P6-SU-F-WP-460

    M7J6S-SU-F-3160 Pouring of Concrete Abutment 2 1 08-Jun-15 08-Jun-15 M7J6S-SU-F-3150 M7J6S-SU-E-3220, P6-SU-F-WP-460

    M7J6S-SU-F-3120 Fixing of Formwork Abutment 1 2 04-Jun-15 06-Jun-15 M7J6S-SU-F-3100, M7J6S-SU-F-3110 M7J6S-SU-F-3130, M7J6S-SU-F-3150

    M7J6S-SU-F-3110 Fixing of Steel Reinforcement Abutment 1 2 02-Jun-15 03-Jun-15 M7J6S-SU-F-3090 M7J6S-SU-F-3140, M7J6S-SU-F-3120

    M7J6S-SU-F-3150 Fixing of Formwork Abutment 2 2 07-Jun-15 08-Jun-15 M7J6S-SU-F-3120, M7J6S-SU-F-3140, M7 M7J6S-SU-F-3160, M7J6S-SU-F-3180

    M7J6S-SU-F-3140 Fixing of Steel Reinforcement Abutment 2 2 04-Jun-15 06-Jun-15 M7J6S-SU-F-3110 M7J6S-SU-F-3170, M7J6S-SU-F-3170, M7J6S-

    SEGMENT 3SEGMENT 3 18 07-Jun-15 27-Jun-15

    P6-SU-F-WP-470 Water Proofing and Backf illing 5 22-Jun-15 27-Jun-15 M7J6S-SU-F-3220, M7J6S-SU-F-3190 M7J6S-SU-DS-2680

    M7J6S-SU-F-3190 Pouring of Concrete Abutment 1 1 10-Jun-15 10-Jun-15 M7J6S-SU-F-3180 M7J6S-SU-E-3070, M7J6S-SU-E-3130, P6-SU-

    M7J6S-SU-F-3220 Pouring of Concrete Abutment 2 1 13-Jun-15 13-Jun-15 M7J6S-SU-F-3210 M7J6S-SU-E-3100, M7J6S-SU-E-3160, P6-SU-

    M7J6S-SU-F-3170 Fixing of Steel Reinforcement Abutment 1 2 07-Jun-15 08-Jun-15 M7J6S-SU-F-3140, M7J6S-SU-F-3140 M7J6S-SU-F-3180, M7J6S-SU-F-3200, M7J6S-

    M7J6S-SU-F-3180 Fixing of Formwork Abutment 1 2 09-Jun-15 10-Jun-15 M7J6S-SU-F-3170, M7J6S-SU-F-3150, M7 M7J6S-SU-F-3190, M7J6S-SU-F-3210

    M7J6S-SU-F-3210 Fixing of Formwork Abutment 2 2 11-Jun-15 13-Jun-15 M7J6S-SU-F-3180, M7J6S-SU-F-3200, M7 M7J6S-SU-F-3220, M7J6S-SU-F-3240

    M7J6S-SU-F-3200 Fixing of Steel Reinforcement Abutment 2 2 09-Jun-15 10-Jun-15 M7J6S-SU-F-3170 M7J6S-SU-F-3230, M7J6S-SU-F-3210, M7J6S-

    SEGMENT 4SEGMENT 4 19 11-Jun-15 02-Jul-15

    P6-SU-F-WP-480 Water Proofing and Backf illing 5 28-Jun-15 02-Jul-15 M7J6S-SU-F-3280, M7J6S-SU-F-3250 M7J6S-SU-DS-2820

    M7J6S-SU-F-3250 Pouring of Concrete Abutment 1 1 15-Jun-15 15-Jun-15 M7J6S-SU-F-3240 M7J6S-SU-E-3250, P6-SU-F-WP-480

    M7J6S-SU-F-3280 Pouring of Concrete Abutment 2 1 18-Jun-15 18-Jun-15 M7J6S-SU-F-3270 M7J6S-SU-E-3280, P6-SU-F-WP-480

    M7J6S-SU-F-3230 Fixing of Steel Reinforcement Abutment 1 3 11-Jun-15 14-Jun-15 M7J6S-SU-F-3200 M7J6S-SU-F-3260, M7J6S-SU-F-3240, M7J6S-

    M7J6S-SU-F-3240 Fixing of Formwork Abutment 1 2 14-Jun-15 15-Jun-15 M7J6S-SU-F-3210, M7J6S-SU-F-3230, M7 M7J6S-SU-F-3270, M7J6S-SU-F-3250

    M7J6S-SU-F-3260 Fixing of Steel Reinforcement Abutment 2 3 15-Jun-15 17-Jun-15 M7J6S-SU-F-3230 M7J6S-SU-F-3270, M7J6S-SU-F-3320, M7J6S-

    M7J6S-SU-F-3270 Fixing of Formwork Abutment 2 2 17-Jun-15 18-Jun-15 M7J6S-SU-F-3240, M7J6S-SU-F-3260, M7 M7J6S-SU-F-3280, M7J6S-SU-F-3330

    SEGMENT 5SEGMENT 5 18 18-Jun-15 08-Jul-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 13 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    P6-SU-F-WP-490 Water Proofing and Backf illing 5 04-Jul-15 08-Jul-15 M7J6S-SU-F-3340, M7J6S-SU-F-3310 M7J6S-SU-DS-2720

    M7J6S-SU-F-3310 Pouring of Concrete Abutment 1 1 24-Jun-15 24-Jun-15 M7J6S-SU-F-3300 M7J6S-SU-E-3310, P6-SU-F-WP-490

    M7J6S-SU-F-3340 Pouring of Concrete Abutment 2 1 21-Jun-15 21-Jun-15 M7J6S-SU-F-3330 M7J6S-SU-E-3340, P6-SU-F-WP-490

    M7J6S-SU-F-3320 Fixing of Steel Reinforcement Abutment 2 2 18-Jun-15 20-Jun-15 M7J6S-SU-F-3260 M7J6S-SU-F-3290, M7J6S-SU-F-3330, M7J6S-

    M7J6S-SU-F-3330 Fixing of Formwork Abutment 2 2 20-Jun-15 21-Jun-15 M7J6S-SU-F-3270, M7J6S-SU-F-3320, M7 M7J6S-SU-F-3300, M7J6S-SU-F-3340

    M7J6S-SU-F-3290 Fixing of Steel Reinforcement Abutment 1 2 21-Jun-15 22-Jun-15 M7J6S-SU-F-3320 M7J6S-SU-F-3300, M7J6S-SU-F-3350, M7J6S-

    M7J6S-SU-F-3300 Fixing of Formwork Abutment 1 2 23-Jun-15 24-Jun-15 M7J6S-SU-F-3330, M7J6S-SU-F-3290, M7 M7J6S-SU-F-3360, M7J6S-SU-F-3310

    SEGMENT 6SEGMENT 6 18 23-Jun-15 13-Jul-15

    P6-SU-F-WP-500 Water Proofing and Backf illing 5 08-Jul-15 13-Jul-15 M7J6S-SU-F-3400, M7J6S-SU-F-3370 M7J6S-SU-DS-2870

    M7J6S-SU-F-3370 Pouring of Concrete Abutment 1 1 27-Jun-15 27-Jun-15 M7J6S-SU-F-3360 M7J6S-SU-E-3370, P6-SU-F-WP-500

    M7J6S-SU-F-3400 Pouring of Concrete Abutment 2 1 29-Jun-15 29-Jun-15 M7J6S-SU-F-3390 M7J6S-SU-E-3400, P6-SU-F-WP-500

    M7J6S-SU-F-3350 Fixing of Steel Reinforcement Abutment 1 2 23-Jun-15 24-Jun-15 M7J6S-SU-F-3290 M7J6S-SU-F-3380, M7J6S-SU-F-3360, M7J6S-

    M7J6S-SU-F-3360 Fixing of Formwork Abutment 1 2 25-Jun-15 27-Jun-15 M7J6S-SU-F-3350, M7J6S-SU-F-3300, M7 M7J6S-SU-F-3390, M7J6S-SU-F-3370

    M7J6S-SU-F-3380 Fixing of Steel Reinforcement Abutment 2 3 25-Jun-15 28-Jun-15 M7J6S-SU-F-3350 M7J6S-SU-F-3390, M8J12S-CU-F-3770, M7J6S

    M7J6S-SU-F-3390 Fixing of Formwork Abutment 2 2 28-Jun-15 29-Jun-15 M7J6S-SU-F-3380, M7J6S-SU-F-3360, M7 M7J6S-SU-F-3400, M7J6S-SU-F-3420

    WALLWALL 39 24-Jun-15 11-Aug-15

    SEGMENT 1SEGMENT 1 9 24-Jun-15 04-Jul-15

    M7J6S-SU-E-3090 Pouring of Concrete for Abutment 1 1 30-Jun-15 30-Jun-15 M7J6S-SU-E-3080 M7J6S-SU-DS-2620

    M7J6S-SU-E-3120 Pouring of Concrete for Abutment 2 1 04-Jul-15 04-Jul-15 M7J6S-SU-E-3110 M7J6S-SU-DS-2620

    M7J6S-SU-E-3080 Fixing of Formwork for Abutment 1 2 28-Jun-15 29-Jun-15 M7J6S-SU-E-3070 M7J6S-SU-E-3090

    M7J6S-SU-E-3070 Fixing of Reinforcement for Abutment 1 3 24-Jun-15 27-Jun-15 M7J6S-SU-F-3190, M7J6S-SU-F-3080, M7 M7J6S-SU-E-3100, M7J6S-SU-E-3080

    M7J6S-SU-E-3100 Fixing of Reinforcement for Abutment 2 3 28-Jun-15 30-Jun-15 M7J6S-SU-E-3070, M7J6S-SU-F-3220, M7 M7J6S-SU-E-3110, M7J6S-SU-E-3130

    M7J6S-SU-E-3110 Fixing of Formwork for Abutment 2 2 01-Jul-15 02-Jul-15 M7J6S-SU-E-3100 M7J6S-SU-E-3120

    SEGMENT 3SEGMENT 3 9 01-Jul-15 11-Jul-15

    M7J6S-SU-E-3150 Pouring of Concrete for Abutment 1 1 07-Jul-15 07-Jul-15 M7J6S-SU-E-3140 M7J6S-SU-DS-2680

    M7J6S-SU-E-3180 Pouring of Concrete for Abutment 2 1 11-Jul-15 11-Jul-15 M7J6S-SU-E-3170 M7J6S-SU-DS-2680

    M7J6S-SU-E-3140 Fixing of Formwork for Abutment 1 2 05-Jul-15 06-Jul-15 M7J6S-SU-E-3130 M7J6S-SU-E-3150

    M7J6S-SU-E-3130 Fixing of Reinforcement for Abutment 1 3 01-Jul-15 04-Jul-15 M7J6S-SU-E-3100, M7J6S-SU-F-3190 M7J6S-SU-E-3160, M7J6S-SU-E-3140

    M7J6S-SU-E-3160 Fixing of Reinforcement for Abutment 2 3 05-Jul-15 07-Jul-15 M7J6S-SU-E-3130, M7J6S-SU-F-3220 M7J6S-SU-E-3170, M7J6S-SU-E-3310

    M7J6S-SU-E-3170 Fixing of Formwork for Abutment 2 2 08-Jul-15 09-Jul-15 M7J6S-SU-E-3160 M7J6S-SU-E-3180

    SEGMENT 5SEGMENT 5 9 08-Jul-15 21-Jul-15

    M7J6S-SU-E-3330 Pouring of Concrete for Abutment 1 1 14-Jul-15 14-Jul-15 M7J6S-SU-E-3320 M7J6S-SU-DS-2720

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 14 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-SU-E-3360 Pouring of Concrete for Abutment 2 1 21-Jul-15 21-Jul-15 M7J6S-SU-E-3350 M7J6S-SU-DS-2720

    M7J6S-SU-E-3320 Fixing of Formwork for Abutment 1 2 12-Jul-15 13-Jul-15 M7J6S-SU-E-3310 M7J6S-SU-E-3330

    M7J6S-SU-E-3310 Fixing of Reinforcement for Abutment 1 3 08-Jul-15 11-Jul-15 M7J6S-SU-E-3160, M7J6S-SU-F-3310 M7J6S-SU-E-3340, M7J6S-SU-E-3320

    M7J6S-SU-E-3340 Fixing of Reinforcement for Abutment 2 3 12-Jul-15 14-Jul-15 M7J6S-SU-E-3310, M7J6S-SU-F-3340 M7J6S-SU-E-3350, M7J6S-SU-E-3190

    M7J6S-SU-E-3350 Fixing of Formwork for Abutment 2 2 15-Jul-15 16-Jul-15 M7J6S-SU-E-3340 M7J6S-SU-E-3360

    SEGMENT 2SEGMENT 2 9 15-Jul-15 28-Jul-15

    M7J6S-SU-E-3210 Pouring of Concrete for Abutment 1 1 25-Jul-15 25-Jul-15 M7J6S-SU-E-3200 M7J6S-SU-DS-2780

    M7J6S-SU-E-3240 Pouring of Concrete for Abutment 2 1 28-Jul-15 28-Jul-15 M7J6S-SU-E-3230 M7J6S-SU-DS-2780

    M7J6S-SU-E-3200 Fixing of Formwork for Abutment 1 2 22-Jul-15 23-Jul-15 M7J6S-SU-E-3190 M7J6S-SU-E-3210

    M7J6S-SU-E-3190 Fixing of Reinforcement for Abutment 1 3 15-Jul-15 21-Jul-15 M7J6S-SU-E-3340, M7J6S-SU-F-3130 M7J6S-SU-E-3220, M7J6S-SU-E-3200

    M7J6S-SU-E-3220 Fixing of Reinforcement for Abutment 2 3 22-Jul-15 25-Jul-15 M7J6S-SU-E-3190, M7J6S-SU-F-3160 M7J6S-SU-E-3230, M7J6S-SU-E-3250

    M7J6S-SU-E-3230 Fixing of Formwork for Abutment 2 2 26-Jul-15 27-Jul-15 M7J6S-SU-E-3220 M7J6S-SU-E-3240

    SEGMENT 4SEGMENT 4 9 26-Jul-15 04-Aug-15

    M7J6S-SU-E-3270 Pouring of Concrete for Abutment 1 1 01-Aug-15 01-Aug-15 M7J6S-SU-E-3260 M7J6S-SU-DS-2820

    M7J6S-SU-E-3300 Pouring of Concrete for Abutment 2 1 04-Aug-15 04-Aug-15 M7J6S-SU-E-3290 M7J6S-SU-DS-2820

    M7J6S-SU-E-3260 Fixing of Formwork for Abutment 1 2 29-Jul-15 30-Jul-15 M7J6S-SU-E-3250 M7J6S-SU-E-3270

    M7J6S-SU-E-3250 Fixing of Reinforcement for Abutment 1 3 26-Jul-15 28-Jul-15 M7J6S-SU-E-3220, M7J6S-SU-F-3250 M7J6S-SU-E-3280, M7J6S-SU-E-3260

    M7J6S-SU-E-3290 Fixing of Formwork for Abutment 2 2 02-Aug-15 03-Aug-15 M7J6S-SU-E-3280 M7J6S-SU-E-3300

    M7J6S-SU-E-3280 Fixing of Reinforcement for Abutment 2 3 29-Jul-15 01-Aug-15 M7J6S-SU-E-3250, M7J6S-SU-F-3280 M7J6S-SU-E-3370, M7J6S-SU-E-3290

    SEGMENT 6SEGMENT 6 9 02-Aug-15 11-Aug-15

    M7J6S-SU-E-3390 Pouring of Concrete for Abutment 1 1 08-Aug-15 08-Aug-15 M7J6S-SU-E-3380 M7J6S-SU-DS-2870

    M7J6S-SU-E-3420 Pouring of Concrete for Abutment 2 1 11-Aug-15 11-Aug-15 M7J6S-SU-E-3410 M7J6S-SU-DS-2870

    M7J6S-SU-E-3380 Fixing of Formwork for Abutment 1 2 05-Aug-15 06-Aug-15 M7J6S-SU-E-3370 M7J6S-SU-E-3390

    M7J6S-SU-E-3370 Fixing of Reinforcement for Abutment 1 3 02-Aug-15 04-Aug-15 M7J6S-SU-E-3280, M7J6S-SU-F-3370 M7J6S-SU-E-3400, M7J6S-SU-E-3380

    M7J6S-SU-E-3410 Fixing of Formwork for Abutment 2 2 09-Aug-15 10-Aug-15 M7J6S-SU-E-3400 M7J6S-SU-E-3420

    M7J6S-SU-E-3400 Fixing of Reinforcement for Abutment 2 3 05-Aug-15 08-Aug-15 M7J6S-SU-E-3370, M7J6S-SU-F-3400 M7J6S-SU-E-3430, M7J6S-SU-E-3410, M8J12S

    DECK SLABDECK SLAB 38 07-Jul-15 23-Aug-15

    SEGMENT 1SEGMENT 1 10 07-Jul-15 21-Jul-15

    M7J6S-SU-DS-2620 Formwork Installation for Deck Slab 1 07-Jul-15 07-Jul-15 M7J6S-SU-E-3120, M7J6S-SU-E-3090, P6 M7J6S-SU-DS-2630

    M7J6S-SU-DS-2630 Fixing of Reinforcement for Deck Slab 3 08-Jul-15 11-Jul-15 M7J6S-SU-DS-2620 M7J6S-SU-DS-2640

    M7J6S-SU-DS-2640 Concrete Works 1 11-Jul-15 11-Jul-15 M7J6S-SU-DS-2630 M7J6S-SU-DS-2650

    M7J6S-SU-DS-2650 Curing 1 12-Jul-15 12-Jul-15 M7J6S-SU-DS-2640 M7J6S-SU-DS-2660

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 15 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-SU-DS-2660 Dismantling the Formwork 1 13-Jul-15 13-Jul-15 M7J6S-SU-DS-2650 P6-SU-DS-WP-450, M7J6S-SU-DS-2680

    P6-SU-DS-WP-450 Water Proofing for Elelvat ion and Deck Slab 4 14-Jul-15 21-Jul-15 M7J6S-SU-DS-2660 P6-SU-DS-WP-460

    SEGMENT 3SEGMENT 3 10 13-Jul-15 27-Jul-15

    M7J6S-SU-DS-2690 Fixing of Reinforcement for Deck Slab 3 14-Jul-15 16-Jul-15 M7J6S-SU-DS-2680 M7J6S-SU-DS-2700

    M7J6S-SU-DS-2700 Concrete Works 1 16-Jul-15 16-Jul-15 M7J6S-SU-DS-2690 M7J6S-SU-DS-2710

    M7J6S-SU-DS-2710 Curing 1 21-Jul-15 21-Jul-15 M7J6S-SU-DS-2700 M7J6S-SU-DS-2715

    M7J6S-SU-DS-2680 Formwork Installation for Deck Slab 1 13-Jul-15 13-Jul-15 M7J6S-SU-E-3150, M7J6S-SU-E-3180, P6 M7J6S-SU-DS-2720, M7J6S-SU-DS-2690

    M7J6S-SU-DS-2715 Dismantling the Formwork 1 22-Jul-15 22-Jul-15 M7J6S-SU-DS-2710 M7J6S-SU-DS-2820, P6-SU-DS-WP-460, M7J6

    P6-SU-DS-WP-460 Water Proofing for Elelvat ion and Deck Slab 4 23-Jul-15 27-Jul-15 M7J6S-SU-DS-2715, P6-SU-DS-WP-450 P6-SU-DS-WP-470

    SEGMENT 5SEGMENT 5 10 22-Jul-15 02-Aug-15

    M7J6S-SU-DS-2720 Formwork Installation for Deck Slab 1 22-Jul-15 22-Jul-15 M7J6S-SU-DS-2680, M7J6S-SU-E-3330, M M7J6S-SU-DS-2730

    M7J6S-SU-DS-2730 Fixing of Reinforcement for Deck Slab 3 23-Jul-15 26-Jul-15 M7J6S-SU-DS-2720 M7J6S-SU-DS-2740

    M7J6S-SU-DS-2740 Concrete Works 1 26-Jul-15 26-Jul-15 M7J6S-SU-DS-2730 M7J6S-SU-DS-2750

    M7J6S-SU-DS-2750 Curing 1 27-Jul-15 27-Jul-15 M7J6S-SU-DS-2740 M7J6S-SU-DS-2760

    M7J6S-SU-DS-2760 Dismantling the Formwork 1 28-Jul-15 28-Jul-15 M7J6S-SU-DS-2750 P6-SU-DS-WP-470, M7J6S-SU-DS-2780

    P6-SU-DS-WP-470 Water Proofing for Elelvat ion and Deck Slab 4 29-Jul-15 02-Aug-15 M7J6S-SU-DS-2760, P6-SU-DS-WP-460 P6-SU-DS-WP-480

    SEGMENT 2SEGMENT 2 10 29-Jul-15 09-Aug-15

    M7J6S-SU-DS-2780 Formwork Installation for Deck Slab 1 29-Jul-15 29-Jul-15 M7J6S-SU-E-3210, M7J6S-SU-E-3240, P6 M7J6S-SU-DS-2790

    M7J6S-SU-DS-2790 Fixing of Reinforcement for Deck Slab 3 30-Jul-15 02-Aug-15 M7J6S-SU-DS-2780 M7J6S-SU-DS-2800

    M7J6S-SU-DS-2800 Concrete Works 1 02-Aug-15 02-Aug-15 M7J6S-SU-DS-2790 M7J6S-SU-DS-2810

    M7J6S-SU-DS-2810 Curing 1 03-Aug-15 03-Aug-15 M7J6S-SU-DS-2800 M7J6S-SU-DS-2815

    M7J6S-SU-DS-2815 Dismantling the Formwork 1 04-Aug-15 04-Aug-15 M7J6S-SU-DS-2810 P6-SU-DS-WP-480, M8J12S-CU-DS-3220

    P6-SU-DS-WP-480 Water Proofing for Elelvat ion and Deck Slab 4 05-Aug-15 09-Aug-15 M7J6S-SU-DS-2815, P6-SU-DS-WP-470 P6-SU-DS-WP-490

    SEGMENT 4SEGMENT 4 10 05-Aug-15 16-Aug-15

    M7J6S-SU-DS-2820 Formwork Installation for Deck Slab 1 05-Aug-15 05-Aug-15 M7J6S-SU-DS-2715, M7J6S-SU-E-3300, M M7J6S-SU-DS-2830

    M7J6S-SU-DS-2830 Fixing of Reinforcement for Deck Slab 3 06-Aug-15 09-Aug-15 M7J6S-SU-DS-2820 M7J6S-SU-DS-2840

    M7J6S-SU-DS-2840 Concrete Works 1 09-Aug-15 09-Aug-15 M7J6S-SU-DS-2830 M7J6S-SU-DS-2850

    M7J6S-SU-DS-2850 Curing 1 10-Aug-15 10-Aug-15 M7J6S-SU-DS-2840 M7J6S-SU-DS-2860

    M7J6S-SU-DS-2860 Dismantling the Formwork 1 11-Aug-15 11-Aug-15 M7J6S-SU-DS-2850 P6-SU-DS-WP-490, M7J6S-SU-DS-2870

    P6-SU-DS-WP-490 Water Proofing for Elelvat ion and Deck Slab 4 12-Aug-15 16-Aug-15 M7J6S-SU-DS-2860, P6-SU-DS-WP-480 P6-SU-DS-WP-500

    SEGMENT 6SEGMENT 6 10 12-Aug-15 23-Aug-15

    P6-SU-DS-WP-500 Water Proofing for Elelvat ion and Deck Slab 4 19-Aug-15 23-Aug-15 M7J6S-SU-DS-2910, P6-SU-DS-WP-490 M7J6S-EE-320

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 16 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-SU-DS-2870 Formwork Installation for Deck Slab 1 12-Aug-15 12-Aug-15 M7J6S-SU-E-3390, M7J6S-SU-E-3420, P6 M7J6S-SU-DS-2880

    M7J6S-SU-DS-2880 Fixing of Reinforcement for Deck Slab 3 13-Aug-15 16-Aug-15 M7J6S-SU-DS-2870 M7J6S-SU-DS-2890

    M7J6S-SU-DS-2890 Concrete Works 1 16-Aug-15 16-Aug-15 M7J6S-SU-DS-2880 M7J6S-SU-DS-2900

    M7J6S-SU-DS-2900 Curing 1 17-Aug-15 17-Aug-15 M7J6S-SU-DS-2890 M7J6S-SU-DS-2910

    M7J6S-SU-DS-2910 Dismantling the Formwork 1 18-Aug-15 18-Aug-15 M7J6S-SU-DS-2900 P6-SU-DS-WP-500, M7J6S-HL-450

    HEADWALL SLAB WORKSHEADWALL SLAB WORKS 15 19-Aug-15 05-Sep-15

    M7J6S-HL-450 Erection of Scaffolding 4 19-Aug-15 23-Aug-15 M7J6S-SU-DS-2910 M7J6S-HL-460

    M7J6S-HL-460 Fixing of Formwork & Steel Reinforcement 6 27-Aug-15 02-Sep-15 M7J6S-HL-450 M7J6S-HL-470

    M7J6S-HL-470 Pouring of Concrete 1 03-Sep-15 03-Sep-15 M7J6S-HL-460 M7J6S-HL-480, M7J6S-EE-310

    M7J6S-HL-480 Deshuttering & Removal of Scaffolds & Formwork 1 05-Sep-15 05-Sep-15 M7J6S-HL-470 P41-FN-250, M7J4-WW-1850

    WINGWALLWINGWALL 6 06-Sep-15 12-Sep-15

    ABUTMENT 1ABUTMENT 1 5 06-Sep-15 10-Sep-15

    M7J4-WW-1850 Steel Works for Foundation Abutment 1 1 06-Sep-15 06-Sep-15 M7J6S-HL-480 M7J4-WW-1860, M7J4-WW-1910

    M7J4-WW-1860 Formworkl Works for Foundation Abutment 1 1 07-Sep-15 07-Sep-15 M7J4-WW-1850 M7J4-WW-1870

    M7J4-WW-1870 Concrete Works for Foundation Abutment 1 1 07-Sep-15 07-Sep-15 M7J4-WW-1860 M7J4-WW-1880

    M7J4-WW-1880 Steel Works for Elevation Abutment 1 1 09-Sep-15 09-Sep-15 M7J4-WW-1870, M7J4-WW-1910 M7J4-WW-1890, M7J4-WW-1940

    M7J4-WW-1890 Formworkl Works for Elevation Abutment 1 1 10-Sep-15 10-Sep-15 M7J4-WW-1880 M7J4-WW-1900

    M7J4-WW-1900 Concrete Works for Elevation Abutment 1 1 10-Sep-15 10-Sep-15 M7J4-WW-1890

    ABUTMENT 2ABUTMENT 2 5 07-Sep-15 12-Sep-15

    M7J4-WW-1910 Steel Works for Foundation Abutment 2 1 07-Sep-15 07-Sep-15 M7J4-WW-1850 M7J4-WW-1920, M7J4-WW-1880

    M7J4-WW-1920 Formworkl Works for Foundation Abutment 2 1 08-Sep-15 08-Sep-15 M7J4-WW-1910 M7J4-WW-1930

    M7J4-WW-1930 Concrete Works for Foundation Abutment 2 1 08-Sep-15 08-Sep-15 M7J4-WW-1920 M7J4-WW-1940

    M7J4-WW-1940 Steel Works for Elevation Abutment 2 1 10-Sep-15 10-Sep-15 M7J4-WW-1930, M7J4-WW-1880 M7J4-WW-1950

    M7J4-WW-1950 Formworkl Works for Elevation Abutment 2 1 12-Sep-15 12-Sep-15 M7J4-WW-1940 M7J4-WW-1960

    M7J4-WW-1960 Concrete Works for Elevation Abutment 2 1 12-Sep-15 12-Sep-15 M7J4-WW-1950 M7J6S-EE-320

    EARTHWALL WORKS & EMBEARTHWALL WORKS & EMBANKMENT WORKS 24 05-Sep-15 04-Oct-15

    M7J6S-EE-310 Storm Water Drainage Works 4 05-Sep-15 08-Sep-15 M7J6S-HL-470 M7J6S-EE-320, M7J6S-EE-320

    M7J6S-EE-320 Laying of Geotextile Membrane 4 08-Sep-15 12-Sep-15 M7J6S-EE-310, M7J6S-EE-310, P6-SU-DS M7J6S-EE-330, M7J6S-EE-330

    M7J6S-EE-330 Embankment Filling works 14 08-Sep-15 26-Sep-15 M7J6S-EE-320, M7J6S-EE-320 M7J6S-HL-490

    M7J6S-HL-490 Construction of Approach Slab 6 28-Sep-15 04-Oct-15 M7J6S-EE-330 P41-FN-270, M7J6S-EW-700

    PHASE 2 (3 PANELS)PHASE 2 (3 PANELS) 110 15-Oct-15 22-Feb-16

    TRAFFIC DIVESION (1ST OCTRAFFIC DIVESION (1ST OCT 2015) 0 15-Oct-15 15-Oct-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 17 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-EW-700 Assuming Traffic Diversion 10 day after phase 1 0 15-Oct-15 M7J6S-HL-490 M7J6S-EW-660

    EARTHWORKS & BLINDINGEARTHWORKS & BLINDING 22 17-Oct-15 10-Nov-15

    M7J6S-EW-690 Blinding & Waterproofing 6 04-Nov-15 10-Nov-15 M7J6S-EW-680 M7J6S-EW-420, M7J6S-SU-F-3410

    M7J6S-EW-660 General Ground Clearances / Grubbing 4 17-Oct-15 20-Oct-15 M7J6S-EW-700 M7J6S-EW-680, M8J12S-EW-460

    M7J6S-EW-680 General Excavation & Formation Preparation 12 21-Oct-15 03-Nov-15 M7J6S-EW-660 M7J6S-EW-690, M7J6S-EW-420

    FOUNDATIONFOUNDATION 18 11-Nov-15 01-Dec-15

    SEGMENT 7SEGMENT 7 10 11-Nov-15 22-Nov-15

    P6-SU-F-WP-510 Water Proofing and Backf illing 5 17-Nov-15 22-Nov-15 M7J6S-SU-F-3460, M7J6S-SU-F-3430 M7J6S-SU-DS-2970

    M7J6S-SU-F-3420 Fixing of Formwork Abutment 1 2 12-Nov-15 14-Nov-15 M7J6S-SU-F-3410, M7J6S-SU-F-3390, M7 M7J6S-SU-F-3430, M7J6S-SU-F-3450

    M7J6S-SU-F-3410 Fixing of Steel Reinforcement Abutment 1 2 11-Nov-15 12-Nov-15 M8J12S-CU-F-3920, M7J6S-EW-690 M7J6S-SU-F-3440, M7J6S-SU-F-3420, M7J6S-

    M7J6S-SU-F-3440 Fixing of Steel Reinforcement Abutment 2 2 14-Nov-15 15-Nov-15 M7J6S-SU-F-3410 M7J6S-SU-F-3450, M7J6S-SU-F-3470, M7J6S-

    M7J6S-SU-F-3450 Fixing of Formwork Abutment 2 2 15-Nov-15 16-Nov-15 M7J6S-SU-F-3440, M7J6S-SU-F-3420, M7 M7J6S-SU-F-3460, M7J6S-SU-F-3480

    M7J6S-SU-F-3430 Pouring of Concrete Abutment 1 1 14-Nov-15 14-Nov-15 M7J6S-SU-F-3420 P6-SU-F-WP-510, M7J6S-SU-E-3490

    M7J6S-SU-F-3460 Pouring of Concrete Abutment 2 1 16-Nov-15 16-Nov-15 M7J6S-SU-F-3450 P6-SU-F-WP-510, M7J6S-SU-E-3520

    SEGMENT 8SEGMENT 8 10 16-Nov-15 26-Nov-15

    P6-SU-F-WP-520 Water Proofing and Backf illing 5 22-Nov-15 26-Nov-15 M7J6S-SU-F-3490, M7J6S-SU-F-3520 M7J6S-SU-DS-2920

    M7J6S-SU-F-3470 Fixing of Steel Reinforcement Abutment 1 2 16-Nov-15 17-Nov-15 M7J6S-SU-F-3440 M7J6S-SU-F-3500, M7J6S-SU-F-3480, M7J6S-

    M7J6S-SU-F-3480 Fixing of Formwork Abutment 1 2 17-Nov-15 18-Nov-15 M7J6S-SU-F-3470, M7J6S-SU-F-3450, M7 M7J6S-SU-F-3510, M7J6S-SU-F-3490

    M7J6S-SU-F-3500 Fixing of Steel Reinforcement Abutment 2 2 18-Nov-15 19-Nov-15 M7J6S-SU-F-3470 M7J6S-SU-F-3530, M7J6S-SU-F-3510, M7J6S-

    M7J6S-SU-F-3510 Fixing of Formwork Abutment 2 2 19-Nov-15 21-Nov-15 M7J6S-SU-F-3480, M7J6S-SU-F-3500, M7 M7J6S-SU-F-3540, M7J6S-SU-F-3520

    M7J6S-SU-F-3490 Pouring of Concrete Abutment 1 1 18-Nov-15 18-Nov-15 M7J6S-SU-F-3480 P6-SU-F-WP-520, M7J6S-SU-E-3430

    M7J6S-SU-F-3520 Pouring of Concrete Abutment 2 1 21-Nov-15 21-Nov-15 M7J6S-SU-F-3510 P6-SU-F-WP-520, M7J6S-SU-E-3460

    SEGMENT 9SEGMENT 9 10 21-Nov-15 01-Dec-15

    P6-SU-F-WP-530 Water Proofing and Backf illing 5 26-Nov-15 01-Dec-15 M7J6S-SU-F-3580, M7J6S-SU-F-3550 M7J6S-SU-DS-3020

    M7J6S-SU-F-3530 Fixing of Steel Reinforcement Abutment 1 2 21-Nov-15 22-Nov-15 M7J6S-SU-F-3500 M7J6S-SU-F-3540, M7J6S-SU-F-3560, M7J6S-

    M7J6S-SU-F-3540 Fixing of Formwork Abutment 1 2 22-Nov-15 23-Nov-15 M7J6S-SU-F-3510, M7J6S-SU-F-3530, M7 M7J6S-SU-F-3550, M7J6S-SU-F-3570

    M7J6S-SU-F-3560 Fixing of Steel Reinforcement Abutment 2 2 23-Nov-15 24-Nov-15 M7J6S-SU-F-3530 M7J6S-SU-F-3570, M7J6S-SU-F-3590, M7J6S-

    M7J6S-SU-F-3570 Fixing of Formwork Abutment 2 2 24-Nov-15 25-Nov-15 M7J6S-SU-F-3540, M7J6S-SU-F-3560, M7 M7J6S-SU-F-3580

    M7J6S-SU-F-3550 Pouring of Concrete Abutment 1 1 23-Nov-15 23-Nov-15 M7J6S-SU-F-3540 P6-SU-F-WP-530, M7J6S-SU-E-3550

    M7J6S-SU-F-3580 Pouring of Concrete Abutment 2 1 25-Nov-15 25-Nov-15 M7J6S-SU-F-3570 P6-SU-F-WP-530, M7J6S-SU-E-3580

    WALLWALL 21 19-Nov-15 13-Dec-15

    SEGMENT 8SEGMENT 8 9 19-Nov-15 29-Nov-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 18 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-SU-E-3450 Pouring of Concrete for Abutment 1 1 25-Nov-15 25-Nov-15 M7J6S-SU-E-3440 M7J6S-SU-DS-2920

    M7J6S-SU-E-3480 Pouring of Concrete for Abutment 2 1 29-Nov-15 29-Nov-15 M7J6S-SU-E-3470 M7J6S-SU-DS-2920

    M7J6S-SU-E-3440 Fixing of Formwork for Abutment 1 2 23-Nov-15 24-Nov-15 M7J6S-SU-E-3430 M7J6S-SU-E-3450

    M7J6S-SU-E-3430 Fixing of Reinforcement for Abutment 1 3 19-Nov-15 22-Nov-15 M7J6S-SU-E-3400, M7J6S-SU-F-3490, M8 M7J6S-SU-E-3460, M7J6S-SU-E-3440

    M7J6S-SU-E-3460 Fixing of Reinforcement for Abutment 2 3 23-Nov-15 25-Nov-15 M7J6S-SU-E-3430, M7J6S-SU-F-3520 M7J6S-SU-E-3470, M7J6S-SU-E-3490

    M7J6S-SU-E-3470 Fixing of Formwork for Abutment 2 2 26-Nov-15 28-Nov-15 M7J6S-SU-E-3460 M7J6S-SU-E-3480

    SEGMENT 7SEGMENT 7 9 26-Nov-15 06-Dec-15

    M7J6S-SU-E-3510 Pouring of Concrete for Abutment 1 1 02-Dec-15 02-Dec-15 M7J6S-SU-E-3500 M7J6S-SU-DS-2970

    M7J6S-SU-E-3540 Pouring of Concrete for Abutment 2 1 06-Dec-15 06-Dec-15 M7J6S-SU-E-3530 M7J6S-SU-DS-2970

    M7J6S-SU-E-3500 Fixing of Formwork for Abutment 1 2 30-Nov-15 01-Dec-15 M7J6S-SU-E-3490 M7J6S-SU-E-3510

    M7J6S-SU-E-3490 Fixing of Reinforcement for Abutment 1 3 26-Nov-15 29-Nov-15 M7J6S-SU-E-3460, M7J6S-SU-F-3430 M7J6S-SU-E-3520, M7J6S-SU-E-3500

    M7J6S-SU-E-3530 Fixing of Formwork for Abutment 2 2 03-Dec-15 05-Dec-15 M7J6S-SU-E-3520 M7J6S-SU-E-3540

    M7J6S-SU-E-3520 Fixing of Reinforcement for Abutment 2 3 30-Nov-15 02-Dec-15 M7J6S-SU-E-3490, M7J6S-SU-F-3460 M7J6S-SU-E-3550, M7J6S-SU-E-3530

    SEGMENT 9SEGMENT 9 9 03-Dec-15 13-Dec-15

    M7J6S-SU-E-3570 Pouring of Concrete for Abutment 1 1 09-Dec-15 09-Dec-15 M7J6S-SU-E-3560 M7J6S-SU-DS-3020

    M7J6S-SU-E-3600 Pouring of Concrete for Abutment 2 1 13-Dec-15 13-Dec-15 M7J6S-SU-E-3590 M7J6S-SU-DS-3020

    M7J6S-SU-E-3550 Fixing of Reinforcement for Abutment 1 3 03-Dec-15 06-Dec-15 M7J6S-SU-E-3520, M7J6S-SU-F-3550 M7J6S-SU-E-3560, M7J6S-SU-E-3580

    M7J6S-SU-E-3560 Fixing of Formwork for Abutment 1 2 07-Dec-15 08-Dec-15 M7J6S-SU-E-3550 M7J6S-SU-E-3570

    M7J6S-SU-E-3580 Fixing of Reinforcement for Abutment 2 3 07-Dec-15 09-Dec-15 M7J6S-SU-E-3550, M7J6S-SU-F-3580 M7J6S-SU-E-3590, M7J6S-SU-E-3610, M8J12S

    M7J6S-SU-E-3590 Fixing of Formwork for Abutment 2 2 10-Dec-15 12-Dec-15 M7J6S-SU-E-3580 M7J6S-SU-E-3600

    DECKSLABDECKSLAB 22 30-Nov-15 24-Dec-15

    SEGMENT 8SEGMENT 8 10 30-Nov-15 10-Dec-15

    M7J6S-SU-DS-2920 Formwork Installation for Deck Slab 1 30-Nov-15 30-Nov-15 P6-SU-F-WP-520, M7J6S-SU-E-3480, M7J M7J6S-SU-DS-2930

    M7J6S-SU-DS-2930 Fixing of Reinforcement for Deck Slab 3 01-Dec-15 03-Dec-15 M7J6S-SU-DS-2920 M7J6S-SU-DS-2940

    M7J6S-SU-DS-2940 Concrete Works 1 03-Dec-15 03-Dec-15 M7J6S-SU-DS-2930 M7J6S-SU-DS-2950

    M7J6S-SU-DS-2950 Curing 1 05-Dec-15 05-Dec-15 M7J6S-SU-DS-2940 M7J6S-SU-DS-2960

    M7J6S-SU-DS-2960 Dismantling the Formwork 1 06-Dec-15 06-Dec-15 M7J6S-SU-DS-2950 P6-SU-DS-WP-510, M7J6S-SU-DS-2970

    P6-SU-DS-WP-510 Water Proofing for Elelvat ion and Deck Slab 4 07-Dec-15 10-Dec-15 M7J6S-SU-DS-2960 P6-SU-DS-WP-520

    SEGMENT 7SEGMENT 7 10 07-Dec-15 17-Dec-15

    M7J6S-SU-DS-2970 Formwork Installation for Deck Slab 1 07-Dec-15 07-Dec-15 P6-SU-F-WP-510, M7J6S-SU-E-3510, M7J M7J6S-SU-DS-2980

    M7J6S-SU-DS-2980 Fixing of Reinforcement for Deck Slab 3 08-Dec-15 10-Dec-15 M7J6S-SU-DS-2970 M7J6S-SU-DS-2990

    M7J6S-SU-DS-2990 Concrete Works 1 10-Dec-15 10-Dec-15 M7J6S-SU-DS-2980 M7J6S-SU-DS-3000

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 19 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-SU-DS-3000 Curing 1 12-Dec-15 12-Dec-15 M7J6S-SU-DS-2990 M7J6S-SU-DS-3010

    M7J6S-SU-DS-3010 Dismantling the Formwork 1 13-Dec-15 13-Dec-15 M7J6S-SU-DS-3000 P6-SU-DS-WP-520, M7J6S-SU-DS-3020

    P6-SU-DS-WP-520 Water Proofing for Elelvat ion and Deck Slab 4 14-Dec-15 17-Dec-15 M7J6S-SU-DS-3010, P6-SU-DS-WP-510 P6-SU-DS-WP-530

    SEGMENT 9SEGMENT 9 10 14-Dec-15 24-Dec-15

    P6-SU-DS-WP-530 Water Proofing for Elelvat ion and Deck Slab 4 21-Dec-15 24-Dec-15 M7J6S-SU-DS-3060, P6-SU-DS-WP-520 M7J6S-EE-540

    M7J6S-SU-DS-3060 Dismantling the Formwork 1 20-Dec-15 20-Dec-15 M7J6S-SU-DS-3050 M7J6S-HL-800, P6-SU-DS-WP-530, M7J6S-SU

    M7J6S-SU-DS-3020 Formwork Installation for Deck Slab 1 14-Dec-15 14-Dec-15 P6-SU-F-WP-530, M7J6S-SU-E-3570, M7J M7J6S-SU-DS-3030

    M7J6S-SU-DS-3030 Fixing of Reinforcement for Deck Slab 3 15-Dec-15 17-Dec-15 M7J6S-SU-DS-3020 M7J6S-SU-DS-3040

    M7J6S-SU-DS-3040 Concrete Works 1 17-Dec-15 17-Dec-15 M7J6S-SU-DS-3030 M7J6S-SU-DS-3050, M7J6S-HL-800

    M7J6S-SU-DS-3050 Curing 1 19-Dec-15 19-Dec-15 M7J6S-SU-DS-3040 M7J6S-SU-DS-3060

    HEADWALL SLAB WORKSHEADWALL SLAB WORKS 15 21-Dec-15 06-Jan-16

    M7J6S-HL-800 Erection of Scaffolding 4 21-Dec-15 24-Dec-15 M7J6S-SU-DS-3040, M7J6S-SU-DS-3060 M7J6S-HL-810

    M7J6S-HL-810 Fixing of Formwork & Steel Reinforcement 6 29-Dec-15 04-Jan-16 M7J6S-HL-800 M7J6S-HL-820

    M7J6S-HL-820 Pouring of Concrete 1 05-Jan-16 05-Jan-16 M7J6S-HL-810 M7J6S-HL-830, M7J6S-EE-530

    M7J6S-HL-830 Deshuttering & Removal of Scaffolds & Formwork 1 06-Jan-16 06-Jan-16 M7J6S-HL-820 M7J6S-IR-250, M7J4-WW-1970

    WINGWALLWINGWALL 6 07-Jan-16 13-Jan-16

    ABUTMENT 1ABUTMENT 1 5 07-Jan-16 12-Jan-16

    M7J4-WW-1970 Steel Works for Foundation Abutment 1 1 07-Jan-16 07-Jan-16 M7J6S-HL-830 M7J4-WW-1980, M7J4-WW-2030

    M7J4-WW-1980 Formworkl Works for Foundation Abutment 1 1 09-Jan-16 09-Jan-16 M7J4-WW-1970 M7J4-WW-1990

    M7J4-WW-1990 Concrete Works for Foundation Abutment 1 1 09-Jan-16 09-Jan-16 M7J4-WW-1980 M7J4-WW-2000

    M7J4-WW-2000 Steel Works for Elevation Abutment 1 1 11-Jan-16 11-Jan-16 M7J4-WW-1990, M7J4-WW-2030 M7J4-WW-2010, M7J4-WW-2060

    M7J4-WW-2010 Formworkl Works for Elevation Abutment 1 1 12-Jan-16 12-Jan-16 M7J4-WW-2000 M7J4-WW-2020

    M7J4-WW-2020 Concrete Works for Elevation Abutment 1 1 12-Jan-16 12-Jan-16 M7J4-WW-2010

    ABUTMENT 2ABUTMENT 2 5 09-Jan-16 13-Jan-16

    M7J4-WW-2030 Steel Works for Foundation Abutment 2 1 09-Jan-16 09-Jan-16 M7J4-WW-1970 M7J4-WW-2040, M7J4-WW-2000

    M7J4-WW-2040 Formworkl Works for Foundation Abutment 2 1 10-Jan-16 10-Jan-16 M7J4-WW-2030 M7J4-WW-2050

    M7J4-WW-2050 Concrete Works for Foundation Abutment 2 1 10-Jan-16 10-Jan-16 M7J4-WW-2040 M7J4-WW-2060

    M7J4-WW-2060 Steel Works for Elevation Abutment 2 1 12-Jan-16 12-Jan-16 M7J4-WW-2050, M7J4-WW-2000 M7J4-WW-2070

    M7J4-WW-2070 Formworkl Works for Elevation Abutment 2 1 13-Jan-16 13-Jan-16 M7J4-WW-2060 M7J4-WW-2080

    M7J4-WW-2080 Concrete Works for Elevation Abutment 2 1 13-Jan-16 13-Jan-16 M7J4-WW-2070 M7J6S-EE-540

    EARTHWALL WORKS & EMBEARTHWALL WORKS & EMBANKMENT WORKS 24 06-Jan-16 02-Feb-16

    M7J6S-EE-530 Storm Water Drainage Works 4 06-Jan-16 10-Jan-16 M7J6S-HL-820 M7J6S-EE-540, M7J6S-EE-540

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 20 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M7J6S-EE-540 Laying of Geotextile Membrane 4 10-Jan-16 13-Jan-16 M7J6S-EE-530, M7J6S-EE-530, P6-SU-DS M7J6S-EE-550, M7J6S-EE-550

    M7J6S-EE-550 Embankment Filling works 14 10-Jan-16 25-Jan-16 M7J6S-EE-540, M7J6S-EE-540 M7J6S-HL-840, M7J6S-IR-250

    M7J6S-HL-840 Construction of Approach Slab 6 27-Jan-16 02-Feb-16 M7J6S-EE-550

    INTERNAL ROAD WORKSINTERNAL ROAD WORKS 13 26-Jan-16 10-Feb-16

    M7J6S-IR-250 Formation Preparation works 3 26-Jan-16 28-Jan-16 M7J6S-EE-550, M7J6S-HL-830 M7J6S-IR-260, M7J6S-IR-260

    M7J6S-IR-260 Laying of Path fill Material 8 27-Jan-16 04-Feb-16 M7J6S-IR-250, M7J6S-IR-250 M7J6S-IR-270

    M7J6S-IR-270 Road Markings & Signages 2 08-Feb-16 10-Feb-16 M7J6S-IR-260 P41-FN-250

    FINISHING WORKSFINISHING WORKS 12 08-Feb-16 22-Feb-16

    P41-FN-250 Electrical works (Installation of Lights & Fittings) 5 08-Feb-16 14-Feb-16 M7J6S-IR-270, M7J6S-HL-480 P41-FN-260, P41-FN-260

    P41-FN-260 Mechanical works (Exhaust Fans & Fittings) 5 08-Feb-16 14-Feb-16 P41-FN-250, P41-FN-250 P41-FN-270, P41-FN-270

    P41-FN-270 Internal Painting & Finishing works 7 15-Feb-16 22-Feb-16 P41-FN-260, M7J6S-HL-490, P41-FN-260

    QP PROTECTION AT 50+900QP PROTECTION AT 50+900 241 26-Mar-15 06-Jan-16

    LONGER PART (152 M) EAST LONGER PART (152 M) EAST SIDE 223 26-Mar-15 16-Dec-15

    SITE CLEARANCESITE CLEARANCE 47 26-Mar-15 19-May-15

    M751-QP51-C-100 Site Clearance 5 26-Mar-15* 31-Mar-15 M751-QP-EX-100

    M751-QP-EX-100 General Excavation 15 01-Apr-15 18-Apr-15 M751-QP51-C-100 M751-QP-EX-110, M751-QP-EX-120

    M751-QP-EX-110 Excavation for Wall 1 5 19-Apr-15 23-Apr-15 M751-QP-EX-100 M751-QP-EX-120, M751-QP-EX-150

    M751-QP-EX-120 Excavation for Wall 2 5 25-Apr-15 29-Apr-15 M751-QP-EX-110, M751-QP-EX-100 M751-QP-EX-130, M751-QP-EX-160

    M751-QP-EX-130 Excavation for wall 3 5 30-Apr-15 05-May-15 M751-QP-EX-120 M751-QP-EX-140, M751-QP-EX-170

    M751-QP-EX-140 Excavation for wall 4 5 06-May-15 11-May-15 M751-QP-EX-130 M751-QP-EX-180

    M751-QP-EX-150 Blindng for Wall 1 5 25-Apr-15 29-Apr-15 M751-QP-EX-110 M751-QP-EX-190

    M751-QP-EX-160 Blindng for Wall 2 5 30-Apr-15 05-May-15 M751-QP-EX-120 M751-QP-EX-200

    M751-QP-EX-170 Blindng for Wall 3 5 06-May-15 11-May-15 M751-QP-EX-130 M751-QP-EX-210

    M751-QP-EX-180 Blindng for Wall 1 5 12-May-15 17-May-15 M751-QP-EX-140 M751-QP-EX-220

    M751-QP-EX-190 Water Proofing for Wall 1 2 30-Apr-15 02-May-15 M751-QP-EX-150 M751-QPF-S1S1-100

    M751-QP-EX-200 Water Proofing for Wall 2 2 06-May-15 07-May-15 M751-QP-EX-160

    M751-QP-EX-210 Water Proofing for Wall 3 2 12-May-15 13-May-15 M751-QP-EX-170

    M751-QP-EX-220 Water Proofing for Wall 4 2 18-May-15 19-May-15 M751-QP-EX-180

    FOUNDATIONFOUNDATION 95 03-May-15 24-Aug-15

    SPAN 1 WALL 1 AND 2SPAN 1 WALL 1 AND 2 54 03-May-15 04-Jul-15

    SEGMENT 1SEGMENT 1 18 03-May-15 23-May-15

    M751-QPF-S1S1-100 Reinfocement for Wall 1 2 03-May-15 04-May-15 M751-QP-EX-190 M751-QPF-S1S1-110, M751-QPF-S1S1-160

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 21 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M751-QPF-S1S1-110 Formwork for Wall 1 2 05-May-15 06-May-15 M751-QPF-S1S1-100 M751-QPF-S1S1-120, M751-QPF-S1S1-170

    M751-QPF-S1S1-120 Concreting for Wall 1 1 07-May-15 07-May-15 M751-QPF-S1S1-110 M751-QPF-S1S1-130

    M751-QPF-S1S1-130 Deshuttering Wall 1 1 09-May-15 09-May-15 M751-QPF-S1S1-120 M751-QPF-S1S1-140, M751-QPF-S1S1-140

    M751-QPF-S1S1-140 Curing Wall 1 7 09-May-15 16-May-15 M751-QPF-S1S1-130, M751-QPF-S1S1-13 M751-QPF-S1S1-150

    M751-QPF-S1S1-160 Reinfocement for Wall 2 4 05-May-15 09-May-15 M751-QPF-S1S1-100 M751-QPF-S1S1-170, M751-QPF-S1S2-100

    M751-QPF-S1S1-170 Formwork for Wall 2 2 10-May-15 11-May-15 M751-QPF-S1S1-160, M751-QPF-S1S1-11 M751-QPF-S1S1-180

    M751-QPF-S1S1-180 Concreting for Wall 2 1 12-May-15 12-May-15 M751-QPF-S1S1-170 M751-QPF-S1S1-190

    M751-QPF-S1S1-190 Deshuttering Wall 2 1 13-May-15 13-May-15 M751-QPF-S1S1-180 M751-QPF-S1S1-200, M751-QPF-S1S1-200, M

    M751-QPF-S1S1-200 Curing Wall 2 7 13-May-15 20-May-15 M751-QPF-S1S1-190, M751-QPF-S1S1-19 M751-QPF-S1S1-210

    M751-QPF-S1S1-150 Waterpoofing Wall 1 2 17-May-15 18-May-15 M751-QPF-S1S1-140

    M751-QPF-S1S1-210 Waterpoofing Wall 2 2 21-May-15 23-May-15 M751-QPF-S1S1-200

    SEGMENT 2SEGMENT 2 18 10-May-15 30-May-15

    M751-QPF-S1S2-100 Reinfocement for Wall 1 2 10-May-15 11-May-15 M751-QPF-S1S1-160 M751-QPF-S1S2-110, M751-QPF-S1S2-160

    M751-QPF-S1S2-110 Formwork for Wall 1 1 12-May-15 12-May-15 M751-QPF-S1S2-100 M751-QPF-S1S2-120, M751-QPF-S1S2-170

    M751-QPF-S1S2-120 Concreting for Wall 1 1 13-May-15 13-May-15 M751-QPF-S1S2-110 M751-QPF-S1S2-130

    M751-QPF-S1S2-130 Deshuttering Wall 1 1 14-May-15 14-May-15 M751-QPF-S1S2-120 M751-QPF-S1S2-140, M751-QPF-S1S2-140

    M751-QPF-S1S2-140 Curing Wall 1 7 14-May-15 21-May-15 M751-QPF-S1S2-130, M751-QPF-S1S2-13 M751-QPF-S1S2-150

    M751-QPF-S1S2-160 Reinfocement for Wall 2 4 12-May-15 16-May-15 M751-QPF-S1S2-100 M751-QPF-S1S2-170, M751-QPF-S1S3-100

    M751-QPF-S1S2-170 Formwork for Wall 2 2 17-May-15 18-May-15 M751-QPF-S1S2-160, M751-QPF-S1S2-11 M751-QPF-S1S2-180

    M751-QPF-S1S2-180 Concreting for Wall 2 1 19-May-15 19-May-15 M751-QPF-S1S2-170 M751-QPF-S1S2-190

    M751-QPF-S1S2-190 Deshuttering Wall 2 1 20-May-15 20-May-15 M751-QPF-S1S2-180 M751-QPF-S1S2-200, M751-QPF-S1S2-200, M

    M751-QPF-S1S2-200 Curing Wall 2 7 20-May-15 27-May-15 M751-QPF-S1S2-190, M751-QPF-S1S2-19 M751-QPF-S1S2-210

    M751-QPF-S1S2-150 Waterpoofing Wall 1 2 23-May-15 24-May-15 M751-QPF-S1S2-140

    M751-QPF-S1S2-210 Waterpoofing Wall 2 2 28-May-15 30-May-15 M751-QPF-S1S2-200

    SEGMENT 3SEGMENT 3 18 17-May-15 06-Jun-15

    M751-QPF-S1S3-100 Reinfocement for Wall 1 2 17-May-15 18-May-15 M751-QPF-S1S2-160 M751-QPF-S1S3-110, M751-QPF-S1S3-160

    M751-QPF-S1S3-110 Formwork for Wall 1 1 19-May-15 19-May-15 M751-QPF-S1S3-100 M751-QPF-S1S3-120, M751-QPF-S1S3-170

    M751-QPF-S1S3-120 Concreting for Wall 1 1 20-May-15 20-May-15 M751-QPF-S1S3-110 M751-QPF-S1S3-130

    M751-QPF-S1S3-130 Deshuttering Wall 1 1 21-May-15 21-May-15 M751-QPF-S1S3-120 M751-QPF-S1S3-140, M751-QPF-S1S3-140

    M751-QPF-S1S3-140 Curing Wall 1 7 21-May-15 28-May-15 M751-QPF-S1S3-130, M751-QPF-S1S3-13 M751-QPF-S1S3-150

    M751-QPF-S1S3-160 Reinfocement for Wall 2 4 19-May-15 23-May-15 M751-QPF-S1S3-100 M751-QPF-S1S3-170, M751-QPF-S1S4-100

    M751-QPF-S1S3-170 Formwork for Wall 2 2 24-May-15 25-May-15 M751-QPF-S1S3-160, M751-QPF-S1S3-11 M751-QPF-S1S3-180

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 22 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M751-QPF-S1S3-180 Concreting for Wall 2 1 26-May-15 26-May-15 M751-QPF-S1S3-170 M751-QPF-S1S3-190

    M751-QPF-S1S3-190 Deshuttering Wall 2 1 27-May-15 27-May-15 M751-QPF-S1S3-180 M751-QPF-S1S3-200, M751-QPF-S1S3-200, M

    M751-QPF-S1S3-200 Curing Wall 2 7 27-May-15 03-Jun-15 M751-QPF-S1S3-190, M751-QPF-S1S3-19 M751-QPF-S1S3-210

    M751-QPF-S1S3-150 Waterpoofing Wall 1 2 30-May-15 31-May-15 M751-QPF-S1S3-140

    M751-QPF-S1S3-210 Waterpoofing Wall 2 2 04-Jun-15 06-Jun-15 M751-QPF-S1S3-200

    SEGMENT 4SEGMENT 4 17 24-May-15 11-Jun-15

    M751-QPF-S1S4-100 Reinfocement for Wall 1 2 24-May-15 25-May-15 M751-QPF-S1S3-160 M751-QPF-S1S4-110, M751-QPF-S1S4-160

    M751-QPF-S1S4-110 Formwork for Wall 1 1 26-May-15 26-May-15 M751-QPF-S1S4-100 M751-QPF-S1S4-120, M751-QPF-S1S4-170

    M751-QPF-S1S4-120 Concreting for Wall 1 1 27-May-15 27-May-15 M751-QPF-S1S4-110 M751-QPF-S1S4-130

    M751-QPF-S1S4-130 Deshuttering Wall 1 1 28-May-15 28-May-15 M751-QPF-S1S4-120 M751-QPF-S1S4-140, M751-QPF-S1S4-140

    M751-QPF-S1S4-140 Curing Wall 1 7 28-May-15 04-Jun-15 M751-QPF-S1S4-130, M751-QPF-S1S4-13 M751-QPF-S1S4-150

    M751-QPF-S1S4-160 Reinfocement for Wall 2 4 26-May-15 30-May-15 M751-QPF-S1S4-100 M751-QPF-S1S4-170, M751-QPF-S1S5-100

    M751-QPF-S1S4-170 Formwork for Wall 2 1 31-May-15 31-May-15 M751-QPF-S1S4-160, M751-QPF-S1S4-11 M751-QPF-S1S4-180

    M751-QPF-S1S4-180 Concreting for Wall 2 1 01-Jun-15 01-Jun-15 M751-QPF-S1S4-170 M751-QPF-S1S4-190

    M751-QPF-S1S4-190 Deshuttering Wall 2 1 02-Jun-15 02-Jun-15 M751-QPF-S1S4-180 M751-QPF-S1S4-200, M751-QPF-S1S4-200, M

    M751-QPF-S1S4-200 Curing Wall 2 7 02-Jun-15 09-Jun-15 M751-QPF-S1S4-190, M751-QPF-S1S4-19 M751-QPF-S1S4-210

    M751-QPF-S1S4-150 Waterpoofing Wall 1 2 06-Jun-15 07-Jun-15 M751-QPF-S1S4-140

    M751-QPF-S1S4-210 Waterpoofing Wall 2 2 10-Jun-15 11-Jun-15 M751-QPF-S1S4-200

    SEGMENT 5SEGMENT 5 18 31-May-15 20-Jun-15

    M751-QPF-S1S5-100 Reinfocement for Wall 1 2 31-May-15 01-Jun-15 M751-QPF-S1S4-160 M751-QPF-S1S5-110, M751-QPF-S1S5-160

    M751-QPF-S1S5-110 Formwork for Wall 1 1 02-Jun-15 02-Jun-15 M751-QPF-S1S5-100 M751-QPF-S1S5-120, M751-QPF-S1S5-170

    M751-QPF-S1S5-120 Concreting for Wall 1 1 03-Jun-15 03-Jun-15 M751-QPF-S1S5-110 M751-QPF-S1S5-130

    M751-QPF-S1S5-130 Deshuttering Wall 1 1 04-Jun-15 04-Jun-15 M751-QPF-S1S5-120 M751-QPF-S1S5-140, M751-QPF-S1S5-140

    M751-QPF-S1S5-140 Curing Wall 1 7 04-Jun-15 11-Jun-15 M751-QPF-S1S5-130, M751-QPF-S1S5-13 M751-QPF-S1S5-150

    M751-QPF-S1S5-160 Reinfocement for Wall 2 4 02-Jun-15 06-Jun-15 M751-QPF-S1S5-100 M751-QPF-S1S5-170, M751-QPF-S1S6-100

    M751-QPF-S1S5-170 Formwork for Wall 2 2 07-Jun-15 08-Jun-15 M751-QPF-S1S5-160, M751-QPF-S1S5-11 M751-QPF-S1S5-180

    M751-QPF-S1S5-180 Concreting for Wall 2 1 09-Jun-15 09-Jun-15 M751-QPF-S1S5-170 M751-QPF-S1S5-190

    M751-QPF-S1S5-190 Deshuttering Wall 2 1 10-Jun-15 10-Jun-15 M751-QPF-S1S5-180 M751-QPF-S1S5-200, M751-QPF-S1S5-200, M

    M751-QPF-S1S5-200 Curing Wall 2 7 10-Jun-15 17-Jun-15 M751-QPF-S1S5-190, M751-QPF-S1S5-19 M751-QPF-S1S5-210

    M751-QPF-S1S5-150 Waterpoofing Wall 1 2 13-Jun-15 14-Jun-15 M751-QPF-S1S5-140

    M751-QPF-S1S5-210 Waterpoofing Wall 2 2 18-Jun-15 20-Jun-15 M751-QPF-S1S5-200

    SEGMENT 6SEGMENT 6 18 07-Jun-15 27-Jun-15

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 23 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M751-QPF-S1S6-100 Reinfocement for Wall 1 2 07-Jun-15 08-Jun-15 M751-QPF-S1S5-160 M751-QPF-S1S6-110, M751-QPF-S1S6-160

    M751-QPF-S1S6-110 Formwork for Wall 1 1 09-Jun-15 09-Jun-15 M751-QPF-S1S6-100 M751-QPF-S1S6-120, M751-QPF-S1S6-170

    M751-QPF-S1S6-120 Concreting for Wall 1 1 10-Jun-15 10-Jun-15 M751-QPF-S1S6-110 M751-QPF-S1S6-130

    M751-QPF-S1S6-130 Deshuttering Wall 1 1 11-Jun-15 11-Jun-15 M751-QPF-S1S6-120 M751-QPF-S1S6-140, M751-QPF-S1S6-140

    M751-QPF-S1S6-140 Curing Wall 1 7 11-Jun-15 18-Jun-15 M751-QPF-S1S6-130, M751-QPF-S1S6-13 M751-QPF-S1S6-150

    M751-QPF-S1S6-160 Reinfocement for Wall 2 4 09-Jun-15 13-Jun-15 M751-QPF-S1S6-100 M751-QPF-S1S6-170, M751-QPF-S1S7-100

    M751-QPF-S1S6-170 Formwork for Wall 2 2 14-Jun-15 15-Jun-15 M751-QPF-S1S6-160, M751-QPF-S1S6-11 M751-QPF-S1S6-180

    M751-QPF-S1S6-180 Concreting for Wall 2 1 16-Jun-15 16-Jun-15 M751-QPF-S1S6-170 M751-QPF-S1S6-190

    M751-QPF-S1S6-190 Deshuttering Wall 2 1 17-Jun-15 17-Jun-15 M751-QPF-S1S6-180 M751-QPF-S1S6-200, M751-QPF-S1S6-200, M

    M751-QPF-S1S6-200 Curing Wall 2 7 17-Jun-15 24-Jun-15 M751-QPF-S1S6-190, M751-QPF-S1S6-19 M751-QPF-S1S6-210

    M751-QPF-S1S6-150 Waterpoofing Wall 1 2 20-Jun-15 21-Jun-15 M751-QPF-S1S6-140

    M751-QPF-S1S6-210 Waterpoofing Wall 2 2 25-Jun-15 27-Jun-15 M751-QPF-S1S6-200

    SEGMENT 7SEGMENT 7 18 14-Jun-15 04-Jul-15

    M751-QPF-S1S7-100 Reinfocement for Wall 1 2 14-Jun-15 15-Jun-15 M751-QPF-S1S6-160 M751-QPF-S1S7-110, M751-QPF-S1S7-160

    M751-QPF-S1S7-110 Formwork for Wall 1 1 16-Jun-15 16-Jun-15 M751-QPF-S1S7-100 M751-QPF-S1S7-120, M751-QPF-S1S7-170

    M751-QPF-S1S7-120 Concreting for Wall 1 1 17-Jun-15 17-Jun-15 M751-QPF-S1S7-110 M751-QPF-S1S7-130

    M751-QPF-S1S7-130 Deshuttering Wall 1 1 18-Jun-15 18-Jun-15 M751-QPF-S1S7-120 M751-QPF-S1S7-140, M751-QPF-S1S7-140

    M751-QPF-S1S7-140 Curing Wall 1 7 18-Jun-15 25-Jun-15 M751-QPF-S1S7-130, M751-QPF-S1S7-13 M751-QPF-S1S7-150

    M751-QPF-S1S7-160 Reinfocement for Wall 2 4 16-Jun-15 20-Jun-15 M751-QPF-S1S7-100 M751-QPF-S1S7-170, M751-QPF-S3S1-100

    M751-QPF-S1S7-170 Formwork for Wall 2 2 21-Jun-15 22-Jun-15 M751-QPF-S1S7-160, M751-QPF-S1S7-11 M751-QPF-S1S7-180

    M751-QPF-S1S7-180 Concreting for Wall 2 1 23-Jun-15 23-Jun-15 M751-QPF-S1S7-170 M751-QPF-S1S7-190

    M751-QPF-S1S7-190 Deshuttering Wall 2 1 24-Jun-15 24-Jun-15 M751-QPF-S1S7-180 M751-QPF-S1S7-200, M751-QPF-S1S7-200, M

    M751-QPF-S1S7-200 Curing Wall 2 7 24-Jun-15 01-Jul-15 M751-QPF-S1S7-190, M751-QPF-S1S7-19 M751-QPF-S1S7-210

    M751-QPF-S1S7-150 Waterpoofing Wall 1 2 27-Jun-15 28-Jun-15 M751-QPF-S1S7-140

    M751-QPF-S1S7-210 Waterpoofing Wall 2 2 02-Jul-15 04-Jul-15 M751-QPF-S1S7-200

    SPAN 3 & 4 WALL 3 AND 4SPAN 3 & 4 WALL 3 AND 4 53 21-Jun-15 24-Aug-15

    SEGMENT 1SEGMENT 1 17 21-Jun-15 09-Jul-15

    M751-QPF-S3S1-100 Reinfocement for Wall 3 4 21-Jun-15 24-Jun-15 M751-QPF-S1S7-160 M751-QPF-S3S1-110, M751-QPF-S3S1-160

    M751-QPF-S3S1-110 Formwork for Wall 3 2 25-Jun-15 27-Jun-15 M751-QPF-S3S1-100 M751-QPF-S3S1-120, M751-QPF-S3S1-170

    M751-QPF-S3S1-120 Concreting for Wall 3 1 28-Jun-15 28-Jun-15 M751-QPF-S3S1-110 M751-QPF-S3S1-130

    M751-QPF-S3S1-130 Deshuttering Wall 3 1 29-Jun-15 29-Jun-15 M751-QPF-S3S1-120 M751-QPF-S3S1-140, M751-QPF-S3S1-140

    M751-QPF-S3S1-140 Curing Wall 3 7 29-Jun-15 06-Jul-15 M751-QPF-S3S1-130, M751-QPF-S3S1-13 M751-QPF-S3S1-150

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRAMME

    Page 24 of 582

    Rev Date Checked ApprovedC5 310315

  • Activity ID Activity Name OriginalDuration

    Start Finish Predecessors Successors

    M751-QPF-S3S1-160 Reinfocement for Wall 4 2 25-Jun-15 27-Jun-15 M751-QPF-S3S1-100 M751-QPF-S3S1-170, M751-QPF-S3S2-100

    M751-QPF-S3S1-170 Formwork for Wall 4 1 28-Jun-15 28-Jun-15 M751-QPF-S3S1-160, M751-QPF-S3S1-11 M751-QPF-S3S1-180

    M751-QPF-S3S1-180 Concreting for Wall 4 1 29-Jun-15 29-Jun-15 M751-QPF-S3S1-170 M751-QPF-S3S1-190

    M751-QPF-S3S1-190 Deshuttering Wall 4 1 30-Jun-15 30-Jun-15 M751-QPF-S3S1-180 M751-QPF-S3S1-200, M751-QPF-S3S1-200, M

    M751-QPF-S3S1-200 Curing Wall 4 7 30-Jun-15 07-Jul-15 M751-QPF-S3S1-190, M751-QPF-S3S1-19 M751-QPF-S3S1-210

    M751-QPF-S3S1-150 Waterpoofing Wall 3 2 07-Jul-15 08-Jul-15 M751-QPF-S3S1-140

    M751-QPF-S3S1-210 Waterpoofing Wall 4 2 08-Jul-15 09-Jul-15 M751-QPF-S3S1-200

    SEGMENT 2SEGMENT 2 17 28-Jun-15 16-Jul-15

    M751-QPF-S3S2-100 Reinfocement for Wall 3 4 28-Jun-15 01-Jul-15 M751-QPF-S3S1-160 M751-QPF-S3S2-110, M751-QPF-S3S2-160

    M751-QPF-S3S2-110 Formwork for Wall 3 2 02-Jul-15 04-Jul-15 M751-QPF-S3S2-100 M751-QPF-S3S2-120, M751-QPF-S3S2-170

    M751-QPF-S3S2-120 Concreting for Wall 3 1 05-Jul-15 05-Jul-15 M751-QPF-S3S2-110 M751-QPF-S3S2-130

    M751-QPF-S3S2-130 Deshuttering Wall 3 1 06-Jul-15 06-Jul-15 M751-QPF-S3S2-120 M751-QPF-S3S2-140, M751-QPF-S3S2-140

    M751-QPF-S3S2-140 Curing Wall 3 7 06-Jul-15 13-Jul-15 M751-QPF-S3S2-130, M751-QPF-S3S2-13 M751-QPF-S3S2-150

    M751-QPF-S3S2-160 Reinfocement for Wall 4 2 02-Jul-15 04-Jul-15 M751-QPF-S3S2-100 M751-QPF-S3S2-170, M751-QPF-S3S3-100

    M751-QPF-S3S2-170 Formwork for Wall 4 1 05-Jul-15 05-Jul-15 M751-QPF-S3S2-160, M751-QPF-S3S2-11 M751-QPF-S3S2-180

    M751-QPF-S3S2-180 Concreting for Wall 4 1 06-Jul-15 06-Jul-15 M751-QPF-S3S2-170 M751-QPF-S3S2-190

    M751-QPF-S3S2-190 Deshuttering Wall 4 1 07-Jul-15 07-Jul-15 M751-QPF-S3S2-180 M751-QPF-S3S2-200, M751-QPF-S3S2-200, M

    M751-QPF-S3S2-200 Curing Wall 4 7 07-Jul-15 14-Jul-15 M751-QPF-S3S2-190, M751-QPF-S3S2-19 M751-QPF-S3S2-210

    M751-QPF-S3S2-150 Waterpoofing Wall 3 2 14-Jul-15 15-Jul-15 M751-QPF-S3S2-140

    M751-QPF-S3S2-210 Waterpoofing Wall 4 2 15-Jul-15 16-Jul-15 M751-QPF-S3S2-200

    SEGMENT 3SEGMENT 3 17 05-Jul-15 27-Jul-15

    M751-QPF-S3S3-100 Reinfocement for Wall 3 4 05-Jul-15 08-Jul-15 M751-QPF-S3S2-160 M751-QPF-S3S3-110, M751-QPF-S3S3-160

    M751-QPF-S3S3-110 Formwork for Wall 3 2 09-Jul-15 11-Jul-15 M751-QPF-S3S3-100 M751-QPF-S3S3-120, M751-QPF-S3S3-170

    M751-QPF-S3S3-120 Concreting for Wall 3 1 12-Jul-15 12-Jul-15 M751-QPF-S3S3-110 M751-QPF-S3S3-130

    M751-QPF-S3S3-130 Deshuttering Wall 3 1 13-Jul-15 13-Jul-15 M751-QPF-S3S3-120 M751-QPF-S3S3-140, M751-QPF-S3S3-140

    M751-QPF-S3S3-140 Curing Wall 3 7 13-Jul-15 23-Jul-15 M751-QPF-S3S3-130, M751-QPF-S3S3-13 M751-QPF-S3S3-150

    M751-QPF-S3S3-160 Reinfocement for Wall 4 2 09-Jul-15 11-Jul-15 M751-QPF-S3S3-100 M751-QPF-S3S3-170, M751-QPF-S3S4-100

    M751-QPF-S3S3-170 Formwork for Wall 4 1 12-Jul-15 12-Jul-15 M751-QPF-S3S3-160, M751-QPF-S3S3-11 M751-QPF-S3S3-180

    M751-QPF-S3S3-180 Concreting for Wall 4 1 13-Jul-15 13-Jul-15 M751-QPF-S3S3-170 M751-QPF-S3S3-190

    M751-QPF-S3S3-190 Deshuttering Wall 4 1 14-Jul-15 14-Jul-15 M751-QPF-S3S3-180 M751-QPF-S3S3-200, M751-QPF-S3S3-200, M

    M751-QPF-S3S3-200 Curing Wall 4 7 14-Jul-15 25-Jul-15 M751-QPF-S3S3-190, M751-QPF-S3S3-19 M751-QPF-S3S3-210

    M751-QPF-S3S3-150 Waterpoofing Wall 3 2 25-Jul-15 26-Jul-15 M751-QPF-S3S3-140

    PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

    JUNCTION -04 CONSTRUCTION PROGRA