Juan Villa Outhouse Full Takeoff PDF

1
ID Tas Mo ID Task Name Duration Start Finish Predecessors Start Slack Finish Slack Cost 1 1 Meeting with Owner/Site Visit 1 day Thu 4/14/16 Thu 4/14/16 2 days 2 days $100.00 2 2 Discussing Plans/Project 1 day Fri 4/15/16 Fri 4/15/16 1 2 days 2 days $0.00 3 3 CM Assigns Tasks to PM & Team 1 day Mon 4/18/16 Mon 4/18/16 2 2 days 2 days $0.00 4 4 Site Surveying 2 days Tue 4/19/16 Wed 4/20/16 2,3 2 days 2 days $200.00 5 5 Clear & Grub 2 days Thu 4/21/16 Fri 4/22/16 4 2 days 2 days $300.00 6 6 Strip Topsoil & Stockpile 3 days Mon 4/25/16 Wed 4/27/16 5 2 days 2 days $500.00 7 7 Cut to Fill 2 days Thu 4/28/16 Fri 4/29/16 6 2 days 2 days $200.00 8 8 Borrow Material 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $300.00 9 9 Utility Excavation 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $500.00 10 10 Sanitary Manhole 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $200.00 11 11 4" Sanitary Pipe, Valves & Fittings 3 days Tue 5/3/16 Thu 5/5/16 10,8,9 2 days 2 days $50.00 12 12 4" H2O Pipe, Valves & Fittings 3 days Tue 5/3/16 Thu 5/5/16 10,8,9 2 days 2 days $50.00 13 13 Hydrant & Valve Box 1 day Fri 5/6/16 Fri 5/6/16 11,12 2 days 2 days $50.00 14 14 Electrical ductbank conduit 4" 1 day Mon 5/9/16 Mon 5/9/16 13 2 days 2 days $50.00 15 15 Electrical ductbank formwork 1 day Tue 5/10/16 Tue 5/10/16 14 2 days 2 days $100.00 16 16 Electrical ductbank concrete 1 day Wed 5/11/16 Wed 5/11/16 15 2 days 2 days $100.00 17 17 All Formwork/Rebar 6 days Thu 5/12/16 Thu 5/19/16 16 2 days 2 days $500.00 18 18 All Concrete 4 days Fri 5/20/16 Wed 5/25/16 17 2 days 2 days $600.00 19 19 Exterior Wood Framing 4 days Thu 5/26/16 Tue 5/31/16 18 2 days 2 days $600.00 20 20 Wood Roof Joists 2 days Wed 6/1/16 Thu 6/2/16 19 2 days 2 days $100.00 21 21 Interior Wall Framing 2 days Fri 6/3/16 Mon 6/6/16 20 2 days 2 days $100.00 22 22 Exterior Sheathing 2 days Thu 5/26/16 Fri 5/27/16 18 3 days 3 days $150.00 23 23 Redwood Siding 3 days Mon 5/30/16 Wed 6/1/16 22 3 days 3 days $150.00 24 24 Batt Insulation Walls 2 days Thu 6/2/16 Fri 6/3/16 23 3 days 3 days $200.00 25 25 Roof Sheathing 2 days Tue 6/7/16 Wed 6/8/16 21,24 2 days 2 days $250.00 26 26 Batt Insulation Walls 2 days Thu 6/9/16 Fri 6/10/16 25 2 days 2 days $300.00 27 27 Standing Seam Roof 2 days Mon 6/13/16 Tue 6/14/16 26 2 days 2 days $320.00 28 28 Exhaust Fans 1 day Fri 6/17/16 Fri 6/17/16 27 0 days 0 days $100.00 29 29 Gypsum Wall Board 2 days Mon 6/20/16 Tue 6/21/16 28 0 days 0 days $100.00 30 30 Gypsum Ceiling System 2 days Wed 6/22/16 Thu 6/23/16 29 0 days 0 days $200.00 31 31 Venner Plaster 2 days Fri 6/24/16 Mon 6/27/16 30 0 days 0 days $20.00 32 32 Marble Wall Panels 2 days Tue 6/28/16 Wed 6/29/16 31 0 days 0 days $150.00 33 33 Door, Frames Hardware, Windows 2 days Thu 6/30/16 Fri 7/1/16 32 0 days 0 days $150.00 34 34 Ductwork for Exhaust Fans 1 day Mon 6/20/16 Mon 6/20/16 28 0 days 0 days $150.00 35 35 Plumbing Piping 2 days Tue 6/21/16 Wed 6/22/16 34 0 days 0 days $100.00 36 36 100A Electrical Panel 1 day Tue 6/21/16 Tue 6/21/16 34 1 day 1 day $100.00 37 37 Electrical Wiring 2 days Wed 6/22/16 Thu 6/23/16 36 1 day 1 day $150.00 38 38 Water Fountain 1 day Thu 6/23/16 Thu 6/23/16 35 1 day 1 day $20.00 39 39 Toilets/Urinals 2 days Thu 6/23/16 Fri 6/24/16 35 0 days 0 days $160.00 40 40 Sinks 2 days Thu 6/23/16 Fri 6/24/16 35 0 days 0 days $60.00 41 41 Light Fixtures 3 days Mon 6/27/16 Wed 6/29/16 40,38,39,37 0 days 0 days $60.00 42 42 Toilet Paper Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 3 days 3 days $20.00 43 43 Sanitary Napkin Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 3 days 3 days $20.00 44 44 Paper Towel Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 0 days 0 days $20.00 45 45 Mirrors 1 day Fri 7/1/16 Fri 7/1/16 42,43,44 3 days 3 days $20.00 46 46 Waste Receptacles 1 day Fri 7/1/16 Fri 7/1/16 44 3 days 3 days $20.00 47 47 Grab Bars 1 day Fri 7/1/16 Fri 7/1/16 44 0 days 0 days $20.00 48 48 All Documents Completed/Filed 1 day Mon 7/4/16 Mon 7/4/16 33,47 0 days 0 days $510.00 49 49 Show Owner Finished Project 1 day Tue 7/5/16 Tue 7/5/16 48 0 days 0 days $0.00 50 50 Project Completion Party 1 day Wed 7/6/16 Wed 7/6/16 49 0 days 0 days $1,000.00 Meeting with Owner/Site Visit Discussing Plans/Project CM Assigns Tasks to PM & Team Site Surveying Clear & Grub Strip Topsoil & Stockpile Cut to Fill Borrow Material Utility Excavation Sanitary Manhole 4" Sanitary Pipe, Valves & Fittings 4" H2O Pipe, Valves & Fittings Hydrant & Valve Box Electrical ductbank conduit 4" Electrical ductbank formwork Electrical ductbank concrete All Formwork/Rebar All Concrete Exterior Wood Framing Wood Roof Joists Interior Wall Framing Exterior Sheathing Redwood Siding Batt Insulation Walls Roof Sheathing Batt Insulation Walls Standing Seam Roof Exhaust Fans Gypsum Wall Board Gypsum Ceiling System Venner Plaster Marble Wall Panels Door, Frames Hardware, Windows Ductwork for Exhaust Fans Plumbing Piping 100A Electrical Panel Electrical Wiring Water Fountain Toilets/Urinals Sinks Light Fixtures Toilet Paper Dispensers Sanitary Napkin Dispensers Paper Towel Dispensers Mirrors Waste Receptacles Grab Bars All Documents Completed/Filed Show Owner Finished Projec Project Completion Party W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F 10, 2016 April 17, 2016 April 24, 2016 May 1, 2016 May 8, 2016 May 15, 2016 May 22, 2016 May 29, 2016 June 5, 2016 June 12, 2016 June 19, 2016 June 26, 2016 July 3, 2016 July 10, 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Late Progress Manual Progress Slack Page 1 Project: Project Outhouse Full T Date: Thu 4/14/16

description

dzgfdgd

Transcript of Juan Villa Outhouse Full Takeoff PDF

Page 1: Juan Villa Outhouse Full Takeoff PDF

ID TasMo

ID Task Name Duration Start Finish Predecessors Start Slack Finish Slack Cost

1 1Meeting with Owner/Site Visit 1 day Thu 4/14/16 Thu 4/14/16 2 days 2 days $100.00

2 2Discussing Plans/Project 1 day Fri 4/15/16 Fri 4/15/16 1 2 days 2 days $0.00

3 3 CM Assigns Tasks to PM & Team 1 day Mon 4/18/16 Mon 4/18/16 2 2 days 2 days $0.00

4 4 Site Surveying 2 days Tue 4/19/16 Wed 4/20/16 2,3 2 days 2 days $200.005 5 Clear & Grub 2 days Thu 4/21/16 Fri 4/22/16 4 2 days 2 days $300.006 6 Strip Topsoil & Stockpile 3 days Mon 4/25/16 Wed 4/27/16 5 2 days 2 days $500.00

7 7 Cut to Fill 2 days Thu 4/28/16 Fri 4/29/16 6 2 days 2 days $200.008 8 Borrow Material 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $300.009 9Utility Excavation 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $500.0010 10 Sanitary Manhole 1 day Mon 5/2/16 Mon 5/2/16 7 2 days 2 days $200.0011 11 4" Sanitary Pipe, Valves & Fittings 3 days Tue 5/3/16 Thu 5/5/16 10,8,9 2 days 2 days $50.00

12 12 4" H2O Pipe, Valves & Fittings 3 days Tue 5/3/16 Thu 5/5/16 10,8,9 2 days 2 days $50.00

13 13Hydrant & Valve Box 1 day Fri 5/6/16 Fri 5/6/16 11,12 2 days 2 days $50.0014 14 Electrical ductbank conduit 4" 1 day Mon 5/9/16 Mon 5/9/16 13 2 days 2 days $50.00

15 15 Electrical ductbank formwork 1 day Tue 5/10/16 Tue 5/10/16 14 2 days 2 days $100.00

16 16 Electrical ductbank concrete 1 day Wed 5/11/16 Wed 5/11/16 15 2 days 2 days $100.00

17 17All Formwork/Rebar 6 days Thu 5/12/16 Thu 5/19/16 16 2 days 2 days $500.0018 18All Concrete 4 days Fri 5/20/16 Wed 5/25/16 17 2 days 2 days $600.0019 19 Exterior Wood Framing 4 days Thu 5/26/16 Tue 5/31/16 18 2 days 2 days $600.00

20 20Wood Roof Joists 2 days Wed 6/1/16 Thu 6/2/16 19 2 days 2 days $100.0021 21 Interior Wall Framing 2 days Fri 6/3/16 Mon 6/6/16 20 2 days 2 days $100.00

22 22 Exterior Sheathing 2 days Thu 5/26/16 Fri 5/27/16 18 3 days 3 days $150.0023 23 Redwood Siding 3 days Mon 5/30/16 Wed 6/1/16 22 3 days 3 days $150.0024 24 Batt Insulation Walls 2 days Thu 6/2/16 Fri 6/3/16 23 3 days 3 days $200.0025 25 Roof Sheathing 2 days Tue 6/7/16 Wed 6/8/16 21,24 2 days 2 days $250.0026 26 Batt Insulation Walls 2 days Thu 6/9/16 Fri 6/10/16 25 2 days 2 days $300.0027 27 Standing Seam Roof 2 days Mon 6/13/16 Tue 6/14/16 26 2 days 2 days $320.0028 28 Exhaust Fans 1 day Fri 6/17/16 Fri 6/17/16 27 0 days 0 days $100.0029 29Gypsum Wall Board 2 days Mon 6/20/16 Tue 6/21/16 28 0 days 0 days $100.0030 30Gypsum Ceiling System 2 days Wed 6/22/16 Thu 6/23/16 29 0 days 0 days $200.00

31 31 Venner Plaster 2 days Fri 6/24/16 Mon 6/27/16 30 0 days 0 days $20.0032 32Marble Wall Panels 2 days Tue 6/28/16 Wed 6/29/16 31 0 days 0 days $150.0033 33Door, Frames Hardware, Windows 2 days Thu 6/30/16 Fri 7/1/16 32 0 days 0 days $150.00

34 34Ductwork for Exhaust Fans 1 day Mon 6/20/16 Mon 6/20/16 28 0 days 0 days $150.00

35 35 Plumbing Piping 2 days Tue 6/21/16 Wed 6/22/16 34 0 days 0 days $100.0036 36 100A Electrical Panel 1 day Tue 6/21/16 Tue 6/21/16 34 1 day 1 day $100.0037 37 Electrical Wiring 2 days Wed 6/22/16 Thu 6/23/16 36 1 day 1 day $150.0038 38Water Fountain 1 day Thu 6/23/16 Thu 6/23/16 35 1 day 1 day $20.0039 39 Toilets/Urinals 2 days Thu 6/23/16 Fri 6/24/16 35 0 days 0 days $160.0040 40 Sinks 2 days Thu 6/23/16 Fri 6/24/16 35 0 days 0 days $60.0041 41 Light Fixtures 3 days Mon 6/27/16 Wed 6/29/16 40,38,39,37 0 days 0 days $60.0042 42 Toilet Paper Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 3 days 3 days $20.00

43 43 Sanitary Napkin Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 3 days 3 days $20.00

44 44 Paper Towel Dispensers 1 day Thu 6/30/16 Thu 6/30/16 41 0 days 0 days $20.00

45 45Mirrors 1 day Fri 7/1/16 Fri 7/1/16 42,43,44 3 days 3 days $20.0046 46Waste Receptacles 1 day Fri 7/1/16 Fri 7/1/16 44 3 days 3 days $20.0047 47Grab Bars 1 day Fri 7/1/16 Fri 7/1/16 44 0 days 0 days $20.0048 48All Documents Completed/Filed 1 day Mon 7/4/16 Mon 7/4/16 33,47 0 days 0 days $510.00

49 49 Show Owner Finished Project 1 day Tue 7/5/16 Tue 7/5/16 48 0 days 0 days $0.00

50 50 Project Completion Party  1 day Wed 7/6/16 Wed 7/6/16 49 0 days 0 days $1,000.00

Meeting with Owner/Site Visit

Discussing Plans/Project

CM Assigns Tasks to PM & Team

Site SurveyingClear & Grub

Strip Topsoil & Stockpile

Cut to FillBorrow MaterialUtility ExcavationSanitary Manhole

4" Sanitary Pipe, Valves & Fittings

4" H2O Pipe, Valves & Fittings

Hydrant & Valve BoxElectrical ductbank conduit 4"

Electrical ductbank formwork

Electrical ductbank concrete

All Formwork/RebarAll Concrete

Exterior Wood Framing

Wood Roof JoistsInterior Wall Framing

Exterior SheathingRedwood Siding

Batt Insulation WallsRoof Sheathing

Batt Insulation WallsStanding Seam Roof

Exhaust FansGypsum Wall Board

Gypsum Ceiling System

Venner PlasterMarble Wall Panels

Door, Frames Hardware, Windows

Ductwork for Exhaust Fans

Plumbing Piping100A Electrical Panel

Electrical WiringWater Fountain

Toilets/UrinalsSinks

Light FixturesToilet Paper Dispensers

Sanitary Napkin Dispensers

Paper Towel Dispensers

MirrorsWaste ReceptaclesGrab Bars

All Documents Completed/Filed

Show Owner Finished Projec

Project Completion Party

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F10, 2016 April 17, 2016 April 24, 2016 May 1, 2016 May 8, 2016 May 15, 2016 May 22, 2016 May 29, 2016 June 5, 2016 June 12, 2016 June 19, 2016 June 26, 2016 July 3, 2016 July 10, 2016

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Late

Progress

Manual Progress

Slack

Page 1

Project: Project Outhouse Full TDate: Thu 4/14/16