J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE...

29
J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional Facilities J.P.Delahaye: EU-GDE co-Deputy Director, D.Schulte: Beam dynamics L.Tavian: Cryogenics ILC project management tools Participation to Data Management System (ILC-DMS) committee to recommend best tools for ILC: J.Ferguson Proposal to use tools (EDMS,…) developed for LHC Offer of technical and administrative support ILC Site Specific Cost Study

Transcript of J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE...

Page 1: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 1

CERN participation to ILC

•ILC- MoU: Support to GDE

•Contribution to GDE:J.L.Baldy: Civil Engineering & Conventional FacilitiesJ.P.Delahaye: EU-GDE co-Deputy Director,D.Schulte: Beam dynamicsL.Tavian: Cryogenics

•ILC project management toolsParticipation to Data Management System (ILC-DMS)

committee to recommend best tools for ILC: J.FergusonProposal to use tools (EDMS,…) developed for LHCOffer of technical and administrative support

•ILC Site Specific Cost Study

Page 2: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 2

ILC site specific cost study•http://ab-div.web.cern.ch/ab%2Ddiv/ILC/ILC-docs.asp

•Two EU sample sites: CERN and DESY•Strong collaboration between CERN and DESY

•W.Bialowons: GDE European Cost engineer•J.L.Baldy: GDE European Conventional Facilities expert

•Limited number of site specific systems•Civil engineering and conventional facilities•Cryogenics

•Major sub-systems are non site specific:•Use of cost studies already done for TESLA •Adaptation to ILC following BCD baselines (from January

06)

•Definition of WBS and tools•following recommendation by dedicated committee (GG4)

•ILC and CLIC cost studies in parallel, on same site with same tools and same method

•Identify cost drivers and main differences

Page 3: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 3

Tesla Project SitingTesla Project Siting

Site map of the Linear Collider and X-FEL at DESYSite map of the Linear Collider and X-FEL at DESY

Page 4: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 4

P4 P5

P6

P8P2

10 kmPO9

PO7

PO5

PO3

PO1

PO2

PO4

PO6

PO8Possible site for a Linear Collider at CERN – P10

P11

Page 5: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 5

Longitudinal section of a Linear Collider on CERN site–

Page 6: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 6

ILC WBS

Page 7: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 7

CERN additional contribution to ILC•Major partner in specific studies:

•Civil engineering and site specific cost study: J.L.Baldy

•Cryogenics and cryostats: L.Tavian

•Beam dynamics issues: D.Schulte

•R&D on generic key issues independent of technology:•Participation in EUROTeV design study, CARE project and ELAN network

•R&D on Beam diagnostics, Beam Delivery System (BDS), Beam dynamics...

•Resources: 2.3 MEur. material, 25 staff-y, 20 fellows-y = 6.75 MEur. total

•Tests with beam in CTF3 Test facility:•Beam instrumentation and beam simulations benchmarking

•Beam combination for DR injection/extraction with RF transv. cavities

•Participation to R&D on Low Emittance generation @ ATF/KEK

Page 8: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 8

0

50

100

150

200

250

300

Tevatron HERA CEBAF RHIC LEP2 LHC (SSC)

[to

nn

es]

VirtualLiquidGas @ 2 MPa

~ ILC

He Inventory of Large Cryogenic Systems

Page 9: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 9

Transport of Refrigeration in Large Distributed Cryogenic systems

0

0.1

0.2

0.3

0.4

0.5

0 1 2 3 4 5Distance [km]

Tem

pera

ture

diff

eren

ce [K

] Pressurised He II Saturated LHe II He I

Tore Supra

TevatronHERA

UNKLHC

SSC (main Ring)

SSC (HEB)

LEP2 TESLA

Low Pressure drop over long distances requires large pumping headers !

Page 10: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 10

Alternative Configuration Distributed 2 K refrigeration

•Increase the distance between cryoplant by a factor 2

•Require specific alcove for 2K cryoplants but saving of a lot civil engineering and infrastructure as well as reducing of the surface site impact.

•Require specific study on the design and operation of “underground” warm compressor station

•Require refrigeration (water) capacity of about 1 to 2 MW per alcove

•Require an additional header in the cryomodule to return the compressed He (20-30 K, few bar) to the main cryoplant

L

2L

surface

surface

alcove

2L

surfacealcove

Page 11: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 11

Alternative Configuration Larger cryoplants

•4.5 K refrigerator•Feasibility study on larger refrigerators (40-50 kW

equivalent at 4.5 K) and impacts on cost, layout, operation, site …

•R&D requirement

•Warm centrifugal compressor as booster•Feasibility study with impacts on cost, operation and

reliability.•Validation test is mandatory.

•2 K refrigeration•Feasibility study on larger cold compressors and

impacts on cost, layout, operation…•R&D requirement

Page 12: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 12

Alternative Configuration Cryomodule

•Cryostat optimization•Cost effectiveness of the 5-8 K shield•Use of conduction cooled current leads for quadrupole (if

HTS retained as baseline). Gain on operation flexibility.

•Separated distribution line•Mainly justified by cost saving, if any (no sectorization

required for cryomodule repair or exchange).•Could be interesting in case of 2 tunnels (operation

availability if the line is in the service tunnel)•Could increase the filling factor of the linacs•Could be justified if the vibration due to He flow is not

acceptable (reduced flows in cryomodules).•Could simplified the heat intercept design and efficiency

(small pipe can be routed close to the components to be thermalized)

•The 300 mm pumping header (thickness 6 mm !!) is use as a rigid beam for cavity alignment inside a module (separated line with or without the pumping header?)

Page 13: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 13

Participants: 22Duration: January 2004 – December 2008Total expenditures: 35.14 MEurosTotal E.U. support: 15.20 MEuros

The main objective of the CARE project is to generate a structured and integrated European area in the field of accelerator research and related R&D. The program includes the most advanced scientific and technological developments relevant to accelerator research for Particle Physics. It is articulated around 3 Networking Activities and 4 Joint Research Activities:

- ELAN (Electron Linear Accelerator Network)- BENE (Beam for European Neutrino Experiments)- HHH (High intensity High brightness Hadron Beams)- SRF (Superconducting RF)- PHIN (PHoto-INjector)- HIPPI (High Intensity Proton Pulsed Injectors)- NED (Next European Dipole)

Initiated:- EUROTeV- Beta beam task in the EURISOL Design Study

Considered:- LHC luminosity upgrade- Neutrino factory- Light quark and Phi factory

Initiated:- None yet

Considered:- None yet

E.U

. p

rog

ram

mes

: [2

/12]

Page 14: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 14

•Goal:… Coordination of R&D on electron accelerators at the European level.

Evaluating the various technologies for improving the present infrastructures and defining a roadmap for future electron accelerators and colliders, including new techniques of acceleration.

•Number of participating laboratories: 55•Total contribution from EU (2004-2007): 0.450 MEuros

[E.U. to CERN contribution: 0.058 Meuros]

•Organization :•Coordinator: F.Richard (LAL/IN2P3)/D.Schulte (CERN)•Five Work Packages:

–Normal Conducting linac technology (G.Guignard/CERN)–Super Conducting Linac Technology (L.Lilje/DESY)–Beam Dynamics (D.Schulte/CERN)–Instrumentation and Diagnostics (S.Smith/CCLRC)–Advanced and novel accelerator development (B.Cros/CNRS)

ELAN (“Electron Linear Accelerator”) Network E

.U.

pro

gra

mm

es:

[4/1

2]

Page 15: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 15

•Goal:… Research and Developments on charge production by

interaction of laser pulse with material within RF field and improve or extend the existing infrastructures in order to fulfil the objectives. Coordinate the efforts done in various institutes on the photo-injectors

•Number of participating laboratories: 9•Total contribution from EU (2004-2007): 3.5 MEuros

[E.U. to CERN contribution: 1.2 Meuros]

•Organization :•Coordinator: A.Ghigo(INFN)/R.Losito(CERN)•Four Work Packages:

–Management and communication (A.Ghigo/INFN)–Charge production (J.Teichert/FRZ-ELBE)–Lasers (I.Ross/CCRLC-RAL)–RF guns and beam dynamics (G.Bienvenu/LAL)

JRA PHIN “Charge production with photo-Injectors”

E.U

. p

rog

ram

mes

: [4

/12]

Page 16: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 16

CERN contribution to CAREELAN&PHIN

Work-package

Task ID Task Description

EU additional resources Personal 1.5 (p.y) Material 1.26 M€

CERN committed resources Personal 11s+2.5f (p.y) Material 0.40 M€

ELAN LTECNC

BDYN

Contribution to the exchange between experts and reflection on the definition of R&D on Sources, Beam dynamics simulation codes, alignment & vibration, RF transverse deflectors

0.08 M€ 3 p.y (staff) 0.18 M€

PHIN WP1

M&C Management & Communication

Oversee and coordinate the work of the entire JRA. Creation of tools, databases and web site.

0 0.02 M€

0.5 p.y (Staff) 0 M€

PHIN WP2

CP Charge Production

Study of fabrication technology and new materials. Tests at different labs.

0. p·y 0.045 M€

4.5 Staff 1 Fellow 0.1 M€

PHIN WP3

LAS Lasers systems Design and develop laser system Amplifier design Stability issues and feedbacks

0. p.y 0.948 M€

(2.5 Staff) (1.5 Fellow) 0.1 M€

PHIN WP4

GUN RF guns and beam dynamics

Design for high charge, high average current, and long pulse trains Study and construction of a RF gun Tests in CTF3.

1.5. p·y (Fellow) 0.165 M€

0.5. p·y (Staff) 0.02 M€

Page 17: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 17

= CERN participation

EU supported (9MEuros)Linear Colliders Design Study

About common L.C. key issues

Page 18: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 18

CERN resources to EUROTeVWork-package Task ID Task Description

EU additional resources

CERN committed resources

BDSLD BDS Lattice Design

Exploration of non-linear collimation schemes

1.0 p·y 0.27 staff·y 0.666 fell.y WP2

(BDS) SWMD Spoiler Wakefields & Mech. Design

Trapped-mode Calculation 0.5 p·y 0.13 p·y 0.33 py

WP3 (DR)

ECLOUD Studies of Electron Cloud and other Instabilities

Development of simulation codes Benchmark and tuning of simulations against experimental data in SPS and co. Application of codes to DR lattices Fast ion instability studies

1.5p·y 2.0 py

PBPM Precision Cavity BPM

BPM with <100 nm resolution, <10 m precision, < 15 ns rise-time design and fabrication of prototype Beam tests in CTF3

2.5 p·y 84kEuro

1.5 p·y 84kEuro

TPMON Timing & Phase Monitoring

design&construction of phase reference system with stability better 15 fs rms over long distances (km) Beam tests in CTF3

2.5 p·y 120kEur

o

2.0 p·y 120kEuro

WBCM Wide-Band Current Monitor

development of a 20 GHz bandwidth bunch charge monitor resolving single bunches in a bunch train design&construction of prototype Beam tests in CTF3

84kEuro 1.0 p·y

84kEuro

WP5 (DIAG)

CFBPM, PBPM, TPMON, WBPM

Confocal Resonator BPM + preceding ones

Tests with beam in CTF3 0.3 p.y

Page 19: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 19

CERN contribution to EUROTeV

FMSIM Failure Mode & Effect Simulations

Key failure modes (FM) determination Simulation of FMs and impact on accelerator performance / design

0.5 p·y 0.1 p·y

COLSIM Collimation Simulations

Simulation of post-linac beam halo Collimation impact on design&perform.

0.5 p·y 0.1 p·y

LAST

Luminosity and alignment system tuning

Alignment and feedback strategy for luminosity performance optimization Develop tools to evaluate luminosity

2.5 p·y 0.5 p·y 2.25py

HTGEN Halo and Tail Generation

Study of potential sources of halo and tail generation in the LET Development of halo models Explore possibilities for benchmarking

2.5 p·y 1.5 p·y

WP6 (BDYN)

BBSIM Beam-Beam Simulation Code Development

Support of development and benchmarking of simulation code GUINEA-PIG

0.1 p·y

Page 20: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 20

Participation to ATF @ KEK

Generation of small emittance beams in ATF1 and nanometer spot sizes in ATF2

Page 21: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 21

Latest stabilization technology applied to the accelerator fieldContribution to ATF of Test Bench developed @ CERN

Collaboration CERN/LAPP/KEK

Stabilizing quadrupoles to the 0.5 nm level!(up to 10 times better than supporting ground, above 4 Hz)

Collaboration on Nanometer Stabilisation

Page 22: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 22

INFN

CLEX

2004 2005

2006

2007

Damped accelerating structure (R1.1)

Drive beam generation scheme (R1.2)ON/OFF PETS (R1.3)Stability bench marking (R2.1)

CLIC sub-unit (R2.3)

Use of CLIC Test Facility (CTF3)

Test with beam of beam diagnostics and RF transverse cavities

Page 23: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 23

1. Executive Summary The current planning phase of the CLEX area at CTF3 has revealed an excellent opportunity to build a flexible Instrumentation Test Beam (ITB), at a time when such a facility is in high demand and short supply, to address both ILC and CLIC instrumentation issues. This proposal addresses some preliminary baseline requirements of the ITB, presents initial cost estimates and timelines, and identifies some key diagnostics tests that could be addressed. 2. Introduction The CLEX layout is presented in Fig. 1.

Figure 1: Outline of the CLEX facility. The Instrumentation Test-Beam (ITB) is indicated at the bottom left of the figure.

D F D F D F D F D F D F D F D F

LIL-ACS LIL-ACS F D D F

D F D

D F D

D F DUMP

8 m

2m

D F D

F D

F D F D

D F D DUMP

D F D

DUMP

40 m

D F D

1m wide passage all around

TBL

30 GHz Teststand

Probe beam injector DUMP DUMP

DUMP

D F D

F

F D

D F D DUMP Instrumentation Testbeam

3m

6 m

13 m

15 m D F D

D F D

DRAFT of a Conceptual Proposal for an Instrumentation Test Beam (ITB) Line at the CTF3 Probe Beam

G. A. Blair , John Adams Institute at RHUL, UK.H. Braun ,CERN, Switzerland

Page 24: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 24

CERN resources towards ILC

EU CERN Total Material Staff Fellows Material Staff Fellows Material Staff Fellows MEuros P-y P-y MEuros P-y P-y MEuros P-y P-y EUROTeV 0.35 0 12.5 0.4 11.7 4 0.75 11.7 16.5 ELAN 0.08 0 0 0.18 3 0 0.26 3 0 PHIN 1.10 0 1.5 0.20 8 2.5 1.30 8 4 CARE mngt 0 0 0 0 2 0 0 2 0 Total 1.53 0 14 0.78 24.7 6.5 2.31 24.7 20.5

Page 25: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 25

CERN FTE/year contribution to ILCSub-systems TOTAL

Vacuum systems

Warm magnet systems

Cryomodule 0.1

Cavity Package

RF Power

Cryogenics 0.4

Accelerator Physics 0.5

Operations & Reliability

Instrumentation 0.5

Controls

Systems integration

CF&S 0.5

Cost 0.2

Overall coordination 0.2

TOTAL 2.4

Page 26: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 26

Conclusion and possible developments•CERN focused on LHC, resources committed up to

2010•CERN committed to demonstrate feasibility of CLIC

technology towards colliding beam energies in multi-TeV range complementary to ILC, within the frame of a multi-lateral network of collaborating institutes

•Limited but substantial participation to ILC within the frame of the EU supported EUROTeV design study and CARE project (ELAN, PHIN) on generic key issues independent of technology with resources (2005-07):

2.3 MEur., 25 staff-years, 20 fellow-years•Additional man-power for BCD and RDR: 2.4

FTE/year•Beam dynamics•Cryogenics and cryostat optimisation•Civil engineering and Conventional Facilities•Site specific cost study

Page 27: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 27

Conclusion and possible developments

•Civil engineering & conventional facilities for site specific cost studies

•170 KCHF/year + 3.4 FTE Funding: CERN&DESY?•Geotechnical & Civil eng consultancy, SW&Database,

Cooling &Ventilation, Siting&Survey, Electrical eng,

Alarms&Access,

•Development and support of ILC project management tools (if LHC tools selected)

•2 to 3 FTE Funding: CERN?

•Beam Diagnostics Beam line in CTF3 CLEX•Estimation: 500 kCHF + 7FTE Funding: EU?,

PPARK?

Page 28: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 28

Conclusion and possible developments

•CARE2 in the frame of FP7:•CARE and EUROTEV presently focused on design,

modeling, prototypes, fabrication techniques, ending 2007

•New Joint Research Activities (JRAs) from 2008 for engineering and fabrication techniques in collaboration with industry

•Taking advantage of available expertise in SC magnet technology and Cryogenics at CERN in parallel with LHC operation

•R&D on BDS SC quadrupoles, DR SC wigglers, Crab cavities (LHC upgrade), ….,

•R&D for cryogenics optimisation•Beam dynamics: Computing cluster, Codes

development and bench-mark•Pre-alignment and stabilisation

• Estimation: ? Funding EU?,

Page 29: J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE Contribution to GDE: J.L.Baldy: Civil Engineering & Conventional.

J.P.Delahaye GDE Meeting OXFORD 25-10-05 29

Future R&D on ILC Cryogenics

1/ Studies and development for BCD (BASELINE)

Large sub-cooling heat exchanger

Feasibility study of efficient large sub-cooling heat exchangers. Construction and validation of prototypes.

LHe II flow characteristics and tests Study and measurement of flow characteristics during steady state and transient operating modes.

Cryomodule optimization

Study of the cost effectiveness of the 5-8 K shields. Review of heat inleaks and piping sizing.

??? ???

2/ Studies and development for ACD (ALTERNATIVES)

Larger 4.5 K refrigerators

Feasibility study on larger refrigerators (40-50 kW equivalent at 4.5 K) with impacts on cost, layout and operation. Specific component development driven by the study conclusion.

Centrifugal compressors as booster for the warm compressor stations of 4.5 K refrigerators

Feasibility study with impacts on cost, operation and reliability. Validation test on proptotype.

Larger 2 K refrigeration

Feasibility study on larger cold compressors and impacts on cost, layout and operation. Specific component development driven by the study conclusion.

Distributed 2 K refrigeration for doubling the distance between cryoplants

Study of specific alcove for 2K cryoplants with impact on civil engineering and site environment. Specific study on the design and operation of warm compressor station “underground” (Alcove refrigeration (water) capacity…) Study on impact on cryomodule design (additional return line…).