J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE...
-
Upload
bertina-sullivan -
Category
Documents
-
view
213 -
download
0
Transcript of J.P.Delahaye GDE Meeting OXFORD 25-10-05 1 CERN participation to ILC ILC- MoU: Support to GDE...
J.P.Delahaye GDE Meeting OXFORD 25-10-05 1
CERN participation to ILC
•ILC- MoU: Support to GDE
•Contribution to GDE:J.L.Baldy: Civil Engineering & Conventional FacilitiesJ.P.Delahaye: EU-GDE co-Deputy Director,D.Schulte: Beam dynamicsL.Tavian: Cryogenics
•ILC project management toolsParticipation to Data Management System (ILC-DMS)
committee to recommend best tools for ILC: J.FergusonProposal to use tools (EDMS,…) developed for LHCOffer of technical and administrative support
•ILC Site Specific Cost Study
J.P.Delahaye GDE Meeting OXFORD 25-10-05 2
ILC site specific cost study•http://ab-div.web.cern.ch/ab%2Ddiv/ILC/ILC-docs.asp
•Two EU sample sites: CERN and DESY•Strong collaboration between CERN and DESY
•W.Bialowons: GDE European Cost engineer•J.L.Baldy: GDE European Conventional Facilities expert
•Limited number of site specific systems•Civil engineering and conventional facilities•Cryogenics
•Major sub-systems are non site specific:•Use of cost studies already done for TESLA •Adaptation to ILC following BCD baselines (from January
06)
•Definition of WBS and tools•following recommendation by dedicated committee (GG4)
•ILC and CLIC cost studies in parallel, on same site with same tools and same method
•Identify cost drivers and main differences
J.P.Delahaye GDE Meeting OXFORD 25-10-05 3
Tesla Project SitingTesla Project Siting
Site map of the Linear Collider and X-FEL at DESYSite map of the Linear Collider and X-FEL at DESY
J.P.Delahaye GDE Meeting OXFORD 25-10-05 4
P4 P5
P6
P8P2
10 kmPO9
PO7
PO5
PO3
PO1
PO2
PO4
PO6
PO8Possible site for a Linear Collider at CERN – P10
P11
J.P.Delahaye GDE Meeting OXFORD 25-10-05 5
Longitudinal section of a Linear Collider on CERN site–
J.P.Delahaye GDE Meeting OXFORD 25-10-05 6
ILC WBS
J.P.Delahaye GDE Meeting OXFORD 25-10-05 7
CERN additional contribution to ILC•Major partner in specific studies:
•Civil engineering and site specific cost study: J.L.Baldy
•Cryogenics and cryostats: L.Tavian
•Beam dynamics issues: D.Schulte
•R&D on generic key issues independent of technology:•Participation in EUROTeV design study, CARE project and ELAN network
•R&D on Beam diagnostics, Beam Delivery System (BDS), Beam dynamics...
•Resources: 2.3 MEur. material, 25 staff-y, 20 fellows-y = 6.75 MEur. total
•Tests with beam in CTF3 Test facility:•Beam instrumentation and beam simulations benchmarking
•Beam combination for DR injection/extraction with RF transv. cavities
•Participation to R&D on Low Emittance generation @ ATF/KEK
J.P.Delahaye GDE Meeting OXFORD 25-10-05 8
0
50
100
150
200
250
300
Tevatron HERA CEBAF RHIC LEP2 LHC (SSC)
[to
nn
es]
VirtualLiquidGas @ 2 MPa
~ ILC
He Inventory of Large Cryogenic Systems
J.P.Delahaye GDE Meeting OXFORD 25-10-05 9
Transport of Refrigeration in Large Distributed Cryogenic systems
0
0.1
0.2
0.3
0.4
0.5
0 1 2 3 4 5Distance [km]
Tem
pera
ture
diff
eren
ce [K
] Pressurised He II Saturated LHe II He I
Tore Supra
TevatronHERA
UNKLHC
SSC (main Ring)
SSC (HEB)
LEP2 TESLA
Low Pressure drop over long distances requires large pumping headers !
J.P.Delahaye GDE Meeting OXFORD 25-10-05 10
Alternative Configuration Distributed 2 K refrigeration
•Increase the distance between cryoplant by a factor 2
•Require specific alcove for 2K cryoplants but saving of a lot civil engineering and infrastructure as well as reducing of the surface site impact.
•Require specific study on the design and operation of “underground” warm compressor station
•Require refrigeration (water) capacity of about 1 to 2 MW per alcove
•Require an additional header in the cryomodule to return the compressed He (20-30 K, few bar) to the main cryoplant
L
2L
surface
surface
alcove
2L
surfacealcove
J.P.Delahaye GDE Meeting OXFORD 25-10-05 11
Alternative Configuration Larger cryoplants
•4.5 K refrigerator•Feasibility study on larger refrigerators (40-50 kW
equivalent at 4.5 K) and impacts on cost, layout, operation, site …
•R&D requirement
•Warm centrifugal compressor as booster•Feasibility study with impacts on cost, operation and
reliability.•Validation test is mandatory.
•2 K refrigeration•Feasibility study on larger cold compressors and
impacts on cost, layout, operation…•R&D requirement
J.P.Delahaye GDE Meeting OXFORD 25-10-05 12
Alternative Configuration Cryomodule
•Cryostat optimization•Cost effectiveness of the 5-8 K shield•Use of conduction cooled current leads for quadrupole (if
HTS retained as baseline). Gain on operation flexibility.
•Separated distribution line•Mainly justified by cost saving, if any (no sectorization
required for cryomodule repair or exchange).•Could be interesting in case of 2 tunnels (operation
availability if the line is in the service tunnel)•Could increase the filling factor of the linacs•Could be justified if the vibration due to He flow is not
acceptable (reduced flows in cryomodules).•Could simplified the heat intercept design and efficiency
(small pipe can be routed close to the components to be thermalized)
•The 300 mm pumping header (thickness 6 mm !!) is use as a rigid beam for cavity alignment inside a module (separated line with or without the pumping header?)
J.P.Delahaye GDE Meeting OXFORD 25-10-05 13
Participants: 22Duration: January 2004 – December 2008Total expenditures: 35.14 MEurosTotal E.U. support: 15.20 MEuros
The main objective of the CARE project is to generate a structured and integrated European area in the field of accelerator research and related R&D. The program includes the most advanced scientific and technological developments relevant to accelerator research for Particle Physics. It is articulated around 3 Networking Activities and 4 Joint Research Activities:
- ELAN (Electron Linear Accelerator Network)- BENE (Beam for European Neutrino Experiments)- HHH (High intensity High brightness Hadron Beams)- SRF (Superconducting RF)- PHIN (PHoto-INjector)- HIPPI (High Intensity Proton Pulsed Injectors)- NED (Next European Dipole)
Initiated:- EUROTeV- Beta beam task in the EURISOL Design Study
Considered:- LHC luminosity upgrade- Neutrino factory- Light quark and Phi factory
Initiated:- None yet
Considered:- None yet
E.U
. p
rog
ram
mes
: [2
/12]
J.P.Delahaye GDE Meeting OXFORD 25-10-05 14
•Goal:… Coordination of R&D on electron accelerators at the European level.
Evaluating the various technologies for improving the present infrastructures and defining a roadmap for future electron accelerators and colliders, including new techniques of acceleration.
•Number of participating laboratories: 55•Total contribution from EU (2004-2007): 0.450 MEuros
[E.U. to CERN contribution: 0.058 Meuros]
•Organization :•Coordinator: F.Richard (LAL/IN2P3)/D.Schulte (CERN)•Five Work Packages:
–Normal Conducting linac technology (G.Guignard/CERN)–Super Conducting Linac Technology (L.Lilje/DESY)–Beam Dynamics (D.Schulte/CERN)–Instrumentation and Diagnostics (S.Smith/CCLRC)–Advanced and novel accelerator development (B.Cros/CNRS)
ELAN (“Electron Linear Accelerator”) Network E
.U.
pro
gra
mm
es:
[4/1
2]
J.P.Delahaye GDE Meeting OXFORD 25-10-05 15
•Goal:… Research and Developments on charge production by
interaction of laser pulse with material within RF field and improve or extend the existing infrastructures in order to fulfil the objectives. Coordinate the efforts done in various institutes on the photo-injectors
•Number of participating laboratories: 9•Total contribution from EU (2004-2007): 3.5 MEuros
[E.U. to CERN contribution: 1.2 Meuros]
•Organization :•Coordinator: A.Ghigo(INFN)/R.Losito(CERN)•Four Work Packages:
–Management and communication (A.Ghigo/INFN)–Charge production (J.Teichert/FRZ-ELBE)–Lasers (I.Ross/CCRLC-RAL)–RF guns and beam dynamics (G.Bienvenu/LAL)
JRA PHIN “Charge production with photo-Injectors”
E.U
. p
rog
ram
mes
: [4
/12]
J.P.Delahaye GDE Meeting OXFORD 25-10-05 16
CERN contribution to CAREELAN&PHIN
Work-package
Task ID Task Description
EU additional resources Personal 1.5 (p.y) Material 1.26 M€
CERN committed resources Personal 11s+2.5f (p.y) Material 0.40 M€
ELAN LTECNC
BDYN
Contribution to the exchange between experts and reflection on the definition of R&D on Sources, Beam dynamics simulation codes, alignment & vibration, RF transverse deflectors
0.08 M€ 3 p.y (staff) 0.18 M€
PHIN WP1
M&C Management & Communication
Oversee and coordinate the work of the entire JRA. Creation of tools, databases and web site.
0 0.02 M€
0.5 p.y (Staff) 0 M€
PHIN WP2
CP Charge Production
Study of fabrication technology and new materials. Tests at different labs.
0. p·y 0.045 M€
4.5 Staff 1 Fellow 0.1 M€
PHIN WP3
LAS Lasers systems Design and develop laser system Amplifier design Stability issues and feedbacks
0. p.y 0.948 M€
(2.5 Staff) (1.5 Fellow) 0.1 M€
PHIN WP4
GUN RF guns and beam dynamics
Design for high charge, high average current, and long pulse trains Study and construction of a RF gun Tests in CTF3.
1.5. p·y (Fellow) 0.165 M€
0.5. p·y (Staff) 0.02 M€
J.P.Delahaye GDE Meeting OXFORD 25-10-05 17
= CERN participation
EU supported (9MEuros)Linear Colliders Design Study
About common L.C. key issues
J.P.Delahaye GDE Meeting OXFORD 25-10-05 18
CERN resources to EUROTeVWork-package Task ID Task Description
EU additional resources
CERN committed resources
BDSLD BDS Lattice Design
Exploration of non-linear collimation schemes
1.0 p·y 0.27 staff·y 0.666 fell.y WP2
(BDS) SWMD Spoiler Wakefields & Mech. Design
Trapped-mode Calculation 0.5 p·y 0.13 p·y 0.33 py
WP3 (DR)
ECLOUD Studies of Electron Cloud and other Instabilities
Development of simulation codes Benchmark and tuning of simulations against experimental data in SPS and co. Application of codes to DR lattices Fast ion instability studies
1.5p·y 2.0 py
PBPM Precision Cavity BPM
BPM with <100 nm resolution, <10 m precision, < 15 ns rise-time design and fabrication of prototype Beam tests in CTF3
2.5 p·y 84kEuro
1.5 p·y 84kEuro
TPMON Timing & Phase Monitoring
design&construction of phase reference system with stability better 15 fs rms over long distances (km) Beam tests in CTF3
2.5 p·y 120kEur
o
2.0 p·y 120kEuro
WBCM Wide-Band Current Monitor
development of a 20 GHz bandwidth bunch charge monitor resolving single bunches in a bunch train design&construction of prototype Beam tests in CTF3
84kEuro 1.0 p·y
84kEuro
WP5 (DIAG)
CFBPM, PBPM, TPMON, WBPM
Confocal Resonator BPM + preceding ones
Tests with beam in CTF3 0.3 p.y
J.P.Delahaye GDE Meeting OXFORD 25-10-05 19
CERN contribution to EUROTeV
FMSIM Failure Mode & Effect Simulations
Key failure modes (FM) determination Simulation of FMs and impact on accelerator performance / design
0.5 p·y 0.1 p·y
COLSIM Collimation Simulations
Simulation of post-linac beam halo Collimation impact on design&perform.
0.5 p·y 0.1 p·y
LAST
Luminosity and alignment system tuning
Alignment and feedback strategy for luminosity performance optimization Develop tools to evaluate luminosity
2.5 p·y 0.5 p·y 2.25py
HTGEN Halo and Tail Generation
Study of potential sources of halo and tail generation in the LET Development of halo models Explore possibilities for benchmarking
2.5 p·y 1.5 p·y
WP6 (BDYN)
BBSIM Beam-Beam Simulation Code Development
Support of development and benchmarking of simulation code GUINEA-PIG
0.1 p·y
J.P.Delahaye GDE Meeting OXFORD 25-10-05 20
Participation to ATF @ KEK
Generation of small emittance beams in ATF1 and nanometer spot sizes in ATF2
J.P.Delahaye GDE Meeting OXFORD 25-10-05 21
Latest stabilization technology applied to the accelerator fieldContribution to ATF of Test Bench developed @ CERN
Collaboration CERN/LAPP/KEK
Stabilizing quadrupoles to the 0.5 nm level!(up to 10 times better than supporting ground, above 4 Hz)
Collaboration on Nanometer Stabilisation
J.P.Delahaye GDE Meeting OXFORD 25-10-05 22
INFN
CLEX
2004 2005
2006
2007
Damped accelerating structure (R1.1)
Drive beam generation scheme (R1.2)ON/OFF PETS (R1.3)Stability bench marking (R2.1)
CLIC sub-unit (R2.3)
Use of CLIC Test Facility (CTF3)
Test with beam of beam diagnostics and RF transverse cavities
J.P.Delahaye GDE Meeting OXFORD 25-10-05 23
1. Executive Summary The current planning phase of the CLEX area at CTF3 has revealed an excellent opportunity to build a flexible Instrumentation Test Beam (ITB), at a time when such a facility is in high demand and short supply, to address both ILC and CLIC instrumentation issues. This proposal addresses some preliminary baseline requirements of the ITB, presents initial cost estimates and timelines, and identifies some key diagnostics tests that could be addressed. 2. Introduction The CLEX layout is presented in Fig. 1.
Figure 1: Outline of the CLEX facility. The Instrumentation Test-Beam (ITB) is indicated at the bottom left of the figure.
D F D F D F D F D F D F D F D F
LIL-ACS LIL-ACS F D D F
D F D
D F D
D F DUMP
8 m
2m
D F D
F D
F D F D
D F D DUMP
D F D
DUMP
40 m
D F D
1m wide passage all around
TBL
30 GHz Teststand
Probe beam injector DUMP DUMP
DUMP
D F D
F
F D
D F D DUMP Instrumentation Testbeam
3m
6 m
13 m
15 m D F D
D F D
DRAFT of a Conceptual Proposal for an Instrumentation Test Beam (ITB) Line at the CTF3 Probe Beam
G. A. Blair , John Adams Institute at RHUL, UK.H. Braun ,CERN, Switzerland
J.P.Delahaye GDE Meeting OXFORD 25-10-05 24
CERN resources towards ILC
EU CERN Total Material Staff Fellows Material Staff Fellows Material Staff Fellows MEuros P-y P-y MEuros P-y P-y MEuros P-y P-y EUROTeV 0.35 0 12.5 0.4 11.7 4 0.75 11.7 16.5 ELAN 0.08 0 0 0.18 3 0 0.26 3 0 PHIN 1.10 0 1.5 0.20 8 2.5 1.30 8 4 CARE mngt 0 0 0 0 2 0 0 2 0 Total 1.53 0 14 0.78 24.7 6.5 2.31 24.7 20.5
J.P.Delahaye GDE Meeting OXFORD 25-10-05 25
CERN FTE/year contribution to ILCSub-systems TOTAL
Vacuum systems
Warm magnet systems
Cryomodule 0.1
Cavity Package
RF Power
Cryogenics 0.4
Accelerator Physics 0.5
Operations & Reliability
Instrumentation 0.5
Controls
Systems integration
CF&S 0.5
Cost 0.2
Overall coordination 0.2
TOTAL 2.4
J.P.Delahaye GDE Meeting OXFORD 25-10-05 26
Conclusion and possible developments•CERN focused on LHC, resources committed up to
2010•CERN committed to demonstrate feasibility of CLIC
technology towards colliding beam energies in multi-TeV range complementary to ILC, within the frame of a multi-lateral network of collaborating institutes
•Limited but substantial participation to ILC within the frame of the EU supported EUROTeV design study and CARE project (ELAN, PHIN) on generic key issues independent of technology with resources (2005-07):
2.3 MEur., 25 staff-years, 20 fellow-years•Additional man-power for BCD and RDR: 2.4
FTE/year•Beam dynamics•Cryogenics and cryostat optimisation•Civil engineering and Conventional Facilities•Site specific cost study
J.P.Delahaye GDE Meeting OXFORD 25-10-05 27
Conclusion and possible developments
•Civil engineering & conventional facilities for site specific cost studies
•170 KCHF/year + 3.4 FTE Funding: CERN&DESY?•Geotechnical & Civil eng consultancy, SW&Database,
Cooling &Ventilation, Siting&Survey, Electrical eng,
Alarms&Access,
•Development and support of ILC project management tools (if LHC tools selected)
•2 to 3 FTE Funding: CERN?
•Beam Diagnostics Beam line in CTF3 CLEX•Estimation: 500 kCHF + 7FTE Funding: EU?,
PPARK?
J.P.Delahaye GDE Meeting OXFORD 25-10-05 28
Conclusion and possible developments
•CARE2 in the frame of FP7:•CARE and EUROTEV presently focused on design,
modeling, prototypes, fabrication techniques, ending 2007
•New Joint Research Activities (JRAs) from 2008 for engineering and fabrication techniques in collaboration with industry
•Taking advantage of available expertise in SC magnet technology and Cryogenics at CERN in parallel with LHC operation
•R&D on BDS SC quadrupoles, DR SC wigglers, Crab cavities (LHC upgrade), ….,
•R&D for cryogenics optimisation•Beam dynamics: Computing cluster, Codes
development and bench-mark•Pre-alignment and stabilisation
• Estimation: ? Funding EU?,
J.P.Delahaye GDE Meeting OXFORD 25-10-05 29
Future R&D on ILC Cryogenics
1/ Studies and development for BCD (BASELINE)
Large sub-cooling heat exchanger
Feasibility study of efficient large sub-cooling heat exchangers. Construction and validation of prototypes.
LHe II flow characteristics and tests Study and measurement of flow characteristics during steady state and transient operating modes.
Cryomodule optimization
Study of the cost effectiveness of the 5-8 K shields. Review of heat inleaks and piping sizing.
??? ???
2/ Studies and development for ACD (ALTERNATIVES)
Larger 4.5 K refrigerators
Feasibility study on larger refrigerators (40-50 kW equivalent at 4.5 K) with impacts on cost, layout and operation. Specific component development driven by the study conclusion.
Centrifugal compressors as booster for the warm compressor stations of 4.5 K refrigerators
Feasibility study with impacts on cost, operation and reliability. Validation test on proptotype.
Larger 2 K refrigeration
Feasibility study on larger cold compressors and impacts on cost, layout and operation. Specific component development driven by the study conclusion.
Distributed 2 K refrigeration for doubling the distance between cryoplants
Study of specific alcove for 2K cryoplants with impact on civil engineering and site environment. Specific study on the design and operation of warm compressor station “underground” (Alcove refrigeration (water) capacity…) Study on impact on cryomodule design (additional return line…).