Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.
-
Upload
candace-mathews -
Category
Documents
-
view
217 -
download
0
Transcript of Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.
![Page 1: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/1.jpg)
Johnson Street Bridge Replacement Project
Technical Briefing
April 8, 2015
![Page 2: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/2.jpg)
New IntersectionHarbour & Esquimalt Road
![Page 3: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/3.jpg)
Delta Hotel Access
![Page 4: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/4.jpg)
Rest Pier Completion
![Page 5: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/5.jpg)
Rest Pier Completion
![Page 6: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/6.jpg)
West Abutment
![Page 7: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/7.jpg)
West Abutment
![Page 8: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/8.jpg)
Bascule Pier Big Pour
![Page 9: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/9.jpg)
Intermediate Pier
![Page 10: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/10.jpg)
New Project Schedule Key Milestones
Steel Fabrication & Shipping March 1, 2015 – June 5, 2016 (66 weeks)
Bridge Machinery Fabrication Feb. 23, 2015 – Nov. 23, 2015 (39 weeks)
Bridge Decks – East June 26, 2015 – Oct. 23, 2015 (17 weeks)
Bridge Decks – West June 26, 2015 – Sept. 18, 2015 (12 weeks)
Bridge Machinery Installation Nov. 23, 2015 – Feb 1, 2016 (10 weeks)
Site Shut Down Feb. 23, 2016 – June 5, 2016 (15 weeks)
Steel Bridge Erection June 5, 2016 – Sept. 18, 2016 (15 weeks)
Bascule Span (Miscellaneous): Sept. 18, 2016 – Nov 27, 2016 (10 weeks)
Traffic shift/bridge ready for traffic Jan. 15, 2017
Demolition Jan. 15, 2017 – April 16, 2017 (13 weeks)
Project completion June 25, 2017
![Page 11: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/11.jpg)
Project Contingency
Item Amount
Initial Contingency
$2,515,000
Value Engineering Savings
$ 300,000
Current Contingency Commitments
-$1,344,573
Projected Contingency items
-$1,870,500
Contingency Shortfall
-$ 400,000
![Page 12: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/12.jpg)
Financial Impact
Description of Costs Amount
Insurance $ 280,000
Additional city costs $ 420,000
Professional consulting services
$1,800,000
Current contingency shortfall
$ 400,000
Legal costs for mediation $ 400,000
Unallocated contingency to completion
$1,500,000
Total $4,800,000
![Page 13: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/13.jpg)
Project Budget – Costs Presented to Council in March
• These costs were recently presented Council and an additional $4.8 million was requested for the project
• $1.5 million was granted by Council
• This brings the total budget for the Johnson Street Bridge Project to $94.3 million
![Page 14: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/14.jpg)
Steel Fabrication
![Page 15: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/15.jpg)
Steel Fabrication
• Steel fabrication restarted in March
• New quality control oversight program now in place in the steel fabrication plant
• Work done to improve Quality Management Plan and Inspection and Testing Plan
![Page 16: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/16.jpg)
Steel Fabrication Non-destructive examination of Orthotropic Steel Deck mockup to inspect quality of welds
![Page 17: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/17.jpg)
Steel Fabrication Truss web plates after plasma cutting. Quality Control verifying traceability of material
![Page 18: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/18.jpg)
Steel Fabrication
• Regular inspections by the fabricator and the contractor’s quality control consultants
• Ensures the bridge is constructed to the highest standard of the design – any steel not meeting the highest quality and safety specifications will be not be accepted by the City
![Page 19: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/19.jpg)
Steel Fabrication Overhead robotic gantry welding equipment used in the production of orthotropic deck panels
![Page 20: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/20.jpg)
Steel Fabrication Ring flange plates cut and beveled, prior to bending to the radius of the rings
![Page 21: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/21.jpg)
How the Bridge is Constructed
• The steel bridge has six main components: two rings, two forward trusses, a counterweight and the steel deck
• The counterweight and steel deck connect the ring and truss structures together to form the complete bridge
![Page 22: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/22.jpg)
How the Bridge is Constructed
![Page 23: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/23.jpg)
How the Bridge is Constructed
• Fabrication begins with the rings
• Starts with cutting, rolling, and splicing together of curved plates that form the ring
• The sides and middle areas of the rings are made by splicing together sections of steel plate to create three complete web-like elements per ring
![Page 24: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/24.jpg)
How the Bridge is Constructed Robotic welding of the orthotropic steel deck test panel
![Page 25: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/25.jpg)
How the Bridge is Constructed
• After the pieces are complete and inspected, they are aligned and the ring is progressively welded together
• The trusses are fabricated in a similar fashion to the rings by creating long, slender pieces of steel, which are then progressively assembled into a fully welded structure
![Page 26: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/26.jpg)
How the Bridge is Constructed
![Page 27: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/27.jpg)
How the Bridge is Constructed
• The deck is constructed with a series of orthotropic panels (a steel plate with welded ribs for added support) that are spliced together and connected with the floor beams
• The deck and floor beams are later connected to each truss to create a fully welded structure
![Page 28: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/28.jpg)
How the Bridge is Constructed
![Page 29: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/29.jpg)
How the Bridge is Constructed
• When the components are complete, inside the steel fabrication factory there are a number of trial assemblies and tests to ensure the bridge performs as it is designed to
• After the bridge has been assembled, tested and measured in position, the machinery responsible for the raising and lowering of the bridge will be installed
![Page 30: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/30.jpg)
How the Bridge is Constructed
![Page 31: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/31.jpg)
How the Bridge is Constructed
• The various bridge components will then be painted and packaged for shipping to Victoria on an ocean freight vessel
• The estimated timelines are:– Fabrication – 7-9 months– Trial erection – 2-3 months– Painting – 1-2 months– Travel time from China to Victoria – 2 months
![Page 32: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/32.jpg)
Seismic Design
![Page 33: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/33.jpg)
Seismic Design
• Presentation in March to explain the seismic design to Council
• The design standards for the Johnson Street Bridge that the H&H final design are based on are the most comprehensive and relevant design requirements for bascule bridges in North America
![Page 34: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/34.jpg)
Seismic Design
• The new JSB has been designed as a “Critical Bridge” – the equivalent to the definition of “Lifeline Bridge”, the performance required by the City
• The design of new JSB will allow the bridge to be available to all traffic after a design earthquake of 1/1000 years.
![Page 35: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/35.jpg)
Seismic Design
• The JSB is being designed and constructed to a very high seismic standard meeting the most stringent current codes in North America
• The JSB will “be usable by emergency vehicles and for security/defense purposes immediately after a large earthquake, e.g. a 2500-yr return period event”
![Page 36: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/36.jpg)
Machinery Fabrication
![Page 37: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/37.jpg)
Mediation
![Page 38: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/38.jpg)
Next Steps
• Next Quarterly Update to Council in May
• Continued onsite work by PCL
• Arrival of the steel bridge span in June 2016
• Updates to Council as needed on contingency and possible project cost savings
![Page 39: Johnson Street Bridge Replacement Project Technical Briefing April 8, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649cca5503460f94992647/html5/thumbnails/39.jpg)
Thank You
Questions