Johnson Creek Covered Bridge
description
Transcript of Johnson Creek Covered Bridge
![Page 1: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/1.jpg)
DRAFT 2/26/08
Johnson Creek Covered Bridge
![Page 2: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/2.jpg)
DRAFT 2/26/08
Construction Statistics Review & Update
In service since May 1, 2005
2386 projects “active” in system
640 finals paid in 2007 for $4,137,168
935 Change Orders approved in 2007
Progress Estimates for payments in 2007 of $1,054,764,758
1614 subcontract approved in 2007
![Page 3: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/3.jpg)
DRAFT 2/26/08
SiteManager DWR• Summary of DWR Quantities on website updated bi-
weekly with pay estimates. This can also be created within SiteManager and send from RE office
http://transportation.ky.gov/construction/sm/dwr/
The CSV File can be loaded into Excel for summary information and assisting in checking final. In Excel, it can filter on each Pay Item to check for weigh sheets, etc.
![Page 4: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/4.jpg)
DRAFT 2/26/08
Pending Pay Estimates Links• ARCHIVED:
http://transportation.ky.gov/construction/sm/est/PENDING/archive/
• Current: http://transportation.ky.gov/construction/sm/est/PENDING/
![Page 5: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/5.jpg)
DRAFT 2/26/08
Approved Pay Estimates Links
• ARCHIVED: http://transportation.ky.gov/construction/sm/est/EST_ARCH/
• Current: • http://transportation.ky.gov/construction/sm/est/
![Page 6: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/6.jpg)
DRAFT 2/26/08
Approved Pay Estimates Links
• Check & EFT numbers
http://transportation.ky.gov/construction/sm/est/payments2008####.xls
![Page 7: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/7.jpg)
DRAFT 2/26/08
Question
• What can be done to provide a better pay plane for subcontractors for work done?
• Pay estimates & DWR csv on web. Our contract is with prime.
![Page 8: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/8.jpg)
DRAFT 2/26/08
Question
• BETTER PLAN TO ADDRESS A QUICKER TURN AROUND TIME ON RECEIVING PAYMENTS FOR WORK PERFORMED .
• State Highway Engineer Gilbert Newman addressed change order issue. Residents with their inspectors keep track of work items. Need to coordinate with RE if you feel you have completed work not on pay estimate
![Page 9: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/9.jpg)
DRAFT 2/26/08
SiteManagerChange Orders
• During SiteManager Review, Resident Engineer should forward by e-mail a copy of change order to Contractor before sending for signature.
• This will allow them to check supplemental prices included in the change order.
![Page 10: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/10.jpg)
DRAFT 2/26/08
Change Order Signature Report
• Resident Engineer is to sign the change order on requested by line and mail, deliver or fax to contractor for signature and further submittal to State Highway Engineer’s Office.
• Contractor is to send change order with original signature (no fax or copy) to:
State Highway Engineer’s Office 6th Floor TCOB 200 Mero Street
Frankfort, KY 40622
![Page 11: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/11.jpg)
DRAFT 2/26/08
Change Order Signature Report
• DSHE for Project Delivery forwards to State Highway Engineer for signature & approval
• If approved, Change order then sent to account for uploading program funding.
• After funding finally secured the Change Order is put in APRV status and payment can be made on items. Approved Change order copies then mailed out.
![Page 12: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/12.jpg)
DRAFT 2/26/08
Payment for Change Order Items
• After Change Order has been put in APRV status, payment can be made on items included in the change order. They are now part of the contract.
http://transportation.ky.gov/construction/ITEMS/ITEMS08.xls
2008 Standard Bid Item List Project let after 1/1/08
![Page 13: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/13.jpg)
DRAFT 2/26/08
Question
• PLEASE ADDRESS THE LENGTH OF TIME THAT IT TAKES TO GET A CHANGE ORDER PROCESSED. EXAMPLE-WORK DONE IN SEPTEMBER & OCTOBER ON CHANGE ORDER STILL NOT PROCESSED.
• State Highway Engineer Gilbert Newman addressed this issue. Residents will keep current one Change Order submittals.
![Page 14: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/14.jpg)
DRAFT 2/26/08
DBE payment information
• Required to pay within 7 days of receipt of payment from KYTC. We pay every two weeks!
• Submit copy of check with Contract ID reference to: Office of Civil Rights & Small Business Development
% DBE Payments 6th Floor West TCOB
200 Mero Street Frankfort, KY 40601
![Page 15: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/15.jpg)
DRAFT 2/26/08
Potential Final Estimates
• 143 Contracts needing Corrective Work Completed to get Formal Acceptancehttp://transportation.ky.gov/construction/projects/correct/correctbycont.pdf
![Page 16: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/16.jpg)
DRAFT 2/26/08
Final Estimates
• Project Engineer will send copy when finished checking. Please let them know of any problems. They will forward to district in 15 days after sending to contractor, so let them know if you have a problem with quantities!
• When Final Release sent from Central Office, Contractor has 60 days to respond. If any errors or disagreements be sure to send notice to both Director of Construction Central Office and District Construction.
• Signing and sending Final Release as soon as possible speeds up final payment!!!
![Page 17: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/17.jpg)
DRAFT 2/26/08
Question
• What should a Contractor do to get a job closed out after 5 years?
• Contact TEBM for Construction & Director of Construction. We are trying to get current on our Finals!
![Page 18: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/18.jpg)
DRAFT 2/26/08
Pre-Qualified Contact Link
• http://transportation.ky.gov/Contract/Pqbook.pdf• Provide the Resident Engineer an e-mail at Pre-
Construction meeting for submitting Change Orders and Pay Estimates.
Poor sign placement & erection
(not a Road Construction Project!!)
![Page 19: Johnson Creek Covered Bridge](https://reader036.fdocuments.us/reader036/viewer/2022070417/568152c4550346895dc0e3c7/html5/thumbnails/19.jpg)
DRAFT 2/26/08
Robert C. Lewis, PE
Assistant State Highway Engineer
200 Mero Street W6-17-02
Frankfort, KY 40622
E-mail [email protected]
Cell 502-330-3470
Office 502-564-3730 ext 3084