![Page 1: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/1.jpg)
River CorridorClosure Project
Waste ManagementPresented by
John Fulton, Washington Closure HanfordFebruary 2007
U.S. Department of EnergyRichland Operations Office
River Corridor Closure ContractE0702044_1
![Page 2: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/2.jpg)
River Corridor ContractA new way of doing business
E0608039
Hanford Site boundary(586 Square Miles)
(300 Area)
EnvironmentalRestorationDisposal Facility(ERDF)
Reactorareas
(100 Area)
River Corridor(218 Square Miles)
• Environmental Restoration Contract at Hanford
• Savannah River Site
• Rocky Flats
• Miamisburg Closure Project
• West Valley
• Weldon Springs
• Commercial nuclear sector
WCH brings together talent and lessons learned from:
• Incentivized contract to reduce cost and improve efficiency
• Increased DOE oversight to ensure environmental compliance
• Expectation that “Closure Culture”spreads to other cleanup work
River Corridor Closure ContractE0702044_2
![Page 3: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/3.jpg)
Total Recordable Rate/Days Away, Restricted or Transferred Performance
As of February 3, 2007
Worked 2.5M hours without a lost work day
River Corridor Closure ContractE0702044_3
![Page 4: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/4.jpg)
Cost/Schedule/Performance Indicator (CSPI)
RCC Project CSPI (cumulative)
1.2211.2311.2251.223
1.164
0.9
0.99
1.08
1.17
1.26
1.35
FY06 Mar Jun Sep FY07 Dec Jan Feb
CSPIMinimum
River Corridor Closure ContractE0702044_4
Contract terms (CPIF) $2.2B (with fee), target completion 2013Cost Variance (PMB): $62,112K; 21.8%Schedule Variance (PMB): $39,653K; 16.2%
![Page 5: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/5.jpg)
The People Behind the Work
River Corridor Closure Contract
![Page 6: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/6.jpg)
377 Building Demolition
River Corridor Closure ContractE0702044_6
![Page 7: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/7.jpg)
D4 (Deactivation, Decontamination, Decommissioning and Demolition)
Progress to Date
Demolished 75 of 486 structures in the 300 and 100 Areas, 50 more than planned
River Corridor Closure ContractE0702044_7
![Page 8: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/8.jpg)
Field Remediation
Progress
Cleaned up 54 of 370 wastes sites, 41 more than planned
River Corridor Closure ContractE0702044_8
![Page 9: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/9.jpg)
Waste Operations
Progress
Treated, transported and disposed 732,000 of 4 million tons of waste, 344,000 tons more than planned
River Corridor Closure ContractE0702044_9
![Page 10: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/10.jpg)
Reactor Interim Safe Storage
Progress
Initialized removal of hazardous materials at N Reactor to prepare for interim safe storage
River Corridor Closure ContractE0702044_10
![Page 11: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/11.jpg)
End State and Final Closure
Progress
Over 1,200 samples collected to support River Corridor Baseline Risk Assessment
River Corridor Closure ContractE0702044_11
![Page 12: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/12.jpg)
River Corridor Closure ContractE0702044_12
Small Business Subcontracting Performance
Through January 2007
Actual-VS- 85%• Since October 2005, over $92 million
has been spent with small businesses
• Currently mentoring two protégé firms– Integrated Logistics Services, Inc.– Terranear PMC
ContractRequirement 65%
E0605051_6
![Page 13: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/13.jpg)
Potential Schedule Impacts
River Corridor Closure ContractE0702044_13
Availability of PNNL occupied facilities
Highly complex facilities with radiological and chemical contamination
ISS of KE and KW reactors may be delayed due to late completion of the Fuel Basin Deactivation Project
![Page 14: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/14.jpg)
Technical ChallengesDemolition of 324 and 327 Building Hot Cells
• High rad dose potential• Thick shield walls• Heavy lifts – heavy haul
618-10 and 11 Burial Ground Remediation
• Suspected transuranic and high dose items randomly disposed
• 618-11 is next to operating nuclear reactor• Limited documentation (type and quantity of material)• Disposed with no intention of retrieval
River Corridor Closure ContractE0702044_14
![Page 15: John Fulton, Washington Closure Hanfordarchive.wmsym.org/2007/Panels/5AA-03.pdf · John Fulton, Washington Closure Hanford February 2007 U.S. Department of Energy Richland Operations](https://reader031.fdocuments.us/reader031/viewer/2022011813/5e37e9e0309beb38e83b736d/html5/thumbnails/15.jpg)
River Corridor Closure Project
Working Safe
Over 2.5 million hours without a lost work day
Working Hard 17% ahead of schedule
River Corridor Closure ContractE0702044_15
Working Smart 22% under budget