John F. Kennedy Middle School Page 1 of 3 March 31, 2020 Addition and Renovations Supplement No. 5 SUPPLEMENT NO. 5 JOHN F. KENNEDY MIDDLE SCHOOL ADDITION AND RENOVATIONS STATE PROJECT NO. 049-0140 RNV GILBANE JOB NO. J08621.000 Bid Packages: (All) Note: Use the below link to access the complete supplement including all attachments: https://dn.gilbaneco.com/?linkid=KZi4zr6VWWVzo0YKoavymbl4PgD7GAC8VIfODS6ncAGbVD1eLJic7g The following items are hereby made part of the bid documents for the John F. Kennedy Middle School Project in Enfield, CT: GENERAL 1. The bid date and time has changed for ONLY the following bid packages (Bid Packages added after Supplement #4 indicated in red): Bid Package Revised Due Date & Time 03A - Concrete Thursday April 9 th , 2020 @ 1:00PM 04A Masonry Thursday April 9 th , 2020 @ 10:00AM 05A Structural Steel Thursday April 9 th , 2020 @ 10:00AM 05B Misc. Metals – Set Aside MBE Thursday April 9 th , 2020 @ 10:00AM 06A Millwork Thursday April 9 th , 2020 @ 1:00PM 07A Roofing Thursday April 9 th , 2020 @ 10:00AM 08A Glass & Glazing Thursday April 9 th , 2020 @ 10:00AM 08B Doors Frames & Hardware Thursday April 9 th , 2020 @ 10:00AM 09A Drywall & General Trades Thursday April 9 th , 2020 @ 10:00AM 09B - Acoustical Ceilings - Set Aside SBE Thursday April 9 th , 2020 @ 1:00PM 09D Flooring (Resilient, Epoxy, & Wood) Thursday April 9 th , 2020 @ 1:00PM 09E Carpet – Set Aside SBE Thursday April 9 th , 2020 @ 1:00PM 10A Signage - Set Aside SBE Thursday April 9 th , 2020 @ 1:00PM 10C Toilet Partitions - Set Aside SBE Thursday April 9 th , 2020 @ 1:00PM 11A - Gym Equipment Thursday April 9 th , 2020 @ 1:00PM 11B Kitchen Equipment Thursday April 9 th , 2020 @ 10:00AM 21A Fire Protection Thursday April 9 th , 2020 @ 10:00AM 22A Plumbing Thursday April 9 th , 2020 @ 10:00AM 23A HVAC Thursday April 9 th , 2020 @ 10:00AM 26A Electrical and Fire Alarm Thursday April 9 th , 2020 @ 10:00AM 26B Telecommunications, Data and Audio/Visual Set Aside MBE Thursday April 9 th , 2020 @ 10:00AM 31A Sitework & Paving Thursday April 9 th , 2020 @ 10:00AM 32A Site Concrete Thursday April 9 th , 2020 @ 1:00PM 32B Landscaping Thursday April 9 th , 2020 @ 1:00PM

Transcript of John F. Kennedy Middle School Page 1 of 3 March 31, 2020 · John F. Kennedy Middle School Page 2 of...

Page 1: John F. Kennedy Middle School Page 1 of 3 March 31, 2020 · John F. Kennedy Middle School Page 2 of 3 March 31, 2020 Addition and Renovations Supplement No. 5 Sealed bids must be

John F. Kennedy Middle School Page 1 of 3 March 31, 2020Addition and Renovations Supplement No. 5

SUPPLEMENT NO. 5JOHN F. KENNEDY MIDDLE SCHOOL

ADDITION AND RENOVATIONSSTATE PROJECT NO. 049-0140 RNV

GILBANE JOB NO. J08621.000Bid Packages: (All)

Note: Use the below link to access the complete supplement including all attachments:https://dn.gilbaneco.com/?linkid=KZi4zr6VWWVzo0YKoavymbl4PgD7GAC8VIfODS6ncAGbVD1eLJic7g

The following items are hereby made part of the bid documents for the John F. Kennedy Middle School Project in Enfield, CT:

GENERAL

1. The bid date and time has changed for ONLY the following bid packages (Bid Packages added after Supplement #4 indicated in red):

Bid Package Revised Due Date & Time03A - Concrete Thursday April 9th, 2020 @ 1:00PM04A Masonry Thursday April 9th, 2020 @ 10:00AM05A Structural Steel Thursday April 9th, 2020 @ 10:00AM05B Misc. Metals – Set Aside MBE Thursday April 9th, 2020 @ 10:00AM

06A Millwork Thursday April 9th, 2020 @ 1:00PM07A Roofing Thursday April 9th, 2020 @ 10:00AM08A Glass & Glazing Thursday April 9th, 2020 @ 10:00AM08B Doors Frames & Hardware Thursday April 9th, 2020 @ 10:00AM09A Drywall & General Trades Thursday April 9th, 2020 @ 10:00AM09B - Acoustical Ceilings - Set Aside SBE Thursday April 9th, 2020 @ 1:00PM09D Flooring (Resilient, Epoxy, & Wood) Thursday April 9th, 2020 @ 1:00PM09E Carpet – Set Aside SBE Thursday April 9th, 2020 @ 1:00PM10A Signage - Set Aside SBE Thursday April 9th, 2020 @ 1:00PM10C Toilet Partitions - Set Aside SBE Thursday April 9th, 2020 @ 1:00PM

11A - Gym Equipment Thursday April 9th, 2020 @ 1:00PM11B Kitchen Equipment Thursday April 9th, 2020 @ 10:00AM21A Fire Protection Thursday April 9th, 2020 @ 10:00AM22A Plumbing Thursday April 9th, 2020 @ 10:00AM23A HVAC Thursday April 9th, 2020 @ 10:00AM26A Electrical and Fire Alarm Thursday April 9th, 2020 @ 10:00AM

26B Telecommunications, Data and Audio/VisualSet Aside MBE

Thursday April 9th, 2020 @ 10:00AM

31A Sitework & Paving Thursday April 9th, 2020 @ 10:00AM32A Site Concrete Thursday April 9th, 2020 @ 1:00PM32B Landscaping Thursday April 9th, 2020 @ 1:00PM

Page 2: John F. Kennedy Middle School Page 1 of 3 March 31, 2020 · John F. Kennedy Middle School Page 2 of 3 March 31, 2020 Addition and Renovations Supplement No. 5 Sealed bids must be

John F. Kennedy Middle School Page 2 of 3 March 31, 2020Addition and Renovations Supplement No. 5

Sealed bids must be delivered to Gilbane’s Glastonbury Office before or by the close of the bid period. Late bids with be rejected and returned unopened.

a. The bid date and time remains unchanged for the balance of the bid packages.

2. The Gilbane Project Manual dated 03/10/2020 R4 has been reissued, the following documents have been edited/issued;a. 00 42 26-EX.A Proposal Form Exhibit A R4 dated 03/31/2020b. 00 74 00 BIM Execution Plan Appendix B R1 dated 03/31/2020c. 00 93 16 Scope Clarifications dated 03/31/2020

3. Bid RFI Log dated 03/31/2020 has been issued.

4. JFK Middle School JCJ Architecture Addendum No. 3 dated 03/30/2020 has been issued.

5. Public Bid Opening Logistics: Upon careful consideration by both Gilbane and the Town of Enfield as it relates to the current situation revolving around COVID-19, please be advised of the following changes to the public bid opening process;

a. The bid opening will be held via live video conference ONLY. Bidders will NOT be permitted to attend the bid opening in person.

b. The live video conference of the public bid opening will open/begin for bidders to join at the specified bid due date/time.

c. Bids will be opened and read aloud on the live video conference thirty (30) minutes following the close of the bid period.

d. Bids will be opened and publicly read aloud in order by Bid Package within the specified wave of Bid Package due date/time indicated on the attached revised 00 42 26-EX.A Proposal Form – Exhibit A R2.

e. Access Information for Live Video Conference of Bid Opening:i. Join URL: https://zoom.us/j/364774283

ii. Meeting ID: 364-774-283

SPECIFIC SCOPE OF WORK

1. BP09F – Painting

a. Reference Specific Scope #2: Delete Reference to specification section 03 35 43 Polished Concrete Finishing.

2. BP11B – Kitchen Equipment

a. Reference Specific Scope #38: This bid package shall furnish the kitchen hoods for installation by BP23A. Include delivery to a location directly below their permanent location in the kitchen.

3. BP22A – Plumbing

a. Reference Specific Scope #2: Add Reference to specification section 23 11 23 Gas piping.

4. BP23A – HVAC

a. Reference Specific Scope #2: DELETE Reference to specification section 23 11 23 Gas piping. b. Reference Specific Scope #43: BP 11B will furnish the kitchen hoods for installation by BP23A.

BP11B will deliver the hoods to directly below their permanent location in the kitchen.

Page 3: John F. Kennedy Middle School Page 1 of 3 March 31, 2020 · John F. Kennedy Middle School Page 2 of 3 March 31, 2020 Addition and Renovations Supplement No. 5 Sealed bids must be

John F. Kennedy Middle School Page 3 of 3 March 31, 2020Addition and Renovations Supplement No. 5

REMINDERS

1. Please be advise that the bid location has CHANGED. Sealed bids for the John F Kennedy Middle School Project will be received by Gilbane Building Company at Gilbane Building Company’s Glastonbury Office, 208 New London Turnpike Glastonbury, CT 06033 until the specified bid due date/time. Reference the attached map of Gilbane’s Office location.

2. Bid Bonds: Each Bid shall be accompanied by a bid security in the form of a Bid Bond in an amount not less than Ten Percent (10%) of the total amount of the base bid. Said surety shall be issued by a surety that is licensed to do business in the State of Connecticut and is rated A-(VII) or better by A.M. Best. The bid security shall be drawn in favor of Gilbane Building Company.

3. Bidders shall EXCLUDE the cost of Payment and Performance Bonds from their base bid. Provide an ADD ALTERNATE in Section I of the Proposal Form for the cost of Payment and Performance Bonds.

4. Submit all RFIs via email to Nate Gengarella ([email protected])

All other terms and conditions remain unchanged. Acknowledge your receipt and inclusion of this Supplement on the proposal form in the space provided.

Sincerely,GILBANE BUILDING COMPANY

Stephanie GreenmanPreconstruction Manager

Cc: Project Team – GilbaneFile

---------------------------------------------End of Supplement #5 ---------------------------------------------

Page 4: John F. Kennedy Middle School Page 1 of 3 March 31, 2020 · John F. Kennedy Middle School Page 2 of 3 March 31, 2020 Addition and Renovations Supplement No. 5 Sealed bids must be

Gilbane Office208 New London TurnpikeGlastonbury, CT 06033 ----------------------------------Deliver bid at the first door

on the right as you arefacing the building.

ENTER HERE

JOHN F. KENNEDY MIDDLE SCHOOLADDITION AND RENOVATIONSSTATE PROJECT NO. 049-0140 RNVGILBANE JOB NO. J08621.000

REVISED BID LOCATION: GILBANE OFFICE - 208 NEW LONDON TURNPIKE GLASTONBURY, CT 06033