John Arthur Photon Systems [email protected] April 16, 2007 1 LCLS Photon Systems...
-
date post
21-Dec-2015 -
Category
Documents
-
view
217 -
download
1
Transcript of John Arthur Photon Systems [email protected] April 16, 2007 1 LCLS Photon Systems...
John Arthur
Photon Systems Status [email protected]
April 16, 2007 1
LCLS Photon Systems Status
• Technical status and accomplishments• Response to FY2007 continuing resolution• LCLS/LUSI coordination
John Arthur
LCLS Photon Systems Manager
John Arthur
Photon Systems Status [email protected]
April 16, 2007 2
Recommendations from Oct 2006
Put effort into design of critical x-ray optics components (mirrors and thin crystals)
Make LCLS Photon Systems and LUSI work together to optimize designs and commissioning plans
Putting both recommendations into practice
John Arthur
Photon Systems Status [email protected]
April 16, 2007 3
XTOD Status
Still in advanced design phaseNearly all components at least through conceptual review
Staying on schedule
About to start major procurementsHardware installation can start 11-07
LLNL team is working well with SLAC
John Arthur
Photon Systems Status [email protected]
April 16, 2007 4
XTOD design for attenuators and x-ray intensity monitors
4.5 meter long, gas attenuator
high pressure N2 section
Embedded (Be) solid
attenuators
Upstream embedded gas detector
Downstream embedded gas
detector
John Arthur
Photon Systems Status [email protected]
April 16, 2007 5
LLNL Zygo 20× images of Si test substrates by two
vendors
0.37 mm
vendor 2, loc. 1 vendor 1, loc. 1
0.37 mm
LLNL full-aperture interferometry images of Si test substrates by two vendors
Vendor 1
Vendor 2
XTOD working with x-ray mirror vendors
John Arthur
Photon Systems Status [email protected]
April 16, 2007 6
Effects of 2007 CR on XTOD
Procurements and some design effort were delayed
New plan was developedCommissioning optics in FEE ready for first lightBeam transport to NEH ready by late FY2008All work on Tunnel and FEH delayed until FY2009All work finished by early FY2010
John Arthur
Photon Systems Status [email protected]
April 16, 2007 7
XES Status
In design phaseAMO instrument design going well
2-d detector development going well
Controls area was behind, catching up
Working with Radiation Physics on PPS items
Ready for installation starting 11-07
John Arthur
Photon Systems Status [email protected]
April 16, 2007 8
Concept for AMO Instrument
Focusing optics
Experimental chamber
Diagnostics chamber
John Arthur
Photon Systems Status [email protected]
April 16, 2007 9
E l e c t r o n
D u m p
F E E
H u t c h 1 H u t c h 2 H u t c h 3
X - R a y T u n n e l
H u t c h 4
H u t c h 5
H u t c h 6
S 0
S 1
S 2
S H 1
M 1 S
M 2 S
M 3 / 4 S
X 3 X 4
M 6
S 3
S H 2
S 4
S 5
S 6
H o r i z o n t a l
O f f s e t M i r r o r s
P P S S t o p p e r S e t
X - R a y M i r r o r
X - R a y C r y s t a l
P r i m a r y M o v a b l e
E l e m e n t s
E x p e r i m e n t
N e a r E x p e r i m e n t a l H a l l
F a r E x p e r i m e n t a l H a l l
M o v e a b l e D u m p
X P C S
P o s 2
X P C S
P o s 1
C X I
HE D
X P P
P o s 1
X P P
P o s 2
AM
O
S
X
P
S X P
X-ray shutter and mirror layoutFrom the LCLS operating modes Physics Requirements Doc
John Arthur
Photon Systems Status [email protected]
April 16, 2007 10
Effects of 2007 CR on XES
Some design effort was delayed
New plan was developedSafety and controls work in NEH ready late FY2008First-stage AMO instrument ready late FY2008Work in FEH delayed until FY2009Some AMO instrumentation delayed until FY2009All work finished by early FY2010
John Arthur
Photon Systems Status [email protected]
April 16, 2007 11
LUSI-LCLS Integration Working Group
Define the interface between LCLS and LUSI
Resolve issues overlapping this interfaceFormalize with Interface Control Documents
Find common solutions to common problemsExperimental instrumentation, diagnostics
Standardization where appropriate
The Working Group was created by Keith Hodgson and John Galayda to:
John Arthur
Photon Systems Status [email protected]
April 16, 2007 12
Jerry Hastings (LUSI)John Arthur (LCLS)
Yiping Feng (LUSI instrument scientist, controls)David Fritz (LUSI instrument scientist, diagnostics)Stefan Moeller (LCLS Endstation Systems Manager)Hal Tompkins (LCLS x-ray installation, commissioning)
Other LCLS/LUSI staff as needed
Co-chairs
Working Group Members
John Arthur
Photon Systems Status [email protected]
April 16, 2007 13
Issues before the Working Group
Experimental data flow and interface standards
Vacuum hardware and controls standards
Conventional facilities/hutches
Installation/commissioning
John Arthur
Photon Systems Status [email protected]
April 16, 2007 14
Summary
XTOD and XES are still in design phase, though XTOD is
moving into procurement and XES will follow soon
FY2007 continuing resolution forced some delays,
extension of project
Technical issues are being resolved with no big problems
Should be ready for installation starting 11-07
FEE, NEH ready in FY2009, FEH ready in FY2010
Coordination with LUSI is going well, has been formalized