4/28/2003CVEN 349 - Maxwell1
Job Site Issues
Module 09-01
April 20, 2023
4/28/2003CVEN 349 - Maxwell2
Purpose
Recap some of the overall job site issues leading to project close out.
4/28/2003CVEN 349 - Maxwell3
Learning Objectives
Be able to list and describe briefly the following Job-Site Issues.
4/28/2003CVEN 349 - Maxwell4
1. Acceptance and Withdrawal Period
Bids are due at a specific time and place.
Bid security (bond) protects Owner from Contractor's failure to sign contract.
Acceptance Period protects Contractor from Owner’s delay in signing the contract.
4/28/2003CVEN 349 - Maxwell5
2. Award of Notice to Proceed
Consummates the relationship between the Owner and contractor.
Letter of Intent – a legally binding agreement to eventually sign a contract.
Establishes a Start Date. Generally grants access to the work
site.
4/28/2003CVEN 349 - Maxwell6
3. Contract Agreement
Pulls together: Plans and specifications Standard forms Payment schedule Standard Terms and Conditions Any special or additional T&C’s, Forms, etc. Processes for Change Orders, Time
Extensions, Payment Schedule changes, etc.
4/28/2003CVEN 349 - Maxwell7
4. Time Extensions
Various reasons:Design problemsOwner modificationsStrikes, Weather, Late Deliveries, etc.
Affects Progress Payments No-Cost extensions are more likely in
research or consulting.
4/28/2003CVEN 349 - Maxwell8
5. Change Orders
Any alteration of the formal agreement requires a Change Order. They may be needed: To correct design and specification problems Owners change their minds. Conditions change – subsurface, new codes,
technology, economy, etc. Only the Owner or his official designee can sign a
change order. Since they are non-competitive in nature, they may
be a “license to steal.”
4/28/2003CVEN 349 - Maxwell9
6. Suspension, Delay, or Interruption
For one reason or another, the Owner may order the Contractor to suspend or delay work. The Contractor will usually claim damages.
For one reason or another, the Contractor may delay job completion. The Owner will usually claim liquidated damages. They are hard to collect.
4/28/2003CVEN 349 - Maxwell10
7. Progress Payments and Retainage
Payments are based upon an agreed upon schedule of values, mile stones, or %-complete estimates.
Retainage is returned after the work is completed to the Owners satisfaction.
4/28/2003CVEN 349 - Maxwell11
8. Job Close Out
Completion of the work (Close Out) may be a contentious exercise.
The “Punch List” is used to protect both parties from unnecessary delays in establishing the actual completion date.
Completion of “Punch List” establishes the completion of the contract.