1 PSFC/JA-07-3 Effect of Compression Ratio and Manifold Pressure ...
Jim Irby MIT-PSFC · Five Year Plan. PAC Meeting 02/20-02/21 2003 Machine • Upgrades will be...
Transcript of Jim Irby MIT-PSFC · Five Year Plan. PAC Meeting 02/20-02/21 2003 Machine • Upgrades will be...
PAC 2003
Jim IrbyMIT-PSFC
PAC Meeting 02/20-02/21 2003
Outline
• Status– Operations– Diagnostics– Data system
• Five Year Plan– Machine– Diagnostics– Data system
• Short Term Plans
PAC Meeting 02/20-02/21 2003
StatusOperations
• Alcator C-Mod operated from 6/7/2002 to 11/12/2002 after the successful inspection of the TF magnet and other major machine components
• During the last run campaign:– Approximately 800 plasma discharges with a startup
reliability of 75% were produced– Startup reliability during the month of October was
85% with several days >95%.– We maintained about 32 shots/day
• By September 30th we had performed 31.5 physics run days out of a proposed 32
PAC Meeting 02/20-02/21 2003
Operations• Milestone 79: inner divertor installation completed on time
on 3/8/2002 – Ip at new record level of 1.67 MA (7.8 T) for C-Mod– More freedom in plasma shape control
Lower δ = 0.73
PAC Meeting 02/20-02/21 2003
Operations
• We continue to improve power handling capability of the ICRF antennas and make upgrades to the control/protection/data acquisition systems– 1.5 MW pulses for 4 s into GA dummy load
• Improvements to cryostat were made– Horizontal port inner seals now outside cryostat where
they can be kept warm– Horizontal ports are removable with igloo in place– Higher magnet cooling rate: 50% increase in number of
discharges per day• Improved tangential access: Mods to cryostat and cylinder
PAC Meeting 02/20-02/21 2003
Changes to Cylinder and Cryostat
Add flat section to cylinderfor tangential access
Instrumentation ports
Openings around portsincreased in size
PAC Meeting 02/20-02/21 2003
Operations: Lower Hybrid Project
• LH HVPS and crowbar have been brought into operation– 50 kV, 208 A supply– Solid state crowbar with < 10 �s time response
• Water cooling system acceptance tests completed– 600 and 1200 gallons/min pumps at 100 psi
• Phase and amplitude control system for klystrons now a major activity
• PPPL is maintaining a 3/31/2003 delivery date for the LH launcher
PAC Meeting 02/20-02/21 2003
Shroud heaters
Port andrails
CouplerBack end
CouplerFront endTaper
RFProbe Grill
Drive
PAC Meeting 02/20-02/21 2003
Operations
• Control coils have been fabricated and driven to full current (control locked modes)
• First of at least two TMX power supplies is operational ---control, data acquisition, protection (300 V, 3000 A)
• Installation of coils proceeding on igloo
PAC Meeting 02/20-02/21 2003
Operations : Preparations for new cryopump1021002021 EFIT: 1.000
0.4 0.5 0.6 0.7 0.8 0.9 1.0
-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6
1021002021 EFIT: 1.000
0.4 0.5 0.6 0.7 0.8 0.9 1.0
-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6
C
G
D
1021002025 EFIT: 1.000
0.4 0.5 0.6 0.7 0.8 0.9 1.0
-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6
1021002025 EFIT: 1.000
0.4 0.5 0.6 0.7 0.8 0.9 1.0
-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6
C
G
D
• Plasma geometry has been varied from lower single null to upper single null
• Pressures at the top and bottom of the vessel have been measured ---upper vessel pressure varied from 0.1 to 10 mTorr
• Baffles will be added to restrict gas flow at top of vesselR (m)R (m)
Z (m
)
Z (m
)
PAC Meeting 02/20-02/21 2003
Diagnostics
• New inner divertor diagnostics are operational and providing important information for reactor design
• Core TS system greatly improved with new polychromator installations (GA polychromator design)
• High speed cameras used to image turbulence at the edge and to follow Li pellet ablation trails (current profiles)
• Inner wall scanning probe used to measure density, temperature, and fluctuation profiles for comparison with outer probes
PAC Meeting 02/20-02/21 2003
Diagnostics
• Number of invessel viewing cameras increased– Improved our ability to correlate machine problems
with activity in vessel• Several new Penning gauges measure pressure under outer
divertor modules and in main chamber– New capillary lines with calibrated flow rates allow gas
to be injected around the vessel to measure resulting pressures and conductances with and w/o plasma
Sawtoothing
MSE q profile
ne=1.2×1020OhmicH.Yuh – Feb 20 2003 C-Mod PAC
MSE Data Scatter is acceptable
Edge Hα (30% higher in L)Viewing GeometryLow Edge Density
Beam PenetrationBeam CurrentITB/Core Density in H-mode 2.220 =n
2.220 =n 3.220 =n
AI Beam 0.4= AI Beam 4.3= AI Beam 5.3=
1
2
.120 =n
.120 =n
3.120 =n
AI Beam 2.4= AI Beam 1.4= AI Beam 3.4=
H.Yuh – Feb 20 2003 C-Mod PAC
PAC Meeting 02/20-02/21 2003
Data System
• Data system currently deals effectively with over 500 MB of data per discharge
• Highly distributed network of servers and workstations has allowed incremental upgrades to match demand
• We continue to move away from DEC/VMS based systems– 12 linux workstations now fully integrated into between
shot data analysis– 36 node (linux) Beowulf cluster developed and used for
between shot analysis and large codes
PAC Meeting 02/20-02/21 2003
Data System
• A second linux server with a 1.5 Tbyte RAID system will soon replace our VMS based data acquisition server
• Tbyte scale RAID magnetic disks --- ALL C-Mod data is online and accessible within a few ms
• Magnetic tape backup system upgraded to accommodate the dramatic increase in data rate
PAC Meeting 02/20-02/21 2003
Data System
• We continue the transition away from CAMAC to CPCIbased hardware– CPCI crates include diskless linux based computers
capable of sub-sampling and preliminary data analysis– Magnetics data acquisition completely replaced during
last run campaign --- better data rates with higher resolution --- Higher reliability
– LH systems will come online as CPCI system– ICRF data acquisition migrating to CPCI
PAC Meeting 02/20-02/21 2003
Five Year Plan
PAC Meeting 02/20-02/21 2003
Machine
• Upgrades will be performed and new systems installed to– Bring lower hybrid project into operation– Allow reliable, high power density, long pulse
operation with density control (divertor, cryopump)– Improve reliability and power handling capability of the
ICRF systems• Plasma control systems will be improved
– Control coils– Power supplies– Digital PCS
• New klystrons will be purchased and old klystrons repaired to ensure replacements will be available
PAC Meeting 02/20-02/21 2003
Machine
FY08Tungsten Brush?Advanced Divertor Prototype (BPX)
FY05Install coils for locked mode control(inside cryostat)
Control Coils
FY05Improved load tolerant designFree port space for diagnostics
2nd ICRF 4-Strap Antenna
FY05Prepare for long pulse, high power operation
ICRF Faraday ScreenUpgrades
FY04FY05
High heat load capability (25 MW/m2)Reactor relevant
Tungsten Brush Tilesand Test Module
FY06Improve heat load capabilityStrengthen
Lower Outer Divertor
FY05Gain density control during H-modeDensity/Impurity control during AT
Cryopump
PAC Meeting 02/20-02/21 2003
Machine
FY04Allow transmitters to see matched load during large changes in plasma loadingInvestigating wg and stripline designs
Fast Ferrite TunerPrototype
FY05Improvements made to EFC and EF2Better plasma control during high performance operation
Power Supply Upgrades
BeginsFY04
Digital system will allow more control lines and much improved control algorithms --- real-time EFIT
Plasma Control System Upgrade
FY05Reduce power density at antenna grill Second LH Launcher
FY05Increase LH source power from 3 to 4 MW
LH Source Power Upgrade
PAC Meeting 02/20-02/21 2003
Cryopump (FY05)– Control density and possibly
reduce impurities during H-mode and AT operation
– Pumping speeds approximately 25k-l/s
– Toroidal LHe filled tube surrounded by LN2 heat shield
– New upper chamber armor protects pump
– Gas flows out between gussets to the pump --- baffle increases pressure in upper chamber
– Preliminary design phase– Loss of diagnostic access
PAC Meeting 02/20-02/21 2003
Lower Outer Divertor (FY05)– Current outer divertor is at heat
load design limits– A new divertor will be required
for long pulse AT operation at auxiliary power levels approaching 10 MW
– New divertor will have a simple cylindrical shape that will be easy to fabricate
– Toroidally continuous vertical plate (no leading edges) ---some loss of diagnostic access
– One module will be of the advanced tile design
PAC Meeting 02/20-02/21 2003
Diagnostics Plans
• New diagnostics are planned for the next grant period to increase our capability– Several new diagnostics will focus on improved
understanding of ITB discharges --- better core profile and rotation information for example
– Others are coming online to help diagnose the operation of the new lower hybrid system
– We will continue to improve diagnostics for the SOL, edge plasma, and turbulence and fluctuations
• Loss of diagnostic access as the lower hybrid system is installed will require installation of new horizontal ports
PAC Meeting 02/20-02/21 2003
Diagnostics
FY04FY05FY07
New 2D CCD detector for current systemImpurity density spectrometer: He3 minoritySpectrometer with new views and better background measurements
CXRS Upgrade
FY04FY05
Double number of radial measurementsSecond view (discriminate E vs V X B)
MSE Upgrade
FY05Replace beam on loan from RFX with even better performance device, 55 kV, 8 amps source, .06 m 1/e, 1.5 s, 70% full energy current fraction in source , Delivery time 14-15 months (start procurement soon)
Long Pulse DNB
PAC Meeting 02/20-02/21 2003
Diagnostics
FY05Confirmation and support of MSEOperate at high density, high temperatureUp to 30 poloidally viewing chords, � > 10 �m
PolarimeterInterferometer
FY06
FY07
FY07
Increased number of channels and improved data acq for better spatial, temporal, and k-space resolutionA second PCI system will be added at another toroidal location: extent of wave prop and mode conversionCrossed beams: 2D imaging of ETG turbulence and mode converted ICRF/IBW waves
PCI
FY04Measure profile and energy spectrum of suprathermal electrons during LH Exp32 channels, 20-200 keV
Hard X-Ray Camera
PAC Meeting 02/20-02/21 2003
Diagnostics
FY06New view to gain information about non-thermal spectrum. Diagnose LH coupling physics and deposition profile
Non Thermal ECE
FY07New radiometers will be added to extend both low and high frequency range: low and high magnetic field accessibility
Heterodyne ECE
FY04Six new channels will be added to improve coverage of the plasma core; particularly important for ITB discharges
Core Thomson Scattering
FY04Allow control of drive phaseActive MHD Antennas
PAC Meeting 02/20-02/21 2003
Diagnostics
FY05Doubly bent crystal and 2D solid state detectorRotation velocity and Ti over most of plasma cross section w/o shot-to-shot scanning
Imaging X-Ray Crystal Spectrometer
FY06High resolution, high throughput grating following design of Chandra X-Ray telescopeMeasure bulk rotation in outer half of plasma
High Resolution Transmission Grating VUV
FY06Improve toroidal resolution; low- to intermediate-n
Inboard Mirnov Coil Upgrade
FY06Study both long and short wavelength fluctuations in large gradient regions (transport region)
Laser Scattering(possibly CO2)
PAC Meeting 02/20-02/21 2003
Diagnostics
FY05Measure bulk flow in plasma edge/SOLDoppler shifts and broadening of emission lines using high resolution visible spectrometer with 2D multi-element detector
SOL Flow Imaging
FY05andFY07
Measure divertor temperatures during high auxiliary power and long pulse dischargesEssential to monitor operation of divertor components
Divertor IR Cameras
FY06Measure ICRF generated hydrogen tail by observing neutrals created by charge exchange with DNB
Active CX NPA
FY05Extend edge TS out to the limiterMeasure temperature and density where typically only probes have been used with limited number of temporal points
SOL Thomson Scattering
PAC Meeting 02/20-02/21 2003
Diagnostics
FY07Investigate pedestal profiles and fluctuationsHigh Resolution Edge ECE System
FY04to FY06
Microbalances will be placed around vessel to measure deposition
Material Deposition Monitors
FY04Measure density profile near surface of the LH grill. Critical to understanding of coupling of LH power --- line ratio, probes?
LH Grill Density Diagnostic
FY052D (radial, poloidal) patterns of density and temperature in outboard SOLFiber based system using ultra-high-speed-movie camera
Edge Fluctuation Imaging
PAC Meeting 02/20-02/21 2003
Diagnostics
FY06Determine if dust plays a significant role in particle fueling and radiation in the SOL
Mie Scattering of Dust in the SOL
FY06Measure 2D neutral density profiles at the plasma edgeMultiple Lyman-� arrays
Spectral Tomography of Neutrals
FY04High resolution measurement of poloidal magnetic field at the edgeMeasure intensity ratios of Li-multiplet lines produced by 50kV Li atomic beam
Li Beam Edge Polarimeter
FY06Measure profiles of ni, Ti, and �ni in the pedestal
LIF Fluctuation Mapping at the Edge
PAC Meeting 02/20-02/21 2003
Diagnostics
FY07Upgrade of detector for impurity source survey spectrometer
2D CCD Detector
FY06andFY08
Provide cameras at MIT to replace camera on loan from PPPL --- turbulence, tranport
Ultra High Speed Framing Cameras
FY05Study probe perturbation effects on transportDouble the number of signals/probe
New A-Port Scanning ProbeDrive
FY05Measure density, temperature, and potential fluctuations at high bandwidth using the three scanning probesAdd 50 MHz sampling rate cPCI data acq
Upgrade to Probe Bias Electronics
PAC Meeting 02/20-02/21 2003
Data System
• Major task over the next few months will be to complete the transition from the VMS to the linux computing environment (est CY2004)
• Linux configuration by the end of 2004– 35 desktop systems– 3 to 4 servers
• Local area network will be upgraded to take full advantage of the i/o rates of the new systems– Gbps links to each desktop– 10 Gbps backbone
PAC Meeting 02/20-02/21 2003
Data System
• Mass storage requirements will be met with large magnetic disk storage arrays– Current data rates require 1 to 2 Tbytes of new capacity
per year– New tape systems will also be required
• The replacement of CAMAC with CPCI digitizers, timing, and waveform modules will continue– Coordination with other major US and international
facilities is important and ongoing• Improvements will be made to video data acquisition
systems
PAC Meeting 02/20-02/21 2003
Short Term Plans
• Pumpdown in early March 2003• Flywheel inspection mid March to early April 2003• LH launcher arrives end March 2003• Plasma operation begins early to mid April 2003• Physics operation through mid June 2003
– Test modifications to ICRF antennas– Test new control coils
• Alternator inspection August 2003 (approx 3 months)• Installation of LH launcher (approx 6 weeks)• Plasma operation for 21 weeks in FY04
PAC Meeting 02/20-02/21 2003