JCOP V8& hazards of building with Timber Frame
Allianz Engineering Risk Control SurveyorsGraham Akeroyd
2File name / department / author
Agenda
1 JCOP Version 8
2 Insurance Contractual Conditions
3 Other Sensible Measures and Further guidance
3File name / department / author
Allianz Engineering – Fire Protection on Construction Sites
JCOP v8 – CDM Regulations
4File name / department / author
© Copyright Allianz SE 19. Apr 2023
5File name / department / author
Construction
© Copyright Allianz SE 19. Apr 2023
Don’t turn this -
Into this!!!!!!!
6File name / department / author
What’s Important in Fire Protection?
• Nature of construction – height / floor area;
• Values at risk;
• Fire travel vertical / horizontal;
• Hazards presented;
• Risk of occurrence;
• External risks – malicious arson, fire transfer etc;
© Copyright Allianz SE 19. Apr 2023
7File name / department / author
JCOP Version 8 – Asset / People Protection
• Agreement between construction world, fire authority and insurance world;
• Over 25 yrs in use;
• Applies mandatorily to contracts with an original value of £2.5+M;
• Applies to all parts of a contract where overall value is £20m+;
• Special requirements for large TF projects;
• Can be applied to any “high risk” contract regardless of value;
© Copyright Allianz SE 19. Apr 2023
8File name / department / author
Section 5 – Design Phase
• Notifiable projects – all parties to comply with their duties;
• All parties to co-operate and co-ordinate activities;
• Co-operate to reduce fire risks;
• At design stage identify fire hazards and eliminate where possible;
• Select non flammable materials, reduce need for hot works, safe access routes, design in fire fighting systems;
• During construction phase check that fire safety measures are not compromised as building progresses;
• For TF structures check surrounding properties and your impact on them
© Copyright Allianz SE 19. Apr 2023
9File name / department / author
Section 6 – Construction Phase
• Provision of a responsible person;
• Nominating fire marshals – training;
• Build a site fire safety plan.
© Copyright Allianz SE 19. Apr 2023
10File name / department / author
Section 7 – Liaison with Emergency Services
• Build and maintain the Fire Brigade Pack;
• Invite fire services to site;
• Check all hydrants on / off site;
• Decide extent of water supplies;
• Brigade access;
• Staircases;
• Floor loadings.
© Copyright Allianz SE 19. Apr 2023
11File name / department / author
Section 8 - Emergency Procedures• Written procedures;
• Signage;
• Escape routes etc;
• Fire alarms;
• Training;
• Ongoing changes – toolbox talks
© Copyright Allianz SE 19. Apr 2023
12File name / department / author
Section 9 – Fire Protection
• Compartmentation – fire divide structure;• Escape staircases – fire protect;• Fire stopping – ducts / services;• Fire alarms – wireless systems;• Water supplies – location – pressures;• Site Hydrants – identify / test / identify;• End of day fire check – fire marshals – record;• No partial occupancy without full protection;• Living in building prohibited
© Copyright Allianz SE 19. Apr 2023
13File name / department / author
Section 10 – Temporary Covering Materials• Any coverings to be fire approved;
• LPS1207 standard, rigid or flexible;
• Scaffold covers to LPS 1215 standard;
• Materials near building fire protect;
• Approved coverings for foams;
• Fire protected room – packaged goods
© Copyright Allianz SE 19. Apr 2023
14File name / department / author
Section 11 – Fire Extinguishers• Training;
• Adequate numbers – suitable types;
• Conspicuous positions each floor – fire points;
• Adjacent other fire risks;
• Accessible;
• Maintained;
• Re-assessed as work progresses
• FEA’s on plant recommended-
refer PUWER
© Copyright Allianz SE 19. Apr 2023
15File name / department / author
Section 12 – Site Security
• Subject to suitable RA;
• Secure building in accordance with RA;
• Suitable fencing – gates;
• Site illumination;
• Secure HFL’s and LPG’s etc;
• Consider guards and cctv;
• Revise RA if site suspended
© Copyright Allianz SE 19. Apr 2023
16File name / department / author
Section 13 – Temporary Accommodation Units
• Strict requirements – fully detailed;
• Construction;
• Location;
• Heating;
• Stacking;
• Fire protection;
• TAU – “villages” – RRO;
© Copyright Allianz SE 19. Apr 2023
17File name / department / author
Section 14 – Flammable Liquids & LPG• Security;
• Location – distances;
• Signage;
• Suitable electrical equipment – flameproof etc;
• Consider automatic gas detection;
• Adequate FEA’s;
Designated area for refuelling
© Copyright Allianz SE 19. Apr 2023
18File name / department / author
Section 15 - AcetyleneSpecial requirements
•Eliminate where possible;
•Reduce cylinders – possible;
•Remove from site at close of business
Remember - fire brigade can shut down site!!!!
© Copyright Allianz SE 19. Apr 2023
19File name / department / author
Section 16 – Hot Work• Strict requirements;
• Avoid where possible;
• Permit scheme;
• FEA’s of suitable types – not those on site;
• HW permit holder trained in use of FEA’s??
• 1 hour monitoring before sign off (2 hours for TF risks)
© Copyright Allianz SE 19. Apr 2023
20File name / department / author
Section 17 – Electricity & Gas• Installed by trained
and certified persons;
• PAT tested;
• Inspection of temporary installations;
• Turned off at night (other than fire / security, safety lighting etc)
© Copyright Allianz SE 19. Apr 2023
21File name / department / author
Section 18 – Waste Materials• Waste control regime;
• High standards of housekeeping expected;
• Clear dry vegetation – not burn it;
• Remove to external skips daily as far away from building as possible – covered units?
• Burning allowed subject to strict comprehensive requirements – don’t do it!
© Copyright Allianz SE 19. Apr 2023
22File name / department / author
Section 19 – Plant and Vehicles• Generators and compressors
in open air;
• Requirements for refuelling – at refuelling point;
• Protect against impact / damage;
• Use sand trays;
• Park vehicles away from building and materials – 10 m;
• Consider fire suppression / CESAR
© Copyright Allianz SE 19. Apr 2023
23File name / department / author
Section 20 – Stored Materials• Store comb materials away from
building - as far away as possible;
• If within building cover with LPS 1207 coverings – no HW – have FEA’s nearby;
• Remove any combustible wrappings;
• Consider steel storage containers;
• Consider internal store room – fire protected.
© Copyright Allianz SE 19. Apr 2023
24File name / department / author
Section 21 - Smoking• Preferably ban from site;
• Provide smoking points – strict requirements;
• Shelter construction – location etc all defined.
© Copyright Allianz SE 19. Apr 2023
25File name / department / author
Section 22 – High Rise Construction Sites• Buildings above which
normal rescue is not practical;
• Specific RA;
• Fire doors to staircases;
• Compartmentation;
• Ducts and risers fire protected;
• Fixed fire alarms;
• Provision of wet risers.
© Copyright Allianz SE 19. Apr 2023
26File name / department / author
Section 23 Large TF Risks• 4 storeys + or floor area in excess of 2500 sq
M;
• Site specific RA;
• Consider ground floor non combustible materials;
• Consider fire treatment of timbers;
• Control exposure between multiple units;
• Consider fire stopping on larger projects;
• Consider temp fire protection materials;
• Compartmentation;
• Clad with non comb materials early if possible;
• Heat producing devices should not be used in the building;
• No refuelling within the structure;
© Copyright Allianz SE 19. Apr 2023
27File name / department / author
Large TF Risks - continued• Remove flammables at end of day;
• TAU’s within 20m must be non combustible and subject to a risk specific RA;
• Heating / drying / de-humidifying units 110v and removed at end of day;
• Turn utilities off at end of day (except life safety systems);
• Automatic fire detection system to TAU’s with off site monitoring BS 5839 ( unless 24 hr guarding provided);
• Reduce foam plastics – polystyrene fall arrest bags prohibited;
• Hot works monitoring for 1 hr and revisited 2 hrs after before closing permit.
© Copyright Allianz SE 19. Apr 2023
28File name / department / author
© Copyright Allianz SE 19. Apr 2023
2
2 Insurance Contractual Conditions
29File name / department / author
Allianz Special Conditions Precedent to Liability• Minimum site safety standards MSS1;
• Applies between £1m - £2.5m;
• No smoking except at designated areas;
• Hoarded or weld mesh fenced site;
• HW by permit and JCOP;
• Waste, flammables and gases removed each day to a safe distance - reasonable;
• Burning of waste prohibited;
• Refuelling in the open as far away as possible;
• All utilities off at night, subject to life safety;© Copyright Allianz SE 19. Apr 2023
30File name / department / author
Allianz Special Conditions Precedent to Liability
• Minimum site safety standards MSS2;
• Applies above £2.5m;
• Separate site specific Fire Safety Plan, before work commences;
• Site protected by monitored CCTV system;
• TAU’s as far as possible from buildings – reasonable distance;
• Heating and de-humidifying equipment removed at end of day.
© Copyright Allianz SE 19. Apr 2023
31File name / department / author
Special Insurance Conditions
Check yours very carefully and comply!!!!
© Copyright Allianz SE 19. Apr 2023
32File name / department / author
© Copyright Allianz SE 19. Apr 2023
3
3 Other Sensible Measures and Further guidance
33File name / department / author
Other sensible measuresNo radios in TF buildings;
No charging in TF buildings;
FEA’s adjacent timber cutting areas;
Collection bags and clean up;
Protect timber cutting areas with plasterboard / steel;
All hot works inc metal cutting – external – permits;
Wireless fire alarm throughout the works;
Charging in TAU’s – FEA and plug in RCD’s;
Management take a strong line on infringements;
© Copyright Allianz SE 19. Apr 2023
34File name / department / author
Other GuidanceSTA – Site Safe – applies to PC;
STA 16 steps to fire safety – JCOP;
HSG 168 v2 – RA based;
STA guides (1-3) to separation distance during construction all bldgs in excess of 300 sq M;
LPC Red Book + mobile phone App
NB - STA now advise all member contracts in excess of 300 sq M to HSE and CFOA
© Copyright Allianz SE 19. Apr 2023
35File name / department / author
Conclusion• Site management trained to control the site;• Properly consider all the fire risks;• Eliminate / reduce / control fire risks;• Have a good fire safety plan;• Design the site arrangements around the plan;• Continually assess and manage fire risks on site;• Train staff to identify and deal with hazards;• Educate sub-contractors;• Consult your insurer on their requirements;• Remember what is required to meet protection of the
assets is not the same as H & S legislation
© Copyright Allianz SE 19. Apr 2023
36File name / department / author
© Copyright Allianz SE 19. Apr 2023
Questions?