Jason Hade, Regional Planner
Kern COG Workshop – November 21, 2002
High-Speed Rail for the Kern
Region
Kern Council of Governments
![Page 2: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/2.jpg)
Workshop Overview
• California High-Speed Rail Authority Progress
• Metropolitan Bakersfield High-Speed Rail Terminal Impact Analysis
• Upcoming Issues
• Resources/Questions
![Page 3: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/3.jpg)
High-Speed Rail Authority Progress
• Rail Authority required to prepare a plan for the construction and operation of a high-speed train system for the state capable of achieving operating speeds of, at least, 200 mph
• Screening report for Sacramento-Bakersfield corridor approved by Authority on January 16, 2002
![Page 4: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/4.jpg)
Environmental Review Process
• 2002/2003 state budget includes $7.05 million for Authority to prepare draft program EIR/EIS
• Draft program EIR/EIS scheduled for completion in August 2003
• Final program EIR/EIS expected to be completed by December 2003
![Page 5: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/5.jpg)
Metropolitan Bakersfield High-Speed Rail Terminal Impact Analysis
• Purpose of study is to analyze terminal impacts and benefits to assist with building consensus for final terminal site recommendation
• Three sites to be evaluated within Metropolitan Bakersfield: 7th Standard Road/West of S.R. 99; Golden State/”F” Street to “M” Street; and Truxtun Avenue and “S” Street/Union Avenue.
• Wilbur Smith Associates to conduct study
![Page 6: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/6.jpg)
Potential Terminal Sites
![Page 7: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/7.jpg)
Project Timeline
![Page 8: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/8.jpg)
Upcoming Issues
• Senate Bill 1856 – Authorizes a $9.95 billion general obligation bond for the November 2004 ballot– $9 billion would create state’s share of construction
costs for San Francisco – Los Angeles segment of system
• Senate Bill 796 – eliminates the Authority’s December 31, 2003 sunset date
• Final alignment and terminal decisions to be made by Authority upon completion of environmental studies (December 2003)
![Page 9: Jason Hade, Regional Planner Kern COG Workshop – November 21, 2002 High-Speed Rail for the Kern Region Kern Council of Governments.](https://reader036.fdocuments.us/reader036/viewer/2022062716/56649dbc5503460f94aadb33/html5/thumbnails/9.jpg)
Resources/Questions
• California High-Speed Rail Authority - http://www.cahighspeedrail.ca.gov/
• SB 1856 and SB 796 information – http://www.leginfo.ca.gov/
• Jason Hade, [email protected] or (661) 861-2191