January 8, 2015 Ackerson Hall Rutgers-Newark€¦ · (10% Capture) Optimize Existing System Green...
Transcript of January 8, 2015 Ackerson Hall Rutgers-Newark€¦ · (10% Capture) Optimize Existing System Green...
© 2014 HDR, Inc., all rights reserved.
Green Infrastructure Performance in NYC
January 8, 2015
Ackerson Hall Rutgers-Newark
Carter H. Strickland, Jr Vice President
NYC Green Infrastructure Plan
Review of post-construction GI monitoring (PCM) results
Evaluating GI for LTCPs and CSO benefits
Discussion
NYC Green Infrastructure Plan
NYC Green Infrastructure
Annu
al C
SO V
olum
e (m
illion
s of
gal
lons
)
21,698
17,896
21,753 19,808 -1,701-1,514
-586
-1,945
-
5,000
10,000
15,000
20,000
25,000
30,000
Cost-EffectiveGrey
Investments(Built &
Planned)
Reduced Flow GreenInfrastructure
(10% Capture)
OptimizeExisting System
Green Strategy Cost-EffectiveGrey
Investments(Built &
Planned)
Potential Tanks,Tunnels, &Expansions
Grey Strategy
-5,666 built/under construction
-2,602 planned -2,547 planned
-5,666 built/under construction
GREEN STRATEGY GREY STRATEGY
2045 BASELINE - PROJECTIONFROM 2007 FACILITY PLANS
Planning Phase: Estimate of Performance
Planning Phase: Estimate of Costs
$2.9 $2.9
$1.5
$0.9 $0.03
$3.9
$-
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
$7.0
$8.0
Green Strategy Grey Strategy
Potential Tanks, Tunnels, & Expansions Optimize Existing SystemGreen Infrastructure - Private Investment Green Infrastructure - Public InvestmentReduced Flow Cost-Effective Grey Investments
$6.8
$5.3
$2.4
Planning Phase: Estimate of Additional Benefits
Co-benefits: Schoolyards to Playgrounds
Co-benefits: Right of Way Bioswale
Co-Benefits: Grant Program
NYC CSO Consent Decree Modification (2012)
Benefits • $1.4 billion in savings from
substituted green and grey infrastructure
• $2 billion in grey infrastructure deferred
Key elements
• Over $187 million in green infrastructure through 2015
• 3 neighborhood scale pilot projects to be monitored
• 5 year milestones and overall commitment to managing 10% of CSS area for 1” storm by 2030
• Adaptive management structure
Performance Standards
Review of NYC’s Post-Construction Monitoring Program and Results
NYC GI Monitoring (Site Scale)
City-Owned Sites • Right-of-Ways • Agency Buildings
and Parking Lots • Public Housing • City Parks • Public Schools
Monitoring Equipment Roof Drain Inserts ISCO 4230 Bubble Flow
Meter Weather Station Arlyn Series 320D-CR
Scales and Data Logger V-notch Weir and Pressure
Transducer Stage Gauge Water Level Logger and
Weir Plate H-flume Water Quality Sampling
Wells Piezometers Hydrant Testing Infiltration Testing
Site Scale
Inflow and outflow measured with remote monitoring equipment.
Soil moisture and ponding levels measured.
Equipment monitored performance at regular intervals, typically five minutes.
Site visits conducted regularly to download data, maintain equipment and assess qualitative monitoring aspects.
Rain gauges or weather stations at most locations to collect locally-accurate weather data.
Calibrate, calibrate, calibrate !!!!
Monitoring Approach
Blue Roofs Modified Inlet
Trays Check Dams
2”
DEP’s Metropolitan Ave. Storehouse
2”
Blue Roof Monitoring
June 22, 2012 1.3” Storm
Benefit
Benefit
Blue Roof Performance: Volume Reduction
Results for 2011-2012 (~70 storms) • Designed for peak shaving, but
achieve good volume capture through ponding/evaporation
• Trays: most consistent results (50-80% retention)
Blue Roof Performance: Peak Flow Reduction
Results for 2011-2012 (~70 Storms) • All types provide good peak
shaving • Trays most consistent, ~80-100%
reduction of peak flow
Permeable Pavement
Porous Pavement Standard Asphalt FilterPave
21
Far Rockaway Bus Terminal Parking Lot
Permeable Pavement Performance: Volume Retained
2012-2013 Results (96 Storms) • FilterPave consistently captures 100% • Standard and Porous Asphalts variable • Porous Asphalt generally captures
>50% • FilterPave experiencing wear and tear
Volu
me
Ret
aine
d Vo
lum
e R
etai
ned
Volu
me
Ret
aine
d
Rainfall Depth (in) Rainfall Depth (in)
Subsurface Detention & Infiltration
North Parking Lot
South Parking Lot
23
Perforated Pipes
NYCHA Bronx River Houses
Subsurface Systems Performance: Peak Flow & Volume Reduction
Chamber System Perforated Pipe System
Rain Gardens
RAIN GARDENS
RAIN GARDENS
NYCHA Bronx River Houses
Rain Gardens Monitoring: 1.4” Storm, May 24, 2012
(Ponding Depth)
Bio 1 - 7:1 Bio 2 - 6:1
Bio 3 - 9:1 Bio 4 - 17:1
0%
20%
40%
60%
80%
100%
0.0625 0.25 1 4
Volu
me
Ret
aine
d
Effective Storm Depth (in)
0%
20%
40%
60%
80%
100%
0.0625 0.25 1 4
V
olum
e R
etai
ned
Effective Storm Depth (in)
0%20%40%60%80%
100%
0.0625 0.25 1 4
Volu
me
Ret
aine
d
Effective Storm Depth (in)
0%20%40%60%80%
100%
0.0625 0.25 1 4
Volu
me
Ret
aine
d
Effective Storm Depth (in)
20112012
Rain Gardens Performance: Volume Retained
Impervious Area 81,870 ft² DA: GI Footprint 11:1
N&S Conduit Bioretention
N&S Bioretention: Data Summary
Monitoring data from August 2011 to December 2012 Maintenance:
• Removal of debris and sediment from curb cuts
• Weeding and mulching
Storm Characteristics
2011 2012 Number of Storms 20 53
Storm Depth 0.11” to 7.78” 0.12” to 2.78” Peak Intensity 0.24 to 4.92 in/hr 0.24 to 4.2 in/hr Storm Duration 0.2 to 53 hrs 1.5 to 77 hrs
Roadway Median Monitoring: 2.6” Storm, June 12, 2012
Ponding Depth
Only 4 outflow events since installation Typical surface drawdown duration < 8 hours Ponding drawdown rate increasing, and fewer ponding events
occurring, likely due to root growth Vegetated swales effective at infiltrating offsite runoff
0.0
0.5
1.0
1.5
2.0
2.5
Jun-11 Sep-11 Dec-11 Mar-12 May-12 Aug-12 Nov-12
Draw
down
Rat
e (in
/hr)
East West
N&S Bioretention: Observations
0%
20%
40%
60%
80%
100%
0.0625 0.25 1 4
Volu
me
Ret
entio
n
Effective Storm Depth (in)
2011 2012 2013
• Dimensions: 20 ft L x 5 ft W x 5 ft D
• Entirely in right-of-way • Widespread opportunity • Pilot findings:
– Performance results
– Design modifications
– Maintenance program
Enhanced Tree Pits
Enhanced Tree Pits Monitoring: 1.5” Storm, Dec 7, 2011
Blake Ave ETP
Enhanced Tree Pits Performance: Volume Retention at 4 Sites
Results of Monitoring Other Bioswales
• Percent of rainfall captured by 10 bioswales over 185 rain events.
• Bioswales performed best during storms with less than one inch of rain.
Rainfall (in.) Mean Median Below 1” 73% 85%
1”-2” 25% 21%
Above 2” 14% 12%
Total 59% 60%
Percent Capture of 10 Bioswales
NYC Neighborhood Demonstration Projects
Demonstration Areas
Data collected to measure sewer flow reductions
Flow meters located at the point where the sewer exits the Demonstration Area catchment area
Meters record flow and depth within the main outlet sewer
Data acquisition is continuous with measurements recorded at 15 minutes intervals
Piezometers and soil moisture sensors were installed with ROWBs to measure local conditions
Monitoring Approach
Demo Area 2 Demo Area 3
Demonstration Projects: In-Sewer Monitoring Locations
Demonstration Areas Runoff Reduction Observations P
erce
ntag
e o
f R
ainf
all
Flow
ing
in
Sew
er
All source controls have provided benefits for storms < 1” In many cases, bioretention source controls have fully retained the
volume of one-inch storms they receive The condition of underlying soils have an impact on retention
performance and overall source control functionality Source controls designed primarily for detention also retain runoff
volumes Porous pavement performance varied for different types Performance generally improved in vegetated systems due to the
growth and establishment of plants
Preliminary Conclusions about Success of GI Systems
Evaluating GI for LTCPs and CSO Benefits
Sewershed
• Infiltration - Native soil - Engineered
soil • Storage
- Stone porosity
- Soil porosity
• Peak flow reductions
• Long term sewer flow reductions
Site
Neighborhood
Scaling up Performance
Hundreds to Thousands of Acres Tens to Hundreds of Acres
Acres to Tens of Acres
Goals • Demonstrate that the potential reduction
in CSO from areawide application of GI system, when performance of GI installations varies based on location, site conditions and type of GI
• Ensure evaluation of grey and green CSO reduction strategies are equivalent
Solutions • Scale-up or “lump” individual installations
subcatchment-wide • Allows for different types of GI i.e.,
detention and retention to be accounted for in model
• Also allows for other types to be added later dependent rate of installations
Modeling Approach for LTCPs
Attainment of water quality standards Planned/constructed grey controls,
remaining CSO volumes and capital costs Ratio of separate stormwater to CSO
discharges Proximity to public access locations,
planned improvement projects, etc.
Identifying Sewersheds for GI Implementation
Opportunities Analysis
Waterbody Based Targets
Managed Acres
Percent of CSIA
Managed Acres
Percent of CSIA
Managed Acres
Percent of CSIA
Managed Acres
Percent of CSIA
Alley Creek 1,490 0% 0% 45 3.0% 45 3.0%Bronx River 2,331 244 10% 13 0.6% 66 2.8% 322 14%Coney Island Creek 694 0% 0% 7 1.0% 7 1.0%Flushing Bay 4,049 401 10% 11 0.3% 110 2.7% 522 13%Flushing Creek 5,923 314 5.3% 0% 165 2.8% 479 8.1%Gowanus Canal 1,387 135 10% 5 0.4% 22 1.6% 162 12%Hutchinson River 1,128 111 10% 15 1.3% 32 2.9% 158 14%Jamaica Bay & CSO Tributaries 7,891 386 4.9% 23 0.3% 266 3.4% 675 8.6%Newtown Creek 4,524 461 10% 14 0.3% 118 2.6% 593 13%Westchester Creek 3,480 348 10% 17 0.5% 122 3.5% 487 14%
ROW Public Onsite Public Onsite Private TotalWaterbodies/Watersheds
CSIA (Acres)
Future Phase: DEP will explore opportunities for remainder of 10% GI target
Current Phase: Priority Drainage Areas
Typically, a multi-step process is applied: 1. Fatal flaw and feasibility review
• Community Disruption/Potential for Nuisances • Constructability/Permitting • Operating Complexity/Ease of O&M
2. Quantify Impacts • Pollutant Reduction/Water Quality Improvements • Control of Discharge to Sensitive Areas • Flood Control • Environmental Justice • Ancillary Community Benefits • Sustainability i.e., Energy Savings
3. Quantify Costs 4. Knee-of-the-curve selected (for highest ranked, acceptable,
technically feasible CSO control measures)
LTCP Alternatives Evaluations for Green & Grey
Questions: • Application of 2012 EPA Recreational Water Quality
Criteria and associated challenges? • How to define non-economic criteria? • Equally relevant criteria for all member communities? • Weighting of criteria? • Guidance for consistent evaluation process and criteria?
LTCP Alternatives Evaluations for Green & Grey
Monitoring over several seasons is critical to testing model assumptions and controlling for site specific soil and other conditions
A common methodology for green infrastructure stormwater controls is important for comparing green and gray alternatives and for consistency between cities
Learn from early action or pilot projects
Cost-effectiveness can be maximized during site and technology selection
Modeling is an effective way to get a working estimate of CSO reductions from green infrastructure for developing LTCPs
Conclusions
Discussion
Carter Strickland [email protected]
Questions?