James River Project Update for the James River Partnership XVII
-
Upload
norfolk-district-us-army-corps-of-engineers -
Category
Government & Nonprofit
-
view
53 -
download
2
description
Transcript of James River Project Update for the James River Partnership XVII
US Army Corps of Engineers
BUILDING STRONG®
U.S. Army Corps of Engineers
Norfolk District James River Partnership XVIII
James River Project Update
Walter Trinkala
Project Manager
July 18, 2014
BUILDING STRONG®
James River Funding
2
FY 14 President's Budget:
FY 14 (work Plan)
FY 14 Sandy Funding
$3,801,000
$4,659,990
$750,000
FY 15 President’s Budget: $3,696,000
FY 15 Capability:
$7,600,000
BUILDING STRONG®
Indefinite Delivery Indefinite Quantity
(IDIQ) Contract
W91236-13-D-0054 • IDIQ Contract Solicitation included a base year and two option years
(3 years total) $12M capacity
• Status:
• Base Contract Awarded August 19, 2013
• Task Order 0001 Awarded August 22, 2013
• Task Order 0002 Awarded December 6, 2013
• Task Order 0003
• YTD Contract Awarded: $8,697,340.61
Capacity Remaining: $3,302,659.39
3
BUILDING STRONG®
Cottrell Contracting Corporation
The Lexington
4
BUILDING STRONG®
Hydraulic Pipeline/CUTTERHEAD
5
BUILDING STRONG®
• Maintenance Dredging Completed:
• Dancing Point - Swann Point Shoal Channel (Task Order 0001)
• Dredged 1 Sept 2013 through 8 Nov 2013
• Tribell Shoal Channel (Task Order 0001)
• Dredged 3 Oct 2013 through 26 Oct 2013
• Goose Hill Shoal Channel (Task Order 0002)
• Dredged 10 Dec 2013 through 4 Feb 2014
• Dancing Point – Swann Point Channel (Task Order 0002)
• Dredged 5 February 2014 through 14 Feb 2014
• Total Volume of Dredged Material:
•1,063,926 Cubic Yards
FY 2013/2014
Accomplishments
6
BUILDING STRONG®
•
7
BUILDING STRONG®
Status of Environmental
Permits
8
Upper James River:
( Hopewell to Richmond Harbor)
• Department of Environmental Quality (DEQ) Virginia Water Protection Permit (VWP)
• Expires 21 Dec 2014
• Corps will be renewing the DEQ VWP permit Aug 2014
Middle James River
(Goose Hill Shoal Channel to City Point Shoal Channel)
• DEQ VWP permit
• Issued 22 April 2014, Expires 21 April 2029
• Virginia Marine Resource Commission (VMRC)
• Permit Issued 19 March 2014, Expires 31 Jan 2017
BUILDING STRONG®
BUILDING STRONG®
• Maintenance Dredging to be Performed:
(Starting early Aug 2014)
• Task Order 0003
• Dancing Point – Swann Point Shoal Channel
• Jordan Point – Windmill Point Shoal Channel
• Task Order 0004 (Subject to Availability of Funds)
• Shoal Channel TBD
• Contract Acquisition Strategy
• Condition Surveys:
•Richmond Deepwater Terminal to Hopewell.
FY 2014/2015 Activities
10
BUILDING STRONG® 11
BUILDING STRONG®
Questions/Comments?
Contact Information:
USACE, Norfolk District
Project Manager Walter Trinkala (757) 201-7715
Walter. A. [email protected]