James River Project Update presented to the XVIII James River Partnership meeting on July 18 2014 by Walter Trinkala

Transcript of James River Project Update for the James River Partnership XVII

Page 1: James River Project Update for the James River Partnership XVII

US Army Corps of Engineers

BUILDING STRONG®

U.S. Army Corps of Engineers

Norfolk District James River Partnership XVIII

James River Project Update

Walter Trinkala

Project Manager

July 18, 2014

Page 2: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

James River Funding

2

FY 14 President's Budget:

FY 14 (work Plan)

FY 14 Sandy Funding

$3,801,000

$4,659,990

$750,000

FY 15 President’s Budget: $3,696,000

FY 15 Capability:

$7,600,000

Page 3: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Indefinite Delivery Indefinite Quantity

(IDIQ) Contract

W91236-13-D-0054 • IDIQ Contract Solicitation included a base year and two option years

(3 years total) $12M capacity

• Status:

• Base Contract Awarded August 19, 2013

• Task Order 0001 Awarded August 22, 2013

• Task Order 0002 Awarded December 6, 2013

• Task Order 0003

• YTD Contract Awarded: $8,697,340.61

Capacity Remaining: $3,302,659.39

3

Page 4: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Cottrell Contracting Corporation

The Lexington

4

Page 5: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Hydraulic Pipeline/CUTTERHEAD

5

Page 6: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

• Maintenance Dredging Completed:

• Dancing Point - Swann Point Shoal Channel (Task Order 0001)

• Dredged 1 Sept 2013 through 8 Nov 2013

• Tribell Shoal Channel (Task Order 0001)

• Dredged 3 Oct 2013 through 26 Oct 2013

• Goose Hill Shoal Channel (Task Order 0002)

• Dredged 10 Dec 2013 through 4 Feb 2014

• Dancing Point – Swann Point Channel (Task Order 0002)

• Dredged 5 February 2014 through 14 Feb 2014

• Total Volume of Dredged Material:

•1,063,926 Cubic Yards

FY 2013/2014

Accomplishments

6

Page 7: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

7

Page 8: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Status of Environmental

Permits

8

Upper James River:

( Hopewell to Richmond Harbor)

• Department of Environmental Quality (DEQ) Virginia Water Protection Permit (VWP)

• Expires 21 Dec 2014

• Corps will be renewing the DEQ VWP permit Aug 2014

Middle James River

(Goose Hill Shoal Channel to City Point Shoal Channel)

• DEQ VWP permit

• Issued 22 April 2014, Expires 21 April 2029

• Virginia Marine Resource Commission (VMRC)

• Permit Issued 19 March 2014, Expires 31 Jan 2017

Page 9: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Page 10: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

• Maintenance Dredging to be Performed:

(Starting early Aug 2014)

• Task Order 0003

• Dancing Point – Swann Point Shoal Channel

• Jordan Point – Windmill Point Shoal Channel

• Task Order 0004 (Subject to Availability of Funds)

• Shoal Channel TBD

• Contract Acquisition Strategy

• Condition Surveys:

•Richmond Deepwater Terminal to Hopewell.

FY 2014/2015 Activities

10

Page 11: James River Project Update for the James River Partnership XVII

BUILDING STRONG® 11

Page 12: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Questions/Comments?