Jamaica Plain Exterior Windows - Phase 2 - 5 MAY 2016

1
523-10-105 Exterior Panel Replacement – Phase 2 – Jamaica Plain Project Overview Replace the exterior façade on the west elevation of Building One. This is a phased project. The scope of work encompasses the removal and replacement of the windows, new structural steel components, metal framing, sheathing, added insulation, floor line fire stopping, (18) three story curtain walls, and a metal panel rain screen system Work includes, but is not limited to, general construction, selective demolition, specified abatement, structural steel, waterproofing, insulation, glazing, solid surface interior casing, painting, and certain other items. Current Status: 5 May 2016 5/11/16 - Mechanical louvers scheduled for delivery. 5/4/2016 – Rain Screen Panels completed in Zone 5 and 6. 5/4/2016 – Rain Screen Panels in progress in Zones 1A,3, and 4 protective film to be removed last. 5/4/2016 – Vent window glazing complete in Zones 1A, 2,3,4 and 5. 5/9/2016 – Vent window glazing starts in Zone 6. 5/12/2016 – Mechanical louvers installation starts in Zone 6. 4/25/2016 – Interior Work begins with removal of temporary window in fills on the 12 th ,13 th and 14 th floors. 5/2/2016 – Interior window blocking for trim starts. 5/5/2016 – Solid surface interior window trim template starts. 5 th floor project louvers installed B-wing. 5/11/2016 – Curtain Wall air and water testing to be performed 9/30/2016 – Contract Completion Date. Project Milestones VA Contracting Specialist Carol Domingue (603) 629-3287 Key Personnel Contractor Monument Construction LLC. Customer Building One – West Elevation of A,B, and C Wing VA Project Engineer Thomas Loos (857) 364-4014 Structural Steel 100% Complete JUL 15 MAY 15 SEP 15 JUN 15 OCT 15 SEP 15 JUN 16 MAR 16 AUG 16 JUN 16 SEP 16 JUN 16 Overall Construction 85% Complete CCD: SEP 30 NTP: MAR 14 Window/Curtain Wall 90% Complete Metal Panels 65% Complete Solid Surface 5% Complete Frame/Sheath 100% Complete Air Vapor Barrier 100% Complete

Transcript of Jamaica Plain Exterior Windows - Phase 2 - 5 MAY 2016

Page 1: Jamaica Plain Exterior Windows - Phase 2 - 5 MAY 2016

523-10-105Exterior Panel Replacement – Phase 2 – Jamaica Plain

Project OverviewReplace the exterior façade on the west elevation of Building One. This is a phased project. The scope of work encompasses the removal and replacement of the windows, new structural steel components, metal framing, sheathing, added insulation, floor line fire stopping, (18) three story curtain walls, and a metal panel rain screen system

Work includes, but is not limited to, general construction, selective demolition, specified abatement, structural steel, waterproofing, insulation, glazing, solid surface interior casing, painting, and certain other items.

End State: This elevation will have a new exterior façade and interior finishes to match existing.

Current Status: 5 May 2016• 5/11/16 - Mechanical louvers scheduled for delivery.• 5/4/2016 – Rain Screen Panels completed in Zone 5 and 6.• 5/4/2016 – Rain Screen Panels in progress in Zones 1A,3, and 4

protective film to be removed last.• 5/4/2016 – Vent window glazing complete in Zones 1A, 2,3,4 and 5.• 5/9/2016 – Vent window glazing starts in Zone 6.• 5/12/2016 – Mechanical louvers installation starts in Zone 6.• 4/25/2016 – Interior Work begins with removal of temporary window in

fills on the 12th,13th and 14th floors. • 5/2/2016 – Interior window blocking for trim starts.• 5/5/2016 – Solid surface interior window trim template starts. 5th floor

project louvers installed B-wing.• 5/11/2016 – Curtain Wall air and water testing to be performed• 9/30/2016 – Contract Completion Date.

Project Milestones

VA Contracting Specialist

Carol Domingue(603) 629-3287

Key Personnel

ContractorMonument Construction LLC.

CustomerBuilding One – West Elevation of A,B, and C Wing

VA Project Engineer

Thomas Loos(857) 364-4014

Structural Steel 100% Complete JUL 15MAY 15

SEP 15JUN 15

OCT 15SEP 15

JUN 16MAR 16

AUG 16JUN 16

SEP 16JUN 16

Overall Construction85% Complete

CCD: SEP 30NTP: MAR 14

Window/Curtain Wall 90% Complete

Metal Panels 65% Complete

Solid Surface 5% Complete

Frame/Sheath 100% Complete

Air Vapor Barrier 100% Complete