523-10-105Exterior Panel Replacement – Phase 2 – Jamaica Plain
Project OverviewReplace the exterior façade on the west elevation of Building One. This is a phased project. The scope of work encompasses the removal and replacement of the windows, new structural steel components, metal framing, sheathing, added insulation, floor line fire stopping, (18) three story curtain walls, and a metal panel rain screen system
Work includes, but is not limited to, general construction, selective demolition, specified abatement, structural steel, waterproofing, insulation, glazing, solid surface interior casing, painting, and certain other items.
End State: This elevation will have a new exterior façade and interior finishes to match existing.
Current Status: 5 May 2016• 5/11/16 - Mechanical louvers scheduled for delivery.• 5/4/2016 – Rain Screen Panels completed in Zone 5 and 6.• 5/4/2016 – Rain Screen Panels in progress in Zones 1A,3, and 4
protective film to be removed last.• 5/4/2016 – Vent window glazing complete in Zones 1A, 2,3,4 and 5.• 5/9/2016 – Vent window glazing starts in Zone 6.• 5/12/2016 – Mechanical louvers installation starts in Zone 6.• 4/25/2016 – Interior Work begins with removal of temporary window in
fills on the 12th,13th and 14th floors. • 5/2/2016 – Interior window blocking for trim starts.• 5/5/2016 – Solid surface interior window trim template starts. 5th floor
project louvers installed B-wing.• 5/11/2016 – Curtain Wall air and water testing to be performed• 9/30/2016 – Contract Completion Date.
Project Milestones
VA Contracting Specialist
Carol Domingue(603) 629-3287
Key Personnel
ContractorMonument Construction LLC.
CustomerBuilding One – West Elevation of A,B, and C Wing
VA Project Engineer
Thomas Loos(857) 364-4014
Structural Steel 100% Complete JUL 15MAY 15
SEP 15JUN 15
OCT 15SEP 15
JUN 16MAR 16
AUG 16JUN 16
SEP 16JUN 16
Overall Construction85% Complete
CCD: SEP 30NTP: MAR 14
Window/Curtain Wall 90% Complete
Metal Panels 65% Complete
Solid Surface 5% Complete
Frame/Sheath 100% Complete
Air Vapor Barrier 100% Complete