Seeking Council's authorization for acceptance of a low bid to replace 850’ of sewer main on 100 block of
Alamo Heights Blvd.
Presented By: Patrick SullivanPublic Works Director
Item #4City Council Meeting
October 24, 2016
![Page 2: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/2.jpg)
BACKGROUND
• On June 2, 2016, staff observed a sewer manhole overflowing at Corona and Alamo Heights Blvd
• Inspection revealed a section of sewer main in the 100 block of AH Blvd was impeded by root intrusion
• Due to the large amount of root growth the use of acid was declined
• The use of acid is a temporary fix for this type of problem; plus there is a concern for the health of the trees
![Page 3: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/3.jpg)
3
BACKGROUND Cont.
• The City’s engineering firm, Freese and Nichols Inc. secured contractors’ low bids for the purpose of rehabilitating the main through a process called “Pipe Bursting”. Fees for service were $20,195.
• Once the project is completed the current ten (10”) inch main will be “up sized” to a twelve (12”) inch seamless main. This process will eliminate root intrusion in the future.
![Page 4: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/4.jpg)
4
![Page 5: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/5.jpg)
5
![Page 6: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/6.jpg)
6
![Page 7: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/7.jpg)
7
![Page 8: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/8.jpg)
8
BACKGROUND Cont.
• Publication of bids were advertised in the San Antonio Express-News on Wednesday, September 14, 2016 and Wednesday, September 21, 2016. Bids closed on Friday, September 30, 2016.
• The City received bid submittals from five (5) contractors for this project.
Horseshoe Construction Inc. in the amount of $134,000PM Construction & Rehab LLC. in the amount of $129,575 T Construction LLC in the amount of $125,531Pronto Sand Blasting & Coating & Oilfield for $119,300Texas Pride Util it ies LLC. in the amount of $77,155
![Page 9: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/9.jpg)
9
SUMMARY
• Texas Pride Utilities LLC is the low bidder.
• Following a background search, Freese and Nichols recommended the contract be awarded to Texas Pride Utilities LLC.
![Page 10: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/10.jpg)
10
FISCAL IMPACT
• Contract cost is $77,155 with a ten percent (10%)contingency of $7,715 for a total not to exceed $84,870
![Page 11: Item #4 ppt ah sewer pipe bursting repair](https://reader031.fdocuments.us/reader031/viewer/2022030302/587ca1731a28ab356c8b4f99/html5/thumbnails/11.jpg)
11
Questions?