IT Project Management: Chapter 4 Resource Plan and Cost Estimation
-
Upload
zeeshan-bhatti -
Category
Documents
-
view
224 -
download
0
Transcript of IT Project Management: Chapter 4 Resource Plan and Cost Estimation
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
1/44
IT PROJECT MANAGEMENT Dr. Zeeshan Bhatti
MPhil (IT)
Chapter 4
BY: DR. ZEESHAN BHATTI 1Institute of Information and Communication TechnologyUniversity of Sindh, Jamshoro
Resource Plan and Cost Estimation
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
2/44
ShareLessonsLearned
EvaluateSuccess
ConductClose-OutMeeting
Roadmap to Project Management Success
FormProject
Team
Statementof WorkPurpose
Project Background
Project Deliverables
WorkBreakdownStructure
ResponsibilityMatrix
R A
A
S S
R
Network Gantt ResourcePlan
UpdatePlan
ResolveIssues
ManageChange
TrackProgress
PerformTasks
Budget
TIME
LEADERSHIP
COMMUNICATION
P R O J E C T
N O T
E B OOK
M E E
T I N G S
R E P O
R T S
L E S S
O N S L E A R N E D
PLAN
I M P L E
M E N
T
C L
O S E
- O U T
ResourcePlan
BY: DR. ZEESHAN BHATTI 2
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
3/44
ASSIGNING RESOURCES
A schedule is not complete until all the resources necessary to complete
the project have been committed or assigned.
BY: DR. ZEESHAN BHATTI 3
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
4/44
NON-LABOR RESOURCES
Lab time
Facilities
Prototype parts/systems
Equipment
Materials
BY: DR. ZEESHAN BHATTI 4
ShareLessonsLearned
EvaluateSuccess
ConductClose-OutMeeting
Roadmap to Project Management Success
FormProjectTeam
Statementof WorkPurpose
Project Background
Project Deliverables
WorkBreakdownStructure
ResponsibilityMatrix
R A
A
SS
R
Network Gantt ResourcePlan
UpdatePlan
ResolveIssues
ManageChange
TrackProgress
PerformTasks
Budget
TIME
LEADERSHIP
COMMUNICATION
P R
O J E C T
N O T
E B OOK
M E E
T I N
G S
R E P O R
T S
L E S S O N S
L E A R N E D
PLAN
I M P L E M
E N
T
C L O S E
- O U T
ResourcePlan
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
5/44
8– 5
WHERE WE ARE NOW
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
6/44
8– 6
THE RESOURCE PROBLEMResources and Priorities Project network times are not a schedule
until resources have been assigned.
The implicit assumption is that resources will be available in the required amounts when needed.
Adding new projects requires making realistic judgments of resource availability and project durations.
Cost estimates are not a budgetuntil they have been time-phased.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
7/448– 7
THE RESOURCE PROBLEM (CONT’D)
Resource Smoothing (or Leveling)
Involves attempting to even out varying demandson resources by using slack (delaying noncritical activities) to manage resource
utilization when resources are adequate over the life of the project.
Resource-Constrained Scheduling
The duration of a project may be increased by delaying the late start of some of itsactivities if resources are not adequate to meet peak demands.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
8/44
8– 8
TYPES OF PROJECT CONSTRAINTSTechnical or Logic Constraints Constraints related to the networked sequencein which project activities must occur.
Physical Constraints Activities that cannot occur in parallel or are affected by contractual or
environmental conditions.
Resource Constraints The absence, shortage, or unique interrelationship and interactioncharacteristics of resources that require a particular sequencing of projectactivities
Kinds of Resource Constraints People, materials, equipment
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
9/44
8– 9
CONSTRAINT EXAMPLES
FIGURE 8.2
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
10/44
8– 10
CLASSIFICATION OF A SCHEDULING
PROBLEMClassification of Problem Using a priority matrix will help determine if
the project is time or resource constrained.
Time-Constrained Project Must be completed by an imposed date.
Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule.
Resource-Constrained Project Is one in which the level of resources available cannot be exceeded.
Resources are fixed, time is flexible: inadequate resourceswill delay the project.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
11/44
8– 11
RESOURCE ALLOCATION METHODSLimiting Assumptions
Splitting activities is not allowed — once an activity is start, it is carried to completion.
Level of resources used for an activity cannot be changed.
Risk Assumptions
Activities with the most slack pose the least risk.
Reduction of flexibility does not increase risk. The nature of an activity (easy, complex) doesn’t increase risk.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
12/44
8– 12
RESOURCE ALLOCATION METHODS (CONT’D)Time-Constrained Projects
Must be completed by an imposed date.
Require use of leveling techniques that focuson balancing or smoothing resource demands.
Use positive slack (delaying noncritical activities) to manage resource utilization over theduration
of the project.
Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
13/44
8– 13
RESOURCE ALLOCATION METHODS (CONT’D)Resource Demand Leveling Techniques
for Time-Constrained Projects Advantages
Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
Disadvantages
Loss of flexibility that occurs from reducing slack.
Increases in the criticality of all activities.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
14/44
8– 14
RESOURCE ALLOCATION METHODS (CONT’D)Resource-Constrained Projects
Resources are limited in quantity or availability.
Activities are scheduled using heuristics(rules-of-thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
The parallel method is used to apply heuristics
An iterative process starting at the first time periodof the project and scheduling period-by-period the start of any activities using the three priority rules.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
15/44
ShareLessonsLearned
EvaluateSuccess
ConductClose-OutMeeting
Roadmap to Project Management Success
FormProject
Team
Statementof WorkPurpose
Project Background
Project Deliverables
WorkBreakdownStructure
ResponsibilityMatrix
R A
A
SS
R
Network Gantt ResourcePlan
UpdatePlan
ResolveIssues
ManageChange
TrackProgress
PerformTasks
LEADERSHIP
COMMUNICATION
Budget
TIME
P R O J E C T
N O T
E B OOK
M E E
T I N G S
R E P O R T S
L E S S
O N S L E A R N E D
PLAN
I M P L E
M E N
T
C L
O S E
- O U T
Budget
TIME
BY: D R. ZEE SHA N BHATT I 15
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
16/44
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
17/44
COST BUDGETING
Cost Budgeting involves allocating overall costestimates to individual work items in order to
establish a cost baseline for measuring projectperformance. Using cost estimates, the WBS, theproject schedule, and cost estimating tools, theproject team develops a time-phased budget.This budget will be used to measure and monitor
cost performance on the project.”
Source: PMI
BY: D R. ZEE SHA N BHATT I 17
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
18/44
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
19/44
WHY ESTIMATING TIME AND COST ARE IMPORTANT
5– 19
EXHIBIT 5.1
•
To support good decisions.• To schedule work.
• To determine how long the project should takeand its cost.
• To determine whether the project is worth doing.
• To develop cash flow needs.
• To determine how well the project is progressing.
• To develop time-phased budgets and establish theproject baseline.
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
20/44
FACTORS INFLUENCING THE QUALITY OF
ESTIMATES
5– 20
Quality of
Estimates
Project
Duration
People
Project Structure
and Organization
Padding
Estimates
Organization
Culture
Other
(Nonproject)
Factors
Planning Horizon
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
21/44
ESTIMATING GUIDELINES FOR TIMES,COSTS, AND RESOURCES
1. Have people familiar with the tasks make the estimate.
2. Use several people to make estimates.
3. Base estimates on normal conditions, efficient methods, and anormal level of resources.
4. Use consistent time units in estimating task times.
5. Treat each task as independent, don’t aggregate.
6. Don’t make allowances for contingencies.
7. Adding a risk assessment helps avoid surprisesto stakeholders.
5– 21BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
22/44
TOP-DOWN VERSUS BOTTOM-UP ESTIMATING
Top-Down Estimates
Are usually are derived from someone who uses experience and/or information todetermine the project duration and total cost.
Are made by top managers who have little knowledge of the processes used tocomplete the project.
Bottom-Up Approach
Can serve as a check on cost elements in the WBSby rolling up the work packages and associated cost accounts to major deliverables
at the work package level.
5– 22BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
23/44
TOP-DOWN VERSUS BOTTOM-UP
ESTIMATING
5– 23
TABLE 5.1
Conditions for Preferring Top-Down or Bottom-up Time andCost Estimates
Condit ion Macro Estimates Micro Estimates
Strategic decision making X
Cost and time important X
High uncertainty X
Internal, small project X
Fixed-price contract X
Customer wants details XUnstable scope X
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
24/44
ESTIMATING PROJECTS: PREFERRED
APPROACHMake rough top-down estimates.Develop the WBS/OBS.
Make bottom-up estimates.
Develop schedules and budgets.Reconcile differences between top-downand bottom-up estimates
5– 24BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
25/44
TOP-DOWN APPROACHES FOR ESTIMATINGPROJECT TIMES AND COSTS
Consensus methods
Ratio methods
Apportion method
Function point methods for software and systemprojects
Learning curves
5– 25
Project Estimate
Times
Costs
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
26/44
APPORTION METHOD OF ALLOCATING PROJECT COSTS USING THEWORK BREAKDOWN STRUCTURE
5– 26
FIGURE 5.1
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
27/44
SIMPLIFIED BASIC FUNCTION POINT COUNT PROCESSFOR A PROSPECTIVE PROJECT OR DELIVERABLE
5– 27
TABLE 5.2
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
28/44
EXAMPLE: FUNCTION POINT COUNT METHOD
5– 28
TABLE 5.3
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
29/44
BOTTOM-UP APPROACHES FOR ESTIMATINGPROJECT TIMES AND COSTS
Template methods
Parametric procedures applied to specifictasks
Range estimates forthe WBS work packages
Phase estimating: A hybrid
5– 29BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
30/44
SUPPORT COST ESTIMATE WORKSHEET
5– 30
FIGURE 5.2
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
31/44
PHASE ESTIMATING OVER PRODUCT LIFE CYCLE
5– 31
FIGURE 5.3
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
32/44
TOP-DOWN AND BOTTOM-UP ESTIMATES
5– 32
FIGURE 5.4
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
33/44
LEVEL OF DETAIL
Level of detail is different for
different levels of management.
Level of detail in the WBS varieswith the complexity of the project.
Excessive detail is costly.
Fosters a focus on departmental outcomes
Creates unproductive paperwork
Insufficient detail is costly.
Lack of focus on goals
Wasted effort on nonessential activities
5– 33BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
34/44
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
35/44
CONTRACT BID SUMMARY COSTS
5– 35
FIGURE 5.5
Direct costs $80,000
Direct overhead $20,000
Total direct costs $100,000
G&A overhead (20%) $20,000Total costs $120,000
Profit (20%) $24,000
Total bid $144,000
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
36/44
THREE VIEWS OF COST
5– 36
FIGURE 5.6
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
37/44
REFINING ESTIMATES
Reasons for Adjusting Estimates
Interaction costs are hidden in estimates.
Normal conditions do not apply.
Things go wrong on projects.
Changes in project scope and plans.
Adjusting Estimates
Time and cost estimates of specific activities are adjusted as the risks, resources, and
situation particulars become more clearly defined.
5– 37BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
38/44
CREATING A DATABASE FOR ESTIMATING
5– 38
FIGURE 5.7
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
39/44
KEY TERMS
5– 39
Apportionment methods
Bottom-up estimates
Contingency funds
Delphi method
Direct costs
Function points
Learning curves
Overhead costs
Padding estimates
Phase estimating
Range estimating
Ratio methods
Template method
Time and cost databases
BY: DR. ZEESHAN BHATTI
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
40/44
WBS FIGURE
5– 40
TABLE 5.4
BY: DR. ZEESHAN BHATTI
Roadmap to Project Management Success
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
41/44
ShareLessonsLearned
EvaluateSuccess
ConductClose-OutMeeting
Roadmap to Project Management Success
FormProjectTeam
Statementof WorkPurpose
Project Background
Project Deliverables
WorkBreakdownStructure
ResponsibilityMatrix
R A
A
SS
R
Network Gantt ResourcePlan
UpdatePlan
ResolveIssues
ManageChange
TrackProgress
PerformTasks
Budget
TIME
LEADERSHIP
COMMUNICATION
P R O J E C
T N O T
E B OOK
M E E
T I N
G S
R E P O R T S
L E S S O
N S L E A R N E D
PLAN
I M P L E
M E N
T
C L O S E
- O U T
BY: D R. ZEE SHA N BHATT I 41
Roadmap to Project Management Success
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
42/44
ShareLessonsLearned
EvaluateSuccess
ConductClose-OutMeeting
Roadmap to Project Management Success
FormProjectTeam
Statementof Work
ResponsibilityMatrix
Purpose
Project Background
Project Deliverables
WorkBreakdownStructure
R A
A
SS
R
Network Gantt BudgetResourcePlan
UpdatePlan
ResolveIssues
ManageChange
TrackProgress
PerformTasks
LEADERSHIP
COMMUNICATION
TIME
P R O J E C
T N O T
E B OOK
M E E
T I N
G S
R E P O R T S
L E S S O
N S L E A R N E D
PLAN
I M P L E
M E N
T
C L O S E
- O U T
BY: D R. ZEE SHA N BHATT I 42
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
43/44
REFERRED NOTESA Short Course in ProjectManagement, by Nayda G.Santiago
BY: D R. ZEE SHA N BHATT I 43
REFERRED BOOK
-
8/18/2019 IT Project Management: Chapter 4 Resource Plan and Cost Estimation
44/44
THANKYOU
Q & A
For Course Slides and Handouts
Blog:http://zeeshanacademy.blogspot.com/
Facebook:
https://www.facebook.com/drzeeshanacademy
http://zeeshanacademy.blogspot.com/http://zeeshanacademy.blogspot.com/