IT Milestone Report · 2019. 12. 11. · IT Milestone Report ... Requirements Plan 11/9/2012...

17
C-20 4/3/19 IT Milestone Report Contract in Effect <12 months Contract Complete-Final Report Progress Report as of: 9/30/19 Agency Number: 478 Agency Name: Healthcare and Family Services Report Date: 9/30/19 Contract Number: 13DP000002 Contract Term: 10/17/12 – 10/15/20 Vendor Name: Deloitte Consulting Total Contract Amount: $271,996,911.49 Conflict of Interest Disclosures for all Involved Individuals? Yes No If no, attach explanation. Business Enterprise Program (BEP) Goal? Yes No If no, attach explanation. Description of Milestone/Deliverable Due Date Actual Completion Date Projected Completion Date Comments – Required if Due Date Was Not Met Statement of Work 1 Change Requests Log 11/2/2012 10/31/2012 Deliverables Log 10/31/2012 10/31/2012 Master Plan 10/26/2012 10/31/2012 L Project Management Plan 11/13/2012 11/28/2012 An extension was granted. Quality Management Plan 11/8/2012 11/9/2012 Work Plan 11/7/2012 11/16/2012 Monthly Status Report 1 (SOW1-2012) 11/21/2012 11/21/2012 Communications Approach 12/6/2012 12/6/2012 Organization Transition Approach 12/6/2012 12/6/2012 Organizational Change Management Strategy 12/6/2012 12/6/2012 Stakeholder Engagement Approach 12/6/2012 12/6/2012 To-Be Business Models 12/6/2012 12/6/2012 To-Be Business Models (UPDATE 1) 4/16/2013 4/16/2013 Configuration Management Plan 12/7/2012 12/7/2012 Requirements Plan 11/9/2012 11/28/2012 An extension was granted. Fit/Gap Analysis 11/19/2012 11/29/2012 An extension was granted. Monthly Status Report 2 (SOW1-2012) 11/30/2012 11/29/2012 Solution Specification (Interface Plan) 1/29/2013 12/20/2012 Construction and Configuration Status Report @20% 3/22/2013 3/22/2013

Transcript of IT Milestone Report · 2019. 12. 11. · IT Milestone Report ... Requirements Plan 11/9/2012...

  • C-20 4/3/19

    IT Milestone Report Contract in Effect

  • Monthly Status Report 3 (SOW1-2012) 12/28/2012 12/28/2012

    Technical Architecture Specification 1/21/2013 1/22/2013

    Construction and Configuration Status Report @40%

    3/29/2013 3/29/2013

    Data Conversion Approach (SI) 4/12/2013 1/29/2013

    Data Conversion Specification 4/12/2013 5/31/2013 L

    Data Conversion Test Plan 4/12/2013 6/18/2013 L

    Rule Set Specification 3/18/2013 7/19/2013 L

    Software Requirements Specification (SRS)

    8/6/2013 8/9/2013 An extension was granted.

    User Interface Specification 3/18/2013 7/19/2013 L

    Interface Design (Specification) 3/18/2013 7/19/2013 L

    Security Test Plan 4/12/2013 2/15/2013

    System Security Plan 4/12/2013 2/19/2013

    Monthly Status Report 4 (SOW1-2012) 1/31/2013 1/31/2013

    Integration Test Plan 4/12/2013 6/21/2013 L

    Performance Test Plan 3/29/2013 3/29/2013

    System Test Plan 4/9/2013 7/12/2013 L

    Test Approach 3/19/2013 3/29/2013 L

    Integration Test Data Plan 4/12/2013 6/21/2013 L

    System Test Data Plan 4/12/2013 7/24/2013 L

    Test Strategy 3/8/2013 3/22/2013 An extension was granted.

    User Acceptance Test Plan 8/30/2013 9/13/2013 L

    Construction and Configuration Status Report @60%

    4/11/2013 4/11/2013

    End-User Training Approach 1/31/2013 2/1/2013

    End-User Training Curriculum 1/31/2013 2/1/2013

    Monthly Status Report 5 (SOW1-2013) 2/28/2013 2/28/2013

    Construction and Configuration Status Report @80%

    5/2/2013 5/2/2013

    Monthly Status Report 6 (SOW1-2013) 3/29/2013 3/29/2013

    Construction and Configuration Status Report @100%

    7/31/2013 7/31/2013

    Monthly Status Report 7 (SOW1-2013) 4/30/2013 4/30/2013

    End of Test Phase Report (QA) 8/6/2013 8/16/2013 L

  • End of Test Phase Report (Unit) 8/6/2013 8/15/2013 L

    Monthly Status Report 8 (SOW1-2013) 5/31/2013 5/31/2013

    Communications Plan 2/15/2013 2/15/2013

    Monthly Status Report 9 (SOW1-2013) 6/28/2013 6/28/2013

    Monthly Status Report 10 (SOW1-2013) 7/31/2013 7/31/2013

    Monthly Status Report 11 (SOW1-2013) 8/30/2013 8/30/2013

    End of Test Phase Report (Data Conversion 1)

    11/1/2013 11/5/2013 L

    End of Test Phase Report (Security) 11/19/2013 11/20/2013

    Production Deployment Plan 6/28/2013 6/28/2013

    Production Support Plan 9/27/2013 9/27/2013

    End of Test Phase Report (UAT) 3/24/2014 3/24/2014

    Monthly Status Report 12 (SOW1-2013) 9/30/2013 9/30/2013

    Production Status Report (1.0) 12/11/2013 10/11/2013

    Production Status Report (1.2) 2/25/2014 2/28/2014 An extension was granted.

    Go-Live Transition Guides 6/7/2013 6/21/2013 L

    Project Team Capability Transfer Approach

    2/28/2014 2/28/2014

    System Run Book 2/7/2014 2/7/2014

    End-User Training Evaluation Report 11/15/2013 11/18/2013 L

    Instructor-Led Training Courseware 6/28/2013 6/21/2013

    Web-Based Training Courseware 6/28/2013 6/18/2013

    Instructor-Led Training Courseware (UPDATE)

    12/6/2013 11/15/2013

    Monthly Maintenance, Enhancement, and Operations Report – October 2013

    1/27/2014 1/27/2014

    Monthly Status Report 13 (SOW1-2013) 10/31/2013 10/31/2013

    Monthly Maintenance, Enhancement, and Operations Report – November 2013

    1/27/2014 1/27/2014

    Monthly Status Report 14 (SOW1-2013) 11/29/2013 11/27/2013

    Monthly Maintenance, Enhancement, and Operations Report – December 2013

    1/27/2014 1/27/2014

  • Monthly Maintenance, Enhancement, and Operations Report – January 2014

    2/7/2014 2/7/2014

    Monthly Maintenance, Enhancement, and Operations Report – February 2014

    3/7/2014 3/7/2014

    Monthly Maintenance, Enhancement, and Operations Report – March 2014

    4/8/2014 4/8/2014

    Monthly Maintenance, Enhancement, and Operations Report – April 2014

    5/13/2014 5/13/2014

    Monthly Maintenance, Enhancement, and Operations Report – May 2014

    6/6/2014 6/6/2014

    Monthly Maintenance, Enhancement, and Operations Report – June 2014

    7/8/2014 7/9/2014

    Monthly Maintenance, Enhancement, and Operations Report – July 2014

    8/8/2014 8/8/2014

    Monthly Maintenance, Enhancement, and Operations Report – August 2014

    9/5/2014 9/5/2014

    Monthly Maintenance, Enhancement, and Operations Report – September 2014

    10/7/2014 10/7/2014

    Construction and Configuration Status Report @100% - B

    4/11/2014 4/11/2014

    End of Test Phase Report (Unit Testing) - B

    4/23/2014 4/23/2014

    End of Test Phase Report UAT- B 4/30/2014 4/30/2014

    Production Status Report - B 4/4/2014 4/7/2014 L

    Production Status Report - B1 4/30/2014 4/30/2014

    End User Training Evaluation Report - B 4/30/2014 4/30/2014

    Instructor Lead Training Courseware - B 4/30/2014 4/30/2014

    Computer Based Training Courseware - B

    4/30/2014 4/30/2014

    Monthly Status Report 15 (SOW1-2013) 12/30/2013 1/3/2014 L

    Monthly Status Report 16 (SOW1-2013) 1/31/2014 1/31/2014

    Monthly Status Report 17 (SOW1-2014) 2/28/2014 2/28/2014

    Monthly Status Report 18 (SOW1-2014) 3/31/2014 3/28/2014

    Statement of Work 2

    Monthly Status Report - April 2014 5/6/2014 5/6/2014

  • Monthly Status Report - May 2014 6/10/2014 6/10/2014

    Monthly Status Report - June 2014 7/8/2014 7/8/2014

    Monthly Status Report - July 2014 8/8/2014 8/8/2014

    Monthly Status Report - August 2014 9/5/2014 9/5/2014

    Monthly Status Report - September 2014

    10/7/2014 10/7/2014

    Monthly Status Report - October 2014 11/7/2014 11/7/2014

    Monthly Status Report - November 2014

    12/9/2014 12/9/2014

    Monthly Status Report - December 2014

    1/6/2015 1/6/2015

    Monthly Status Report - January 2015 2/10/2015 2/10/2015

    Monthly Status Report - February 2015 3/10/2015 3/10/2015

    Monthly Status Report - March 2015 4/7/2015 4/7/2015

    Monthly Status Report - April 2015 5/8/2015 5/8/2015

    Monthly Status Report - May 2015 6/9/2015 6/9/2015

    Monthly Status Report - June 2015 7/7/2015 7/7/2015

    Monthly Status Report - July 2015 8/12/2015 8/12/2015

    Monthly Status Report - August 2015 9/8/2015 9/8/2015

    UPDATED Work Plan 5/16/2014 5/16/2014

    UPDATED Project Management Plan 5/9/2014 5/9/2014

    Deliverables Log 5/6/2014 5/6/2014

    Fit/Gap Analysis 5/23/2014 5/23/2014

    UPDATED Configuration Management Plan

    * 7/21/2014

    Interface Plan 9/12/2014 9/13/2014

    Software Requirements Specification 10/10/2014 10/10/2014

    User Interface Specification 10/10/2014 10/10/2014

    Rule Set Specification 10/10/2014 10/10/2014

    Interface Specification 10/10/2014 10/10/2014

    UPDATED Technical Architecture Specification

    9/26/2014 9/26/2014

    UPDATED Data Conversion Approach 8/1/2014 8/1/2014

    UPDATED Data Conversion Specification 9/30/2014 9/30/2014

    UPDATED Data Conversion Specification 9/30/2014 9/30/2014

  • UPDATED Data Conversion Test Plan 12/2/2014 12/2/2014

    UPDATED Security Test Plan 9/26/2014 9/26/2014

    Construction and Configuration Status Report @20%

    11/18/2014 11/18/2014

    Construction and Configuration Status Report @40%

    12/19/2014 12/19/2014

    Construction and Configuration Status Report @60%

    1/13/2015 1/13/2015

    Construction and Configuration Status Report @80%

    2/13/2015 2/13/2015

    Construction and Configuration Status Report @100%

    3/10/2015 3/10/2015

    Final Construction and Configuration State Report @ 100%

    3/10/2015 3/10/2015

    Final Construction and Configuration State Report @ 100%

    3/10/2015 3/10/2015

    End of Test Phase Report (Unit Testing) 3/24/2015 3/24/2015

    End of Test Phase Report (Unit Testing) 2nd Submission

    3/24/2015 3/24/2015

    Test Approach 12/2/2014 12/2/2014

    System Test Plan 1/16/2015 1/16/2015

    Performance Test Plan 3/27/2015 3/27/2015

    End of Test Phase Report for System Testing (2nd Submission)

    9/9/2015 9/9/2015

    Go Live Readiness Guide 2/17/2015 2/17/2015

    End of Test Phase Report (UAT) (2nd Submission)

    9/6/2016 7/15/2016

    Production Deployment Plan (2nd resubmission)

    6/23/2016 4/29/2016

    Production Support Plan 8/14/2015 8/14/2015

    End User Training Approach 11/25/2014 11/25/2014

    End User Training Curriculum 11/25/2014 11/25/2014

    UPDATE Training Courseware - Wave 2 10/1/2015 1/6/2017 Phase 2 Go-Live delay.

    UPDATE Training Courseware - Wave 3 10/1/2015 1/27/2017 Phase 2 Go-Live delay.

    UPDATE Training Courseware - Wave 1 10/1/2015 12/9/2016 Phase 2 Go-Live delay.

  • Project Team Capability Transfer Plan (5th submission)

    6/2/2015 9/13/2016 Phase 2 Go-Live delay.

    Go-Live Transition Guides (2058A) 2/3/2015 6/30/2015 Phase 2 Go-Live delay.

    System Run Book (4th submission) 9/26/2016 6/17/2016

    Monthly Maintenance, Enhancement, and Operations Report - January 2015

    2/10/2015 2/10/2015

    Monthly Maintenance, Enhancement, and Operations Report - February 2015

    3/10/2015 3/10/2015

    Monthly Maintenance, Enhancement, and Operations Report - March 2015

    4/7/2015 4/7/2015

    Monthly Maintenance, Enhancement, and Operations Report - April 2015

    5/8/2015 5/8/2015

    Monthly Maintenance, Enhancement, and Operations Report - May 2015

    6/9/2015 6/9/2015

    Monthly Maintenance, Enhancement, and Operations Report - May 2015 Addendum

    6/9/2015 6/9/2015

    Monthly Maintenance, Enhancement, and Operations Report - June 2015

    7/7/2015 7/7/2015

    Monthly Maintenance, Enhancement, and Operations Report - July 2015

    8/7/2015 8/7/2015

    Monthly Maintenance, Enhancement, and Operations Report - August 2015

    9/8/2015 9/8/2015

    Monthly Maintenance, Enhancement, and Operations Report - September 2015

    10/9/2015 10/9/2015

    Monthly Maintenance, Enhancement, and Operations Report - October 2015 (Addendum)

    11/12/2015 11/12/2015

    Monthly Maintenance, Enhancement, and Operations Report - November 2015

    12/8/2015 12/8/2015

    Monthly Maintenance, Enhancement, and Operations Report - December 2015

    1/8/2016 1/9/2016

  • Monthly Maintenance, Enhancement, and Operations Report - January 2016

    2/9/2016 2/9/2016

    Monthly Maintenance, Enhancement, and Operations Report - February 2016

    3/8/2016 3/8/2016

    Monthly Maintenance, Enhancement, and Operations Report - March 2016

    4/8/2016 4/8/2016

    Monthly Maintenance, Enhancement, and Operations Report - April 2016

    5/6/2016 5/6/2016

    Monthly Maintenance, Enhancement, and Operations Report - May 2016

    6/7/2016 6/7/2016

    Monthly Maintenance, Enhancement, and Operations Report - June 2016

    7/8/2016 7/8/2016

    Monthly Maintenance, Enhancement, and Operations Report - July 2016

    8/9/2016 8/9/2016

    Monthly Maintenance, Enhancement, and Operations Report - August 2016

    9/9/2016 9/9/2016

    Monthly Maintenance, Enhancement, and Operations Report - September 2016

    10/7/2016 10/7/2016

    Monthly Maintenance, Enhancement, and Operations Report - October 2016

    11/8/2016 11/9/2016

    Monthly Maintenance, Enhancement, and Operations Report - November 2016

    12/6/2016 12/6/2016

    Monthly Maintenance, Enhancement, and Operations Report - December 2016

    1/10/2017 1/10/2017

    Monthly Maintenance, Enhancement, and Operations Report - January 2017

    2/7/2017 2/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - February 2017

    3/7/2017 3/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - March 2017

    4/7/2017 4/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - April 2017

    5/9/2017 5/9/2017

  • ABE Usability Production Status Report - #1

    12/19/2014 12/19/2014

    ABE Usability Production Status Report - #2

    *

    3/27/2015

    ABE Usability Production Status Report - #3

    * 5/29/2015

    Task Based Production Status Report * 11/14/2014

    WVS System Requirements Specification

    * 2/13/2015

    WVS User Interface Specification * 2/13/2015

    WVS Data Conversion Approach / Specification

    * 3/13/2015

    WVS System Test Plan * 5/8/2015

    WVS Construction and Configuration Report 50%

    * 5/8/2015

    WVS Construction and Configuration Report 100%

    * 6/23/2015

    WVS System Test Results * 12/17/2015

    WVS Conversion Test Results * 8/21/2015

    WVS Instructor Led Training (ILT) Courseware (2nd Submission)

    * 3/29/2016

    WVS Training Evaluation Report * 7/15/2016

    TO#13 Software Requirements Specification

    * 1/16/2015

    TO#13 User Interface Specification * 1/16/2015

    TO#13 Interface Specification * 1/16/2015

    TO#13 Interface Plan * 1/30/2015

    TO#13 Construction and Configuration Report 50%

    * 4/3/2015

    TO#13 Construction and Configuration Report 100%

    * 5/29/2015

    TO #13 System Test Results * 7/31/2015

    TO#13 System Run Book * 3/24/2015

    LTSS User Interface Specification * 3/27/2015

    March Quality Review Report (1st resubmission)

    4/21/2016 5/5/2016 L

  • Group 1 Design Specifications (3rd Submisison)

    4/29/2016 5/6/2016 L

    Group 1 Software Requirements Specifications (4th submission)

    4/29/2016 5/6/2016 L

    Group 1 Configuration & Construction Status Report @ 100% (1st resubmission)

    5/6/2016 5/6/2016

    Group 1 End of Test Phase Report (Unit Testing) (1st resubmission)

    5/6/2016 5/6/2016

    Group 1 End of Test Phase Report (System Testing) (1st resubmission)

    5/13/2016 5/13/2016

    UPDATED Quality Management Plan (2nd resubmission)

    5/6/2016 5/6/2016

    Security Software Requirements Specifications (1st resubmission)

    4/29/2016 5/6/2016 L

    Interim Quality Review Report #1 (4th resubmission)

    7/11/2016 9/9/2016 L

    Preliminary System Security Plan (Part A)

    7/11/2016 9/9/2016 L

    Interim Quality Review Report #2 (3rd submission)

    7/11/2016 9/9/2016 L

    Preliminary System Security Plan (Part B)

    7/11/2016 9/9/2016 L

    Final System Security Plan (Part A) 7/20/2016 10/4/2016 L

    System Quality Target Report #1 (1st resubmission)

    7/20/2016 10/4/2016 L

    Final System Security Plan (Part B) 7/20/2016 10/4/2016 L

    System Quality Target Report #2 (3rd Submission)

    6/21/2016 6/21/2016

    Interim Quality Review Report #3 (4th submission)

    7/1/2016 6/24/2016

    Interim Quality Review Report #3 (4th submission)

    7/1/2016 6/24/2016

    Individual Match Target #1 (1st resubmission)

    5/3/2016 5/3/2016

    Benefit Match Target #1 6/21/2016 6/29/2016 L

  • System Observation Sessions Report 8/3/2015 6/27/2016 L

    Additional Training Final Progress Report

    1/13/2017 1/13/2017

    Additional Webinars Courseware 2/7/2017 2/7/2017

    Practice Environment Final Report 1/10/2017 1/10/2017

    Mid-Point Onsite Support Report - 50% (Part A)

    1/13/2017 1/13/2017

    Final Onsite Support Report - 100% (Part A)

    1/20/2017 1/20/2017

    Group 4 Design Specification 1/24/2017 1/24/2017

    Group 4 End of Test Phase Report (System Testing)

    3/31/2017 3/31/2017

    Mid-Point Onsite Support Report - 50% (Part B)

    2/14/2017 2/14/2017

    Final Onsite Support Report - 100% (Part B)

    4/11/2017 4/11/2017

    Mid-Point Onsite Support Report - 50% 5/26/2017 5/26/2017

    Train-the-Trainer Approach 5/5/2017 5/5/2017

    Wave 1 ILT Training Courseware & Web-Based Training Courseware

    * 6/5/2015

    Wave 3 ILT Training Courseware & Web-Based Training Courseware

    * 6/19/2015

    Wave 3 - ILT Training Courseware & Web-Based Training Courseware

    * 4/8/2016

    End User Training Evaluation Report - 50% (1st resubmission)

    7/11/2016 6/28/2016

    End User Training Evaluation Report - 100% (2nd Submission)

    9/16/2016 6/21/2016

    Operational Support Items Production Deployment Report

    * 6/16/2016

    UPDATES Go-Live Transition Guides (1st resubmission)

    * 6/16/2016

    Monthly Maintenance, Enhancement, and Operations Report - July 2014

    * 8/8/2014

    Monthly Maintenance, Enhancement, and Operations Report - August 2014

    * 9/5/2014

  • Monthly Maintenance, Enhancement, and Operations Report - September 2014

    * 10/7/2014

    Monthly Maintenance, Enhancement, and Operations Report - October 2014

    * 11/7/2014

    Monthly Maintenance, Enhancement, and Operations Report - November 2014

    * 12/5/2014

    Monthly Maintenance, Enhancement, and Operations Report - December 2014

    * 1/9/2015

    Maintenance, Enhancement, and Operations Report - May 2014

    * 6/6/2014

    Monthly Maintenance, Enhancement, and Operations Report - June 2014

    * 7/8/2014

    End of Test Phase Report (Data Conversion 1)

    10/13/2017 9/20/2016

    End of Test Phase Report (Security) 9/29/2017 9/20/2016

    Production Status Report – October 2017

    10/6/2017 10/16/2017 L

    End of Test Phase Report (Data Conversion 2)

    11/14/2017 11/7/2017

    Operational Support Items Production Deployment Report

    6/5/2014 6/5/2014

    Monthly Maintenance, Enhancement, and Operations Report - May 2017

    6/7/2017 6/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - May 2017

    6/7/2017 6/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - June 2017

    7/7/2017 7/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - June 2017

    7/7/2017 7/7/2017

    Monthly Maintenance, Enhancement, and Operations Report - July 2017

    8/8/2017 8/8/2017

    Monthly Maintenance, Enhancement, and Operations Report - July 2017

    8/8/2017 8/8/2017

  • Monthly Maintenance, Enhancement, and Operations Report - August 2017

    9/8/2017 9/8/2017

    Monthly Maintenance, Enhancement, and Operations Report - August 2017

    9/8/2017 9/8/2017

    Monthly Maintenance, Enhancement, and Operations Report - September 2017

    10/6/2017 10/6/2017

    Monthly Maintenance, Enhancement, and Operations Report - September 2017

    10/6/2017 10/6/2017

    Monthly Maintenance, Enhancement, and Operations Report - October 2017

    10/12/2017 10/12/2017

    Monthly Maintenance, Enhancement, and Operations Report - October 2017

    10/12/2017 10/12/2017

    ABE Mobile Software Requirements Specification

    3/30/2018 5/3/2016

    TO 13 Production Status Report 10/6/2017 10/6/2017

    System Quality Target Report #4 10/1/2018 10/1/2018

    Benefit Match Target Report #2 11/7/2017 11/6/2017

    Individual Match Target Report #2 11/7/2017 11/6/2017

    Group 1 Production Status Report 11/10/2017 11/6/2017

    TIER 1 Spring 2018 End of Design 10/23/2018 10/16/2018

    TIER 1 Spring 2018 End of System Test 2/15/2019 10/16/2018

    TIER 1 Spring 2018 End of User Acceptance Test

    2/15/2019 10/16/2018

    TIER 1 Summer 2018 End of Design 2/15/2019 11/16/2018

    TIER 1 Summer 2018 End of System Test

    3/15/2019 1/29/2019

    TIER 1 Summer 2018 End of User Acceptance Test

    1/31/2020

    TIER 1 Fall 2018 End of Design 5/7/2019 3/22/2019

    TIER 1 Fall 2018 End of System Test 9/6/2019 9/6/2019

    TIER 1 Fall 2018 End of User Acceptance Test

    6/30/2020

    IES Phase 2 Deployment Report 10/31/2017 1/23/2018 L

  • Additional Training Final Progress Report

    7/14/2017 7/14/2017

    Practice Environment Final Report 7/14/2017 7/14/2017

    Final Onsite Support - 100% 7/14/2017 7/14/2017

    (Batch Thresholds) Design Specifications

    10/27/2017 10/20/2017

    (Batch Thresholds) Configuration & Construction Status Report at 100%

    10/31/2017 10/20/2017

    (Batch Thresholds) End of Test Phase Report (System Testing)

    11/3/2017 10/20/2017

    (Batch Thresholds) End of Test Phase Report (the UAT environment)

    11/7/2017 10/20/2017

    (Enhancement Requests) Configuration & Construction Status Report at 100%

    11/3/2017 10/20/2017

    (Enhancement Requests) End of Test Phase Report (System Testing)

    11/7/2017 10/20/2017

    (Enhancement Requests) End of Test Phase Report (UAT)

    11/14/2017 10/20/2017

    Mid-Point Training Report – 50% 10/27/2017 10/24/2017

    Final Training Report – 100% 10/31/2017 11/1/2017

    Training Overview and Schedule 10/27/2017 10/20/2017

    Mid-Point Facilitated Practice Report - 50% (Pre-Go Live (7/1/17-10/23/17) Mid-Point Onsite Support Report – 50%)

    10/27/2017 10/24/2017

    Facilitated Practice Report 100 / Final Pre-Go Live (7/1/17-10/23/17) Onsite Support Report – 100%

    1/9/2017 11/1/2017 L

    End User Support Plan 10/27/2017 10/20/2017

    Mid-Point Onsite Support Report – 50% (post- Go–Live, 10/24/17-3/16/18)

    1/9/2018 2/6/2018 L

    Final Onsite Support Report – 100% (post- Go–Live, 10/24/17-3/16/18)

    3/27/2018 3/27/2018

    Temporary Operational Support Items Production Development Report

    11/3/2017 10/20/2017

  • IES Go-Live Progress Checkpoint #1 Report

    11/3/2017 10/20/2017

    IES Go-Live Progress Checkpoint #2 Report

    11/7/2017 10/20/2017

    IES Go-Live Progress Checkpoint #3 Report

    11/14/2017 10/18/2017

    Benefit Management Functional Design 7/11/2017 7/11/2017

    Benefit Management Technical Design 9/26/2017 9/26/2017

    Support of Online Testing Effort Report 10/31/2017 10/31/2017

    Post-Batch Remediation Performance Testing Completion Report

    10/31/2017 10/31/2017

    SMA OpCon Batch Job Scheduler Installation

    3/20/2018 3/20/2018

    SAP Business Objects Installation 3/16/2018 3/16/2018

    Mock Run Completion Report 10/31/2017 10/31/2017

    Quality Metrics Baseline Report * 6/23/2017

    Monthly Maintenance, Enhancement, and Operations Report - October 16, 2017 through October 31, 2017

    12/8/2017 12/8/2017

    Monthly Maintenance, Enhancement, and Operations Report - November 2017

    12/15/2017 12/15/2017

    Monthly Maintenance, Enhancement, and Operations Report - December 2017

    1/16/2018 1/16/2018

    Monthly Maintenance, Enhancement, and Operations Report - January 2018

    2/16/2018 2/16/2018

    Monthly Maintenance, Enhancement, and Operations Report - February 2018

    3/16/2018 3/16/2018

    Monthly Maintenance, Enhancement, and Operations Report - March 2018

    4/13/2018 4/13/2018

    Monthly Maintenance, Enhancement, and Operations Report - April 2018

    5/15/2018 5/15/2018

    Monthly Maintenance, Enhancement, and Operations Report - May 2018

    6/15/2018 6/15/2018

  • Monthly Maintenance, Enhancement, and Operations Report - June 2018

    7/13/2018 7/13/2018

    Monthly Maintenance, Enhancement, and Operations Report - July 2018

    8/14/2018 8/14/2018

    Monthly Maintenance, Enhancement, and Operations Report - August 2018

    9/14/2018 9/14/2018

    Monthly Maintenance, Enhancement, and Operations Report - September 2018

    10/16/2018 10/16/2018

    Monthly Maintenance, Enhancement, and Operations Report - October 2018

    11/13/2018 11/13/2018

    Monthly Maintenance, Enhancement, and Operations Report - November 2018

    12/14/2018 12/14/2018

    Monthly Maintenance, Enhancement, and Operations Report - December 2018

    1/15/2019 1/15/2019

    Monthly Maintenance, Enhancement, and Operations Report - January 2019

    2/15/2019 2/15/2019

    Monthly Maintenance, Enhancement, and Operations Report - February 2019

    3/15/2019 3/15/2019

    Monthly Maintenance, Enhancement, and Operations Report - March 2019

    4/16/2019 4/16/2019

    Monthly Maintenance, Enhancement, and Operations Report - April 2019

    5/14/2019 5/14/2019

    Monthly Maintenance, Enhancement, and Operations Report - May 2019

    6/14/2019 6/14/2019

    Monthly Maintenance, Enhancement, and Operations Report - June 2019

    7/16/2019 7/16/2019

    Monthly Maintenance, Enhancement, and Operations Report - July 2019

    8/16/2019 8/16/2019

    Monthly Maintenance, Enhancement, and Operations Report - August 2019

    9/17/2019 9/17/2019

    Monthly Maintenance, Enhancement, and Operations Report - September 2019

    10/15/2019 10/15/2019

  • Monthly Maintenance, Enhancement, and Operations Report - October 2019

    11/19/2019 11/15/2019

    Monthly Maintenance, Enhancement, and Operations Report - November 2019

    12/17/2019

    Monthly Maintenance, Enhancement, and Operations Report - December 2019

    1/14/2020

    Monthly Maintenance, Enhancement, and Operations Report - January 2020

    2/14/2020

    Monthly Maintenance, Enhancement, and Operations Report - February 2020

    3/13/2020

    Monthly Maintenance, Enhancement, and Operations Report - March 2020

    4/14/2020

    Monthly Maintenance, Enhancement, and Operations Report - April 2020

    5/15/2020

    Monthly Maintenance, Enhancement, and Operations Report - May 2020

    6/16/2020

    Monthly Maintenance, Enhancement, and Operations Report - June 2020

    7/14/2020

    Monthly Maintenance, Enhancement, and Operations Report - July 2020

    8/14/2020

    Monthly Maintenance, Enhancement, and Operations Report - August 2020

    9/15/2020

    Monthly Maintenance, Enhancement, and Operations Report - September 2020

    10/16/2020

    Monthly Maintenance, Enhancement, and Operations Report - October 2020

    11/13/2020

    Note – Actual completion date represents the date vendor submitted deliverable to the state.

    * Gathering information to confirm due date.