IS 15472 (2004): Guidelines for ... - Public.Resource.Org

10
Disclosure to Promote the Right To Information Whereas the Parliament of India has set out to provide a practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, and whereas the attached publication of the Bureau of Indian Standards is of particular interest to the public, particularly disadvantaged communities and those engaged in the pursuit of education and knowledge, the attached public safety standard is made available to promote the timely dissemination of this information in an accurate manner to the public. इंटरनेट मानक !ान $ एक न’ भारत का +नम-णSatyanarayan Gangaram Pitroda “Invent a New India Using Knowledge” प0रा1 को छोड न’ 5 तरफJawaharlal Nehru “Step Out From the Old to the New” जान1 का अ+धकार, जी1 का अ+धकारMazdoor Kisan Shakti Sangathan “The Right to Information, The Right to Live” !ान एक ऐसा खजाना > जो कभी च0राया नहB जा सकता ह Bharthari—Nītiśatakam “Knowledge is such a treasure which cannot be stolen” IS 15472 (2004): Guidelines for planning and design of low level outlets for evacuating storage reservoirs [WRD 10: Reservoirs and Lakes]

Transcript of IS 15472 (2004): Guidelines for ... - Public.Resource.Org

Page 1: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

Disclosure to Promote the Right To Information

Whereas the Parliament of India has set out to provide a practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, and whereas the attached publication of the Bureau of Indian Standards is of particular interest to the public, particularly disadvantaged communities and those engaged in the pursuit of education and knowledge, the attached public safety standard is made available to promote the timely dissemination of this information in an accurate manner to the public.

इंटरनेट मानक

“!ान $ एक न' भारत का +नम-ण”Satyanarayan Gangaram Pitroda

“Invent a New India Using Knowledge”

“प0रा1 को छोड न' 5 तरफ”Jawaharlal Nehru

“Step Out From the Old to the New”

“जान1 का अ+धकार, जी1 का अ+धकार”Mazdoor Kisan Shakti Sangathan

“The Right to Information, The Right to Live”

“!ान एक ऐसा खजाना > जो कभी च0राया नहB जा सकता है”Bhartṛhari—Nītiśatakam

“Knowledge is such a treasure which cannot be stolen”

“Invent a New India Using Knowledge”

है”ह”ह

IS 15472 (2004): Guidelines for planning and design of lowlevel outlets for evacuating storage reservoirs [WRD 10:Reservoirs and Lakes]

Page 2: IS 15472 (2004): Guidelines for ... - Public.Resource.Org
Page 3: IS 15472 (2004): Guidelines for ... - Public.Resource.Org
Page 4: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

F ---

IS 15472:2004

Indian Standard

GUIDELINES FOR PLANNING AND DESIGN OFLOW LEVEL OUTLETS FOR EVACUATING

STORAGE RESERVOIRS

ICS 93.16

@ BIS 2004

BUREAU OF IN DIAN STANDARDSMANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG

NEW DELHI 110002

November 2004 Price Group 2

Page 5: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

Spillways Including Energy Dissipators Sectional Committee, WRD 10

FOREWORD

This Indian Standard was adopted by the Bureau of Indian Standards, after the draft finalized by the SpillwaysIncluding Energy Dissipators Sectional Committee had been approved by the Water Resources DivisionCouncil.

Evacuation outlets are provided in dams for depletion of reservoirs for inspection, maintenance and repairs andfor controlling the reservoir pool rise during initial filling of reservoirs. These outlets need not necessarily bealways located in the spillways. They can be located in the main dam or in the abutment also.

The composition of the technical committee responsible for the formulation of this standard is given inAnnex A.

For the purpose of deciding whether a particular requirement of this ktandard is complied with, the final value,observed or calculated, expressing the result of a test of analysis, shall be rounded off in accordance withIS 2:1960 ‘Rules for rounding off numerical values (revised)’. The number of significant places retained inthe rounded off value should be the same as that of the specified value in this standard.

,.. ‘—.—

Page 6: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

IS 15472:2004

Indian Standard

GUIDELINES FOR PLANNING AND DESIGN OFLOW LEVEL OUTLETS FOR EVACUATING

STORAGE RESERVOIRS1 SCOPE

This standard provides general guidelines for planningand design of evacuation outlets for evacuating thereservoirs.

2 GENERAL PROVISIONS

2.1 It is desirable to provide low level outlets ofadequate capacity in all dams for the followingpurposes:

a) Evacuation of the reservoir to a specifiedelevation for inspection, maintenance andrepairs; and

b) Controlling the rate of reservoir pool riseduring initial filling of the reservoir.

2.2 For lowering the water level of the reservoir forinspection and repairs when necessary, therequirement would be to evacuate a major portion ofthe reservoir in such time that after the water level islowered, sufficient time is available for repairs beforethe water level rises due to higher inflows. For such aconsideration, the outlets should be at the lowestpossible level and of sufficient number, size andcapacity to evacuate the reservoir taking into accountthe concurrent inflows.

2.3 The low level outlets should be located and sizedto provide discharging capacity sufficient to evacuatethe reservoir in a reasonable time and to maintain thereservoir filling rates as specified in the initial fillingcriteria for the project.

2.4 The drawdown levels and the evacuation timeshould be set forth for projects on a case to case basis.For structural safety, the reduction in height of water,which gives relief, is important. For very largereservoirs this may mean very large capacity outletsfor speedy evacuation.

2.5 The initial reservoir elevation to be used forperforming reservoir evacuation computationsdepends upon the reservoir storage allocations andproject needs. Normally the full reservoir level (FRL)is selected as the initial reservoir level for reservoirevacuation studies.

2.6 The volume corresponding to the dead storagecapacity of the reservoir is not to be considered forevacuation purposes.

2.7 Suitable inflows in the reservoir should beassumed while computing the period of evacuationand for initial filling of the reservoir as per thefollowing guidelines.

2.7.1 For Reservoir Evacuation

Inflows into the reservoir for analysis purposes shouldbe the highest consecutive mean monthly inflows forthe duration of the evacuation period.

2.7.2 For Initial Filling of the Reservoir

Inflows for initial filling should be based on acombination of base flow and a frequency flood event.If the selected frequency flood includes base flow,average monthly stream flow should not be added tothe hydrography. Base flow should be the average ofthe mean monthly stream flow for the anticipatedfilling period. Generally the selected frequency floodwill have a return period of five times the filling periodwith a minimum return period of 5 years.

2.8 All water release facilities, for example, gatedspillways, sluices, outlet works, penstocks, etc, shouldbe considered to be available for evacuation forsupplementing the low level outlets to the extent thattheir reliability can be considered as reasonablycertain.

2.9 For normal evacuation purposes, the drawdownrate should be limited to the safe downstream carryingcapacity of the river. In case of canal outlets, thereshould be a positive means of making releases into anatural water course throBgh a bypass or a wastewayas it is possible that there may not be any irrigationrequirement at that time. In case of power plants, morethan one unit must be installed and made operational.Generally only 50 percent of the release capability ofthe turbines should be considered available becausesome units could be inoperational when theirdischarge capacily is needed.

Other factors like possible adverse flowconditions/cavitation in case of simultaneousoperation of both spillway and sluices, if they arelocated in the spillway blocks, should also ~ kept inview.

1

... .-

Page 7: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

IS 15472:2004

3 DESIGN REQUIREMENTS

3.1 Location and sizing of low level outlets should bedone in a systematic way, considering the followingaspects:

a) Emergency evacuation requirements of theproject,

b) Possibility of taking advantage of the outletwork in routing the inflow design flood as asupplement to the spillway arrangements, and

c) Initial filling requirement.

3.2 In our country, reservoir sedimentation is apotential problem. Normally the evacuation outletsshould be located. above the predicted 100 year siltelevation or else a multilevel intake structure shouldbe provided to prevent the outlet works from beingplugged by sediment load during the life of theproject. Any deviation from the above aspects basedon site specific factors can be considered on case tocase basis.

3.3 Low level outlets can be provided both as sluicesand as depletion tunnels. These can be located eitherin the main dam or in the spillway or in theabutments. However it is to be ensured that thesedo not get blocked due to any possible landslides inthe reservoir. Suitable energy dissipationarrangements are required to be provided for energydissipation at the exit.

4 EVACUATION TIME

4.1 Guidelines on this aspect should generally takeinto account assessment of hazard potential and riskpotential of the dam. However, in the Indianconditions where population growth in downstreamareas is not controllable, the hazard potential at theinitial stage and its subsequent increase cannot beassessed. In most cases the dams would come underhigh hazard category.

Similarly risk is very difficult to classify because ofvarious combinations of adverse conditions that maybe involved at a particular dam site and the type ofdam.

Classification is also recommended to be based on theheight of dams so far as determination of risk potentialis concerned and dams with a height of more than50 m are to be considered more important than thoseof height less than 50 m.

For evacuating storage reservoirs and sizing low-leveloutlets, three categories are suggested as given in thetable below. These assume a general balance betweenhazard and risk and could be adjusted on the basis ofdetailed site specific studies.

Evacuation Time (in Days)

Depth of Evacuation Degree t#Hauvd or Risk;;. (@m Initiol Pool ~

Level) High Significant Low(Evacuation time in days)

i) 2s 20 30 50ii) 50 40 50 70

iii) 75 80 90 100

The above evacuation periods would generally bewithin the overall requirement to drawdown thereservoir within a period of one to four monthsallowing sufficient time for carrying out inspectionand repairs before the water level rises due to higherinflows of monsoon.

In some exceptional case, it may not be technicallypossible and economically feasible to provide therequired drawdown capability to meet the abovecriteria because of the size of the project (unusuallysmall or large) or because of some special feature. Insuch a case, the criteria regarding drawdown level orthe evacuation time could be altered to suit the sitespecific case if the results of studies so indicate.

4.2 Site specific sequence of operations to befollowed for evacuation needs to be planned for everyproject. In case of gated spillways, reservoir can belowered from initial pool level which is generally thefull reservoir level, to the spillway crest level bysuitably opening the spillway gates taking cognizanceof the downstream channel capacity. Further loweringof the reservoir could be through the low level andother outlets. Actual details axe however required tobe planned on case to case basis.

5 INITIAL FILLING OF RESERVOIRS

Initial reservoir filling is the first test of a darn toperform its intended functions. As the sizing of theoutlet works to meet the probable outflowrequirements during initial filling has to be fixedduring designs, the information on the desired rates ofpool rise must also be available at the time the designrequirements are established.

In order to monitor reservoir performance, the rate offilling should be controllqxl to allow in accomplishinga predetermined monitoring program. Low leveloutlets should be located and sized to providedischarge capacity sufficient to maintain the reservoirfilling rates specified by the initial filling criteria tohold reservoir levels reasonably constant forelevations above 50 percent of the hydraulic height ofthe dam. Inflows in the reservoir should be assumedas per 2.7.2.

Reservoir filling criteria are established on a dam todam basis. In general the objective as already statedabove is to provide a planned program with adequatetime for monitoring and evaluating performance of the

2

—...... ,-. -

Page 8: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

dam and its foundation as the reservoir is being filledfor the first time.

The major factors to be considered in establishinginitial filling criteria are as undec

a)

b)

c)d)

e)

f)

g)

h)

j)k)

Type of dam — Concrete, masonry, earth orrockfili.Geology of the dam foundation and reservoirarea including seismicity and landslide poten-tial along the banks of the reservoirs.Hazard potential.Inflow characteristics — Controlled or uncon-trolled.Hydrology — Flood patterns and seasonalbase flows.Release provisions for project requirements,flood release and emergency evacuation.Type of instrumentation and provision formonitoring, instrument response time andevaluation time needed.Safe channel capacities downstream of thedam.Characteristics of reservoir storage.Construction schedule.

Filling rates for concrete/masonry dams are much lessrestrictive than for embankment dams.

Site specific initial filling programs should beprepared based on the factors enumerated above. Ageneral initial filling program in respect ofembankment dams, which can be suitably modified asnecessary, is as under:

a)

b)

The first stage consists of filling the reservoirup to MDDL. This tilling can be done withoutrestraint as the hazard potential to the publicand economic development downstream of thedam is low.The second stage consists of filling the reser-voir from MDDL to the crest of spillway. For

IS 15472:2004

earth and rockfill dams this stage filling shouldbe done in two parts.

The reservoir above MDDL should be gradual-ly built at a rate not exceeding 3 m per fortnightand tilling should be temporarily stopped athalf the height between MDDL and crest ofspillway, for a reasonable time in order toassess the behaviour of the structure on thebasis of observed values and to take a decisionabout further storage and remedial measures incase of distress.

After a decision is taken to continue the filling,further building up of the storage should bedone in gradual sub-stages of 2 to 3 m perfortnight depending upon the height of the damand increase in storage capacity. The reservoirshould then be temporarily held at the crestlevel of the spillway for a reasonable time formonitoring and evaluating the performance ofthe dam and to take a decision about furtherstorage.

c) The third stage consists of filling above thecrest of the spillway up to the full reservoirlevel (FRL).

The rate of reservoir filling above crest ofspillway should be restricted to sub-stages of0.3 m in 48 h. The reservoir should be tem-porarily held at half the height between FRLand crest of spillway for sufficient time formonitoring and evaluating performance ofdam and to take a decision about furtherstorage/remedial measures, if any.

5.1 The instrumentation program and frequency oftaking observations during initial filling of thereservoir including the periods for which the reservoiris held constant at specified levels should also befinalised simultaneously for structural monitoring ofthe structure at that time. The structural behaviourreports should be prepared for each stage of filling.

-j

,.. ._ ~.

Page 9: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

IS 15472:2004

ANNEX A

( Foreword)

COMMITTEE COMPOSITION

Spillways Including Energy Dissipators Sectional Committee, WRD 10

OrganisationSardar Sarovar Narmada Nigam Ltd, GandhinagarBhakra Beas Management Board, Nangal Township

Bodhi Water Resources Dept. Bhopal

Central Design Organization, GandhinagarCentral Water & Power Research Station. pane

Central Water Commission, New Delhi

Consulting Engineering Services (I) Ltd, New Delhi

Gujarat Engineering Research Institute, Vadodara

Hindustan Construction Company Ltd, Mumbai

Indian Association of Hydrologists, New DelhiIndian Institute of Technology, Roorkee

Irrigation Department, Govt of Andhra Pradesh,Hyderabad

Irrigation & Water Ways Dkctorate, Govt of West Bengal,Dist Darjeeling

Irrigation Department, Govt of Orissa, Bhubaneshwar

Irrigation Department, Govt of Punjab, Chandigarh

Irrigation Department, Govt of Ut@nchal, Roorkee

Irrigation Department, Govt of Karnatak% KarnatakaIrrigation Department, Govt of Maharashtra, Nashik

Jaiprakash Industries Ltd, New Delhi

Nathpa Jhatil Power Corporation, Shitrda

National Hydroelectric Power Corporation Ltd, Faridabad

Sardar Sarovar Narmada Nigam Ltd, Gandhinagar

Wapcos (India) Ltd, New Delhi

BIS Directorate General

Representative(s)SHRt N. B. DE-SAI(Clrahrun)SUPEIWTENDINGf?NGtNEER

EXECUTtVEENGINEER(Alternate)SHru J. K. TIWARI

SHrrtR. K. CHACHONDIA(Alternate)SUPERtNTENDtNGENGINEER

SHRIP. B. DEOLALtKAR

SHRIMATtV. V. BHOSEKAR(Alternate)DIRECTOR[CMDD-N&W]

DIRECrOR[SSD&C] (Alternate)SHRIV. K. KAPUR

SHra P. K. SANGHt(Alternate)SHRtV. S. BRAHMABHAIT

RESEARCHOFFtCSR (Alternate)SHRt R. G. VARTAK

SHRtK. R. VISHWANATH(Alternate)SHRt PMTAMSINGHDIRECTOR[WRTDC]

DR NAYANSHARMA(Ahernare)CHIEF ENGINEER

SUPERltWENDtNGENGtNEER(DAMS) (Afterrrafe)SUPERINTENDINGENGINEER

EXECUTIVEENGINEER(Ahernate)CHIEF ENGINEER(D&R)

DIRECTOR[HEAD WORKS(Alternate)CHIEF ENGINEER(RSDD)

DIRECTORSPtLLWAY (RSDD) (Alternate)CHtEF ENGINEER& DIRECTOR

SUPERINTENDINGENGINEER(Alternate)DIREtIOR

SUPERINTENDINGENGINEER(MD)EXECUTtVEBNGtNEER(MD-5) (Alternate)

SHRt D. G. KADKADE

SHRtNARENDRASINGH(Altemute)SHRIR. S. CHAUHAN

SHRIV. K. VERMA(Alternate)SHtUS. C. tvftTTAL

SHRt SAtWSH KUMAR(Alternate)SHRt G. L. JAVA

SHru S. J. DESAI (Alternate)SHRIS. R. NARAYANAN

SHRIA. P. CHOUDHARY(Alternate)SHRIS. S. SETHL Director & Head (WRD)[Representing Director General (Ex-oficio)]

‘1L’

.,

Member-SecretarySHRtMATIROSY DHAWAN

Joint Director (WRD), BIS

4

—.,.-. .

Page 10: IS 15472 (2004): Guidelines for ... - Public.Resource.Org

Bureau of Indian Standards

BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promoteharmonious development of the activities of standardization, marking and quality certification of goodsand attending to connected matters in the country.

Copyright

BIS has the copyright of all its publications. No part of these publications may be reproduced in any formwithout the prior permission in writing of BIS. This does not preclude the free use, in the course ofimplementing the standard, of necessary details, such as symbols and sizes, type or grade designations.Enquiries relating to copyright be addressed to the Director (Publications), BIS.

Review of Indian Standards

Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewedperiodically; a standard along with amendments is reaffirmed when such review indicates that no changes areneeded; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standardsshould ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of‘BIS Catalogue’ and ‘Standards: Monthly Additions’.

This Indian Standard has been developed from Doc : No. WRD 10 (318).

Amendments Issued Since Publication

Amend No. Date of Issue Text Affected

BUREAU OF INDIAN STANDARDS

Headquarters :

Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002 Telegrams : ManaksansthaTelephones :23230131,23233375,2323 9402 (Common to all oftlces)

Regional Offices : Telephone

Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg

{

23237617NEW DELHI 110002 23233841

Eastern : 1/14 C.I.T. Scheme VII M, V, I. P. Road, Kankurgachi

{

23378499,23378561KOLKATA 700054 23378626,23379120

Northern : SCO 335-336, Sector 34-A, CHANDIGARH 160022

{

603843609285

Southern : C. LT. Campus, IV Cross Road, CHENNAI 600113

{

22541216,22541442

22542519,22542315

Western : Manakalaya, E9 MIDC, Marol, Andheri (East)

{

28329295,28327858MUMBAI 400093 28327891,28327892

.

}i

Branches : AHMEDABAD. BANGALORE. BHOPAL. BHUBANESHWAR, COIMBATORE. FARIDABAD.

GHAZIABAD. GUWAHATI. HYDERABAD. JAIPUR. KANPUR. LUCKNOW. NAGPUR.NALAGARH. PATNA. PUNE. RAJKOT. THIRWANANTHAPURAM. VISAKHAPATNAM.

Printed at Prabhat Offset Press. New Delhi-2