Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization...
Transcript of Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization...
![Page 1: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/1.jpg)
Irvine High School Classroom Modernization Public Information Meeting
September 27, 2017
![Page 2: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/2.jpg)
MEETING AGENDA
• Introductions
• Overview of Measure E Program
• Project Overview
• Resources
• Questions and Answers
![Page 3: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/3.jpg)
INTRODUCTIONS
• Kim Coffeen – IUSD, Director Facilities Planning• Jill Cheng – IUSD Supervisor, Facilities/Construction• Milo Oostinga – Ledesma & Meyer, Construction Manager
Additional Team Members:• Kelvin Okino – IUSD, Executive Director, Facilities Planning and Construction• Monica Colunga– IUSD, Principal of Irvine HS• Annie Brown – IUSD, Public Information Officer• Kevin Wilkeson – HMC Architects, Architect
![Page 4: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/4.jpg)
Overview of Measure E Program
![Page 5: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/5.jpg)
• Comprehensive plan created in 2012
• Refined in 2015 with current cost estimates
• Districtwide improvement needs over $800.0 million
• Districtwide needs include:
• facilities improvements
• enrollment growth
• site upgrades
• upgrades to non-school site facilities
• Determined the need for a General Obligation Bond
HISTORY OF MEASURE E
![Page 6: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/6.jpg)
SFID BOND MEASURE
• Schools Facility Improvement District (SFID)
• Carved out newer schools under a Mitigation Agreement (Mello-Roos)
• Focused on 28 schools of the 38 schools
• June 7, 2016 Ballot
• $319.0 million Bond Measure (Measure E)
• $29 / $100,000 assessed value tax increase
• Four bond series sales
• Proposition 39 (School Facilities Local Vote Act of 2000)
• Passed at 60.2% (55% required)
![Page 7: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/7.jpg)
55
1828
![Page 8: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/8.jpg)
Irvine
Stone CreekCollege Park
University
Venado
Eastshore
Brywood
Meadow Park
Westpark
Creekside
Lakeside
Rancho
Sierra Vista
South Lake
Woodbridge
Bonita
Culverdale
Greentree
Santiago Hills Springbrook
Northwood
AUG 2017 AUG 2018 AUG 2019 AUG 2020
PROJECT COMPLETION DATE
![Page 9: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/9.jpg)
SERIES 1 PRIORITIES
• Safety and security
• Install interior doors at elementary school classrooms
• Age of the school site
• Modernize eligible schools over 25 years old
• Projects that will impact the greatest amount of students
• Projects for high schools and middle schools, which benefit most Irvine USD students, who will attend these schools
• Upgrade Science Labs at middle schools
![Page 10: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/10.jpg)
Irvine HSa $9.6 M
Venado MSh $5.5 M
College Park b, m $4.7 M
Deerfield
Greentreeb $3.3 M
Plaza Vista
Culverdaleb $2.6 M
Woodbridge HS
g $23.6 M
Lakeside MS
Eastshorei, f $4.3 M
Oak Creek
Stone Creekb, f $2.9 M
South Lake MS
Meadow Park
a,b,c,e $9.7 M
Westpark
Springbrook
University HS
a, h $4.9 M
Rancho MSh, f $5.7 M
Bonita Canyonb $0.4 M
Turtle Rock
University Park
PROJECT TYPES
a. Modernize facilities over 25 years of age
b. Enclose open classrooms c. Construct Music Classroomsd. Construct Multipurpose Roome. Construct/Upgrade Food Servicef. Construct Career Tech and
Innovation/Design Labsg. Construct Visual and Performing Arts,
Media Arts Elective Labs and New/Upgrade Theaters
h. Construct/upgrade science labs and Elective Spaces
i. Construct/Upgrade Kinder Classrooms j. Construct all weather track and field k. Construct Classrooms to replace
portablesl. Construct Practice Gymm. Construct/Upgrade Site Specific
Support Facilities
Northwood HS
j $3.1 M
Sierra Vista MS
Brywooda,b,c,e $10 M
Canyon View
Northwood
Santiago Hillsb $1.5 M
Creekside HS
f $3.9 M
$18.3 M$25.7 M $64.4 M $11.0 M $3.9 M+ + + + = $123.3 MProgram Escalation + $8.1 M
Total Program Cost $131.4 MFunding $95.0 M Bond$36.4 M IUSD
h $3.7 M h $1.4 M h $2.1 M
a,b,e $7.4 M
a,b,c,e $12 M
Canyon View
Northwood
Measure E Series 1 Projects and Costs1
![Page 11: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/11.jpg)
Woodbridge HS
a, h $12.6 M
Lakeside MS
Eastshore
Oak Creek
Stone Creek
South Lake MS
a, h $12.2 M
Meadow Park
Westpark
Springbrook
Irvine HSg $23.6 M
Venado MS
College Park
Deerfield
Greentree
Plaza Vista
Culverdale
Northwood HS
Sierra Vista MS
Brywood
Canyon View
Northwoodc, e $4.4 M
Santiago Hills
University HS
Rancho MS
Bonita Canyon
c,d,e $5.0 M
Turtle Rock
c $3.5 M
University Park
k $7.3 M
PROJECT TYPES
a. Modernize facilities over 25 years of age b. Enclose open classrooms c. Construct Music Classroomsd. Construct Multipurpose Roome. Construct/Upgrade Food Servicef. Construct Career Tech and
Innovation/Design Labsg. Construct Visual and Performing Arts,
Media Arts Elective Labs and New/Upgrade Theaters
h. Construct/upgrade science labs and Elective Spaces
i. Construct/Upgrade Kinder Classrooms j. Construct all weather track and field k. Construct Classrooms to replace
portablesl. Construct Practice Gymm. Construct/Upgrade Site Specific Support
Facilities
Creekside HS
$4.4 M$23.6 M $24.8 M $15.8 M -+ + + + = $68.6 MProgram Escalation + $11.0 M
Total Program Cost $79.6 MFunding $51.9 M Bond$27.7 M IUSD
Sites that are not part of the first and second bond series
Measure E Series 2 Projects and Costs2
![Page 12: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/12.jpg)
University HS
g, m $20.9 M
Rancho MS
Bonita Canyon
Turtle Rock
University Park
Northwood HS
g, l $5.5 M
Sierra Vista MS
Brywood
Canyon View
c, f, m $3.1M
Northwood
Santiago Hills
Woodbridge HS
Lakeside MS
d,e,m $7.8 M
Eastshore
Oak Creek
c, m $2.5 M
Stone Creek
South Lake MS
Meadow Park
Westpark
Springbrook
Irvine HS
Venado MS
d $0.8 M
College Park
c $3.3 M
Deerfield
Greentree
Plaza Vista
c, i $5.8 M
Culverdale
Creekside HS
$8.6 M$9.9 M $10.3 M $20.9 M -+ + + + = $49.7 MProgram Escalation + $11.0 M
Total Program Cost $60.7 M
Funding $49.4 M Bond$ 7.7 M IUSD$ 3.6 M TBD
PROJECT TYPES
a. Modernize facilities over 25 years of age b. Enclose open classrooms c. Construct Music Classroomsd. Upgrade/Construct Multipurpose Roome. Construct/Upgrade Food Servicef. Construct Career Tech and
Innovation/Design Labsg. Construct Visual and Performing Arts,
Media Arts Elective Labs and New/Upgrade Theaters
h. Construct/upgrade science labs and Elective Spaces
i. Construct/Upgrade Kinder Classrooms j. Construct all weather track and field k. Construct Classrooms to replace
portablesl. Construct Practice Gymm. Construct/Upgrade Site Specific Support
Facilities
Site that is not part of the previous bond series
Measure E Series 3 Projects and Costs3
![Page 13: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/13.jpg)
PROJECT TYPES
a. Modernize facilities over 25 years of age
b. Enclose open classrooms c. Construct Music Classroomsd. Construct/Upgrade Multipurpose Roome. Construct/Upgrade Food Servicef. Construct Career Tech and
Innovation/Design Labsg. Construct Visual and Performing Arts,
Media Arts Elective Labs and New/Upgrade Theaters
h. Construct/upgrade science labs and Elective Spaces
i. Construct/Upgrade Kinder Classrooms j. Construct all weather track and field k. Construct Classrooms to replace
portablesl. Construct Practice Gymm. Construct/Upgrade Site Specific
Support Facilities
Woodbridge HS
Lakeside MS
Eastshorec, m $3.2 M
Oak Creek
Stone Creekc, e $4.9 M
South Lake MS
c. $1.5 M
Meadow Park
Westparkc, m $3.6 M
Springbrook
University HS
Rancho MS
Bonita Canyon
Turtle Rockf, m $2.2 M
University Park
Irvine HS
Venado MS
College Park
e, m $2.2 M
Deerfield
c,e,m $5.0 M
Greentree
c,d,e $7.1 M
Plaza Vista
Culverdale
d,e,f $6.7 M
Northwood HS
Sierra Vista MS
c,d,m $3.0 M
Brywood
Canyon View
Northwood
Santiago Hills
c,d,e $6.3 M
Measure E Series 3 Projects and Costs
Creekside HS
m $1.2 M
$9.3 M$21.0 M $13.2 M $2.2 M $1.2 M+ + + + = $46.9 MProgram Escalation + $11.0 M
Total Program Cost $57.9 M
Funding $54.5 M Bond
- 0 - IUSD$ 3.4 M TBD
4
![Page 14: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/14.jpg)
ACRONYMS
RFPRequest for Proposal
A/EArchitect / Engineer
CDECalifornia Department of Education
DSADivision of State Architect
OPSCOffice of Public School Construction
and Community Outreach
DESIGN & CONSTRUCTION PROCESS
![Page 15: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/15.jpg)
Staff Logistics/Impacts
Community Outreach• Parents /Students• H.O.A• Neighbors• City of Irvine
AGENCY APPROVALS• California Dept. of Ed.• Div. of State Architect• Fire Authority• State Funding
INTERNAL REVIEWS• Ed. Specs./Technical Specs.• Maintenance and Operations• IT: network, data, AV• Security• Ed. Services• Milestone Meetings
(Architect & Construction Manager)
• Schools Facilities Improvement Measure Committee
• Citizens Oversight Committee• Board of Education Study
Sessions
THEPROJECT
Planning Committee
STAKEHOLDERS
![Page 16: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/16.jpg)
Project Overview
![Page 17: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/17.jpg)
TYPICAL CLASSROOM
![Page 18: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/18.jpg)
• FIRE ALARM UPGRADE• REPLACE LIGHTS• REPLACE HVAC SYSTEM• PAINT INTERIOR WALL• REPAIR CASEWORK• REPLACE FLOORING• REPLACE CEILING TILES• NEW AUDIO AND VISUAL
SYSTEM
BUILDING M (Math)
![Page 19: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/19.jpg)
• FIRE ALARM UPGRADE• REPLACE LIGHTS• REPLACE HVAC SYSTEM• PAINT INTERIOR WALL• REPAIR CASEWORK• REPLACE FLOORING• REPLACE CEILING TILES• RECONFIGURE SPECIAL ED
CLASSROOMS• NEW AUDIO AND VISUAL
SYSTEM
BUILDING WL (World Language)
![Page 20: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/20.jpg)
SPECIAL ED
![Page 21: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/21.jpg)
• REMOVE FLOOR RISERS• REMOVE CONTROL ROOM• NEW FLOORING• PAINT INTERIOR WALL• NEW INTERIOR LIGHTS• NEW CASEWORK WITH
SINKS• NEW AUDIO AND VISUAL
SYSTEM
SLG
![Page 22: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/22.jpg)
SLG
![Page 23: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/23.jpg)
PROJECT MILESTONE SCHEDULEOccupancyPhase 2Jan 2018
October – December2017
Bid and Award
May – July2017
CD
August – November2017DSA Review
2017 2018
Interim Housing Ready 2017 Winter Break
February - August 2018Phase 1: Building M
Summer 2018
Move-in and Occupancy
Summer 2018Phase 2A: SLG
June - January 2019
Phase 2B: Building WL
Mid January 2019
Move-in and Occupancy
OccupancyPhase 1August 2017
Portables Upgrade
![Page 24: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/24.jpg)
DRAFT SITE LOGISTIC PLAN – PHASE 1
![Page 25: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/25.jpg)
DRAFT SITE LOGISTIC PLAN – PHASE 2
![Page 26: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/26.jpg)
DRAFT SITE LOGISTIC PLAN – PHASE 3
![Page 27: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/27.jpg)
• Measure E Webpageiusd.org/MeasureE
• Irvine HS Measure E Webpage – school site updatesiusd.org/sites/default/files/documents/imported/irvine_hs.pdf
• Citizens Oversight Committee Webpage iusd.org/COC
• Contact Email for Questions/[email protected]
MEASURE E RESOURCES
![Page 28: Irvine High School Classroom Modernization Public ... · Irvine High School Classroom Modernization Public Information Meeting ... MEETING AGENDA • Introductions • Overview of](https://reader033.fdocuments.us/reader033/viewer/2022041622/5e3fafc5abc76463e750595e/html5/thumbnails/28.jpg)
QUESTIONS and ANSWERS