IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

12
IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

Transcript of IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

Page 1: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

IRTBA “STATE OF THE

INDUSTRY”

Will CountyFY 2012

Page 2: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

• 2008– Build Will unveiled

• 60 projects on County Highway System• $300 million program

– Funded with • RTA sales tax• Federal, State, & other Local funding sources

• 2009-Present– Additional 12 projects– Total additional cost $57 million– $100 million in bonds approved

by County Board

BUILD WILL UPDATE

Page 3: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

• Largest Overlay Program in History– Last 2 Years

• 84 Center-line Miles• 25 County Highways

– FY 2012• 36 Center-line Miles• 14 County Highways• Total estimated cost $10 million

– 3 Year Total• 120 Center-line Miles• 39 County Highways

BUILD WILL UPDATE (cont.)

Page 4: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

Road Construction $40.7 million

Structure Rehab & Reconstruction $11.9 million

Engineering $14.0 million

ROW Acquisition $14.8 million

Build Will Total $81.4 million

Maintenance $10 million

Program Total $91.4 million

FY 2012 PROGRAM

Page 5: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

• Weber Road @ Renwick Road

• 135th Street @ Il Route 171 (Archer Avenue)

• 95th Street Extension (Plainfield-Naperville Road to Boughton Road)

• Will-Peotone Road @ Old Chicago Road over Jordan Creek

• South Briggs over Metra & Hickory Creek

PROGRAM HIGHLIGHTS

Page 6: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

WEBER ROAD @ RENWICK ROAD

• Scope – Weber Road

• Widen to 6 lanes • Barrier Median

– Renwick Road• Widen to 4 lanes• Barrier Medians

• Total Cost: $ 14 million• Approximately $ 4 million in

Federal Funds (STP & CMAQ)• Quick Take approved for ROW

acquistion

Page 7: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

135TH STREET @ IL ROUTE 171(ARCHER AVENUE)

• Scope of Work– Realign

Intersection– New Structure over

Long Run Creek

• Total Cost: $ 7.1 million

Page 8: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

95TH STREET EXTENSION:PLAINFIELD-NAPERVILLE ROAD TO BOUGHTON

ROAD• Scope

– Approximately 2 miles of new Roadway

– New Structure over DuPage River

– Intersection Improvements at termini

– Noise Walls• Total Cost: $ 25.9 million• Funding: Over $10 million

in Federal Funds (STP & STR)

Page 9: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

WILL-PEOTONE ROAD @ OLD CHICAGO ROAD

• Scope– Turn Lanes on all legs– Reconstruction of

Structures over Jordan Creek on both roads

• Total Cost: $7.04 million

Page 10: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

SOUTH BRIGGS STREET OVER METRA & HICKORY CREEK

• Scope: Structure Rehabilitation

• Total Cost: $2.5 million

Page 11: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

• According to Labor Statistics – 42, 000 jobs are created – Per $1 billion in Construction

• Build Will FY 2012 Creates: 2210 jobs

JOB CREATION

Page 12: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012.

QUESTIONS?