IR-75 THRU THE VALLEY PRESENTATION • TRAFFIC ENGINEERING WORKSHOP, JUNE 5, 2019
![Page 2: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/2.jpg)
2 |
IR-75
THRU THE VALLEY
UPDATE R Scott Kramer, P.E.
D-8 Bridge Design Engineer
TTV Coordinator
ODOT District 8 Engineering
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
![Page 3: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/3.jpg)
3 |
PROJECT OVERVIEW
o TTV – Thru The Valley is the
rehabilitation, and one lane
addition in each direction, of IR 75
from a little south of Cross County
Interchange to just south of the
IR 275 Outerbelt.
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 4: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/4.jpg)
4 |
PROJECT OVERVIEW
o The project initially started out in
8 phases plus building demolition,
and now consists of 7 separate
phases plus demolition.
o Original phase numbering have
been retained to maintain
continuity with the NEPA
Document. TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 5: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/5.jpg)
5 |
PROJECT OVERVIEW
• District sequenced construction
and prioritized the order of the
phases. • Building Demolition
• Phases in order of priority
• Fully Funded Phases: 1&2, 3
• Unfunded Phases: 8, 4, 5, 6
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 6: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/6.jpg)
6 |
INDIVIDUAL PHASES
• Phase 1&2 is under construction with
additional needed funding being
provided though National Highway
Freight, SIB Loan and District
Preservation.
• Total: $118.2M, $90.0M for Const.
• Construction: 2017 through 2020
• Video
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 7: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/7.jpg)
7 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 8: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/8.jpg)
8 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 9: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/9.jpg)
9 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 10: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/10.jpg)
10 |
INDIVIDUAL PHASES
• Phase 3,
• I75 and Cross County Interchange.
• Replaces high speed NB Galbraith off ramp
with a fly over ramp configuration.
• Construction needs have been funded with
$51.4 million Multi-Lane Major Rehab.
• Total $53.4M
• Construction: 2024 through 2025
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 11: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/11.jpg)
11 |
INDIVIDUAL PHASES
• Phase 8 (Not funded for Construction)
• IR-75 and Sharon Road Interchange.
• Will complete the IR75 4th lane addition from
the IR75 Split to the Montgomery County line
and connect the completed Phase 1&2 to
IR275 Outerbelt.
• Asking TRAC for $37.9M construction funding.
• Total Project Cost about $51.6M
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 12: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/12.jpg)
12 |
INDIVIDUAL PHASES
• Phase 4 (Not funded for Construction)
• Prephase to replace NS Railroad’s bridge
north of Galbraith Road.
• Miami Erie Canal Built by the State of
Ohio in 1820’s.
• 1906, Railroad built bridge over canal.
• Rule of Causality - Railroad caused the
bridge to be built so the railroad owns
and maintains the bridge.
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 13: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/13.jpg)
13 |
INDIVIDUAL PHASES
Phase 4 (Not funded for Construction)
• 1940’s, canal drained and 4 lane SH987
built.
• reduce impacts and costs.
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 14: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/14.jpg)
14 |
INDIVIDUAL PHASES
Phase 4 (Not funded for Construction)
• 1960’s Converted to SB 75. As seen today.
• Up until 2013, ODOT was sending monthly
letters to railroad with structural concerns
for years.
• Railroad claimed bridge was in satisfactory
condition, and ODOT should pay for,
maintain, and own the future bridge.
• Railroad performed repairs in 2013
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 15: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/15.jpg)
15 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 16: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/16.jpg)
16 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 17: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/17.jpg)
17 |
INDIVIDUAL PHASES
Phase 4 (Not funded for Construction)
• Reevaluated with an Alternative Technical
Concept that resulted in the railroad
taking over the ownership and
maintenance of the bridges for a savings of
$16 M in future maintenance.
• Estimated Construction cost $32M.
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 18: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/18.jpg)
18 |
INDIVIDUAL PHASES
• Phase 5 (Not funded for Construction)
• Removes deficient on and off ramps to
Cooper Ave.
• Adds connection to Milsdale St. and CD
ramp to Galbraith Road.
• Adds a new connection from Galbraith to
WB SR 126.
• Estimated Construction cost $46M.
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 19: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/19.jpg)
19 |
INDIVIDUAL PHASES
• Phase 6 (Not funded for Construction)
• Northbound 75 in the split.
• Traffic will be maintained with 3 lanes
south and north in the southbound split.
• New connection of westbound SR126 to
IR75 northbound.
• Loosing NB off ramp to Davis St.
• Construction Costs about $139M
• RW Cost about $40M
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 20: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/20.jpg)
20 |
INDIVIDUAL PHASES
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124
![Page 21: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING ...](https://reader034.fdocuments.us/reader034/viewer/2022052620/628e609723d9da6f9c18d0b3/html5/thumbnails/21.jpg)
21 |
SUMMARY
• Phase 1&2 • Construction till fall of 2020
• Phase 3 • Construction from 2024 through 2026
• Unfunded Phases in order of priority
• Phase 8, Sharon Road Interchange
• Phase 4, Replace RR Bridge in SB IR 75
• Phase 5, SB IR 75
• Phase 6, NB IR 75
TTV TRAFFIC ENGINEERING WORKSHOP UPDATE
Phase 8
HAM-75-14.61
PID 76256
Phases 1 & 2
HAM-75-12.60
PID 82288
Phase 5
HAM-75-10.87
PID 88132 Phase 6
HAM-75-10.62
PID 88133
Phase 4
HAM-75-11.09
PID 88129
Phase 3
HAM-75-10.10
PID 88124