Invitation to comment on Sunrise Energy’s request to amend ... · 2.5 The PLEM includes allowance...
Transcript of Invitation to comment on Sunrise Energy’s request to amend ... · 2.5 The PLEM includes allowance...
Invitation to comment on Sunrise Energy’s request to amend its licence
application to construct LPG loading and storage facilities in Saldanha Bay (PPL.sf.F1/88/2009)
The National Energy Regulator (‘NERSA’ or ‘Energy Regulator’) is a regulatory authority established as a juristic person in terms of Section 3 of the National Energy Regulator Act, 2004 (Act No. 40 of 2004). NERSA’s mandate is to regulate the electricity, piped-gas and petroleum pipelines industries in terms of the Electricity Regulation Act, 2006 (Act No. 4 of 2006), Gas Act, 2001 (Act No. 48 of 2001) and Petroleum Pipelines Act, 2003 (Act No. 60 of 2003). Sunrise Energy (Pty) Ltd (‘Sunrise’) published its licence application to construct a Liquefied
Petroleum Gas (LPG) loading and storage facilities in Saldanha Bay (Application reference
number PPL.sf.F1/88/2009) for public viewing during the period 15 September 2010 to 18
October 2010.
Subsequently, on 16 November 2010 NERSA held a public hearing to consider the matter. In
its presentation at the public hearing, Sunrise informed the Energy Regulator that it wishes to
amend its licence application. The Energy Regulator is of the opinion that the changes are
material and requested Sunrise to submit the revised documentation reflecting the
amendments sought.
On 6 December 2010 Sunrise submitted the amended documentation to NERSA. The
amendments to the original licence application are available on the NERSA website at
http://www.nersa.org.za under “Petroleum Pipelines > Licences > Applications under
consideration”.
Stakeholders and members of the public are invited to comment on the application in writing.
Requests for confidential treatment of information contained in the comments must be made in
accordance with rule 4 of the Petroleum Pipelines Act Rules, 2009 (GN R. 1072 in GG 32704
of 13 November 2009) (“the Rules”). The Rules are also available on the NERSA website at
http://www.nersa.org.za under “Petroleum Pipelines/Legislation”.
The deadline for comments is 24 December 2010. Written comments must be sent to Mr Thabo Ramanamane at: Post: Petroleum Licensing, Compliance & Dispute Resolution
The National Energy Regulator PO Box 40343
Arcadia Pretoria, 0007
Email: [email protected] Fax: (012) 401-4767 For further information regarding the licence application, please contact: Mr Thabo Ramanamane (012) 401 4082 or Martin Untiedt (012) 401 4799.
Nersa Queries CBM and Land 7dec2010a
Page 1 of | 16
Sunrise Energy Pty Ltd
1 Northbank, 3rd
Floor
Northbank Lane
Century City, Cape Town
7th
December 2010
The Director of Petroleum
Att: Dr Rod Crompton
Copy: Mr Martin Untiedt
Nersa
Kulawula House
526 Vermeulen Street
Arcadia
Pretoria
Ref No: PPL.SF.F!/88/2009
Dear Sirs
Subject: Sunrise Energy License Application for the construction of LPG storage facilities in Saldanha
Bay
Your fax and email of 2nd
December 2010 refers.
Attached please find our response to the queries raised by Nersa in the same chronological order as the
request for information. Please feel free to contact me should you require any further information or
clarification on the contents of the attached submission. We have included some additional information
to aid understanding of the key technical, commercial and environmental issues.
None of the information provided is of a confidential nature and may be used in the public domain.
Thank you and regards.
Nunda Naidoo
Director of Sunrise Energy
Sunrise Energy (Pty) Ltd Registration No. 2005/027952/07 VAT No. 4140253800
t. +27 21 552 9993 f. +27 44 552 9906
No. 1 Northbank, 3rd Floor, Northbank Lane, Century City, 7441, South Africa
PostNet Suite 68, Private Bag X18, Milnerton, 7435
Directors: D Welbourne* (Managing), DH Mzamo, M Shibanda, B Harmse, P Naidoo, Z Burghers (*British)
Nersa Queries CBM and Land 7dec2010a
Page 2 of | 16
For Further Information
EIA PROCESS COMMENCED
The EIA process was kicked off on 17th
November 2010 and two meetings were held with stakeholders
and interested parties in Saldanha Bay with the object of informing the public of the Sunrise Energy’s
intention to pursue the CBM option and use the land indicated on the ArcelorMittal site to construct the
storage bullets.
A CASH offer to purchase (OTP) was signed by Sunrise Energy and is under consideration by
ArcelorMittal.
Sunrise Energy has the necessary funds to purchase the land without having to rely on a bond or outside
funding.
PROGRESS ON FINAL DESIGN AND VESSEL FABRICATION
A rigorous tender and evaluation was done in order to shortlist manufacturers of the storage bullets for
the LPG project. The short list comprises two companies who have been selected.
Directors of Sunrise Energy and contractors will visit fabrication yards in India and Malaysia between 3-8
December 2010 to finalise the details around manufacturing the storage bullets and logistics to get them
to the site.
Effectively, this means that the orders for vessels can be PLACED in within the next 4 weeks to begin
fabrication.
Nersa Queries CBM and Land 7dec2010a
Page 3 of | 16
1 Item No. 1 – Details of Proposed Conventional Buoy Mooring
(CBM) and Pipeline End Manifold (PLEM)
1.1 Drawing no. 1039/01/2001 (Annexure 1) shows the proposed CBM layout.
1.2 The layout consists of four buoys, two off the bow and two off the stern. The number of buoys
required as been determined through numerical vessel motions analysis using TERMSIM.
1.3 The buoys are anchored using 76mm stud link chain (250m) connected to a mass gravity anchor
blocks.
1.4 The design vessel is a 6,000 DWT tanker (131m Length, 20.1m Beam, 8m Draft).
Numerical wave modelling has been undertaken to determine the design and operational
conditions at the proposed site.
1.5 The coordinates for the proposed Pipeline End Manifold (PLEM) and CBM positions are as
follows:
1.5.1 CBM (Mid-point of vessel) = Y+ 93 747.731 X+ 3 656 004.666
1.5.2 PLEM (CH 2100) = Y+ 93 682.916 X+ 36 56 042.402
1.5.3 Co-ordinate system WG19
NOTE: As part of the EIA being done, Sunrise Energy will consider BOTH THE CBM OPTION (preferred) as
well as the Jetty Option.
A Public Meeting was held on 17th
November 2010 in Saldanha Bay to inform stakeholders and affected
parties of the project and the plans to pursue the CBM route. EIA Consultants ERM and PRDW as well as
Sunrise Energy were in attendance to provide feedback and information.
Nersa Queries CBM and Land 7dec2010a
Page 4 of | 16
1.6 The CBM Option has the following advantages over the Jetty
1.6.1 TNPA has extensive experience in providing services to the offshore loading and unloading
facilities including the CBM in Mossel Bay, SPM in Mossel Bay and SPM in Durban (SPM means
SINGLE POINT MOORING).
1.6.2 The CBM will not “sterilise” TNPA jetty space which may be required in future.
1.6.3 Unlike a Jetty which is fixed and more permanent, a CBM is movable and therefore flexible
enough to fit into future port development plans such as a liquid fuel berth.
1.6.4 A CBM requires a minimal amount of construction.
1.6.5 A CBM is significantly cheaper than a Jetty to construct.
1.6.6 A vessel moored to a CBM in big bay is considered to be safer option compared to a vessel
moored on a jetty in a busy working part of the port with activities including (i) the iron ore
loading, (ii) multiproduct terminal handling (MPT), (iii) crude oil unloading, (iv) ship repair yard,
etc.
1.6.7 In the event of an onboard fire the vessel from a CBM can be towed out to sea thereby
reducing the risk to other activities on the Jetty.
1.6.8 The CBM is in a area of very little seagoing traffic, unlike the Jetty.
1.6.9 No dredging is required at the CBM whereas dredging may be required to accommodate larger
vessels in the Jetty.
1.6.10 Larger ships can be accommodated in future given the water depth of 12.5m at the PLEM. This
allows for future growth in market demand.
Nersa Queries CBM and Land 7dec2010a
Page 5 of | 16
1.7 Places in the world where LPG is unloaded and loaded via CBM and sea buoys.
Location Name Type of LPG Marine Terminal
Israel Ashkelon CBM
Turkey Lpragaz Sea Buoy CBM
Turkey BP Gaz Sea Buoy CBM
Turkey Milangaz Sea Buoy CBM
Dominican Republic Coastal Dominican Republic CBM
India Hazira CALM Terminal
Portugal Canical Marine Terminal Madeira CBM
Sri Lanka Shell Lanka CBM
Sri Lanka Colombo SPBM1 & 2, CBM
Turkey Delta CBM
Nersa Queries CBM and Land 7dec2010a
Page 6 of | 16
2 Item No. 2 – Details of Proposed Submarine Pipeline
2.1 Drawing no. 1039/01/2000 shows the proposed submarine pipeline layout (annexure 2).
2.2 The pipeline characteristics are as follows:
2.2.1 A-333 Grade 6 Low Temperature, Carbon Steel
2.2.2 20 bar design pressure
2.2.3 Minus 30 deg C design temperature
2.2.4 12” pipeline diameter
2.2.5 12mm wall thickness
2.2.6 Flow rates: 500 m3/hr (normal) and 750 m3/hr (maximum)
2.3 The pipeline is to be coated with a polypropylene coating (e.g. 3LPP coating)
2.4 Cathodic protection in the form of sacrificial anodes will be provided
2.4.1 he pipeline is to be protected with concrete stabilisation mattresses between the PLEM and the
shore crossing. The pipeline through the shore crossing is to be protected with rock armour.
2.5 The PLEM includes allowance for a pig launcher.
2.5.1 The shore crossing and servitude along which the pipeline will run, is situated on the eastern
side of the existing oyster dam (see drawing no. 1039/01/2000) (Annexure 2).
2.6 The undersea pipeline will be covered with a Smartmat system shown in Annexure 2.
Nersa Queries CBM and Land 7dec2010a
Page 7 of | 16
3 Item 3 – Servitude to be followed by the Pipeline En-Route to Storage Area
LPG
Undersea Line
SFF Crude Oil Pipeline
Existing
Servitude to SFF Tanks
LPG Pipeline to
Storage Area
Nersa Queries CBM and Land 7dec2010a
Page 8 of | 16
3.1 DETAILS OF OVERLAND PIPELINE
3.1.1 From the beach crossing above the pipeline will follow the existing SFF 48” crude line to the SFF
ultra large crude storage way lease servitude over TNPA land to the ArcelorMittal land.
3.1.2 General overland pipeline information
Size, outside diameter 12”
Length (Km) 1.8
Highest elevation above sea level (m) 16
Lowest elevation above sea level (m) 4
Laying method Buried up to B/L
No. of Road Crossing Nil
No. of Railway Crossing Nil
Nersa Queries CBM and Land 7dec2010a
Page 9 of | 16
4 Item 4 – Geographic Location of the proposed Site for the LPG
Facility
4.1 Sunrise Energy analysed several sites in terms of environmental impact, operations, safety and
commercial considerations.
4.2 The ArcelorMittal quarry site has proved to be the most ideal.
4.3 This is damaged quarry site that needs remediation. All of the environmental remediation
obligations have been taken over by Sunrise Energy as per the Offer to Purchase Agreement.
4.4 Excavation on the site during the quarrying operation has left a substantial cavity in the ground
which is ideal for burying the storage bullets. There is a significant cost saving in excavation
and civil works that would have had to be done on an alternate site. THIS FEATURE WILL BOTH
REDUCE THE CIVIL WORKS PROGRAMME while achieving the objectives of remediating the
site.
4.5 From the EIA work done to date, the eastern side of the site is bounded by fynbos and
vegetation classified as very high conservation value.
4.6 Sunrise Energy will use 40-50% of the site only. The results of the EIA study shows that that it
will be extremely difficult to use the remainder of the site for industrial development owing to
the sensitive nature of the plants in the area (refer to the attached Google Map below as well
as X and Y co-ordinates).
4.7 Boundaries selected to completely avoid encroachment on sensitive environmental areas.
4.8 The land survey has been completed by Sunrise Energy.
Nersa Queries CBM and Land 7dec2010a
Page 10 of | 16
4.9 Google Map showing Location of Study Area and proposed LPG Storage Area
Very High
Conservation Value
Medium to HighConservation
Value
Nersa Queries CBM and Land 7dec2010a
Page 11 of | 16
4.10 Sunrise Energy LPG Site X and Y Coordinates
Nersa Queries CBM and Land 7dec2010a
Page 12 of | 16
5 Item 5 – Geographic Location of Proposed Site Showing TNPA Land
5.1 The map below indicates the boundary between TNPA land and the proposed Sunrise Energy
site.
TNPA
Land
ArcelorMittal Land
Preferred Option G2
Sunrise Energy
Site
5.2 Sunrise Energy investigated ALL the options indicated in the above schematic as part of the
technical, commercial and environmental studies.
5.3 G2 is the preferred location of the CBM as presented in this application.
Nersa Queries CBM and Land 7dec2010a
Page 13 of | 16
6 Annexure 1: Drawing indicating the CBM Layout
Extract from consultant’s report indicating CBM layout.
Nersa Queries CBM and Land 7dec2010a
Page 14 of | 16
6.1 Simulation Results of Modelling Vessel navigation up to CBM (using wave, channel and wind
modelling sub-studies)
Nersa Queries CBM and Land 7dec2010a
Page 15 of | 16
7 Annexure 2: Location Details of the Undersea Pipeline Layout
Undersea
Pipeline Routing
Nersa Queries CBM and Land 7dec2010a
Page 16 of | 16
7.1 SUBSEA LINE COVERING AND CATHODIC PROTECTION
The SmartMat is a standard flexible concrete stability mattress integrated with a cathodic protection
system. The system involves casting anodes directly into the individual concrete blocks of the mat and
wiring them to the pipeline with the use of a connection clamp (RetroClamp), as shown below.
SmartMat
Retroclamp
SmartMat
Retroclamp