K/C - 4 GOVERNMENT OF KARNATAKA REQUEST FOR PROPOSAL TSCL/SPV/PMC/2016-17 APPOINTMENT OF PROJECT MANAGEMENT CONSULTANT FOR IMPLEMENTATION OF SMART CITY MISSION PROJECT OF TUMAKURU CITY TUMAKURU SMART CITY LIMITED OFFICE OF THE COMMISSIONER TUMAKURU CITY CORPORATION TOWN HALL CIRCLE, TUMAKURU-572101 KARNATAKA, INDIA

Transcript of INTRODUCTION · Web viewThe sub-projects identified in the SCPs can be broadly classified as Area...

K/C - 4

GOVERNMENT OF KARNATAKA

REQUEST FOR PROPOSAL

TSCL/SPV/PMC/2016-17

APPOINTMENT OF PROJECT MANAGEMENT CONSULTANT

FOR

IMPLEMENTATION OF SMART CITY MISSION PROJECT

OF

TUMAKURU CITY

TUMAKURU SMART CITY LIMITED

OFFICE OF THE COMMISSIONER

TUMAKURU CITY CORPORATIONTOWN HALL CIRCLE, TUMAKURU-572101

KARNATAKA, INDIA

Table of ContentsSECTION-1. LETTER OF INVITATION.....................................................................................................................1

SECTION-2. INFORMATION TO CONSULTANTS................................................................................................3

1. INTRODUCTION....................................................................................................................................................3

2. CLARIFICATION AND AMENDMENT OF RFP...........................................................................................5

3. PREPARATION OF PROPOSAL........................................................................................................................6

4. SUBMISSION, RECEIPT, AND OPENING OF PROPOSALS....................................................................8

5. PROPOSAL EVALUATION..................................................................................................................................9

6. NEGOTIATIONS.................................................................................................................................................. 10

7. AWARD OF CONTRACT...................................................................................................................................12

8. CONFIDENTIALITY...........................................................................................................................................12

A. DATA SHEET........................................................................................................................................................ 13

SECTION 3. TECHNICAL PROPOSAL - STANDARD FORMS............................................................................18

3A. TECHNICAL PROPOSAL SUBMISSION FORM.....................................................................................19

3B. CONSULTANT’S REFERENCES..................................................................................................................20

3C. COMMENTS AND SUGGESTIONS OF CONSULTANT ON THE EXISTING PROJECT FACILITIES (WASTE PROCESSING PLANT AND LANDFILL SITE) TO BE PROVIDED BY THE EMPLOYER.................................................................................................................................................................23

3D. DESCRIPTION OF THE METHODOLOGY AND WORK PLAN FOR PERFORMING THE ASSIGNMENT............................................................................................................................................................24

3E. TEAM COMPOSITION AND TASK ASSIGNMENTS.............................................................................25

3F. FORMAT OF CURRICULUM VITAE (CV) FOR PROPOSED KEY PROFESSIONAL STAFF.. .27

3G. TIME SCHEDULE FOR PROFESSIONAL PERSONNEL......................................................................29

3H. ACTIVITY (WORK) SCHEDULE.................................................................................................................31

SECTION 4 FINANCIAL PROPOSAL - STANDARD FORMS..............................................................................35

4A. FINANCIAL PROPOSAL SUBMISSION FORM.......................................................................................36

4B. SUMMARY OF COSTS.....................................................................................................................................37

4C. BREAK DOWN OF COSTS (Rs.)..................................................................................................................39

SECTION 5. TERMS OF REFERENCE......................................................................................................................42

SECTION 6: CONTRACT FOR CONSULTANT’S SERVICES...............................................................................55

I. FORM OF CONTRACT.......................................................................................................................................58

II. GENERAL CONDITIONS OF CONTRACT...................................................................................................60

1. General Provisions.......................................................................................................................................60

2. Commencement, Completion, Modification and termination of Contract...........................61

3. Obligations of the Consultant:.................................................................................................................64

1

4. Consultant’ Personnel and Sub-Contractors.....................................................................................67

5. Obligations of the Employer.....................................................................................................................67

6. Payment to the Consultant:......................................................................................................................68

7. Settlement of Disputes................................................................................................................................68

III. SPECIAL CONDITIONS OF CONTRACT.....................................................................................................70

IV. APPENDICES........................................................................................................................................................ 74

Appendix A: Description of the Services......................................................................................................74

Appendix B: Reporting Requirements...........................................................................................................75

Appendix C: Key Personnel and Sub-Contractor......................................................................................78

Appendix D: Services and Facilities to be provided by the Employer.............................................82

Appendix E: Payment of Contract Price........................................................................................................83

Appendix –F :Format of the Performance Bank Guarantee.................................................................88

2

TUMAKURU SMART CITY LIMITED

The Commissioner,

Tumakuru City Corporation.

TUMAKURU CITY CORPORATION PREMISES,TOWN HALL CIRCLE, TUMAKURU-572101

KARNATAKA, INDIA

SECTION-1. LETTER OF NOTIFICATION

No. Tender Number Date : 21-11-2016

1. The Tumakuru City Corporation invites bids for the “Appointment of Project Management Consultants” for implementation of Smart City mission projects in Tumakuru city. Details of the services required is provided in the attached Terms of Reference (ToR)

2. Tumakuru City Corporation on behalf of Tumakuru Smart City Special Purpose Vehicle invites eligible consultants to indicate their interest in providing the aforementioned services. Evaluation of bids shall be done in Single stage but Three Cover System

1 Pre-Qualification Bidders to meet the minimum pre-qualification conditions (Max Top six Bidders would be prequalified).

2 Technical Proposal Minimum Passing Mark -70

3 Financial Proposal The financial proposal of Technically responsive bidders will be opened as per the procedures prescribed in this RfP.

2.1 The interested consultants shall furnish the following information in support of the required pre-qualification and experience to carry out the said services:

a) A Registered company under Companies Act 1956 and latest amendment thereafter. b) Minimum annual turnover of Rs. 50 Crore, in any one of the last 5 financial years. The

lead member shall meet at least 50% of this requirement.c) Provided design and project management consultancy services in a single Urban

Infrastructure Project with a consultancy fee of not less than Rs 15 Crore during the last 7 years.

d) Implemented at least two ICT (Information Communication & Technology) based smart solution projects of value not less than Rs.5 Crore in urban areas in last 7 years.

e) Successfully structured and signed concession agreement in at least two PPP projects in last 7 years.

f) Experience of working with Government and/or Government bodies.

1PMC Appointment City Corporation

2.2 Firms may submit proposal as Sole Bidder or Joint Venture/Consortium. Maximum JV/Consortium allowed is 3, including the lead member. However, local consortium partner will be given additional weightage.

2.3 Maximum top six consultants would be considered for the technical Stage. Scoring system will be applicable only for 2.1(b),(c),(d) & (e). Higher scores will be provided for relevance of the project to the assignment and for the number of projects carried out in the last 7 years.

2.4 Maximum Two smart city PMC contracts of the State (out of 6 smart cities) shall be awarded to any Sole Bidder/Consortium/Members of consortium

3. The Consultant will be selected under Quality-and Cost-Based Selection (QCBS) and as per

procedure described in this RFP.

4. The RFP includes the following documents:

• Section 1 - Letter of Invitation

• Section 2 - Information to the Consultant

• Section 3 - Technical Proposal - Standard Forms

• Section 4 - Financial Proposal - Standard Forms

• Section 5 - Terms of Reference

• Section 6 - Standard Form of Contract.

• Section 7 - Appendix

Yours sincerely, Sd/-

Phone : +91816-2278480/2272200E-mail: [email protected]: www.tumkurcity.mrc.gov.in

2PMC Appointment City Corporation

SECTION-2. INFORMATION TO CONSULTANTS

1. INTRODUCTION

1.1. The Employer named in the “Data Sheet” will select a firm, in accordance with the method

of selection indicated in the Data Sheet.

1.2. The Consultant are invited to submit a Pre-Qualification Proposal, Technical Proposal and a

Financial Proposal, as specified in the Data Sheet (the Proposal) for consulting services

required for the Assignment named in the Data Sheet through the e-procurement

platform. The Proposal will be the basis for contract negotiations and ultimately for a

signed contract with the selected Consultant.

1.3. The Assignment shall be implemented in accordance with the phasing indicated in the Data

Sheet. When the Assignment includes several phases, the performance of the Consultant

under each phase must be to the Employer’s satisfaction before work begins on the next

phase.

1.4. The Consultants must familiarize themselves with local conditions and take them into

account in preparing their Proposals. To obtain first-hand information on the Assignment

and on the local conditions, Consultant are encouraged to pay a visit to the Employer’s City

before submitting a Proposal and to attend the Pre-Proposal conference as specified in the

Data Sheet. Attending the Pre-Proposal Cconference is optional. The Consultant’s

representative should contact the officials named in the Data Sheet to arrange for their visit

or to obtain additional information on the Pre-Proposal conference. Consultant should

ensure that these officials are advised of the visit in advance and obtain their concurrence

to allow them to make appropriate arrangements.

1.5. The Employer will provide the inputs specified in the Data Sheet, the firm shall cause to

obtain licenses and permits needed to carry out the services. The Employer may assist if

needed.

1.6. Please note that (i) the costs of preparing the Proposal and of negotiating the contract,

including a visit to the Employer, are not reimbursable as a direct cost of the Assignment;

and (ii) the Employer is not bound to accept any of the Proposals submitted without

assigning any reasons.

1.7. The Employer expects Consultant to provide professional, objective, and impartial advice

and at all times hold the Employer’s interests paramount, without any consideration for

future work, and strictly avoid conflicts with other assignments or their own corporate

interests. Consultant shall not be hired for any assignment that would be in conflict with

3PMC Appointment City Corporation

their prior or current obligations to other Employers that may place them in a position of

not being able to carry out the assignment in the best interest of the Employer.

1.7.1 Without limitation on the generality of this rule, Consultant shall not be hired

under the circumstances set forth below:

a) A firm which has been engaged by the Employer to provide goods or works for

a project, and any of their affiliates, shall be disqualified from providing

consulting services for the same project. Conversely, firms hired to provide

consulting services for the preparation or implementation of a project, and any

of their affiliates, shall be disqualified from subsequently providing goods or

works or services related to the initial assignment (other than a continuation

of the firm’s earlier consulting services) for the same project.

b) Consultant or any of their affiliates shall not be hired for any assignment

which, by its nature, may be in conflict with another assignment of the

Consultant.

1.7.2 As pointed out in para. 1.7.1(a) above, Consultant may be hired for downstream

work, when continuity is essential, in which case this possibility shall be

indicated in the Data Sheet and the factors used for the selection of the

Consultant should take the likelihood of continuation into account. It will be the

exclusive decision of the Employer whether or not to have the downstream

assignment carried out, and if it is carried out, which Consultant will be hired for

the purpose.

1.8. It is GoK’s/Employers policy to require that Consultant observe the highest standard of

ethics during the execution of such contracts. In pursuance of this policy, the

GoK/Employer:

a. defines, for the purposes of this provision, the terms set forth below as follows:

i. “corrupt practice” means the offering, giving, receiving, or soliciting of

anything of value to influence the action of a public official in the

selection process or in contract execution; and

ii. “fraudulent practice” means a misrepresentation of facts in order to

influence a selection process or the execution of a contract to the

detriment of GoK, and includes collusive practices among Consultant

(prior to or after submission of Proposals) designed to establish prices at

artificial, non-competitive levels and to deprive GoK of the benefits of

free and open competition.

4PMC Appointment City Corporation

b. will reject a Proposal for award if it determines that the firm recommended for

award has engaged in corrupt or fraudulent activities in competing for the

contract in question;

c. will declare a firm ineligible, either indefinitely or for a stated period of time, to

be awarded GoK-financed contract if it at any time determines that the firm has

engaged in corrupt or fraudulent practices in competing for, or in executing a

GoK-financed contract; and

d. Will have the right to require that, GoK to inspect Consultant’s accounts and

records relating to the performance of the contract and to have them audited by

auditors appointed by GoK.

1.9. Consultant shall not be under a declaration of ineligibility for corrupt and fraudulent

practices issued by GoK in accordance with the above sub para 1.8 (d).

1.10. Consultant shall be aware of the provisions on fraud and corruption stated in the

standard contract under the clauses indicated in the Data Sheet.

2. CLARIFICATION AND AMENDMENT OF RFP

2.1 Consultants may request a clarification of any item of the RFP document up to the number of

days indicated in the Data Sheet before the Proposal submission date. Any request for

clarification must be sent in writing by paper mail, cable, telex, facsimile, or electronic mail

to the Employer’s address indicated in the Data Sheet. The Employer will respond by cable,

telex, facsimile, or electronic mail to such requests and will send copies of the response

(including an explanation of the query but without identifying the source of inquiry) to all

invited consultants who intend to submit proposals.

2.2 Before the deadline for submission of proposals, the Employer may modify the RFP

documents by issuing online addendum. The addendum will appear on the web page of the

website https://eproc.karnataka.gov.in/eprocurement/common/ eproc_tenders_list.seam.

Any addendum thus issued shall be part of the RFP documents and deemed to have been

communicated to all the prospective Consultants. To give prospective Consultants

reasonable time in which to take an addendum into account in preparing their proposals,

the Employer may extend as necessary the deadline for submission of proposals.

5PMC Appointment City Corporation

3. PREPARATION OF PROPOSAL

3.1 Consultants are requested to submit the Proposal (para 1.2) written in the language

specified in the Data Sheet.

PRE-QUALIFICATION PROPOSAL

3.1.1 In preparing the Pre-Qualification Proposal, Consultant is expected to examine the

documents comprising this RFP in detail. Material deficiencies in providing the

information requested may result in rejection of the Proposal. The details of documents

to be provided is listed in the Data Sheet.

TECHNICAL PROPOSAL

3.2 In preparing the Technical Proposal, Consultant is expected to examine the documents

comprising this RFP in detail. Material deficiencies in providing the information requested

may result in rejection of the Proposal.

3.3 While preparing the Technical Proposal, Consultant must give particular attention to the

following:

i. If a Consultant considers that he does not have all the expertise for the Assignment,

he may obtain a full range of expertise by associating with individual Consultant(s)

and/or other Consultant or entities in a joint venture or sub-consultancy, as

appropriate. Consultant may associate with the other Consultant invited for this

Assignment only with approval of the Employer as indicated in the Data Sheet.

Consultant must obtain the approval of the Employer to enter into a Joint

Venture/Consortium with Consultant not invited for this assignment.

The Consultant shall submit JV/Consortium letter along with the bid in the format as

detailed under Section III.

ii. For assignments on a staff-time basis, the estimated number of key professional

staff-months is given in the Data Sheet. The Proposals shall, however be based on

the number of key professional staff-months estimated by the firm.

iii. It is desirable that the majority of the key professional staff proposed be

permanent employees of the firm or has an extended and stable working relation

with it.

iv. Proposed key professional staff must have at least the minimum experience

indicated in the Data Sheet.

v. Alternative key professional staff shall not be proposed, and only one curriculum

vitae (CV) may be submitted for each position.

6PMC Appointment City Corporation

vi. Reports to be issued by the Consultant as part of this assignment must be in the

language(s) specified in the Data Sheet. It is desirable that the firm’s personnel

have a working knowledge of the Employer’s official language.

3.4 The Technical Proposal should provide the following information using the attached

Standard Forms (Section 3):

i. A brief description of the Consultant’s organization and an outline of recent

experience on assignments (Section 3B) of a similar nature. For each assignment,

the outline should indicate, inter alia, the profiles and names of the staff

provided, duration of the assignment, contract amount, and firm’s involvement.

ii. Any comments or suggestions on the Terms of Reference and on the data, a list

of services, and facilities to be provided by the Employer (Section 3C) .

iii. A description of the methodology and work plan for performing the assignment

(Section 3D).

iv. The list of the proposed staff team by specialty, the tasks that would be assigned

to each staff team member, and their timing (Section 3E).

v. CVs recently signed by the proposed key professional staff and the authorized

representative submitting the Proposal (Section 3F). Key information should

include number of years working for the firm in the last 10 years. Letter of

Consent from the proposed key professional staff only, are to be appended to

the bid. However, in respect, of other experts, the Consultant can submit the

duly signed CVs at the time of Negotiation. Estimates of the total staff effort

(professional and support staff; staff time) and tools, equipments and machines

to be provided to carry out the Assignment, supported by bar chart diagrams

showing the time proposed for each key professional staff team member.

(Sections 3E and 3G).

vi. A detailed description of the proposed methodology, staffing, and monitoring of

training, if the Data Sheet specifies training as a major component of the

assignment.

vii. Any additional information requested in the Data Sheet.

3.5 The Technical Proposal shall not include any financial proposal forms. Bid will be treated

Technically Non Responsive if technical proposal includes any financial submission forms.

FINANCIAL PROPOSAL

3.6 In preparing the Financial Proposal, Consultant is expected to take into account the

requirements and conditions of the RFP document. The Financial Proposal should follow

Standard Forms (Section 4). It lists all costs associated with the Assignment, including (a)

remuneration for staff , and (b) reimbursable such as subsistence (per diem, housing),

7PMC Appointment City Corporation

transportation (national and local, for mobilization and demobilization), services (vehicles,

office equipment, furniture, and supplies), office rent, insurance, printing of documents,

surveys; and training, if it is a major component of the assignment. If appropriate, these

costs should be broken down by activity. If financial forms under section 4 are not

uploaded, the bid shall stand rejected.

3.7 Consultant shall express the price of their services (Consultancy fee) in Indian Rupees in

the e-procurement portal and the same shall be inclusive of all Taxes. However, in RFP

Section 4, Form B the same shall be quoted exclusive of applicable taxes. For evaluation

purpose the quote excluding applicable taxes will be considered.

3.8 The Data Sheet indicates how long the Proposals must remain valid after the submission

date. During this period, the Consultant is expected to keep available the key professional

staff proposed for the assignment. The Employer will make its best effort to complete

negotiations within this period. If the Employer wishes to extend the validity period of the

Proposals, the Consultant who do not agree, have the right not to extend the validity of their

Proposals which also results in rejection of their Bid.

4. SUBMISSION, RECEIPT, AND OPENING OF PROPOSALS

4.1 The Pre-qualification proposal, Technical Proposal and Financial Proposal; see para 1.2 shall

be uploaded in the e-procurement portal. The documents and details mentioned in clause 3

above shall be submitted online on website https://eproc.karnataka.gov.in. Details and

process of online submission of the tender and relevant documents are given in the website

mentioned above.

4.2 The proposal under this contract is electronic proposal submission through website

https://eproc.karnataka.gov.in. Detailed guidelines for viewing proposals and submission

of online proposals are given on the website. The Invitation for Proposals is published on

this website. Consultant can logon to this website and view the Invitation for Proposals and

can view the details of works for which proposals are invited. The prospective Consultant

can submit proposals online; for this, the Consultant is required to have

enrolment/registration in the website and should have valid Digital Signature Certificate

(DSC). The DSC can be obtained from any authorized certifying agencies. The Consultant

should register in the web site https://eproc.karnataka.gov.in. After this, the Consultant can

login the site through the secured login.

Note: The Employer shall not be responsible for any technical issues pertaining to internet

connectivity, browser compatibility and any other technical issues pertaining to e-

procurement portal.

8PMC Appointment City Corporation

4.3 Consultants are requested to go through the RFPs carefully and submit the required

information without exception, otherwise proposals will be rejected.

4.4 The completed proposal comprising documents indicated in clause 3, should be uploaded

on the website given above through e-tendering along with scanned copies of requisite

certificates as are mentioned in different sections in the RFP document

4.5 Proposals must be received by the Employer on line not later than time specified in the

proposal data sheet. The electronic system would not allow any late submission of

proposals after due date and time as per server time.

4.6 After the deadline for submission of Proposals, the Prequalification proposals will be

opened after 2 working days from the date & time of submission of proposals. After

evaluation of prequalification proposals, the Technical Proposals of the top 6/available

bidders will be opened. . The Financial Proposal of the successful Consultants only will be

opened after completion of technical proposal evaluation.

5. PROPOSAL EVALUATION

General

5.1 From the time the Proposals are opened to the time the contract is awarded, if any

Consultant wishes to contact the Employer on any matter related to its Proposal, it should

do so in writing at the address indicated in the Data Sheet. Any effort by the firm to

influence the Employer in the Employer’s Proposal evaluation, Proposal comparison or

contract award decisions may result in the rejection of the Consultant’s Proposal.

5.2 Evaluators of prequalification proposals shall have no access to technical & financial

proposal. Evaluators of Technical Proposals shall have no access to the Financial Proposals

until the technical evaluation, including its approval by competent authority is obtained.

Evaluation of Pre qualification Proposal

5.2.1 The evaluation committee appointed by the Employer as a whole, and each of its

members individually will evaluate the Proposals on the basis of their responsiveness to

the pre qualification conditions. A Proposal shall be rejected at this stage if it does not

respond to important aspects of the pre qualification criteria or it fails to achieve the

minimum score indicated in the Data Sheet. Technical proposal of the pre qualified

bidder will only be opened and same will be intimated prior to the opening of technical

proposal.

Evaluation of Technical Proposals

5.3 The evaluation committee appointed by the Employer as a whole, and each of its members

individually will evaluate the Proposals on the basis of their responsiveness to the Terms of

9PMC Appointment City Corporation

Reference, applying the evaluation criteria, sub-criteria (typically not more than three per

criteria) and point system specified in the Data Sheet. Each responsive Proposal will be

given a technical score (St). A Proposal shall be rejected at this stage if it does not respond to

important aspects of the Terms of Reference or if it fails to achieve the minimum technical

score indicated in the Data Sheet.

Public Opening and Evaluation of Financial Proposals; Ranking

5.4 After the evaluation of technical Proposal is completed, the Employer shall notify those

Consultants whose Proposals did not meet the minimum qualifying mark or were

considered non-responsive to the RFP and Terms of Reference, indicating that their

Financial Proposals will not be opened after completing the selection process. The Employer

shall simultaneously notify the Consultant those have secured the minimum qualifying

mark, indicating the date and time set for opening the Financial Proposals. The notification

may be intimated through the e-procurement portal.

5.4.1 The Financial Proposals of the Smart Cities will be opened sequentially in the

alphabetical order of the Cities by name namely

1. Hubballi-Dharward

2. Mangaluru

3. Shivamogga

4.Tumakuru

5.4.2 In the event, a bidder (sole bidder/consortium/ one of the consortium member) is

already awarded with one PMC contract and H1 as per QCBS in one city OR the bidder is

H1 in 2 cities, his technical bid for the subsequent cities will not be considered for

opening of Financial bids.

5.5 The Financial Proposals shall be opened publicly in the presence of the Consultants’

representatives who choose to attend. The name of the Consultant, the quality scores, and

the proposed prices shall be read aloud and recorded when the Financial Proposals are

opened. The Employer shall prepare minutes of the public opening.

5.6 The evaluation committee will determine whether the Financial Proposals are complete,

(i.e., whether they have quoted all items of the corresponding Technical Proposals, if not, the

Employer will cost them and add their cost to the initial price, correct any computational

errors.

5.7 The lowest Financial Proposal (Fm) will be given a financial score (Sf) of 100 points. The

financial scores (Sf) of the other Financial Proposals will be computed as indicated in the

10PMC Appointment City Corporation

Data Sheet. Proposals will be ranked according to their combined technical (St) and financial

(Sf) scores using the weights (T = the weight given to the Technical Proposal; P = the weight

given to the Financial Proposal; T + P = 1) indicated in the Data Sheet: St.Tx Sf.P=×+×% . The

Consultant achieving the highest combined technical/ financial score will be invited for

negotiations.

6. NEGOTIATIONS

6.1 Negotiations will be held at the address indicated in the Data Sheet and through the

e-procurement portal. The aim is to reach agreement on all points and sign a contract.

6.2 Negotiations will include a discussion of the Technical Proposal, the proposed methodology

(work plan), staffing and any suggestions made by the firm to improve the Terms of

Reference. The Employer and Consultant will then work out final Terms of Reference,

staffing, and bar charts indicating activities, staff, periods in the field and in the home office,

staff-months, logistics, and reporting. The agreed work plan and final Terms of Reference

will then be incorporated in the “Description of Services” and form part of the contract.

Special attention will be paid to getting the most the Consultant can offer within the

available budget and to clearly defining the inputs required from the Employer to ensure

satisfactory implementation of the Assignment.

6.3 Unless there are exceptional reasons, the financial negotiations will involve neither the

remuneration rates for staff (no breakdown of fees) nor other proposed unit rates.

6.4 Having selected the Consultant on the basis of, among other things, an evaluation of

proposed key professional staff, the Employer expects to negotiate a contract on the basis of

the experts named in the Proposal. Before contract negotiations, the Employer will require

assurances that the experts and the tools and equipment’s will be actually available. The

Employer will not consider substitutions during contract negotiations unless both parties

agree that undue delay in the selection process makes such substitution unavoidable or that

such changes are critical to meet the objectives of the assignment. If this is not the case and

if it is established that key staff was offered in the Proposal without confirming their

availability, the Consultant may be disqualified.

6.5 The negotiations will conclude with a review of the draft form of the contract. To complete

negotiations the Employer and the Consultant will initial the agreed contract. If negotiations

fail, the Employer will invite the firm whose Proposal received the second highest score to

negotiate a contract.

11PMC Appointment City Corporation

7. AWARD OF CONTRACT

7.1 Not more than two smart city PMC contracts of the State (Out of six), including already

awarded contracts of two cities Davanagere and Belagavi, shall be awarded to any Sole

Bidder/Consortium/Members of consortium. The contract will be awarded following

negotiations. After negotiations are completed, the Employer will promptly notify other

Consultants on the shortlist that they were unsuccessful.

7.1.1 In the event, a bidder (sole bidder/consortium/ one of the consortium member) is

already awarded with one PMC contract and H1 as per QCBS in one city OR the

bidder is H1 in 2 cities, his technical bid for the subsequent cities will not be

considered for opening of Financial bids.

7.2 The Consultant is expected to commence the Assignment on the date and at the location

specified in the Data Sheet.

8. CONFIDENTIALITY

8.1 Information relating to evaluation of Proposals and recommendations concerning awards

shall not be disclosed to the Consultant who submitted the Proposals or to other persons

not officially concerned with the process, until the winning Consultant has been notified that

it has been awarded the contract.

12PMC Appointment City Corporation

A. DATA SHEETInformation to Consultant

Clause Ref.

1. 1 The name of the Employer is: Tumakuru Smart City Limited.The method of selection is: Quality & Cost Based Selection (QCBS)

1.2 Pre-Qualification, Technical and a Financial Proposals are requested: Yes The name, objectives and description of the Assignment are: “APPOINTMENT OF PROJECT MANAGEMENT CONSULTANT FOR IMPLEMENTATION OF SMART CITY MISSION PROJECTS IN TUMAKURU CITY”

Objective:

The objective of engaging The Project Management Consultant’s (PMC) is to

provide strategic & project management assistance to TSCL for ensuring timely

completion of projects and achieving the outcomes outlined in the Smart City

Proposal (SCP), based on the Smart City Mission Guidelines.

1.3 The Assignment is phased: Yes1. Design Phase2. Implementation Phase

1.4 A Pre-Proposal conference will be held: Yes Date: 08-12-2016 Time: 11:30 AMThe name(s), address(es), and telephone/numbers of the Employer’s Official(s) are: Address: Karnataka Urban Infrastructure Development & Finanace Corporation Limited (KUIDFC),Nagarabhivruddi Bhavan, #22, 17th F Cross, Old Madras Road, Indiranagar 2nd Stage, Bengaluru – 560 038

Telephone : 080-25196159, 080 -25196124-129

Email: 1) [email protected] 2) [email protected]

1.5 The Employer will provide the following inputs: 1. Necessary assistance in coordinating with the Consultant for ensuring availability of

existing data, records, reports etc.2. The Smart City proposal submitted and approved by MoUD.

1.7.2 The Employer envisages the need for continuity for downstream work: Yes

1.11 The clauses on fraud and corruption in the contract are Sub-Clause 2.7.1 of G.C.C.

2.1 Clarifications may be requested up to Five days prior to Pre-Proposal conference

3.1 Proposals should be submitted in the following language(s): English

3.1.1 The interested consultants shall furnish information in support of the required pre-

13PMC Appointment City Corporation

Clause Ref.

qualification and experience to carry out the said services.

a) A Registered company under Companies Act 1956 and latest amendment thereafter

b) Minimum annual turnover of Rs. 50 Crore, in any one of the last 5 financial years. The lead member shall meet at least 50% of the required qualification and the balance members shall meet at least 25% of the required qualification.

c) Provided design and project management consultancy services in a single Urban Infrastructure Project with a consultancy fee of not less than Rs 15 Crore during the last 7 years.

d) Implemented at least two ICT based smart solution projects of value not less than Rs.5 Crore in urban areas in last 7 years.

e) Successfully structured and signed concession agreement in at least two PPP project in last 7 years.

f) Experience of working with Government and/or Government bodies.

Maximum Top Six consultants would be considered for the next stage (Technical Stage). Scoring system will be applicable only for 2.1(d),(e),(f) & (g). Higher scores will be provided for relevance of the project to the assignment and for the number of projects carried out in the last 7 years.

3.3 i. Consultant may associate with other consultant participating in this bid: Consultant may associate with other Consultant on the following lines:

✓ JV/Consortium is restricted to 3 Numbers.✓ All JV/Consortium partners combined together shall meet the Qualification

Criteria. ✓ The bidder at the time of submission of bids shall submit a Joint Venture

agreement/Consortium letter declaring the lead partner. ii. The estimated number of key professional staff months required for the assignment

is: need to be assessed by the Consultant on the basis of SCP. (unit man months)iii. Reports which are part of the assignment must be written in the following language:

Englishiv. The minimum required experience of proposed key professional staff whose CV will

be evaluated is:

No Position Qualifications &Skills Experience

1 Team Leader cum Urban Management specialist

Bachelor in Engineering with Masters in Urban Planning

20 Years experience in Urban Sector Experience of Project Management in

Urban Infrastructure Works. Experience as Team leader/ Deputy Team leader for minimum one project.

Knowledge of urban development issues and Project experience.

Experience in Project Management, Project Financing and Contract structuring.

14PMC Appointment City Corporation

Clause Ref.

2 Infrastructure/ Engineering Specialist with Civil building construction expert

Masters Degree in Civil Engineering

At least 10 yrs experience in related assignment.

Experience in working in building construction & urban infrastructure projects which shall include preparation of designs, drawings & DPRs.

3 Town Planning Scheme Expert

Master Degree in Urban Planning

At least 5 yrs experience in related assignment.

Experience in designing/implementation of minimum 2 Town Planning Schemes.

4 Urban Finance Specialist

Masters Degree in Finance/ Economics/ Chartered Accountant/ Commerce/ ICWA / Post Graduate in Economics with specialization in Public Finance.

At least 10 years relevant experience. Experience of municipal finance

analysis, municipal budgeting and accounting and financial projections.

Experiences in Financial Modeling in Urban Infrastructure, PPP & Market borrowing are desirable/MBA in Finance.

5 PPP Specialist Degree in Civil Engineering/ Master of Business Administration is desirable.

At least 10 years relevant experience. Experience of procurement related

activities for urban infrastructure projects.

Experience in PPP contract structuring and concluding concession Agreements.

6 E-Governance/ICT Specialist

Degree in Information Technology/ Electronics Engineering or equivalent

At least 5 years’ relevant experience Experience in MIS for institutional /

Governance level and integration of various user data

Experience in preparation of technical requirements document of the e-Services and solution to implementing the IT related infrastructure services /e-services, networking infrastructure etc.

Proven knowledge of modern Internet technologies and experience in software development projects/ GIS;

Working experience in network administration and use of hardware/software, telecommunications facilities,

Experience in databases development, programming and web designing; Crowd sourcing on e and m – platforms with respect to local bodies.

Experience in institutional lasing various services under e-government, creation of command centre.

15PMC Appointment City Corporation

Clause No

3.4 vii. Training is an important feature of this Assignment: Yes (Impart training to personnel authorized by SPV on aspects like O&M , QAP etc)

viii. Additional Information in the Technical Proposal shall include Schedule 3H consisting of deployment details key professionals, development professional and support staff. In the event of submission of incomplete information in the said form, the technical proposal will be treated as non-responsive.

3.10 Proposals must remain valid 120 days after the submission date.

4.5 Proposals must be submitted no later than the following date and time 06/01/2017 & 16:00 Hrs

5.1 The address to send information to the Employer is: Address: TUMAKURU SMART CITY LIMITED TUMAKURU CITY CORPORATIONTOWN HALL CIRCLE, TUMAKURU-572101AddressTelephone : +91816-2278480/2272200

Email: 1) [email protected] 2) [email protected]

5.3 The number of points to be given under each of the evaluation criteria are:1. The Sole Bidder/ Consortium with local presence (Corporate/Branch Office) -10 Marks

a. State Level - 5 Marksb. City Level – 10 Marks

2. Specific experience of the Consultant related to the Assignment in the last 7 years: - 20 Marks.

a) Provided Design and Project Management Consultancy services in Urban Infrastructure Projects -10 marks

b) Implemented ICT based smart solution projects in urban areas – 5 marks(Consultant may demonstrate various type of ICT based smart solutions. If Consultant demonstrates that he has offered different type of ICT solutions additional marks would be given)

c) Successfully structured and signed concession agreement for PPP project – 5 marks Note: Certificate in respect of a, b & c above the certificate issued by the officer of the rank not below the commissioner/equivalent of the concerned ULB shall only be accepted.

The consultant may also submit the details of ongoing projects which have been awarded at least 1 year prior to the date of Bidding. However, Employer’s certificate from the Competent Authority is a must. The language of Certification shall be English. Completed projects with work done certificate will be given additional weightage.

3. Adequacy of the proposed work plan and methodology in responding to the TOR - 20 Marksa) Technical approach & Methodology – 10 Marksb) Work Plan – 5 Marks

16PMC Appointment City Corporation

Clause No

c) Organization & Staffing – 5 Marks

4. Qualifications and competence of key professionals – 50 Marksa) Team Leader cum Urban Management specialist -15b) Infrastructure/ Engineering Specialist (Civil building construction expert ) –7c) Town Planning Scheme expert -8d) Urban Finance Specialist-05e) PPP Specialist -05f) E-Governance/ICT Specialist -10

The marks to be given for qualifications and competence of the Team Leader and Infrastructure specialist (Sl.No A-C) for the assignment will be: 1. General qualifications - 20 Marks 2. Adequacy for the project – 55 Marks 3. Experience of working as Resident Engineer/Expert in Tire -2 cities @ any position -10

Marks4. If the CV proposed is based from the Project City -10 Marks5. Experience in region & language -05 Marks The marks to be given for qualifications and competence of the other 3 key professional experts (Sl.No D-E) for the assignment will be:

1. General qualifications - 20 Marks 2. Adequacy for the project – 65 Marks 3. If the CV proposed is based from the Project City -10 Marks4. Experience in region & language -05Marks

The minimum technical score required to pass is : 70 Marks

5.8 The formula for determining the financial scores is the following:[Sf = 100 x Fm/F, in which Sf is the financial score, Fm is the lowest price, and F the price of the proposal under consideration]

The weights given to the Technical and Financial Proposals are: T= 0.75 & F=0.25

6.1 The address for negotiation is:Address: TUMAKURU SMART CITY LIMITED PREMISES, TUMAKURU CITY CORPORATIONTOWN HALL CIRCLE, TUMAKURU-572101Telephone : +91816-2278480/2272200/9902815928

Email: [email protected]

7.2 The Assignment is expected to commence on [Month, Year] at [Location]: Tentative Date: Within 10 days of signing of agreement @ Tumakuru

17PMC Appointment City Corporation

SECTION 3. TECHNICAL PROPOSAL - STANDARD FORMS

Content

3A. Proposal submission form.

3B. Consultant’s references.

3C. Comments and suggestions on the Terms of Reference and on data services, and facilities to be provided by the Employer.

3D. Description of the methodology and work plan for performing the assignment.

3E. Team composition and task assignments.

3F. Format of Curriculum Vitae of proposed key professional staff.

3G. Time schedule for professional personnel

3H. Activity (work) schedule

18PMC Appointment City Corporation

3A. PROPOSAL SUBMISSION FORM

[Location, Date]

FROM: (Name of Consultant) To: The Commissioner,Tumakuru City Corporation

Madam/Sir:

Subject: “Appointment of Project Management Consultants for implementation of Smart City Mission project in Tumakuru city” –Proposal Submission.

-------------

We, the undersigned, offer to provide the consultancy services for the above in accordance with your Request for Proposal dated [Date], and our Proposal. We are hereby submitting our Proposal which includes the Pre qualification proposal, Technical Proposal, and a Financial Proposal through e-procurement.

We are submitting our Proposal in association with: Insert a list with full name and address

of each joint venture partner

We hereby declare that all the information and statements made in this Proposal are true and accept that any misinterpretation contained in it may lead to our disqualification.

If negotiations are held during the period of validity of the Proposal, i.e., before [Date ] we undertake to negotiate on the basis of the proposed staff. Our Proposal is binding upon us and subject to the modifications resulting from contract negotiations.

We understand you are not bound to accept any Proposal you receive.

We remain, Yours sincerely,

Authorised Signatory [In full and initials]: Name and Title of Signatory: Name of Firm: Address:

19PMC Appointment City Corporation

3A(1). PRE QUALIFICATION SUBMISSION FORMPROSPECTIVE BIDDERS SHALL SUBMIT INFORMATION IN THE FOLLOWING FORMAT IN

THE UPLOADED BID

No Description

1 Registered company under Companies Act Yes/No (proof to be enclosed)

2 Annual turnover of Rs. 50 crore for the last 5 financial years

FY2011-12 12-13 13-14 14-15 15-16 Audited Balance sheet to be enclosed.

3 Provided design and project management consultancy services in a single Urban Infrastructure Project with a consultancy fee of not less than Rs 15 Crore during the last 7 (financial) years. (2009-10 to 2015-16)

No Name of Work(s) Employer Brief Scope of Work Value of the Project

(Work Order Copies/Completion certificate in English to be enclosed)

4 Implemented at least two ICT based smart solution projects of value not less than 5 cr in urban areas in last 7 (financial) years. (2009-10 to 2015-16)

No Name of Work(s) Employer Brief Scope of Work Value of the Project

(Work Order Copies/Completion certificate in English to be enclosed)

5 Successfully structured and signed concession agreement in at least two PPP project in last 7 (financial) years. (2009-10 to 2015-16)

No Name of Work(s) Employer Brief Scope of Work Concession Agreement Status

20PMC Appointment City Corporation

Proof of concession Agreement Signed to be provided

Experience of working with Government and/or Government bodies

Yes/No (proof to be enclosed)

21PMC Appointment City Corporation

TECHNICAL PROPOSAL SUBMISSION FORMS

3B. CONSULTANT’S REFERENCES

Relevant Services Carried Out in the Last Five Years

Using the format below, provide information on each reference assignment for which your firm/entity, either individually as a corporate entity or as one of the major companies within an association, was legally contracted.

Assignment Name: Country:

Location within Country: Key professional staff Provided by

Your Firm/entity(profiles)

Name of Employer: No. of Staff:

Address:No. of Staff-Months; duration of assignment:

Start Date (Month/Year):

Completion Date (Month/Year): Approx. Value of Services (Rs.):

Name of Associated Consultant, if any:

No. of Months of Key professionalstaff, providedby Associated

Consultant:

Name of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions performed:

Narrative Description of Project:

Description of Actual Services Provided by Your Staff:

22PMC Appointment City Corporation

3C. COMMENTS AND SUGGESTIONS OF CONSULTANT

On the Terms of Reference1.

2.

3.

4.

5

On the data, services, and facilities to be provided by the Employer

1.

2.

3.

4.

5

23PMC Appointment City Corporation

CONSULTANT’S NAME:

3D. DESCRIPTION OF THE METHODOLOGY AND WORK PLAN FOR PERFORMING THE ASSIGNMENT

Technical approach, methodology and work plan are the key components of the Technical Proposal. You shall present your Technical Proposal (maximum of 15 pages, inclusive of charts and diagrams) divided into the following three chapters which will be submitted for the Design Phase and the Implementation Phase of the Project:

a) Technical Approach and Methodologyb) Work Plan, c) Key Professional, Development Professional and Necessary Support Staff deployment

Schedule – Sub Project Specific

a) Technical Approach and Methodology: In this chapter the bidder should explain your understanding of the objectives of the assignment, approach to the services, methodology for carrying out the activities and obtaining the expected output, and the degree of detail of such output. Proposed technical approach & methodology should be tailored made to the assignment for the projects proposed in Smart City Proposal. The bidder should highlight the critical areas for each of the major projects of SCP and explain how the problems will be addressed and the technical approach that would be followed for the same. The bidder shall also indicate the ways to improve the implementation of the sub projects by using state-of-the art technologies.

b) Work Plan

In this chapter the bidder should propose the main activities of the assignment, their content and duration, phasing and interrelations, milestones (including interim approvals by the Employer), and delivery dates of the reports. The proposed work plan should be consistent with the technical approach and methodology, showing understanding of the TOR and ability to translate them into a feasible working plan. A list of the final documents, including reports, drawings, and tables to be delivered as final output, should be included here. The work plan should be consistent with the Work Schedule of Form TECH-8. Consultant shall identify the Critical path and suggest measures to ensure that there will be no delays in the list of activities identified under the critical path.

c) Key Professional, Development Professional and Necessary Support Staff deployment Schedule Sub Project Specific:

In this chapter the bidder should propose the structure and composition of Consultant’s team for both design phase and implementation phase. Consultant shall also list the main disciplines of the assignment, the key professionals, development professionals responsible and proposed support personnel.

24PMC Appointment City Corporation

3E. TEAM COMPOSITION AND TASK ASSIGNMENTS1. Technical/ Managerial Staff

Sl. No.

Name Position Task List of sub projects likely to be involved

KEY PROFESSIONAL

1

2

3

4

5

6

Development Professional

1…

18

Construction Supervision Engineers

1 Construction Manager

2 Assistant Construction Manager

3 Site Engineers

4 Project Manager – Information Technology

5 Assistant Project Manager – Information Technology

6 Others (Draftsmen, surveyors etc..)

25PMC Appointment City Corporation

2. Support Staff

Sl. No.

Name Position Task

1….

5

6

26PMC Appointment City Corporation

3F. FORMAT OF CURRICULUM VITAE (CV) FOR PROPOSED KEY PROFESSIONAL STAFF Proposed Position:

Name of Consultant:

Name of Staff:

Profession:

Date of Birth:

Years with Firm/Entity: Nationality:

Membership in Professional Societies:

Detailed Tasks Assigned:

Key Qualifications:

[Give an outline of staff member’s experience and training most pertinent to tasks on assignment. Describe degree of responsibility held by staff member on relevant previous assignments and give dates and locations. Use about half a page.]

Education:

[Summarise college/university and other specialised education of staff member, giving names of schools, dates attended, and degrees obtained and any relevant certification/courses. Use about one quarter of a page.]

Employment Record:

[Starting with present position, list in reverse order every employment held. List all positions held by staff member since graduation, giving dates, names of employing organisations, titles of positions held, and locations of assignments. For experience in last ten years, also give types of activities performed and Employer references, where appropriate. Use about two pages.]

Resident Engineer:[List the projects where the said professional has worked as Resident Engineer in Tier-2 Cities. (Tier 2 City – excluding all Metropolitan cities)

Sl.No

Project City Duration Position Worked as

Languages:

[For each language indicate proficiency: excellent, good, fair, or poor; in speaking, reading, and writing ]

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, these data correctly

27PMC Appointment City Corporation

describe me, my qualifications, and my experience.

Date:

[Signature of staff member and authorized representative of the Consultant]

Day/Month/Year

Name of staff member:______________________________________

Full name & Signature of authorized representative: ___________________________

28PMC Appointment City Corporation

3G. TIME SCHEDULE FOR KEY PROFESSIONAL, DEVELOPMENT PROFESSIONAL & CONSTRUCTION SUPERVISION PERSONNEL

Months (in the form of a Bar Chart)*

Sl. No. Name PositionReports Due/Activities 1 2 3 4 5 ---- 60 Number of

Months

1.Subtotal (1)

2.Subtotal (2)

3.Subtotal (3)

4.Subtotal (4)

Design Phase:

Full-time:

Implementation Phase:

Part-time:

29PMC Appointment City Corporation

Reports Due:

Activities Duration:

Signature:

* The Schedule should be for the period of completion of assignment (Authorized Representative)

Full Name:

Title:

Address:

30PMC Appointment City Corporation

3H. ACTIVITY (WORK) SCHEDULE

No. Item of Activity (Work) Month-wise Program (in the form of Bar Chart)

[1st, 2nd, etc. are months from the start of assignment]

1st 2nd 3rd --- --- 60th

1

2

3

4

5

B. Completion and Submission of Reports

No Reports: Programme: (Date)

1

2

4

5

31PMC Appointment City Corporation

JOINT VENTURE/CONSORTIUM LETTER FORMAT

[To be executed on Rs. 300/- stamp paper]

This Consortium letter (hereinafter called the “Agreement”) made and entered into this …………………. day of the month of …………. 2016 by and among:

A. LEAD MEMBER:

1. [Name and address of the Lead Member firm] (hereinafter called “[Short Name or Acronym]”),

which expression shall include its successors, legal representatives and permitted assigns, who

for the purpose of this Agreement shall hereinafter called “Lead Member”;

B. ASSOCIATE MEMBERS:

2. [Name and address of the Member firm] (hereinafter called the “[Short Name or Acronym]”),

which expression shall include its successors, legal representatives and permitted assigns, who

for the purpose of this Agreement shall hereinafter called “Associate Member”.

3. [Name and address of the Member firm] (hereinafter called the “[Short Name or Acronym]”),

which expression shall include its successors, legal representatives and permitted assigns, who

for the purpose of this Agreement shall hereinafter called “Associate Member”.

WHEREAS

(a) the Employer (as defined hereunder) intends to appoint /has appointed the Consultants for providing Project management services; hereinafter called the “Services” for [Name/Title of the Project]; hereinafter called the “Project”; and

(b) the Members have agreed to join hands in the form of a Joint Venture to provide the said professional Project management services.

NOW THEREFORE, the Members have agreed as follows:

1. The words and expressions of all clauses shall have the meanings assigned to them as per the

RFP and Agreement thereafter.

2. “Consortium” means the joint venture formed between the Members in accordance with this

Agreement;

3. “Lead Member” means the member which will take the lead in the management of the Joint

Venture’s affairs and which will provide the Joint Venture’s Representative for liaison with the

Employer and, unless otherwise agreed by the Members, the Services Manager for direction of

the conduct of the Services;

4. "Associate Members" means the individuals or firms which have agreed to Joint Venture in

connection with the Project;

5. The Lead member shall be authorized to incur liabilities and receive instructions for and on

behalf of any and all members of the joint venture and the entire execution of the contract,

including payment, shall be done exclusively with the Lead member;

6. All members of the joint venture shall be liable jointly and severally for the execution of the

contract in accordance with the contract terms;

32PMC Appointment City Corporation

7. The Power of attorney of the signatory[ies] on behalf of the Consortium for all purposes

including signing of agreement, payment, regular communication etc is attached.

8. The Performance security for the contract shall be in the name of the Lead Partner.

9. The Lead Member of the Consortium will make all reasonable efforts to maintain insurance cover

in the amounts stated in the contract necessary to comply with the Agreement.

10.The precise role of all members of Consortium in respect of planning, design, construction

equipment, key personnel, work execution, and financing of the project are enclosed as

Annexure-1. All members of JV shall have active participation in execution during the currency of

the contract. This is not varied/modified subsequently without prior approval of the employer;

IN WITNESS WHEREOF the Members hereto have executed this Agreement in [state number of copies]

identical counterparts each of which shall be deemed as original.

1. For and on behalf of

[Name of the Lead Member firm]

Name of Authorized Representative: _______________

Designation: _______________

Date : ________________

Seal: _________________

2. For and on behalf of

[Name of the Member firm]

Name of

Authorized Representative ________________

Designation ________________

Date : ________________

Seal ________________

3. For and on behalf of

[Name of the Member firm]

Name of

Authorized Representative ________________

Designation ________________

Date : ________________

Seal ________________

33PMC Appointment City Corporation

Annexure-1

DETAILS OF PARTICIPATION IN THE JOINT VENTURE

PARTICIPATION DETAILS FIRM ‘A’ (Lead Member)

FIRM ‘B’(Member)

FIRM ‘C’(Member)

Financial

Name of the Banker(s)

Planning

Key professional /Development Professional

Execution of Consultancy Services (Give details on contribution of each)

Design and up to Bid process

Implementation support

* Fill the relevant fields.

34PMC Appointment City Corporation

SECTION 4 FINANCIAL PROPOSALS - STANDARD FORMS

Content

4A. Financial Proposal submission form.

4B. Summary of Costs

4C. Break Down Of Costs (Rs.)

35PMC Appointment City Corporation

4A. FINANCIAL PROPOSAL SUBMISSION FORM

[Location, Date]

FROM: (Name of Consultant) To: The Commissioner, City Corporation

Madam/Sir:

Subject: Appointment of Consultant for “Appointment of Project Management Consultants for implementation of Smart City Mission project in Tumakuru city” - Financial Proposal.

We, the undersigned, offer to provide the Design and Project Management Consultancy services for the above in accordance with your Request for Proposal dated [Date], and our Proposal (technical and Financial Proposals). Our attached financial Proposal is for the sum of …………………………………………….[Amount in words and figures] inclusive of all taxes and the sum of ……………………………[Amount in words and figures] exclusive of service taxes. In the event there is a difference between the quoted amount in the e-procurement portal and the RFP, the amount quoted in the RFP Section 4, 4B shall prevail.

Our Financial Proposal shall be binding upon us subject to the modifications resulting from contract negotiations, up to expiration of the validity period of the Proposal, i.e., [Date].

We undertake that, in competing for (and, if the award is made to us, in executing) the above contract, we will strictly observe the laws against fraud and corruption in force in India namely “Prevention of Corruption Act 1988”.

We understand you are not bound to accept any Proposal you receive.

We remain,

Yours sincerely,

Authorised Signatory: Name and Title of Signatory: Name of the Consultant: Address

36PMC Appointment City Corporation

4B. SUMMARY OF COSTS

1.0 General

1.1 The Price Schedules are divided into separate Schedules as follows:

Schedule 1 Price Schedule

Schedule 2 Break down of Prices

1.2 The Price Schedules do not give a full description of the services to be provided by the

Consultants. Consultants are deemed to have read the RFP and schedule to ascertain the

full scope of the requirements of the Contract included in each item prior to filling in the

prices. The entered prices are deemed to include the full scope as aforesaid, including

overheads, and profit.

1.3 If Consultants are unclear or uncertain as to the scope of any item, they shall seek

clarification in accordance with the Instructions to Consultants in the RFP Documents

prior to submitting their Proposal.

2.0 Pricing

2.1 The prices shall be fixed and firm for the duration of the Contract, except as adjusted in

accordance with the Contract, if applicable.

2.2 The Proposal Price shall be quoted in the manner indicated and in the currencies

specified in the Instructions to Consultants in the RFP Documents. For each item,

Consultants shall complete each appropriate column in the respective Schedule 4B,

giving the price breakdown as indicated in the Schedule 4c. Prices given in the

Schedules against each item shall be for the scope covered by that item as detailed in the

ToR or elsewhere in the RFP Documents.

2.3 When requested by the Employer for the purposes of making payments or part

payments, valuing changes or evaluating claims, or for such other purposes as the

Employer may reasonably require, the Consultant shall provide the Employer with a

breakdown of any composite or lump sum items included in the Schedules.

2.4 The Total Estimated Project value likely to be executed by the SPV is Rs. 1,000 Crore Plus

value of PPP project. However, the list of projects to be taken up will be prioritized by

the SPV and only after approval of SPV the same shall be taken up. The list of projects is

already made available in the SCP. Consultants are required to study the same before

quoting. The PMC is also expected to study the convergence projects for

comprehensiveness and identify gaps, if any. In the event of any portion of the

37PMC Appointment City Corporation

Convergence Project, if taken up for funding under SCM, the same will be considered for

payment of consultancy fee.

2.4 For any other project/s approved by SPV, in consultation with KUIDFC, over and above

the list of projects in the SCP for which consultancy services are provided by the PMC

will be considered for additional payment As per the quoted percentage fee.

2.5 The Consultant is supposed to quote the lump sum fee, exclusive of Service Tax, in

Column B and the same will form the basis for deriving the fee as a percentage (Column

C) of the total project cost (Column A). The % fee so derived will be rounded of to 2

decimal places. All payments pertaining to sub projects will be based on this % as

detailed vide Appendix

Description Total Project Cost(A)

Lump Sum Consultancy Fee

(B)

Consultancy Fee derived as

% of Project Cost (C)

(B/A*100)PMC fee towards – Goods, Works & Services

(1000 Cr + 344 Cr (PPP Projects))

Rs.-------

Note: The details of the components constituting the approved Smart City Proposal may be obtained by accessing the website : www.tumkurcity.mrc.gov.in

The above quote shall include all the taxes, duties, fees, levies and other impositions likely to be levied under the existing, amended or enacted laws during life of this contract except Service Tax.

Service Tax shall be paid extra as per prevailing rates from time to time, by the Employer.

Note: The ceiling cost of the project is as shown in the Summary of Costs. Payments will be made as per stipulations of the Special Conditions of Contract. The break-up of cost as given in formats 4C is to facilitate assessment of reasonableness of costs and conducting negotiations in accordance with clause 6 of the Information to Consultant.

Name and Title of Signatory:Name of the Consultant:

Address:

38PMC Appointment City Corporation

4C. BREAK DOWN OF COSTS (Rs.)The Form in Bid Document to be replaced as follows:

Payment will be made only on % basis; however the following details needs to be provided by the Consultants

SUMMARY OF COSTS

No Description Amount (Rs)

I REMUNERATION FOR STAFF FOR ENTIRE 5 YEARS FOR ALL SUBPROJECTS

II TRANSPORTATION COST FOR 5 YEARS

III DUTY TRAVEL TO SITE FOR 5 YEARS

IV OFFICE SUPPLIES, UTILITIES AND COMMUNICATION/ANNUM

V OFFICE FURNITURE AND EQUIPMENT

VI REPORTS AND DOCUMENT PRINTING

VII SURVEY & OTHER COST

GRAND TOTAL

Note: The Consultant shall provide subproject wise manpower requirement at the time of negotiations

Date: Signature:

39PMC Appointment City Corporation

I. REMUNERATION FOR STAFF FOR ENTIRE 5 YEARS FOR ALL SUBPROJECTS

No. PositionMan Month Rate* (Rs.)

Phase wise no. of Man MonthsAmount (Rs)

DesignImplementation

Total

A.1 Key Professional staff

Sub Total (A.1)A.2 Development Professional staff

Sub Total(A.2)A.3 Construction Supervision

Engineers

ABD ProjectsPan City Projects

Sub Total(A.3)A.4 SUPPORT STAFF

Sub Total(A.4)TOTAL (A)

II Transportation Cost for 5 Years (Details to be Provided)

Total:

III. Duty Trav el to Site for 5 Years (Details to be Provided)

Total:

40PMC Appointment City Corporation

IV. Office Supplies, Utilities and Communication

No. Item* Months Monthly Rate (Rs)

Amount (Rs)

1.

2.

3.

4.

Total:

* Prepare details as appropriate for the consultancy assignment.

V. Office Furniture and Equipment (Details to be provided)

No. Description(*) Unit Quantity Rate Amount

Office Furniture (Purchase)

Office Equipment (Purchase)*

Total

VI. Documentation & Report Submission

No. Description* Number No. of Copies Rate per Copy

( Rs.)

Amount ( Rs. )

1.

Total

VII. Survey & other cost

Total

Date: Signature:

41PMC Appointment City Corporation

SECTION 5. TERMS OF REFERENCEScope Requirement Document

1. Background:

The Ministry of Urban Development (MoUD), Government of India (GoI) has rolled out Smart City

Mission (SCM). Karnataka Urban Infrastructure Development & Finance Corporation Limited

(KUIDFC) is the State Level Nodal Agency (SLNA) for the Smart Cities Mission in Karnataka. ............ is

one of the ULBs selected under the 2nd Round Competition of SCM based on the Smart City Plan

(SCP) submitted by the City through GoK. Objective of the Smart Cities Mission is to promote Cities

that provide core infrastructure, give a decent quality of life to their citizens and apply smart

solutions to improve services and infrastructure.

2. Need for Present Assignment

The ULB, based on the public consultation, has prioritized sub-projects in the SCPs, which need to be

reviewed, improved, finalised and implemented. In order to implement/realise these plans a Special

Purpose Vehicle (SPV) – Tumakuru Smart City Limited (TSCL) is established. The assistance of

Project Management Consultant is required to support TSCL for designing, developing, managing and

implementing Smart City projects & hence the need for assignment.

3. Brief Scope of Work:

The principal objective of the Project Management Consultants (PMC) assignment is to assist the

TSCL/ SLNA to realize the vision of the City, contemplated in the SCP, by preparing the final designs

and implementation of sub-projects based on the Smart City Mission Guidelines. The sub-projects

identified in the SCPs can be broadly classified as Area Based Development (ABD) for city

improvement (retrofitting), city renewal (redevelopment), city extension (Greenfield development)

and Pan-city initiative in which Smart Solutions are applied covering larger parts of the city.

4. An Outline of the Tasks to be carried out by the Consultant

The PMC will be responsible for dissemination of project related information to all stake holders and

ensure appropriate level of community mobilization and participation. The PMC will also be

responsible for implementation of the sub-projects identified under SCP. The Consultant would

support the Employer in overall management of Smart City project, including project planning,

budgeting, supervision, monitoring & evaluation, reporting and coordination to ensure timely project

development and implementation in line with Smart City Proposal and Smart Cities Mission

guidelines.

The assignment is in two Phases, the first phase – Design Phase for Planning, designing and

procurement assistance; and the second phase – Implementation Phase for Implementation

42PMC Appointment City Corporation

assistance. The PMC will work under the overall supervision, direction and guidance of the SPV/

SLNA. The broad scope of work shall cover, but not limited to:

- Support Employer to identify, conceptualize, develop and execute projects on models such as

joint ventures, subsidiaries, public-private partnership (PPP), turnkey contracts, etc to

implement SCM projects.

- Advice the Employer on technical, commercial, financial, and legal aspects of project

development and implementation based on Employer requirements.

- Support Employer in preparation of feasibility study, develop project structures, designs,

prepare detailed project reports, tender documents and provide bid process management

support for selection of implementing agency.

- Establish base line data of all the urban infrastructure sectors, existing service level of the

city.

- Provide transaction advisory /bid process management support including preparation of bid

documents, managing bid process including bid evaluation, preparation of bid evaluation

report, preparation of letter of intent, contract agreement for appointment of

Contractors/suppliers/service providers.

- Prepare proposals for consideration of various project development, financing and

implementation partners including concept notes, presentations, and follow-ups.

- Provide implementation support including contract negotiation, contract management and

contract closure.

- Support Employer to frame policies, regulations and bye-laws required in accordance with

proposed smart city projects and their project development and implementation activities.

- Support Employer in bringing convergence with other ongoing schemes of the city

- Shall ensure compliance & monitoring of project activities by using latest Project

Management Tools such as real time monitoring of work progress on field

- Assist the Employer in conducting project review meetings, preparation of minutes of

meeting etc.

- After completion of each of the sub project, project completion report to be submitted along

with project impact assessment study, listing out all the beneficiaries of the project.

- Provide Project Management Support through regular monitoring of the projects for time

and scope deadlines and handholding the government in ensuring that all projects under the

SCP are run as per the contractual terms and conditions.

- Provide Capacity building support to the client in terms of conduct of trainings for inducting

newer technologies. Undertaking Trainings needs assessment, formulating a training

43PMC Appointment City Corporation

calendar and training schedules to be incorporated in various SCP projects. Undertaking

effectiveness assessments of all trainings undertaken by individual projects etc.

- Putting in place change management initiatives of the government so as to ensure the

success of new projects implemented under the SCP initiatives. This shall include

development and implementation of effective communication to inform the citizens about

the advantages of the new services and technologies put in place to ease their use of public

utilities. Conduct of regular workshops for the relevant stakeholders, publication of

newsletters etc.

- Wherever Land Acquisition is involved, the Consultant shall strive to adopt Town Planning

Scheme mechanism (TPS). For all the green field development proposals of the SPV, TPS

mechanism shall be followed scrupulously.

The tasks to be completed under this assignment are detailed below:

4.1 Phase-I: Planning, designing and procurement assistance

a. Brief Scope of Work for Area based/ Greenfield development

Review of earlier studies & project reports/documents relevant to the project.

Carrying out all necessary surveys including market & traffic &transportation related surveys,

studies and site investigations for sub-project preparation. The cost towards survey and field

investigations shall be part of the consultant’s quote. The Consultant may refer to the

available information, pertaining to topographical and other surveys, with the ULB. However,

PMC shall make its own assessment and provide details in the breakup of costs.

Identify underground utilities.

Establish baseline data wherever necessary

Prepare a feasibility study including technical, commercial, financial, institutional and

safeguards aspects in accordance with the prevailing guidelines.

Prepare a road map for guiding the overall investment, specifying the physical and non

physical investments, a financiers’ matrix and the corresponding resources needed.

Explore options of project financing to optimize financial leveraging.

Prepare, review and finalize the preliminary designs for each of the identified sub-projects.

On approval of the preliminary designs by the competent authority, prepare Detailed Project

Reports which shall include detailed engineering designs that are cost effective and use

appropriate technology and materials, cost and quantity estimates, BoQs, specifications,

consistent with relevant standards and designs, construction drawings and tender

documentations. DPRs shall also include design of O&M phase, both in terms of the

institutional arrangements and the financial means to ensure the subprojects provide

sustainable services during their lifetime.

44PMC Appointment City Corporation

Establishing the subproject costs, ensuring that they are within the acceptable cost limits.

Assisting the SPV/SLNA in tendering, bid evaluation and award of contract.

The consultant shall comply & carry out the assignment as per the guidelines issued by

MoUD/GoK/SPV from time to time over the entire period of the contract.

b. Brief Scope of Work for Pan city development

Examine the Pan-city proposal submitted in the SCPs and prepare proposal for development

of selected Smart Solutions to the existing city-wide infrastructure which shall involve the use

of technology, information and data to make infrastructure and other allied services better.

Prepare the functional & non-functional requirement specifications.

Prepare Networking and connectivity requirements

Identify & prepare Data digitisation requirements

Identify & prepare Training requirements

Identify & prepare the list of necessary software & hardware

Study of various technologies and suggest the most viable techno economical solution:

Prioritize the activities of the projects/components and prepare a tentative implementation

plan.

Identify the risk & prepare mitigations measures.

The Consultant shall engage Standard Testing and Quality Consultant (STQC) to conduct the

assessment/review for the system before rolling it out. The Consultant shall review and

inspect all the procedures and systems relating to the solution.

The proposed ICT solution across various sectors of the city shall be in line with the Cyber

Security Model Framework proposed by MoUD vide their OM No; K-15016/61/2016-SC-1 dtd

20th May 2016.

The consultant shall comply & carry out the assignment as per the OM/guidelines issued by

MoUD/GoK/SPV from time to time over the entire period of the contract.

c. Brief scope of work for PPP projects:

The Consultant shall play the role of transaction advisor in all PPP projects and shall do all the

detailed financial, technical and legal work required to prepare the Project Sponsor to

implement the proposed project.

The transaction advisor will complete a feasibility study to a standard that will enable the SPV

to establish the commercial attractiveness and bankability of the project.

During the procurement phase, the transaction advisor will advise the SPV on optimum risk

allocation and the resultant contract structure including preparation of all necessary

documentation and requisite approvals.

In broad terms, the TA shall provide his services in two phases:

- Phase I: Initial project review and technical due diligence prior to financial closing.

45PMC Appointment City Corporation

- Phase II: Construction and performance test monitoring and operations monitoring

during commercial operation and after financial closing.

4.2 Deliverables

i. Detailed Project Reports and detailed engineering for Area based/ Greenfield & Pan

city Development

Review SCP and understand the SPV/ULB’s priorities and situation

For the identified sub-projects, conduct all necessary investigations, surveys and tests as

required for the preparation of DPRs, taking into account possibilities of optimizing existing

assets / systems.

- Necessary topographical survey.

- Necessary soil testing as per standard engineering practice and determine the soil

strata

Assess need and demand for each particular service along with the expected impact &

outcome.

Preparation of comprehensive designs and DPRs for infrastructure projects as required

Reconfirm the desired service level improvements through the respective sub-projects and in

accordance with such desired levels, finalize/update the preliminary engineering designs,

and prepare detailed engineering designs and drawings. While preparing the designs, follow

the Sector Investment Guidelines prepared by SPV if any or else follow standard engineering

practices. The designs and drawings shall be sufficiently detailed to enable the SPV and the

contractor for easy interpretation and execution of the works. The detailed designs and

working drawings prepared along with necessary test reports shall be incorporated into a

detailed design report, to be submitted for the approval of the SPV/Government. All

necessary calculations shall be prepared to determine and justify the engineering solution

proposed for each subproject / component, and the same shall be incorporated in the design

reports. The design should also include life cycle cost analysis.

Ensure quality planning through good engineering practices and adoption of appropriate

design standards.

Prepare all detailed cost estimates as per the prevailing PWD/ other applicable Schedule of

Rates, (KUWS & DB, NH, Irrigation, etc), and where such Schedule of Rates are not available

prepare data rates based on market rates.

Prepare designs for Infrastructure projects, especially of water supply, underground drainage

system using standard software’s like WaterCAD, WaterGem, SewerCAD, SewerGem or

equivalent.

Prepare appropriate tender packages, procurement and implementation plan in consultation

with SPV/SLNA.

46PMC Appointment City Corporation

Prepare implementation schedules for each contract package considering working season,

critical activities of construction etc and suggest financial flow. (Disbursement schedule)

Project cost must take into account market prices, and must include estimated price

escalation, depending on the proposed implementation schedule for the works.

Prepare detailed specifications and bill of quantities (BoQs) for all items of works, goods and

equipment.

Preparation of the designs and cost estimate should be accurate and that during execution –

contract variation if any, shall not be beyond 10% above or below the estimated costs. The

PMC will have to justify any such variations going beyond 10%.

ii. Detailed Project Reports and detailed engineering for PPP projects

Phase I – Technical Due Diligence

- Basic Design and Assessment of Capex

-  Project Documentation and preparation of concession agreement

- Technical Review of the bids submitted by EPC contractor

- Assist SPV in signing Concession Agreement

Phase-II –Prior construction Phase

Acts as owners engineer and review and opine on the construction related activity as follows:

- Construction schedule including construction and payment milestones and

contractors’ and subcontractors’ execution plans;

- Assessment of reasonableness of Project Cost estimation (including potential

scenarios of cost overruns), including spare parts;

- Safety assurance program;

- Site conditions, including site accessibility as well as adequacy of the available

infrastructure (ports, roads, vehicles) to transport to the Project site the different

components of the wind farm including the turbines;

- Review of the commissioning and start-up plan including performance testing and

acceptance criteria. The PMC should plan to observe and attend the full plant

commissioning.

- Provide an independent estimation of the Project completion date as well as

recommendation for delay contingencies.

iii. Project Finance

Review financing and implementation plan of Smart City Proposal and assess project cost

estimates, financing requirements, future cash flows, and sources of funds and financing

modalities.

Develop revenue model for SPV, identify revenue streams, support SPV to operationalize

47PMC Appointment City Corporation

revenue streams such as user fees, beneficiary charges and impact fees, land monetization,

debt, loans, etc.

Develop financial models, capital investment plans, finance and operating plans and resource

mobilization strategy for smart city sub projects.

Support SPVs to conceptualize and implement financing instruments and tools such as

municipal bonds with credit rating of ULBs, pooled finance mechanism, tax increment

financing (TIF), transit oriented development, transfer of development rights (TDR), FSI

incentives etc. to raise financial resources from the market and attract private investments.

Support SPV to access financing from State government institutions and Financing

Institutions and other government and quasi-government sources as per need.

Support SPV in dovetailing with other ongoing Government schemes for technical

completeness.

Develop business cases and bankable projects to leverage borrowings from financial

institutions and potential investors, including but not limited to bilateral and multilateral

development aid institutions.

Support Employer in identifying and reaching out potential partners and investors and

organizing investment road shows and shall also ensures funding tie-ups.

Support Employer in preparing financial pitches to potential investors.

iv. Operation and Maintenance (O&M) & Financial Assessments

Review O&M options and prepare a strategy for improved implementation, including

technical procedures to ensure efficiency and sustainability and proper financial, accounting

and managerial arrangements for O&M.

Examine the current provision of the subproject services, and propose/design the

institutional arrangements. Hence, as part of the same, the consultant shall undertake:

- A detailed institutional assessment of those departments/sectors within the SPV

where the proposed intervention is focused on. This will include an assessment of

institutional structure and systems, procedures, human resources, types of IT

systems, etc.

- In addition, this will also include a financial assessment in terms of extent of O&M

costs involved (before and after the project) and budgets, extent of cost recovery in

case of sectors where user charges are involved, tariff implications and modelling of

various scenarios; including financial projections for 5-10 years.

- Based on the aforesaid assessment, the Consultant will arrive at an O&M plan for each

sector where intervention is proposed, including a plan for routine and recurring

operations (costs for O&M etc), action plan for maintenance, etc, a human resource

plan and strategies for meeting institutional capacity gaps (outsourcing, new IT

48PMC Appointment City Corporation

systems, new staff positions, etc.)

The same shall include financial analysis for the proposed subprojects

working out the financial means to cover O&M expenses, and designing the

respective mechanisms (for instance tariffs in water, budget allocations in

roads) to guarantee reliable adequate funding during the O&M period.

- The Consultant shall update the financial assessments for the ULB carried out during

the SCP process, based on updated sub-project costs, sources of finance/financing

plan, revised repayment schedules if any, sub-project related cash-flow statements

etc.

- The output from the aforesaid exercise shall be a Financial and Operating Plan (FOP)

for the SPV as a whole, including 5-10 year financial projections separately for both

the operating and capital budgets (a capital investment plan), taking into account also

the likely impact of the prioritized sub-project proposed to be undertaken over the

medium term.

- This will include financial impact of service improvement interventions in terms of

additional costs / revenues, etc.

v. Environment Safeguards

Conduct and prepare environmental impact assessment and management plans. The

Environmental Assessment shall necessarily (but not limited to) cover the following details:

- Review applicable environmental laws/rules/regulations with a view to define the

specific clearances/approvals required to be obtained by ULB/SPV and contractors

from different organizations. Also prepare necessary documentation to facilitate SPV

to obtain necessary clearances.

- Screen the proposed sub-projects to identify sensitive environmental features and

obtain relevant baseline information/data specific to the sub-project. The data

collected shall include primary as well as secondary data for meaningful

environmental assessment.

- Based on the screening, define specific environmental concerns/issues to be

addressed and conduct meaningful stakeholder consultations at various stages of sub-

project’s preparation.

- Analyze the possible alternatives for the sub-project components (e.g. Infrastructure

project, UGD/Road network alignments, source of water, setting of STPs, disposal

points, etc.)

- Cost effective mitigation measures in the form of implementable and budgeted EMP

and integration of the same in to bidding documents (bidding documents shall

necessarily integrate EMP in the form of Technical specification. drawings, BOQ items,

49PMC Appointment City Corporation

etc.)

- Define monitoring plan for the proposed EMP, responsible institutions. Such plans

shall reflect the requirements during construction and operational phases.

vi. Social Safeguards

Conduct and prepare Social Impact Assessment and management plans. The Social

Assessment shall necessarily (but not limited to) cover the following details:

- Screen the proposed sub projects to identify sensitive social features and obtain

relevant baseline information specific to the sub project.

- Based on the screening, define specific social concerns/issues to be addressed and

categorization of the sub project and conduct meaningful stakeholder consultations at

various stages of sub-project’s preparation.

- Conduct socio-economic survey among the affected population with potentially

adverse social impacts.

- Confirm the requirement of land to be acquired for each sub-project (land required

for the sub-project would have been tentatively identified by the SCP consultants) and

estimate cost implications of such land acquisition.

- Analyse the possible alternatives for the sub-project components (e.g. Infrastructure

projects, UGD/Road network alignments, source of water, setting of STPs, disposal

points, etc.) with a view to minimizing adverse social impacts.

- Assist ULB/SPV in getting clearances from the other government departments where

ever necessary.

- When required, confirm the requirement of land to be acquired for each sub-project

and estimate cost implications of such land acquisition, including rehabilitation &

resettlement plan.

- Training of ULB/SPV staff on procurement, planning and engineering.

vii. Procurement

The PMC would be required to comprehensively assist the SPV in procurement of goods/

/equipments/Hardware/Software/works (as per tasks listed below), as per KTPP guidelines, in the

context of implementation of smart city sub-projects.

Prepare procurement plan duly indicating the method of procurement

Prepare the necessary procurement documentation as per the KTPP guidelines and GoK

procurement Policy. The tender and contract documents shall include instruction to bidders;

pre-qualification criteria, general and special conditions of contract, technical specifications,

bill of quantities, good for construction drawings, and forms of contract agreement. The

specifications will be detailed and use locally applicable standards (KPWD, CPHEEO, IS, IRC,

50PMC Appointment City Corporation

MORTH, etc). The bill of quantities will be based on detailed calculations of quantities and

estimate based on (i) schedule of rates and (ii) market prices. The tender documents will also

take into account the Environment Management Plan (EMP), if applicable, for the sub-project.

Assist SPV in pre-qualification, pre-bid meetings, issuance of addendums/corrigendums, bid

opening and evaluation including preparation of evaluation reports, award of bids, and any

other assistance as may be required for overall management of bidding process.

Assist the SPV in the negotiations as appropriate with the successful bidders and award of

tender.

4.3 Phase-II: Implementation Assistance

Providing implementation assistance and quality control services, which includes:

Preparation of Implementation Plan with roles and responsibilities of each of the stake

holders

Acting as an early warning system for the ULB/SPV/SLNA.

Contract management, progress monitoring & reporting.

Capacity building of the SPV staff, on-job training on implementation and quality and contract

management and O&M.

Scrutinize the Contractor’s detailed work programme and guide the contractor in preparation

supervision schedule & work plan for each sub-project.

Scrutinize construction method proposed by contract including environmental safety,

personnel & public issues.

Assess the adequacy of the contractors input in material, labour and construction

methodology and provide advisories when required.

Monitor the implementation of environmental standards and safeguards and resettlement

plans, if any.

Establish Quality assurance system including verification of source of material and

certification.

Assist the Employer in final certification of the bills for payment

Assistance for resolution of all contractual issues including examining the contractors claims

for variations/extensions or additional compensations etc and prepare recommendations for

approval by the Employer.

Assist third party inspections, if necessary, as decided by the Employer.

Proof checking & issuance for execution of contractors design and drawing for lump sum

turnkey contracts.

Review and finalize the “as built” drawings submitted by Contractor

Assist the Employer in issue of completion certificates

51PMC Appointment City Corporation

Prepare monthly project progress reports describing the physical and financial progress of

each subprojects, highlighting impediments to the quality and progress of the works and

remedial accounts.

The consultant shall comply & carry out the assignment as per the guidelines issued by

MoUD/GoK/SPV from time to time over the entire period of the contract.

i. Quality Assurance, Quality Control and Certification

The role of PMC during implementation is as follows:

Assist SPV for day to day construction supervision, contract administration, recording

measurements, processing & certifying bills for payment release etc.

Deploy full time well qualified and adequately experienced site engineer to each sub

component to assist SPV during implementation phase.

Assist the SPV with respect to quality control procedures and quality control of the works.

Ensure quality implementation by establishing quality control procedures and preparing and

disseminating quality control manual.

Ensure setting up of quality control laboratory by the contractor or list out Government

laboratories/established laboratories/Reputed engineering colleges/institutions for

conducting quality control tests

Conduct/Supervise quality tests as required on materials/equipment supplied/ works

executed at site and in the approved labs approved and assist the ULB/SPV engineers in

witnessing tests at manufacturers site as per the standard procedures and best engineering

practice laid down and certify the test results.

Advise the SPV on carrying out and documenting the planned quality control tests as part of

the works progress reports.

Assist SPV/contractor in preparation of completion reports that include as-built drawings

and certify the as-built drawings.

ii. Sub-Project Implementation Management

Prepare Project Implementation framework highlighting the roles and responsibilities

various stakeholders of project, contract management procedures;

Disseminate the same to all stakeholders of the project by conducting workshops.

Provide technical, financial and project management advice to the SPV for preparing sub-

project implementation management checklist. This checklist would be focusing on the

procurement management, contract management, time and input management and social and

environmental management with regard to actions to be initiated for smooth and timely

implementation.

Oversee the sub-project performance, physical and financial, from the date of Project

52PMC Appointment City Corporation

commencement and report to the ULBs/ SPV periodically.

Prepare quarterly sub-project budgets including financial allocations to sub-projects and sub-

project accounting. Prepare monthly monitoring reports for submission to ULB/SPV. The

budgetary requirement and achievement should be on quarterly basis and should be for both

calendar year and financial year.

Suggest mid-course corrections as required for sub-project control.

Prepare O&M Plan for the assets created

Assist the ULB/SPV staff on establishing and operationalizing the institutional and financial

arrangements envisaged for O&M.

During the PMC’s contract period, assist the ULB/SPV in overseeing contractor‘s

responsibilities during defect liability period

iii. Training

Training of ULB/SPV staff on procurement, planning management and engineering related to

project implementation as well as O&M phase.

iv. Legal

Assist ULBs/SPV in addressing and complying with all legal, statutory and mandatory

requirements with regard to social and environmental issues.

Assist ULBs/SPV in interpreting and applying the various legal provisions of the contract

documents, and in amicably resolving disputes.

Assist ULBs/SPV in getting clearances from the other government departments/ agencies

where ever necessary

5. Time Frame for the Assignment

The overall duration of the engagement will be 5 years i.e. for the entire duration of the Smart City

Proposal implementation and may be extended if required by the Employer in consultation with

PMC.

6. Output, Deliverables, Payment Terms :

The following outputs are expected to be delivered in stages in total duration of assignment. The

details are provided in Appendix -B

7. Team Composition - Please Refer –Appendix -C

7.1 The team leader shall be present in the city throughout the project period.

53PMC Appointment City Corporation

7.2 At the time of preparing the DPRs, desired Key Professionals/ Development Professionals are

to be stationed in the city for at least 15 working days in a month.

7.3 During implementation phase, adequate number of site engineers and dedicated quality

control team need to be stationed permanently in the city.

7.4 A detailed deployment plan shall be submitted in the Methodology & work plan. The breakup

of cost for the said deployment to be provided in Schedule 4C .

7.5 The desired Key Professionals/ Development Professionals shall visit each sub project at

least once in fortnight and also as and when required during the implementation phase of

individual sub projects. Moreover, the total number of days spent in the town shall not be

less than 5 days in a month.

7.6 Required office space with basic infrastructure will be provided by the SPV like Floor Space,

Electricity and Water. Rest all arrangements to be made by PMC

7.7 The guideline for minimum manpower deployment during implementation phase for the

ABD projects is suggested as follow:

7.7.1 Construction Manger - 2

7.7.2 Assistant Construction Managers - 5

7.7.3 Support Engineers – 15

However, the man months required for the above personnel shall be estimated by the

PMC based on the implementation time frame of individual sub projects and not for

the entire implementation time frame of 53 months.

7.8 For Pan City solutions (IT Components) PMC shall deploy at least One Project Manager and 2

Assistant Project Managers well versed in the field of IT, with the approval of MD, SPV.

7.9 The Position of professionals is illustrative and Smart City/SPV may change as per the

requirement of the project. The Consultant shall deploy Support Team as per the

requirement. The Support Team may also include office manager, research associates,

analysts, surveyor, draughtsman, quantity surveyors, office manager etc. The details are

provided vide Appendix C

54PMC Appointment City Corporation

SECTION 6: CONTRACT FOR CONSULTANT’S SERVICES Between

TUMAKURU SMART CITY LIMITED

and

____________________________

[Name of Consultant]

Dated:

55PMC Appointment City Corporation

CONTENTS

I. FORM OF CONTRACT

II. GENERAL CONDITIONS OF CONTRACT

1. General Provisions

1.1 Définitions

1.2 Law Governing the Contract

1.3 Language

1.4 Notices

1.5 Location

1.6 Authorized Representatives

1.7 Taxes and Duties

2. Commencement, Completion, Modification, and Termination of Contract

2.1 Effectiveness of Contract

2.2 Commencement of Services

2.3 Expiration of Contract

2.4 Modification

2.5 Force Majeure

2.5.1 Definition

2.5.2 No Breach of Contract

2.5.3 Extension of Time

2.5.4 Payments

2.6 Suspension

2.7 Termination

2.7.1 by the Employer

2.7.2 by the Consultant

2.7.3 Cessation of Rights and Obligations

2.7.4 Cessation of Services

2.7.5 Payment upon Termination

3. Obligations of the Consultant

3.1 General

3.2 Conflict of Interest

3.2.1 Consultant Not to Benefit from Commissions, Discounts, etc

56PMC Appointment City Corporation

3.2.2 Procurement Rules of Funding Agencies

3.2.3 Consultant and Affiliates Not to engage in certain Activities

3.2.4 Prohibition of Conflicting Activities

3.3 Confidentiality

3.4 Insurance to Be Taken Out by the Consultant

3.5 Consultant’ Actions Requiring Employer’s Prior Approval

3.6 Reporting Obligations

3.7 Documents Prepared by the Consultant to be the Property of the Employer

3.8 Equipment and Materials Furnished by the Employer

4. Consultant ’Personnel and Sub-Contractor

4.1 Description of Personnel

4.2 Removal and/or Replacement of Personnel

5. Obligations of the Employer

5.1 Assistance and Exemptions

5.2 Services and Facilities

6. Payments to the Consultant

6.1 Lump Sum Remuneration

6.2 Contract Price

6.3 Payment for Additional Services

6.4 Terms and Conditions of Payment

6.5 Interest on Delayed Payments

7. Settlement of Disputes

7.1 Amicable Settlement

7.2 Dispute Settlement

III. SPECIAL CONDITIONS OF CONTRACT

IV. APPENDICES.

Appendix A — Description of the Services

Appendix B — Reporting Requirements

Appendix C — Key Personnel and Sub-Contractor

Appendix D — Services and Facilities to be provided by the Employer

Appendix E — Breakdown of Contract price in Indian Rupees

Appendix F — Form of Performance Bank Guarantee

57PMC Appointment City Corporation

I. FORM OF CONTRACT

This CONTRACT (hereinafter called the "Contract") is made the _________ day of the month of

______________, 200___ , between, on the one hand, ___________ (hereinafter called the "Employer")

and, on the other hand, _______________(hereinafter called the "Consultant").

[*Note: If the Consultant consist of more than one entity, the above should be partially amended

to read as follows:

“......(hereinafter called the "Employer") and, on the other hand, a joint venture consisting of the

following entities, each of which will be jointly and severally liable to the Employer for all the

Consultant' obligations under this Contract, namely, ________________ and _______________________

(hereinafter called the "Consultant.")”]

WHEREAS

(a) the Employer has requested the Consultant to provide certain consulting services as

defined in the General Conditions of Contract attached to this Contract (hereinafter called

the "Services");

(b) the Consultant, having represented to the Employer that they have the required

professional skills, and personnel and technical resources, have agreed to provide the

Services on the terms and conditions set forth in this Contract;

NOW THEREFORE the parties hereto hereby agree as follows:

1. The following documents attached hereto shall be deemed to form an integral part of this

Contract:

(a) The General Conditions of Contract (hereinafter called "GC");

(b) The Special Conditions of contract (hereinafter called "SC");

(c) The following Appendices:

Appendix A: Description of the Services

Appendix B: Reporting Requirements

Appendix C: Key Personnel and Sub-Contractor

Appendix D: Services and Facilities to be provided by the Employer

Appendix E: Breakdown of Contract Price

Appendix F: Form of Guarantee for Advance Payments

The mutual rights and obligations of the Employer and the Consultant shall be as set forth in the

Contract, in particular:

(a) The Consultant shall carry out the Services in accordance with the provisions of the

Contract; and

58PMC Appointment City Corporation

(b) the Employer shall make payments to the Consultant in accordance with the provisions of

the Contract.

IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their

respective names as of the day and year first above written.

FOR AND ON BEHALF OF

[NAME OF EMPLOYER]

By

(Authorised Representative)

FOR AND ON BEHALF OF

[NAME OF CONSULTANT]

By

(Authorised Representative)

[Note: If the Consultant consist of more than one entity, all of these entities should appear as

signatories, e.g., in the following manner:]

FOR AND ON BEHALF OF EACH OF

THE MEMBERS OF THE CONSULTANT

[Name of Member]

By

(Authorised Representative)

[Name of Member]

By

(Authorised Representative)

59PMC Appointment City Corporation

II. GENERAL CONDITIONS OF CONTRACT

1. General Provisions

1.1. Definitions

Unless the context otherwise requires, the following terms whenever used in this Contract have

the following meanings:

(a) "Applicable Law" means the laws and any other instruments having the force of law in

India, as they may be issued and in force from time to time;

(b) "Contract" means the Contract signed by the Parties, to which these General Conditions of

Contract (GC) are attached, together with all the documents listed in Clause 1 of such signed

Contract;

(c) “Effective Date” means the date on which this Contract comes into force and effect

pursuant to Clause GC 2.1

(d) “Contract Price” means the price to be paid for the performance of the Services, in

accordance with Clause 6;

(e) "GC" means these General Conditions of Contract;

(f) "Government" means the Government of Karnataka;

(g) "Local currency" means Indian Rupees;

(h) "Member", in case the Consultant consist of a joint venture of more than one entity, means

any of these entities, and "Members" means all of these entities; ‘Member in Charge’ means

the entity specified in the SC to act on their behalf in exercising all the Consultant’ rights and

obligations towards the Employer under this Contract.

(i) "Party" means the Employer or the Consultant, as the case may be, and Parties means both

of them;

(j) "Personnel" means persons hired by the Consultant or by any Sub-Contractor as employees

and assigned to the performance of the Services or any part thereof; and ‘key personnel’

means the personnel referred to in Clause GC4.2 (a)

(k) "SC" means the Special Conditions of Contract by which these General Conditions of

Contract may be amended or supplemented;

(l) “SCM” means Smart Cities Mission

(m) “SCP” means Smart City Proposal

(n) "Services" means the work to be performed by the Consultant pursuant to this Contract as

described in Appendix A; and

(o) "Sub-Contractor" means any entity to which the Consultant subcontract any part of the

Services in accordance with the provisions of Clauses 3.5 and 4.

60PMC Appointment City Corporation

(p) State Government means Government of Karnataka

(q) “Third party” means any person or entity other than the Government, the Employer, the

Consultant, or a Sub-Contractor.

1.2. Law Governing the Contract

This Contract, its meaning and interpretation, and the relation between the Parties shall be

governed by the Applicable Law.

1.3. Language

This Contract has been executed in English language, which shall be the binding and

controlling language for all matters relating to the meaning or interpretation of this Contract.

1.4. Notices

Any notice, request or consent made pursuant to this Contract shall be in writing and shall be

deemed to have been made when delivered in person to an authorised representative of the

Party to whom the communication is addressed, or when sent by registered mail, telex,

telegram or facsimile to such Party at the address specified in the SC.

1.5. Location

The Services shall be performed at such locations as are specified in Appendix A and, where the

location of a particular task is not so specified, at such locations, whether in Karnataka or

elsewhere, as the Employer may approve.

1.6. Authorized Representatives

Any action required or permitted to be taken, and any document required or permitted to be

executed, under this Contract by the Employer or the Consultant may be taken or executed by

the officials specified in the SC.

1.7. Taxes and Duties

The Consultant, Sub-contractors and their Personnel shall pay such taxes, duties, fees and other

impositions as may be levied under the Applicable Law, the amount of which is deemed to

have been included in the Contract Price.

2. Commencement, Completion, Modification and termination of Contract

2.1 Effectiveness of Contract

This Contract shall come into effect on the date the Contract is signed by both Parties or such

other later date as may be stated in the SC.

2.2 Commencement of Services

The Consultant shall begin carrying out the Services within thirty (30) days after the date the

Contract becomes effective, or at such other date as may be specified in the SC.

61PMC Appointment City Corporation

2.3 Expiration of Contract

Unless terminated earlier pursuant to Clause 2.7, this Contract shall terminate at the end of

such time period after the Effective Date as is specified in the SC.

2.4 Modification

Modification of the terms and conditions of this Contract, including any modification of the

scope of the Services or of the Contract Price, may only be made by written agreement

between the Parties.

2.5 Force Majeure

2.5.1 Definition

For the purposes of this Contract, "Force Majeure" means an event which is beyond the

reasonable control of a Party, and which makes a Party's performance of its obligations under

the Contract impossible or so impractical as to be considered impossible under the

circumstances.

2.5.2 No Breach of Contract

The failure of a Party to full-fill any of its obligations under the contract shall not be considered

to be a breach of, or default under this Contract insofar as such inability arises from an event

of Force Majeure, provided that the Party affected by such an event (a) has taken all reasonable

precautions, due care and reasonable alternative measures in order to carry out the terms and

conditions of this Contract, and (b) has informed the other Party as soon as possible about the

occurrence of such an event.

2.5.3 Extension of Time

Any period within which a Party shall, pursuant to this Contract, complete any action or task,

shall be extended for a period equal to the time during which such Party was unable to

perform such action as a result of Force Majeure.

2.5.4 Payments

During the period of their inability to perform the Services as a result of an event of Force

Majeure, the Consultant shall be entitled to continue to be paid under the terms of this

Contract, as well as to be reimbursed for additional costs reasonably and necessarily incurred

by them during such period for the purposes of the Services and in reactivating the Service after

the end of such period.

2.6 Suspension:

The Employer may by written notice of suspension to the Consultant, suspend all payments to

the Consultant hereunder if the Consultant fail to perform any of their obligations under this

contract, including the carrying out of the Services, provided that such notice of suspension (i)

shall specify the nature of the failure, and (ii) shall request the Consultant to remedy such failure

62PMC Appointment City Corporation

within a period not exceeding thirty (30) days after receipt by the Consultant of such notice of

suspension.

2.7 Termination

2.7.1 By the Employer

The Employer may terminate this Contract, by not less than thirty (30) days’ written notice

of termination to the Consultant, to be given after the occurrence of any of the events specified

in paragraphs (a) through (d) of this Clause 2.7.1 and sixty (60) days’ in the case of the event

referred to in (e):

(a) if the Consultant do not remedy a failure in the performance of their obligations under

the Contract, within thirty (30) days of receipt after being notified or within such

further period as the Employer may have subsequently approved in writing;

(b) if the Consultant (or any of their Members) become insolvent or bankrupt;

(c) if, as the result of Force Majeure, the Consultant are unable to perform a material portion

of the Services for a period of not less than sixty (60) days; or

(d) if the Consultant, in the judgment of the Employer has engaged in corrupt or fraudulent

practices in competing for or in executing the Contract.

For the purpose of this clause:

“corrupt practice” means the offering, giving, receiving or soliciting of anything of value to

influence the action of a public official in the selection process or in contract execution.

“fraudulent practice” means a misrepresentation of facts in order to influence a selection

process or the execution of a contract to the detriment of GOK, and includes collusive

practice among Consultant (prior to or after submission of proposals) designed to establish

prices at artificial non-competitive levels and to deprive GOK of the benefits of free and open

competition.

(e) if the Employer, in its sole discretion and for any reason whatsoever, decides to

terminate this Contract.

2.7.2 By the Consultant

The Consultant may terminate this Contract, by not less than thirty (30) days' written notice

to the Employer, such notice to be given after the occurrence of any of the events specified in

paragraphs (a) through (c) of this Clause 2.7.2:

(a) if the Employer fails to pay any monies due to the Consultant pursuant to this Contract

and not subject to dispute pursuant to Clause 7 hereof within forty-five (45) days after

receiving written notice from the Consultant that such payment is overdue;

(b) If the Employer is in material breach of its obligations pursuant to this Contract and has

not remedied the same with in forty-five (45) days (or such longer period as the

63PMC Appointment City Corporation

Consultant may have subsequently approved in writing) following the receipt by the

Employer of the Consultant’ notice specifying such breach;

(c) if, as the result of Force Majeure, the Consultant are unable to perform a material portion

of the Services for a period of not less than sixty (60) days.

2.7.3 Cessation of Rights and Obligations

Upon termination of this Contract pursuant to Clause GC 2.7 , or upon expiration of this Contract

pursuant to Clause GC 2.3, all rights and obligations of the Parties hereunder shall cease, except :

i. such rights and obligations as may have accrued on the date of termination or expiration;

ii. the obligation of confidentiality set forth in Clause GC 3.3 hereof;

iii. any right which a Party may have under the Applicable Law.

2.7.4 Cessation of Services

Upon termination of this Contract by notice of either Party to the other pursuant to Clauses GC

2.7.1 or GC 2.7.2 hereof, the Consultant shall, immediately upon dispatch or receipt of such

notice, take all necessary steps to bring the Services to a close in a prompt and orderly

manner and shall make every reasonable effort to keep expenditures for this purpose to a

minimum. With respect to documents prepared by the Consultant and equipment and materials

furnished by the Employer, the Consultant shall proceed as provided, respectively, by Clauses

GC 3.7 and GC 3.8 .

2.7.5 Payment upon Termination

Upon termination of this Contract pursuant to Clauses 2.7.1 or 2.7.2, the Employer shall make

the following payments to the Consultant:

(a) remuneration pursuant to Clause 6 for Services satisfactorily performed prior to the

effective date of termination;

(b) except in the case of termination pursuant to paragraphs (a) and (b) of Clause 2.7.1,

reimbursement of any reasonable cost incident to the prompt and orderly termination of

the Contract.

3. Obligations of the Consultant:

3.1 General

The Consultant shall perform the Services and carry out their obligations hereunder with all

due diligence, efficiency and economy, in accordance with generally accepted professional

techniques and practices, and shall observe sound management practices, and employ

appropriate advanced technology and safe methods. The Consultant shall always act, in

respect of any matter relating to this Contract or to the Services, as faithful advisers to the

Employer, and shall at all times support and safeguard the Employer's legitimate interests in

any dealings with Sub-contractors or third parties.

64PMC Appointment City Corporation

3.2 Conflict of Interests

3.2.1 Consultant Not to Benefit from Commissions, Discounts, etc.

The remuneration of the Consultant pursuant to Clause 6 shall constitute the Consultant' sole

remuneration in connection with this Contract or the Services, and the Consultant shall not

accept for their own benefit any trade commission, discount or similar payment in connection with

activities pursuant to this Contract or to the Services or in the discharge of their obligations under

the Contract, and the Consultant shall use their best efforts to ensure that the Personnel, any Sub-

Contractors, and agents of either of them, similarly shall not receive any such additional

remuneration.

3.2.2 Procurement Rules of Funding Agencies

If the Consultant, as part of the Services, have the responsibility of advising the Employer on the

procurement of goods, works or services, the Consultant shall comply with any applicable

procurement guidelines of the funding agencies and shall at all times exercise such

responsibility in the best interest of the Employer. Any discounts or commissions obtained by

the Consultant in the exercise of such procurement responsibility shall be for the account of the

Employer.

3.2.3 Consultant and Affiliates Not to engage in certain Activities

The Consultant agree that, during the term of this Contract and after its termination, the

Consultant and their affiliates, as well as any Sub-Contractor and any of its affiliates, shall be

disqualified from providing goods, works or services (other than the Services and any

continuation thereof) for any project resulting from or closely related to the Services.

3.2.4 Prohibition of Conflicting Activities

Neither the Consultant nor their Sub-Contractors nor the Personnel shall engage, either directly

or indirectly, in any of the following activities:

(a) during the term of this Contract, any business or professional activities in the Government's

country which would conflict with the activities assigned to them under this Contract; or

(b) after the termination of this Contract, such other activities as may be specified in the SC.

3.3 Confidentiality

The Consultant, their Sub-Contractors, and the Personnel of either of them shall not, either

during the term or within two (2) years after the expiration of this Contract , disclose any

proprietary or confidential information relating to the Project, the Services, this Contract, or

the Employer's business or operations without the prior written consent of the Employer.

3.4 Insurance to Be Taken out by the Consultant

The Consultant (a) shall take out and maintain, and shall cause any Sub-Contractors to take out

and maintain, at their (or the Sub-Contractors', as the case may be) own cost but on terms and

conditions approved by the Employer, insurance against the risks, and for the coverage, as

65PMC Appointment City Corporation

shall be specified in the SC; and (b) at the Employer's request, shall provide evidence to the

Employer showing that such insurance has been taken out and maintained and that the current

premiums have been paid.

3.5 Consultant’ Actions Requiring Employer’s Prior Approval

The Consultant shall obtain the Employer’s prior approval in writing before taking any of the

following actions:

(a) entering into a subcontract for the performance of any part of the Services, it being

understood (i) that the selection of the Sub-Contractor and the terms and conditions of the

subcontract shall have been approved in writing by the Employer prior to the execution of

the subcontract, and (ii) that the Consultant shall remain fully liable for the performance

of the Services by the Sub-Contractor and its Personnel pursuant to this Contract;

(b) appointing such members of the Personnel not listed by name in Appendix C (“Key

Personnel and Sub-Contractors”), and

(c) any other action that may be specified in the SC.

3.6 Reporting Obligations

The Consultant shall submit to the Employer the reports and documents specified in

Appendix B in the form, in the numbers, and within the periods set forth in the said Appendix.

3.7 Documents Prepared by the Consultant to Be the Property of the Employer

All plans, drawings, specifications, designs, reports and other documents and software

submitted by the Consultant in accordance with Clause 3.6 shall become and remain the

property of the Employer, and the Consultant shall, not later than upon termination or

expiration of this Contract, deliver all such documents and software to the Employer, together

with a detailed inventory thereof. The Consultant may retain a copy of such documents and

software. Restrictions about the future use of these documents, if any, shall be specified in the

SC.

3.8 Equipment and Materials Furnished by the Employer

Equipment and materials made available to the Consultant by the Employer or purchased by

the Consultant with funds provided by the Employer shall be the property of the Employer

and shall be marked accordingly. Upon termination or expiration of this Contract, the

Consultant shall make available to the Employer an inventory of such equipment and materials

and shall dispose of such equipment and materials in accordance with the Employer’s

instructions. While in possession of such equipment and materials, the Consultant, unless

otherwise instructed by the Employer in writing, shall insure them at the expense of the

Employer in an amount equal to their replacement value.

66PMC Appointment City Corporation

4. Consultant’ Personnel and Sub-Contractors

4.1 Description of Personnel

The titles, agreed job descriptions, minimum qualifications and estimated periods of

engagement in the carrying out of the Services of the Consultant' Key Personnel are described

in Appendix C. The Key Personnel and Sub-Contractors listed by title as well as by name in

Appendix C are hereby approved by the Employer.

4.2 Removal and/or Replacement of Personnel

(a) Except as the Employer may otherwise agree, no changes shall be made in the Key

Personnel. If, for any reason beyond the reasonable control of the Consultant, it becomes

necessary to replace any of the Key Personnel, the Consultant shall forthwith provide as a

replacement a person of equivalent or better qualifications.

(b) If the Employer finds that any of the Personnel have (i) committed serious misconduct or

has been charged with having committed a criminal action, or (ii) have reasonable cause

to be dissatisfied with the performance of any of the Personnel, then the Consultant shall,

at the Employer's written request specifying the grounds therefor, forthwith provide as a

replacement a person with qualifications and experience acceptable to the Employer.

(c) The Consultant shall have no claim for additional costs arising out of or incidental to any

removal and/or replacement of Personnel.

5. Obligations of the Employer

5.1 Assistance and Exemptions

Unless otherwise specified in the SC, the Employer shall use its best efforts to ensure that the

Government shall:

(a) issue to officials, agents and representatives of the Government all such instructions as

may be necessary or appropriate for the prompt and effective implementation of the

Services;

(b) assist the Consultant and the Personnel and any Sub-Contractors employed by the

Consultant for the Services from any requirement to register or obtain any permit to

practice their profession or to establish themselves either individually or as a corporate

entity according to the Applicable Law;

(c) provide to the Consultant, Sub-Contractors and Personnel any such other assistance as may

be specified in the SC.

5.2 Services and Facilities

The Employer shall make available to the Consultant and the Personnel, for the purposes of the

services and free of any charge, the services, facilities and property described in Appendix D

at the times and in the manner specified in said Appendix D, provided that if such services,

facilities and property shall not be made available to the Consultant as and when so specified,

67PMC Appointment City Corporation

the Parties shall agree on (i) any time extension that it may be appropriate to grant to the

Consultant for the performance of the Services, (ii) the manner in which the Consultant shall

procure any such services, facilities and property from other sources, and (iii) the additional

payments, if any, to be made to the Consultant as a result thereof.

6. Payment to the Consultant:

6.1 Lump Sum Remuneration

The Consultant’s total remuneration shall not exceed the Contract Price and shall be a fixed

lump sum including all staff costs, Sub-Contractors’ costs, printing, communications, travel,

accommodation, and the like, and all other costs incurred by the Consultant in carrying out

the Services described in Appendix A. Except as provided in Clause 5.2, the Contract Price may

only be increased above the amounts stated in clause 6.2 if the Parties have agreed to

additional payments in accordance with Clause 2.4.

6.2 Contract Price

The Contract price is set forth in the SC.

6.3 Payment for Additional Services

For the purpose of determining the remuneration due for additional services as may be

agreed under Clause 2.4, a breakdown of the lump sum price is provided in Appendices A

and E.

6.4 Terms and Conditions of Payment

Payments will be made to the account of the Consultant and according to the payment

schedule stated in the SC. unless otherwise stated in the SC, the first payment shall be made

against the provision by the Consultant of a bank guarantee for the same amount, and shall be

valid for the period stated in the SC. Any other payment shall be made after the conditions listed

in the SC for such payment have been met, and the Consultant have submitted an invoice to the

Employer specifying the amount due.

6.5 Interest on Delayed Payments

If the Employer has delayed payments beyond fifteen (15) days after the due date stated in

the SC, interest shall be paid to the Consultant for each day of delay at the rate stated in the

SC.

7. Settlement of Disputes

7.1 Amicable Settlement

The Parties shall use their best efforts to settle amicably all disputes arising out of or in

connection with this Contract or its interpretation.

68PMC Appointment City Corporation

7.2 Dispute Settlement

Any dispute between the Parties as to matters arising pursuant to this Contract that cannot be

settled amicably within thirty (30) days after receipt by one Party of the other Party's request

for such amicable settlement may be submitted by either Party for settlement in accordance

with the provisions specified in the SC.

69PMC Appointment City Corporation

III. SPECIAL CONDITIONS OF CONTRACT

Number of General GC Clause Amendments of, and Supplements to, Clauses in the Conditions of Contract

1.1 (h) The Member in charge is :

Managing Director, Tumakuru Smart City Limited/ Commissioner

Tumakuru City Corporation

1.4.1

(Notices)

The addresses are:

Employer:

The Managing Director, Tumakuru Smart City Limited/ Commissioner Tumakuru City CorporationAddress. TUMAKURU CITY CORPORATIONTOWN HALL CIRCLE, TUMAKURU-572101KARNATAKA, INDIA

Telephone -- +91816-2278480/2272200Consultant:

----------

1.4.2

(Notices)

Notice shall be deemed to be effective as follows:

(a) in the case of personal delivery or registered mail, on delivery;

(b) in the case of telexes/e-mail, 24 hours following confirmed transmission;

(c) in the case of telegrams, 24 hours following confirmed transmission; and

(d) in the case of facsimiles, 24 hours following confirmed transmission.]

1.6

(Authorized Representatives)

The Authorized Representatives are:

For the Employer : The Managing Director, Tumakuru Smart City Limited/ Commissioner Tumakuru City CorporationFor the Consultant : _______________

1.7

(Taxes and Duties)

The Consultant and the personnel shall pay the taxes, duties, fees, levies and

other impositions levied under the existing, amended or enacted laws

during life of this contract.

1.7.2 However the Services tax payable for this Services shall be paid/ reimbursed by

the Employer separately.

2.1

(Effectiveness of contract)

The date on which this Contract shall come into effect is :

On the date of signing of agreement

2.2

(Commencement of Contract)

The time period shall be 15 days

70PMC Appointment City Corporation

Number of General GC Clause Amendments of, and Supplements to, Clauses in the Conditions of Contract

2.3

(Expiration of Contract)

The period shall be 60 Months (Max) from the date of signing of agreement.

3.4

(Insurance to Be Taken out by

the Consultant)

The risks and the coverage shall be:

1. Professional liability insurance, with a minimum coverage equal to total

contract value for this consultancy; and

2. Employer’s liability and workers' compensation insurance in respect of the

Personnel of the Consultant and of any Sub-Contractor, in accordance with

the relevant provisions of the Applicable Law, as well as, with respect to

such Personnel, any such life, health, accident, travel or other insurance as

may be appropriate; and

3. Insurance against loss of or damage to (i) equipment purchased in whole

or in part with funds provided under this Contract, (ii) the Consultant's

property used in the performance of the Services, and (iii) any documents

prepared by the Consultant in the performance of the Services.

3.5 (c)

(Consultant’ Actions

Requiring Employer’s Prior

Approval)

The other actions are – Refer Appendix A

3.7

(Documents Prepared by the

Consultant to Be the Property

of the Employer)

The Consultant shall not use these documents for purposes unrelated to this

Contract without the prior written approval of the Employer

5.1

(Assistance and Exemptions)

Nil

6.2

(Contract Price)

The Contract Amount is .................................... (exclusive of service tax)

No price escalation proposed for preparation of DPRs

Refer Appendix E, Clause 4.

6.4

(Terms and Conditions of

Payment)

Refer Appendix E

6.5

(Interest on Delayed

Payments)

5% per annum.

71PMC Appointment City Corporation

Number of General GC Clause Amendments of, and Supplements to, Clauses in the Conditions of Contract

7.2

(Dispute Settlement-

Reference to the Deputy

Commissioner for Settlement)

All disputes arising out of or in connection with this Contract, shall be finally referred to the Board, Tumakuru Smart City Limited. Upon such reference, the Board, ----SCL shall attempt to amicably resolve the Dispute within 60 (Sixty) days. If the dispute is not settled, the first appeal shall lie with the Additional Chief Secretary (ACS), Urban Development Department (UDD), Government of Karnataka (GoK). The decision of ACS, UDD shall be binding on either Party.

If the Dispute is not settled within 60 (Sixty ) days from the date of reference to

ACS UDD or 120 (One Hundred Twenty) days from the first reference to the

Board , either Party may refer the dispute to the Court of law in accordance with

the provisions of Clause 7.3.

7.3

(Governing Law and

Jurisdiction)

All disputes arising out of or in connection with this Contract shall be

governed by the Indian laws for the time being in force, and as amended

from time to time and the Civil Court at Tumakuru city, India, shall have

jurisdiction over all matters arising out of or relating to this Agreement.

8. Know- How and Transfer

and Training

The Consultant shall:

Transfer such know-how, management systems, manuals and similar

knowledge if any, tools and capacity for managing a utility

The cost towards the same shall be included in Consultants remuneration

9. Variations Refer Appendix E, Clause 5

10. Liquidated Damages

/Penalty

Refer Appendix E, Clause 6

Refer Appendix E, Clause 8

11. Delay in

deployment/replacement

/non-deployment of Key

Professional/Developmen

t professionals

Refer Appendix E, Clause 9

12. Bonus for early

completion in Design

Phase

Refer Appendix E, Clause 10

13.Performance Security 13.1 The Performance Security for an amount of 5% of the consultants

quoted rate, shall be provided to the Employer no later than the date

specified in the Letter of Acceptance and shall be issued in an amount and

the form provided in Appendix F and by a scheduled commercial bank or

surety acceptable to the Employer, and denominated in Indian Rupees.

13.2 The Performance Security shall be valid until 28 days from the

Intended date of Completion of the project Period.

72PMC Appointment City Corporation

Number of General GC Clause Amendments of, and Supplements to, Clauses in the Conditions of Contract

13.3 The Operator shall keep the Performance Bank Guarantee valid and

enforceable throughout the Term and for a period of 28 days after the Term.

In case the Performance Bank Guarantee provided by the Operator to the

Employer is set to expire for any reason whatsoever at any time before

expiry of 28 days after the Term, the Operator shall renew and provide to

the Employer renewed Performance Bank Guarantee at least 30 days prior

to its date of expiry. Upon any failure on part of the Operator to renew the

Performance Bank Guarantee or to keep it valid and enforceable in terms of

this Clause, the Performance Bank Guarantee will be en-cashed by the

Employer without giving any notice to the Operator or to any other Party.

This is without prejudice to any other action that may be taken by the

Employer under the terms and conditions of this Contract.

13.4 The Employer, without prejudice to any of its rights or remedies under

this Contract, is free to en-cash the Performance Bank Guarantee in part or

in full, in terms. In the event of the invocation of any amount of the

Performance Bank Guarantee by the Employer under this Contract, the

Operator shall immediately take appropriate steps to establish the

Performance Bank Guarantee at its full value contemplated under this

Contract within 15 days of the date when the Performance Bank Guarantee

is wholly or partially invoked by the Employer.

73PMC Appointment City Corporation

IV. APPENDICES

Appendix A: Description of the Services

As detailed in the Terms of Reference

74PMC Appointment City Corporation

Appendix B: Reporting Requirements

The following outputs are expected to be delivered in stages in total duration of assignment

1 Infrastructure Development Work & ICT work –BoQ Based

1.1 Stage-A (Design Phase)

No. Deliverable

Elapsed Timeframe (T0 is from the time sub project is approved by the Employer for preparation of DPR)

A Design

1 Conduct Survey & Necessary Studies T0 + 2Weeks

2Submission of Concept/Feasibility Report (approach and methodology)

T0 + 2 Months

3

Submission of Draft DPR:

(Draft Design and Detailed Project Report for each sub project containing maps and drawings, detailed designs, cost estimates, economic analysis, draft environmental assessment, construction drawings etc.,)

T0 + 4 Months

4

Submission of Final DPR:

(Final Design and Detailed Project Report for each sub project including final EA and EMP , Implementation Plans, Contract Packages, Procurement and Implementation Plans, Quality Assurance and Management Plans , Customer house connection management programme, Construction and Contract Management Framework)

T0 + 5 Months

B Bid Process

1Submission of Draft Bid Documents for each sub projects (EMP to be integrated in to the bidding documents)

T0 + 6 Months

2Submission of Final Bid Documents for each sub project (include applicable environmental approvals and clearances)

3 Bid Evaluation report T0 + 7 Months

75PMC Appointment City Corporation

No. Deliverable

Elapsed Timeframe (T0 is from the time sub project is approved by the Employer for preparation of DPR)

4 Award of Contract

1.2 Stage-2 (Project Implementation Support)

B Project Implementation Support (The duration of construction of various Packages would be different.

T1 is the date of appointment of implementing agency for sub project

1 For ABD Modules T1+ 53 Months (Max or as per bidders assesment)

2 For Smart Solution Module

a) Submission & acceptance of User Acceptance Test (UAT) Reports

b) Submission of Standardization Testing and Quality Certification (STQC) Certificate(s)

c) Submission & acceptance of “Go-Live” Report

T1+ 53 Months (Max or as per bidders assesment)

The deliverables to be submitted during Phase 2 are as follows:

Monthly Progress Reports including compliance with EMP provisions and relevant monitoring details)

5 copies + 1 soft copy

Quarterly and Periodic Reports 5 copies + 1 soft copy

Quality Assurance Plans 5 copies + 1 soft copy

Asset Management Plans for the assets created

5 copies + 1 soft copy

2 Infrastructure Development Work based & ICT work –PPP based

2.1 Stage-A (Design Phase)

76PMC Appointment City Corporation

No. Deliverable

Elapsed Timeframe (T0 is from the time the sub project is approved by the Employer)

A Design

1 Inception Report (approach and methodology) T0 + 2Weeks

2 Submission of REIA & Social Impact Study report T0 + 2 Months

B Bid Process

1 Submission of Draft Concession Agreement

T0 + 3 Months2 Submission of Final Concession Agreement

3 Bid Evaluation reportT0 + 5 Months

4 Signing of Concession Agreement

2.2 Stage-2 (Project Implementation Support)

B Project Implementation Support (The duration of construction of various Packages would be different.

T1 is the date of commencement of implementation phase

1 Vetting of DPR submitted by the Concessioner and freezing the Capital Investment

T0+ 7 Months (Max)

2 Construction Supervision T1+ 53 Months (Max)

The deliverables to be submitted during Phase 2 are as follows:

Monthly Progress Reports including compliance with EMP provisions and relevant monitoring details)

5 copies + 1 soft copy

Quarterly and Periodic Reports 5 copies + 1 soft copy

Quality Assurance Plans 5 copies + 1 soft copy

Asset Management Plans for the assets created

5 copies + 1 soft copy

77PMC Appointment City Corporation

Appendix C: Key Personnel and Sub-Contractor

List of Key Positions whose CV and Experience would be evaluated

The Consultant has to estimate the staff requirement to satisfactorily complete the assignment. The staffing input requirement given below is only indicative and some positions need not be on full time basis, the Consultant has to make assessment of the requirements and submit the technical and financial Proposals accordingly. The following key professionals CVs will be evaluated.

The Consultant shall provide the Consultant’s Personnel to fill the positions as listed in this Appendix throughout the term of the Contract.

78PMC Appointment City Corporation

No Position Qualifications &Skills Experience

1 Team Leader cum Urban Management specialist

Masters in Urban Planning Engineering with MBA is desirable

20 Years experience in Urban Sector Experience of Project Management in

Urban Infrastructure Works. Experience as Team leader/ Deputy Team leader for minimum one project.

Knowledge of urban development issues and Project experience

2 Infrastructure/ Engineering Specialist with Civil building construction expert

Masters Degree in Civil Engineering

At least 10 yrs experience in related assignment.

Experience in working in building construction & urban infrastructure projects which shall include preparation of designs, drawings & DPRs.

3 Town Planning Scheme Expert

Master Degree in Urban Planning

At least 5 yrs experience in related assignment.

Experience in designing/implementation of minimum 2 Town Planning Schemes

4 Urban Finance Specialist

Masters Degree in Finance/ Economics/ Chartered Accountant/ Commerce/ ICWA / Post Graduate in Economics with specialization in Public Finance.

At least 10 years relevant experience. Experience of municipal finance analysis,

municipal budgeting and accounting and financial projections.

Experience in Financial Modeling in Urban Infrastructure , PPP & Market borrowing are desirable.

5 PPP Specialist Degree in Civil Engineering/ Master of Business Administration is desirable.

At least 10 years relevant experience. Experience of procurement related

activities for urban infrastructure projects.

Experience in PPP contract structuring and concluding concession Agreements.

6 E-Governance /ICT Specialist

Degree in Information Technology/ Electronics Engineering or equivalent

At least 5 years’ relevant experience Experience in MIS for institutional /

Governance level and integration of various user data

Experience in preparation of technical requirements document of the e-Services and solution to implementing the IT related infrastructure services /e-services, networking infrastructure etc.

Proven knowledge of modern Internet technologies and experience in software development projects/ GIS;

Working experience in network administration and use of hardware/software, telecommunications facilities,

Experience in databases development, programming and web designing; Crowd sourcing on e and m – platforms with respect to local bodies.

79PMC Appointment City Corporation

In addition to the above staff the minimum sub key professional staff to be deployed by the Consultant shall be in accordance with the projects as proposed in the SCP and modifications therof from time to time by SPV. The C.Vs of these personnel needs to be submitted, however, the same will not be considered for evaluation. Some of Such experts are as follows:

No Position Qualifications &Skills Experience

1. Assistant Construction Manager

Graduate in Engineering

5 years’ experience in construction management of Urban Service delivery (Water Supply/ Sewerage/ Drainage/ Transportation/ Drainage/ Solid Waste Management)

2. Support Engineer Degree/Diploma in relevant branch

Degree in (relevant branch) Engineering with 2 years’ experienceOr

Diploma in (relevant branch) Engineering with 4 years’ experience

Development Professionals: The following CVs shall be submitted by the Consultant. However the same shall not be evaluated by the Employer for technical scores:

1. Urban Designer -1 Masters in Urban Design/Architecture or equivalent

12 years similar experience

2. Transportation Planner/ Engineer -1

Masters Degree in Transportation Planning/ Transportation Engineering/ Highway Engineering/ Highway Planning

10 years of experience in the area of Urban Transportation

Experience of preparation of Transit Oriented Development (TOD) / Urban Mobility Plan

3. Procurement Specialist -1

Degree in Engineering/ Management/ law / Business Administration or Equivalent

10 years of experience in the area of public procurement

Experience in construction contract procurement /management in infrastructure projects.

4. Landscape / pavement design Architects -1

Degree in Architecture 10 years’ relevant experience Experience in preparation of technical

requirements plans / document pavement design / landscaping

5. Solar Energy/ Renewable Energy Expert -1

B-Tech in Electrical/ Power Engineering

12 years of experience in power projects viz., planning/designing for power generation, transmission and distribution.

6. Electrical Engineering Expert -1

B-Tech in Electrical/ Power Engineering

12 years similar experience

7. Affordable Housing Expert -1

Masters in Urban Planning/Housing

12 years similar experience

8. Communication Masters in mass 10 years similar experience

80PMC Appointment City Corporation

Specialist -1 communication Experience in management of multimedia and activities pertaining to social media

9. Environment Management expert -1

Postgraduate in Environmental Planning / Engineering /Environmental Sciences

10 years’ experience in conducting EIA, environment modelling & preparing Environmental Management plans, Clean Development mechanism.

10. Utility Engineer -1 Degree in Civil/ Mechanical Engineering

10 years’ similar experience

11. Social Development Specialist -1

Masters Degree or equivalent in social development disciplines

10 years relevant experience Experience in urban social welfare

projects/ community mobilization/ Social Development Sub-Plan

12. Structural Engineer -1 Masters in Structural Engineering

10 Years in Structural Engineering. Should have the experience in structural

design of infrastructure projects.13. GIS & Remote

Sensing Expert -1 MCA/ Post Graduate in

any discipline and Diploma / degree in

GIS

At least 7 years of experience in working on similar projects (i.e use of remote sensing & GIS technology in urban sector projects)

Knowledge of major GIS software products, GPS, total station, coordinate reference systems, satellite remote sensing technology and GIS applications.

14. Heritage conservation expert -1

Bachelor’s in Architecture

10 years experience in heritage conservation work.

15.Business Analyst/ Junior BPR Specialist -1

MCA / Post Graduate in any discipline with diploma / degree in IT / BE/B-Tech. with MBA

10 years experience in similar field

16. Information Security Systems Expert -1

MCA/ B Tech / M Tech in IT with certification in CISSP/ CCSP

10 years experience in similar field

17. Solution Architect -1 Degree in Information Technology/ Electronics Engineering or equivalent

10 years experience in similar field

18. Networking & IT Infrastructure Specialist -1

MCA/ B Tech / M Tech in IT with certification in CCNA

10 years experience in similar field

19. Construction Manager -1 Graduate in Civil Engineering

10 years’ experience in construction management of Urban Service delivery projects (Water Supply/ Sewerage/ Drainage / Drainage/ Solid Waste Management).

81PMC Appointment City Corporation

Knowledge of different construction methodologies.

The guideline for minimum manpower deployment for the ABD projects is suggested as follows

1. Construction Manger - 22. Assistant Construction Managers - 5 3. Support Engineers – 15

For Pan City solutions (IT Components) PMC shall deploy at least One Project Manager and 2 Assistant Project Managers well versed in the field of IT, with the approval of MD, SPV.

The CV of the above professionals needs to be approved by MD, SPV at the time of deployment.

Appendix D: Services and Facilities to be provided by the Employer

As detailed in Terms Of Reference

82PMC Appointment City Corporation

Appendix E: Payment of Contract Price

1. Although, the Consultants have quoted for the entire project in lump-sum ,the detailed

breakdown of cost shall be provided in Section 4C and man power deployment shall be

provided in Section 3G. The same will be scrutinized and shall be finalized prior to signing

of Agreement and the same will be the basis for levying penalties and variations, if any,

during the execution of the contract.

2. Further, the payments will be made for each projects individually based on the deliverables

submitted as follows:

a) The ceiling price of consultancy fee (M) for an individual project would be M =derived

% x amount of the DPR , where amount of DPR shall mean Amount Put To Bid

(Excluding Tender Premium, Contingencies, price escalation)

b) The said fee M will be further divided and payment will be made as follows:

For Design Phase Activities (M1) = 40% of M

For Project Implementation Activities (M2) = 60% of M

The further breakdown of payment activity wise is as follows:

2.1 Payment terms for works, goods & services Based Projects:

No Deliverables Payment Schedule

A Design Phase (M1= 40% of M)

1 Activity 1: Mobilization Advance 5 % of M1

2 Activity 2 : Submission of Concept/Feasibility Report 10 % of M1

3 Activity 3 : Submission of Draft DPR 15 % of M1

4 Activity 4; Submission of Final DPR 25% of M1

5 Activity 5: Approval of Final DPR 15 % of M1

6 Activity 6: Approval of Bid Document 20% of M1

7 Activity 7: Completion of Bid Evaluation Report & Award

of work

10 % of M1

Note: Payment to the Consultants for activities 1-3 will be made on the basis of project

cost indicated in the SCP

Upon finalization of DPR difference in amount, if any, will be adjusted in future

83PMC Appointment City Corporation

payments.

In case of convergence and DPR being prepared by other agencies the same would

not be considered for consultancy fee.

B Project Implementation Support (PIS) M2 (60% of M)

1 Payment to the Consultants during implementation be

made on pro rata basis every quarter for the entire

duration of the project upon submission and acceptance of

monthly progress report.

In the event there is a stoppage of work of more than 3

months or for spill over of works beyond the project

implementation period for reasons not attributable to the

consultants, the fee payable will be remuneration of

personnel specifically deployed (as per man days) for the

particular sub-project.

M2/ Number of

Quarters proposed for

the said project

Note:

The % payment is based on the DPR cost and not on actual contract/implementation value. For reasons not attributable to the PMC, if there is any reduction in the scope of work during implementation, the 1st Phase payment will not be reduced.

2.2 Payment terms for PPP Projects:

No Deliverables Payment Schedule

A Design Phase (M1= 40% of M)

1 Activity 1: Mobilization Advance and submission of

Inception Report

5 % of M1

2 Activity 2 :submission of Market assessment and

Prefeasibility reports

5 % of M1

3 Activity 3: Approval of Prefeasibility Report 5 % of M1

4 Activity 4: Submission of REIAand Social Impact Study

Report

10% of M1

5 Activity 5: Approval of Concession Agreement 30% of M1

6 Activity 6: Completion of BER 20% of M1

7 Activity 7: Signing of Concession Agreement 25% of M1

B Project Implementation Support (PIS) (M2= 60% of M)

1 Vetting of DPR and Designs submitted by the 10% of M2

84PMC Appointment City Corporation

Concessioner

Note: Payment to the Consultants for all design activities and activity1 of

Implementation period will be made on the basis of project cost indicated in the

SCP. Upon finalization of DPR, difference in amount, if any, will be adjusted in

future payments.

2 Payment to the Consultants during implementation be

made on pro rata basis every quarter for the entire

duration of the project upon submission and

acceptance of monthly progress report.

In the event there is a stoppage of work of more than 3

months or for spill over of works beyond the project

implementation period, for reasons not attributable to

the consultants, the fee payable will be remuneration of

personnel specifically deployed (as per man days) for

the particular sub-project.

90% of M2/ Number

of Quarters Proposed

for commissioning the

scheme.

Note:

The consultants are expected to do a proper feasibility study prior to proposing PPP projects.

All efforts shall be made to conclude signing of Concession Agreement. As such, it is unlikely that PPP projects will be taken up in EPC mode. However, in the event of failure to sign the concession agreement of PPP projects the decision to take up projects on EPC mode shall vest with the SPV in consultation with KUIDFC.

3. PMC will be paid fees only for the implementation phase, as per his % quote, in such cases.

4. During implementation, if there is change in scope not attributable to the PMC, which increases the project cost beyond 10% , the consultancy fee will be increased appropriately.

a. Any change in scope will be reviewed by a Committee constituted by the SPV/Government. The decision of the Committee shall stand final with respect to type and extent of change in scope.

5. No price escalation is envisaged for the entire contract duration of 5 years. In the event the consultancy services is extended beyond the project period of 5 years , then price escalation as per CPI/WPI , whichever is applicable, will be made applicable as approved by the SPV. The CPI/WPI, whichever is applicable, base rate will be taken from the end of the 5th Year.

6. Variations shall not be beyond 10% above or below the DPR costs. The PMC will be subjected to penal action if variations are found to be greater than the set bench mark and also for delay in submitting the DPRs, bid documents, supply of drawings, designs etc., The SPV will be responsible for monitoring the PMCs performance and initiate action / penalise for non-compliance with the ToR, wrong/incomplete specification in the bid documents,

85PMC Appointment City Corporation

improper estimate, improper / poor progress monitoring, not informing in advance about necessary actions to be taken by the IA, etc.

7. For variation beyond 10% above are below, on account of faulty design and estimates, of the project value the following penalty shall be levied

Variation Amount LD leviable

+/- >10 & ≤20% of project value 2.5 % of the consultancy fee for the said project

+/- >20 & ≤ 30% of project value 5 % of the consultancy fee for the said project

+/- >30 & ≤40% of project value 7.5 % of the consultancy fee for the said project

> 40% of project value 10 % of the consultancy fee for the said project

Note: While calculating the variation the same will be rounde of to two decimal places.

8. The SPV will be responsible for monitoring PMC performance and initiate actions for non-compliance with the Terms of Reference. Based on the periodic review of the performance of PMC, necessary action will be initiated. In the event of total default / failure of the firm in execution of the services, the employer reserves the right to get the work executed by any other consultancy firm at the risk and cost of the defaulting consultancy firm. Decision of employer is final & binding on the consultancy firm.

9. Penalty for delays in submission of deliverables (Only for Design Phase) for works, goods & services Based Projects:

If the consultants fails to submit the bid document as mentioned in Appendix B, clause 1.1 (B.2) within T0+ 6 months, the Employer shall, without prejudice to its other remedies under the Contract, deduct from the Contract Price, as penalty, a sum equivalent to 0.1 % of the consultancy fee, payable for the design phase for the sub project, for each day of delay until actual submission or , up to a maximum deduction of 10% of the consultancy fee payable for the design phase. Once sum of such penalties of all the subprojects reaches the maximum of 10% of the overall consultancy fee payable for the design phase., the Employer may consider termination of the Contract pursuant to GCC Clause 2.7. No penalty will be levied for delays not attributable to the consultants.

For PPP Projects:If the consultants fails to submit the Final Concession Agreement as mentioned in Appendix B, clause 2.1 (B.2) within T0+ 3 months, the Employer shall, without prejudice to its other remedies under the Contract, deduct from the Contract Price, as penalty, a sum equivalent to 0.1 % of the consultancy fee, payable for the design phase for the sub project, for each day of delay until actual submission or , up to a maximum deduction of 10% of the consultancy fee payable for the design phase. Once sum of such penalties of all the subprojects reaches

86PMC Appointment City Corporation

the maximum of 10% of the consultancy fee payable for the design phase, the Employer may consider termination of the Contract pursuant to GCC Clause 2.7. No penalty will be levied for delays, not attributable to the consultants.

10. Penalty for delay in deployment/replacement/ non-deployment of Key Professionals:

Whenever a change in Key Professional is proposed, approval of the CV for replacement personnel has to be obtained from the Employer. Further, for every replacement proposed for a particular position, 5% of the applicable man month rate/fee detailed in Schedule 4C , Break down of cost, payable for the entire project for that position , will be deducted, as a onetime lump sum deduction in ongoing bills.

In the event the sum of such of penalties totals to 10% of the total key professional remuneration for the entire project duration as detailed in Schedule 4C, Break Down of Cost, the Employer may consider termination of the Contract pursuant to GCC Clause 2.7. No penalty will be levied for delays, not attributable to the consultants.

In the event the consultancy firm does not deploy the key professional/Development Professional, as specified in the Schedule 4 C & Deployment Plan, for a period not more than 15 days, a penalty of twice the man day rate will be levied for the number of days of non deployment. The same will be deducted in the ongoing bills.

11. Bonus for early completion of Design Phase:For works, goods & services Based Projects:If the consultants submits the bid document prior to the time frame, as mentioned in Appendix B, clause 1.1 (B.2) within T0+ 6 months, the Employer shall, pay a bonus of 0.1 % of the consultancy fee payable for the design phase for the sub project for each day of early completion , up to a maximum bonus of 5% of the consultancy fee payable for the design phase for the said sub project

For PPP Projects:If the consultants submit the Final Concession Agreement prior to the time frame, as mentioned in Appendix B, clause 2.1 (B.2) within T0+ 3 months, the Employer shall, pay a bonus of 0.1 % of the consultancy fee payable for the design phase for the sub project for each day of early completion , up to a maximum bonus of 5% of the consultancy fee payable for the design phase for the said sub project

87PMC Appointment City Corporation

Appendix –F : Format of the Performance Bank Guarantee

To:

Whereas [name and address of the successful bidder] (hereinafter called the "Successful Bidder") has

undertaken, in pursuance of Contract No. [number] dated [date] to execute [name of Contract and brief

description of Services] (hereinafter called the "Contract");

And whereas it has been stipulated by you in the said Contract that the Successful Bidder shall furnish

you with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance

with his obligations in accordance with the Contract;

And whereas we have agreed to give the Successful Bidder such a Bank Guarantee;

Now therefore we hereby affirm that we are the Guarantor and responsible to you, on behalf of the

Successful Bidder, up to a total of [amount of Guarantee] [amount in words], , and we undertake to pay

you, upon your first written demand and without cavil or argument, any sum or sums within the limits of

[amount of Guarantee] as aforesaid without your needing to prove or to show grounds or reasons for your

demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Successful Bidder before

presenting us with the demand.

We further agree that no change or addition to or other modification of the terms of the Contract or of the

Services to be performed there under or of any of the Contract documents which may be made between

you and the Successful Bidder shall in any way release us from any liability under this Guarantee, and we

hereby waive notice of any such change, addition, or modification.

This Guarantee shall be valid until a date 28 days from the date of issue of the Certificate of Completion.

Signature and seal of the Guarantor

Name of Bank

Address

i. Date

88PMC Appointment City Corporation