Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the...

18
Introduction to the power sector baseline scenarios and the IRENA SPLAT-W/MESSAGE tool International Renewable Energy Agency (IRENA) Innovation and Technology Centre Development of the ECOWAS RE and EF National Action Plans and SE4ALL Abidjan, 17-19 March 2014

Transcript of Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the...

Page 1: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Introduction to the power sector baseline scenarios and the IRENA SPLAT-W/MESSAGE tool International Renewable Energy Agency (IRENA) Innovation and Technology Centre Development of the ECOWAS RE and EF National Action Plans and SE4ALL Abidjan, 17-19 March 2014

Page 2: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

RE target setting

Common inconsistencies: Bottom-up targets do not meet the overall energy

needs Sum of sector targets does not meet the overall

energy needs Top-down targets imply unrealistic speed of

technology transition

It is crucial to have an accounting framework for: Overall future energy needs Overall future energy supply mix

2

Page 3: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Energy system models

Bottom up models Accounting – suited to demand side analysis (e.g.,

LEAP, MAED) Optimization – suited to supply side analysis (e.g.,

MARKAL, TIMES, MESSAGE etc)

IRENA SPLAT-W model: optimization model built based on the MESSAGE modelling framework

3

Page 4: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

NREAP and SPLAT-W

Interested countries can use SPLAT-W to benchmark their power sector trajectory

Define the future energy mix (installed capacity and power generation by technology to meet a given set of demand)

Assess implications on policy goals (financial, environmental, energy security etc)

Compare with alternative future energy mix under different scenarios

4

Page 5: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

NREAP scenario

At the request of ECREEE, a NREAP scenario is being developed for each ECOWAS countries using SPLAT-W.

Note on process IRENA’s desk-top study, not meant to give recommendations

on countries trajectories It provides a useful benchmark Interested countries are invited to verify data with IRENA

(data verification sheet) Interested countries are invited to use the tool to

develop/adjust the scenario Many ECREEE countries have trained national experts

5

Page 6: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

How did we define the NREAP scenario? (1)

Step 1 • Power demand till 2030 is defined for industry, urban, rural

demand

• Demand patterns (seasonal, weekly, daily) are defined for each demand category

• Distribution losses are defined for each demand category

Step 2 • Database of existing power plans and international transmission

lines are set up, with performance parameters

6

Page 7: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

How did we define the NREAP scenario? (2)

Step 3 • Database of projects (PP or interconnector) under

implementation/considerations are set up

• Database of possible power generation options is set up with economic and performance parameters

PP with fossil fuel inputs (diesel 1kW system, Diesel 100kW system, utility diesel, utility HFO, coal, OCGT, CCGT)

Hydro (utility / decentralized – only to serve rural demand) Biomass Wind (20% CF, 30% CF) Solar PV (utility scale) Solar PV 1 kW decentralized (no storage / 1 hour storage / 2 hour storage) CSP (no storage, with storage, with gas co-firing)

• Database of RE resource availability is set up

7

Page 8: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

How did we define the NREAP scenario? (3)

Step 4 The model calculates the least-cost combinations of power supply options to meet the specified demand at a specified time, under certain conditions

Step 5 Certain conditions includes:

NREAP regional targets are met Reserve margin to be at least 10% (installed ‘firm’ capacity need to be 10%

higher than peak-demand) Capacity credits of non-dispatchable RE technologies vary depends on CF

and level of spatial distribution of resources locations Coal and biomass plants cannot be ramped-up very fast Among those interconnecting projects being considered, economically

viable ones would be implemented to allow electricity trade Other conditions are similar to those assumed under WAPP master plan Trade with Central Africa / CO2 price could be added as an option

8

Page 9: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Share of renewable [capacity]

9

0%

20%

40%

60%

80%

100%

120%

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

Share of RE capacity: Regional results

in relation to peak in relation to total installed capacity

(non-hydro) (non-hydro)

Page 10: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Share of renewable [capacity]

10

0%

50%

100%

150%

200%

250%

300%

350%

400%

450%

500%

2010 2015 2020 2025 2030

In relation to peak

Benin Burkina Cape Verde Cote d'Ivoire GambiaGhana Guinea Guinea-Bissau Liberia MaliNiger Nigeria Senegal Sierra Leone Togo

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

2010 2015 2020 2025 2030

In relation to total installations

Page 11: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Cote D’Ivoire

11

0

2

4

6

8

10

12

14

16

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

TWh

Industry Urban Rural

Final energy demand Existing PP (as of 2010) Gas Turbine: 790 MW Hydro: 585 MW (1.8-2.4 TWh)

In the pipeline Gas Turbine: 860 MW

Resources Additional identified hydro:

3-5 TWh Wind 20% CF: 430 TWh CSP 220 TWh Solar PV 10,300 TWh

Fuel availability

Coal: import Gas: domestic Oil: import

Import from neighbors

Existing: Ghana, Burkina Faso Committed: Ghana, Liberia,

Mali

Page 12: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Cote D’Ivoire

12

LCOE at generation

50

100

150

200

250

300

2010 2030

LCO

E ($

/MW

h)

HFO

OCGT

CCGT

CCGT (in the pipeline)

Supercritical coal

Hydro (280 MW project)

Hydro (50MW project)

Small Hydro

Biomass

Bulk Wind (20% CF)

Solar PV (utility)

Solar PV (roof top)

Rooftop PV with 1h Battery

Rooftop PV with 2h Battery

Solar thermal no storage

Solar thermal with Storage

Solar thermal with gas co-firing

Page 13: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Cote D’Ivoire LCOE with TnD needs

50

100

150

200

250

300

350

400

2010 2030

LCO

E ($

/MW

h)

industry

2010 2030

urban

2010 2030

Rural Diesel Centralized

Diesel 100 kWsystemHFO

OCGT

CCGT

CCGT (in thepipeline)Supercritical coal

Hydro (280 MWproject)Hydro (50MWproject)Small Hydro

Biomass

Bulk Wind (20%CF)Solar PV (utility)

Solar PV (roof top)

Rooftop PV with1h BatteryRooftop PV with2h BatterySolar thermal nostorageSolar thermal withStorageSolar thermal withgas co-firing

Page 14: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Cote D’Ivoire

14

Electricity production [TWh] Share of RE [capacity]

Rural demand [GWh] RE capacity [GW]

(10)

(5)

-

5

10

15

20

25

2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030

Dist.Solar PVMini HydroDist. OilNet ImportsWindSolar ThermalSolar PVBiomassHydroNuclearGasOilCoaldom. System dmd

0

0.1

0.2

0.3

0.4

0.5

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

RE share capacity (peak) (total installed capacity)

0

100

200

300

400

500

600

700

2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030

Grid Diesel Mini-hydro

0

0.5

1

1.5

2

2.5

2010 2015 2020 2025 2030

Hydro Biomass Mini Hydro Dist.Solar PV

Page 15: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Cote D’Ivoire

Annualized costs [billion $]

Investment needs [billion $]

-1

0

1

2

3

2010 2015 2020 2025 2030

O&M

Inv.

Fuel

Ann.Dom.Trans InvAnn.TransInvImport costs

ExportRevenues

0

0.5

1

1.5

2

2.5

2010 2015 2020 2025 2030

Bill

ion

$

InternationalTransmissionDomestictransmissionDecentralized

60

70

80

90

100

110

120

130

140

150

160

2010 2015 2020 2025 2030

Cote D'Ivoir ECOWAS average

Average generation costs [$/MWh]

Page 16: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Development of power sector baseline trajectory for ECOWAS countries

IRENA’s desk-top study, developed using SPLAT-W Normative scenario, illustrating the implications of EREP on

each country Provide useful benchmark Data review sheet can be made available to interested

countries The SPLAT-W is available with tutorials

16

Contributions to NREAP

Page 17: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Planning for the Global Energy Transition

IRENA’s resources: Sound statistics and data

Statistical methodology: [email protected] GIS mapping and assessment of theoretical

generation potential RE technology costing analysis: [email protected] RE technology brief

• Transparent methodology: SPLAT-W model (benchmarking, transfer the tool, list of resource people)

• Ownership of the planning skill: long term CB is being discussed, engaging local experts

17

Page 18: Introduction to the power sector baseline scenarios and ... · PDF fileIntroduction to the power sector baseline scenarios and the IRENA ... demand category ... Capacity credits of

Thank you for your attention Asami Miketa

[email protected]

www.irena.org