Introduction to IRRIIS MIT Add-On Components IRRIIS, CRUTIAL & GRID Review Meeting 15 March 2007,...
-
Upload
diane-stevens -
Category
Documents
-
view
228 -
download
0
Transcript of Introduction to IRRIIS MIT Add-On Components IRRIIS, CRUTIAL & GRID Review Meeting 15 March 2007,...
IRRIIS- FP6-2005–IST-4
EC - LOGO
Introduction to IRRIIS MIT Add-On Components
IRRIIS, CRUTIAL & GRID Review Meeting
15 March 2007, Brussels
Sandro Bologna
IRRIIS
Three Layers Model for the Critical Infrastructure
CyberCyber
LayerLayer
Organisational Organisational
LayerLayer
Intra-dependency
Inter-dependencyPhysical Physical
LayerLayer
IRRIIS
Three Layers Model for the Critical Infrastructure
Electrical ComponentsElectrical Componentsgenerators, transformers, breakers,generators, transformers, breakers,
connecting cables etcconnecting cables etc
Control and supervisory hardware/software components
(Scada/EMS systems)
Electrical Power OperatorsIndependent System Operator
for electricity planning and transmission
Intra-dependency
National Electrical Power Transmission Infrastructure
Telecomunication Infrastructure
Oil/Gas Transport System Infrastructure
Foreign Electrical Transmission Infrastructure
Inter-dependency
IRRIIS
MIT Introduction
MIT is a software system aiming at enhancing the availability and survivability of LCCIs by mitigating dependency and interdependency effects.
Communication Components. Add-On Components. Other software resources (Databases,GUI,
Configuration Files, Run-Time Environment, etc.)
IRRIIS
Control Room with MIT WorkStation
LCCI 1
LCCI 2
MIT WorkStation
MIT WorkStation
Control Room
Control Room
IRRIIS
MIT integration with existing SCADA systems
IRRIIS
MIT integration with existing SCADA systems
IRR
IIS
In
ter-
LC
CI
Com
mu
nic
ati
on
Hig
hw
ay
LC
CI
1L
CC
I 2
IRRIIS
Overall MIT architecture
IRRIIS
MIT Add-On Components
Internal Assessment– Tool to extract LCCI functional status
Risk Assessment– Risk Estimator– Incident Knowledge Analyser
Emergency Management– Assessment of cascading/escalating effects– Display of Emergency Management Procedures– Negotiator
IRRIIS
Risk Estimator functions
Reasoning about the states of processes and services, mainly focusing on the services to be exchanged with other LCCIs.
Estimating the levels of risks associated to services exchanges with other LCCIs.
Working on a service-process model of the LCCIs by making use of a fuzzy rules-based mechanism.
IRRIIS
Visualisation of the levels of risks associated to the services
LCCI internal stateestimation
After external &internal states
correlation
IRRIIS
Risk Estimator workflow and relations with other add-on components
ISRIA
INPUTS
Internal status table
External status table
Rule Based Correlation
Module
Current State DB
Expert Rules
DB
IKA
Historical status facts
GUI DEMP
OUTPUTSINTELLIGENCE
RuleEditor
Maps ofRisks
Maps ofRisks
LEGENDIA: Internal Assesment ISR: Information Subscriber & ReaderIKA: Incident Knowledge AnalyserDEMP: Display of Emergency Management Procedures GUI: Graphical User Interface
Estimated State DB
IRRIIS
Risk Estimator Benefits
• Make operators more aware about the global LCCIs state, correlating local LCCI and external LCCIs states.
• Give to the LCCIs operators schematic pictures evidencing the potential risks to loss internal and external services.
• Improve coordination between the LCCI operator and the neighbouring LCCIs.
IRRIIS
LAMPSSys RTI
GUI Logger
To
ol 1
Electricity
Simulator LCCI
DataTlc SCADA
Emulator
To
ol 2
Agent / Scenario
Behaviours
An
alysis 1A
nalysis 2
Fault /
Attack
Tool
An
alysis 3
MIT 1
MIT 2
SimCIP
Proposed DEMONSTRATION Logic Set up
Ele SCADA
Emulator
Telco
Simulator
IRRIIS
GUILogger
LAMPSSys RTI
Agent / Scenario
Behaviours
Electricity
Simulator
Com
Simulator
LCCI
Data
Fault /Attack
Tool
Tool 1
Tool 2
Analysis 1, 2, 3 ..
SimCIP
MIT 1Electrical LCCI
MIT 2TeleCommunication LCCI
Proposed TESTBED Physical Configuration
IRRIIS
Roma Mini TELCO Black-out January 2004
Pre-incident TELCO
network in secure state
Station continue
working with decreased
battery autonomy
Many external Telco services
go down, as the ACEA data links between
control centers
The normal power supply
from ACEA was
restarted
Returnto
normal state
AND AND
Trip of main power
supply
Loss of power supply
Damaged equipment replaced
Telco services restart
AND AND
NETWORK STATE OVERVIEW & ROOT CAUSES
1Flood on the
apparatus room of the Telco SGT
station. UPS start from batteries
2The battery autonomy
finished as Fire Brigate was not able to
eliminate water in time.
3The full
functionality of the SGT station is
restored
4 hoursSafe network state
Endangerednetwork state
Disturbednetwork state
Collapsednetwork
Event
Root cause
Legend
90 min.
IRRIIS
ACEA Remote control system: an overview
Distribution grid TLC tools Owned by Status
High Voltage
Copper cables Power line carrier GSM service
AceaAceaOthers
Complete and working
Medium Voltage GSM Copper cables
OthersOthers
Advanced, but non yet complete
Low Voltage Power line carrier (1)
GPRS (2)
AceaOthers
Advanced 20%
(1) From energy meter to secondary cabin
(2) From secondary cabin to control room
IRRIIS
Effects on the public telecom network
Telecom inter district fixed traffic
OFL Overall Failed Load
ASR Answer Seizure Ratio
IRRIIS
Effects on the ACEA tele-control Centers
Data flux A
Data flux B
FLAMINIA
Control Centre
Electrical
grid 1
Substationsdirectly affected
by Telco blackout
OSTIENSE
Control Centre
Electrical
grid 2
Substations
not directly
affected by
Telco blackout9:30:54 Out of service of data flux A
9.32:00 - 9.32:00 Few number of tele command failures
9.32:15 Out of service of data flux B
9.32:19 - 9.32:30 General tele command failures
9.32: 32 Service restoration of data flux B
9.32:34 - 9.32:59 General tele command restoration
9.33:01 Out of service of data flux B
9.33:34 - 9.34:12 General tele command failures
9.34:12 - 9.44:00 Total substations un visibility
9.44:00 - 9.56:00 Service restoration of some substations in backup mode
10.54:35 Service restoration of data flux A
10.54:43 -10.56:29 All substations reactivated, many of them in local command operation
10:57:56 Service restoration of data flux B
Sequence of Events
ACEA Control Centers configuration
IRRIIS
Roma Mini TELCO Black-out January 2004
Pre-incident TELCO
network in secure state
Station continue
working with decreased
battery autonomy
Many external Telco services
go down, as the ACEA data links between
control centers
The normal power supply
from ACEA was
restarted
Returnto
normal state
AND AND
Trip of main power
supply
Loss of power supply
Damaged equipment replaced
Telco services restart
AND AND
NETWORK STATE OVERVIEW & ROOT CAUSES
1Flood on the
apparatus room of the Telco SGT
station. UPS start from batteries
2The battery autonomy
finished as Fire Brigate was not able to
eliminate water in time.
3The full
functionality of the SGT station is
restored
4 hoursSafe network state
Endangerednetwork state
Disturbednetwork state
Collapsednetwork
Event
Root cause
Legend
90 min.Also before the crisis contingencies, MIT Add-on components could support different LCCIs operators to negotiate
possibilities for short term black-outs in case of need.
IRRIIS
Roma Mini TELCO Black-out January 2004
Pre-incident TELCO
network in secure state
Station continue
working with decreased
battery autonomy
Many external Telco services
go down, as the ACEA data links between
control centers
The normal power supply
from ACEA was
restarted
Returnto
normal state
AND AND
Trip of main power
supply
Loss of power supply
Damaged equipment replaced
Telco services restart
AND AND
NETWORK STATE OVERVIEW & ROOT CAUSES
1Flood on the
apparatus room of the Telco SGT
station. UPS start from batteries
2The battery autonomy
finished as Fire Brigate was not able to
eliminate water in time.
3The full
functionality of the SGT station is
restored
4 hoursSafe network state
Endangerednetwork state
Disturbednetwork state
Collapsednetwork
Event
Root cause
Legend
90 min.
MIT Add-on components could estimate the internal risks associated to possible external services degradation.
IRRIIS
Roma Mini TELCO Black-out January 2004
Pre-incident TELCO
network in secure state
Station continue
working with decreased
battery autonomy
Many external Telco services
go down, as the ACEA data links between
control centers
The normal power supply
from ACEA was
restarted
Returnto
normal state
AND AND
Trip of main power
supply
Loss of power supply
Damaged equipment replaced
Telco services restart
AND AND
NETWORK STATE OVERVIEW & ROOT CAUSES
1Flood on the
apparatus room of the Telco SGT
station. UPS start from batteries
2The battery autonomy
finished as Fire Brigate was not able to
eliminate water in time.
3The full
functionality of the SGT station is
restored
4 hoursSafe network state
Endangerednetwork state
Disturbednetwork state
Collapsednetwork
Event
Root cause
Legend
90 min.
MIT Add-on components could help the LCCI operator to be more prepared during the black out contingencies.