Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

14
Introduction SAP Material Planning Dr. Djamal Ziani King Saud University
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    220
  • download

    6

Transcript of Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Page 1: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Introduction SAP Material Planning

Dr. Djamal ZianiKing Saud University

Page 2: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Organizational Level in Material Planning

• Client• Company code• Plant• Storage location

Page 3: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Master Data Used

• Material Master• Bill Of Material (BOM)• Routings

Page 4: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Material Master

Page 5: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Material Type

• Raw materials• Operating supplies• Semi-finished products• Finished products

Page 6: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• The BOM contains the assemblies or components, to be included in the

production of a material.

• Used in MRP, production, procurement and for product costing

Page 7: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• The BOM are single level.

• The items of the BOM can themselves contain further BOM

Page 8: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• Plant: is the plant for which you wish to create or process the BOM. You can

assign more than one plant.

• Alternative BOM: For distinguish the different BOM for the same material

• BOM usage: Where you want to use the BOM (production, engineering,

costing…)

Page 9: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Routings

• Routings contain the steps that are necessary for production: – The corresponding operations– The sequence– Work center in which these operations are to be

executed– Time elements that are relevant for scheduling

the operations

Page 10: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Routings

Page 11: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP: Material Requirement Planning• The system calculates the quantity required to continue the sales of the

final product without any delays, considering the following resources: – Stock on hand.– Receipts: purchase orders, production orders (for the parent item)

• The system then subtracts the following requirements:– Sales orders– Forecasts– Production orders (for the child items)– A/R reserve invoices

• The system uses the planning policy to make the production/purchase order recommendations. The planning policy is based on:

– Lead time, Minimum amount ,, Time intervals

• Complete production orders for the parent item, quantities of the child items that comprise the BOM are needed. The system calculates the quantity of the child items, taking the MRP-dependent requirements into account. The system then recommends purchase/ production orders for the child items required for producing the parent item.

Page 12: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP: Material Requirement Planning

Page 13: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP

Page 14: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP-Processing Key• NEUPL : Regenerative Planning. It will process ALL materials,

disregards the fact whether or not planning relevant changes were made to the material.

• For NETCH and NETPL: the system take into consideration only changes that are relevant for planning a material (like sales order entry, purchase order entry, stock release, etc.). – NETCH : Net Change Planning– NETPL : Net Change Planning within Planning Horizon. if a change

occurs outside the planning horizon (e.g. a sales order is entered 2 months away and your planning horizon is 6 weeks), then the material is not included in MRP even though there is a change.