Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

41

description

OUTLINE. JW Marriott Greg Kochalski. Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations. JW Marriott Greg Kochalski. Introduction. Project Information - PowerPoint PPT Presentation

Transcript of Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Page 1: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System
Page 2: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 3: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Project Information•24 story Marriott signature series Hotel •Located along the Grand River in downtown Grand Rapids, MI•340 Rooms•376,000 sq. ft. •Amenities include restaurant, lounge, business center, fitness center, and spa•Stylistic architecture with reflective glass cladding•Open Air Atrium •Heated Helipad

Introduction JW MarriottGreg Kochalski

Page 4: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Site Plan

Introduction JW MarriottGreg Kochalski

Downtown Grand Rapids

Page 5: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Project Teamowner- Alticor inc.Architect- Goettsch Partners and

Beta Design GroupStructural- Thornton Tomasetti EngineersContractor- Pepper Construction and

Rockford ConstructionMEP- Cosentini Associates

Introduction JW MarriottGreg Kochalski

Page 6: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 7: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Foundation•200 ton micro piles•Pile caps located along the perimeter and beneath the core•4-7 micro piles per group

Existing Structure

JW MarriottGreg Kochalski

Page 8: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Floor System•Flat Plate R.C. •Short spans- 17 ft.•One way action•Typical bay approx 17x35 ft•7.5 in. Slab• f’c = 5700 psi•Blade-Columns located along perimeter•Transfer girders at levels 3-5

Existing Structure

JW MarriottGreg Kochalski

Eccentric loading requires heavy torsional reinforcing in beam

Page 9: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Blade-Columns•Reduce spans•Limit slab thickness•Maximize patron views•Fit within interior partitions•Boundary confinement at edges

Existing Structure

JW MarriottGreg Kochalski

Typical Floor with Radial Columns

Confinement

Typical bay

Page 10: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System•Two pairs of shear walls•F’c varies from 10 ksi to 6ksi •Boundary elements for increased inertia in east-west•12 in. thick in both directions

Existing Structure

JW MarriottGreg Kochalski

Heavy confinement in boundary elements

Page 11: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 12: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Structural Redesign JW MarriottGreg Kochalski

Proposal Summary•Relocation to Monterey, CA•New lateral system•New Post tension floor system•Use updated building code

Design Goals•Achieve desired non-linear response•Avoid pitfalls of peer review •Limit vertical walls to <3.0% of floor area

Grand Rapids

•MBC 3003 (IBC 2003)•ACI318 2002•ASCE7 2002

Monterey•IBC 2006

•ACI318 2002 •ASCE7 2005

Building Codes

Page 13: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Post Tension System JW MarriottGreg Kochalski

Characteristics •Typical span = 35 ft.•9.5 in. PT flat plate (l/45)•Class U system•Balance 85% dead load•½ in. 270 ksi strands•F’c = 4000 psi

Labeling Scheme

Dead 20 20

Live 40 40

PT Floor LoadsDesign

Loads (psf)ASCE 7

(psf)

Page 14: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Post Tension System JW MarriottGreg Kochalski

Page 15: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Post Tension System JW MarriottGreg Kochalski

Large banded tendons Small banded tendons

Page 16: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Post Tension System JW MarriottGreg Kochalski

AB 0.268 L/1150

CD 0.361 L/1150

Slab Deflections

Span Deflection (in)

Deflection Equivalent

Average Stresses

529'279

'3.0667'6217

79,442,225

c

c

c

n

n

f

fff

psipsiSMpsi

AF

SM

AFf

*9.5 in. PT flat slab works*

Page 17: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

•Force dissipation mechanism ensures integrity•Plastic hinging in beams, walls approach yielding•Detailed for proper ductility•Even deformations over height

•256 ft exceeds 240 ft height limit•Requires “code equivalent performance”…•Inherent uncertainties when interpreting code

Nonlinear Response

Peer Review

Page 18: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Analysis Methods•Equivalent lateral force method

•Manual calculations•Etabs

•Modal response (dynamic) analysis•Etabs

Spectral Response Parameters•Sds=0.97•Sd1=0.53•S.D.C.= D•S.C. = C

•O.C.=II•R=5.0•Cd=4.5

Page 19: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Etabs Cases & Combinations•Static analysis (accidental torsion)

•EXZ1- ecc in x, cw moment•EXZ2- ecc. In –x, ccw moment•EYZ1•EYZ2

•Dynamic analysis (member forces)•XSPECF•YSPECF

•Dynamic analysis (Displacements)•XSPECD•YSPECD

Scale Factors

Page 20: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Pier and Spandrel Labeling

Page 21: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Coupling Beams

gross2effective I/31

2.0I

nlh

bdfV cu '0.8

Cracked section

Ultimate shear

Interpreting the outputInfluence…•Period•Shear (in walls)•displacements

0

0.5

1

1.5

2

2.5

3

0.00 0.20 0.40 0.60 0.80

IePe

riod

(s),

V (n

orm

aliz

ed)

Period

Vnormalized

Ie Vmax Vnorm Period

0.10 189 0.814655 2.760.16 232 1 2.4250.5 317 1.366379 1.99

0.75 340 1.465517 1.90

Varying Ieff

Page 22: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Ultimate ShearDetermined Group, and will be the Maximum of

•0.8Vmax

•Vaverage

0.8 Vmax Vaverage 0.8 Vmax Vaverage

(K) (K) (K) (K)Roof 90

24 11123 11322 12121 13120 14219 15218 16217 17116 17915 18714 19413 20112 20811 21410 2209 2258 2297 2326 2315 2284 2203 205

2 Mezz 1812 163

Level Shear (K)

Shears

122 122

161 182

186 221

Coupling Beam Ultimate Shear

186 205

Design Group Shears

122 122

161 182

186 213

Reinforcing must ensure•Proper Ductility•Failure in moment, not shear

Detailing

Page 23: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Page 24: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Displacement

<2.0% Height (code)<1.0% Height (imposed)

0.01H = 30 in.

Max Displacement16.6 in. (x)21.4 in. (y)

X direction Y direction

yx

Page 25: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Displacement

0.00 5.00 10.00 15.00 20.00 25.00

2nd

Story 3

Story 5

Story 7

Story 9

Story 11

Story 13

Story 15

Story 17

Story 19

Story 21

Story 23

Roof

Leve

l

Inches

delta y

delta x

Interpreting output•Beam action in Y•Frame action in X

Max Displacement16.6 in. (x)21.4 in. (y)

yx

Page 26: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Shear Walls

Direct Shear•Distributes by area•Limit shear to:

Flexure•Distributes by inertia•Reinforce to resist tension

Design Criteria

ltfV cu '0.4

Page 27: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Direct Shear

ltfV cu '0.4

)22cos(ft2.12)33cos(ft77.9*

ft5.19*where,'78.3k350:8&7Pier

ft0.26where,'11.4k876:6Pier

ft67.18where,'24.2k343:5&4Pier

ft33.37where,'59.3k1100:3Pier

228/7

28/7

26

25/4

23

v

vvc

vvc

vvc

vvc

A

AAf

AAf

AAf

AAf

Page 28: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Interpreting the Output

Av (ft2) 26 37.3 37.3 26 Kv 0.7 1.0 1.0 0.7 DFv 0.21 0.29 0.29 0.21

VOP 876 1100 1100 876 DFOP 0.22 0.28 0.28 0.22

Theoretical

Etabs Output (YSPECF)

Av shown in blue

Page 29: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

FlexureReinforce Tension Areas•PCA column•Load cases derived from ASCE7

GRAVITYWTSELF

yy

xx

yx

yx

yx

yx

yx

yx

yx

yx

DSDSv

v

PPD

MEME

EED

EED

EED

EED

EED

EED

EED

EED

LSDSEEELD

XinEarthquaketodueYinEarthquaketodueWhere

0.13.07.08

0.13.07.07

0.13.07.06

0.13.07.05

3.00.17.04

3.00.17.03

3.00.17.02

3.00.17.01:becomes then ASCE7

0 and , 0.97,2.0where0.10.15.09.0:ASCE7

My Mx

Moment sign convention

Page 30: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

ReinforcingTrends:•Heavy reinforcing in outer areas of flanges•Light reinforcing in webs

3 9 1 16 18 0.264 9 2 6 38 1.415 9 2 6 38 1.416 9 1 11 15 0.40

7 outer 9 3 3.5 30 1.137 inner 9 2 6.5 24 1.708 outer 9 3 3.5 30 1.138 inner 9 2 6.5 24 1.70

Pier Rebar # Spacing (in)

ρ, per Pier (%)

ρ, per section (%)

As (sq. in.)Rows

1.16

0.94

Pier Vertical Reinforcing Schedule

3 4 2 10 0.48 0.254 5 2 10 0.74 0.265 5 2 10 0.74 0.266 4 2 10 0.48 0.257 5 2 10 0.74 0.268 5 2 10 0.74 0.26

Pier Horizontal Reinforcing Schedule

Pier Rebar # Rows Spacing (in) As (in2/ft)

ρ, per Pier (%)

Page 31: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Lateral System JW MarriottGreg Kochalski

Verifying the Results

Page 32: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 33: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Architectural Redesign JW MarriottGreg Kochalski

Affected Areas

Notable IBC codes

•Stairwells•Patron elevators•First floor service corridor and restrooms•Second floor fire corridor

1019.1: “exit enclosure shall not be used for other than egress…”1019.1.2: “no penetrations shall be allowed except those related to exit egress or systems directly related to the function of the exit way…”

The atrium is a large focal point of the architecture

Page 34: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Typical Floor

Page 35: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Ground floor

Page 36: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 37: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Cost Analysis JW MarriottGreg Kochalski

Primary Losses•PT system more skill intensive•Lower daily production •Thicker slab

Post tension system require longer durations and more expensive labor

Secondary Losses•Duration increase•Interest earnings

Page 38: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Cost Analysis JW MarriottGreg Kochalski

Direct Loss Comparison

Secondary Losses•$230/night average room price•60% occupancy expected•$8 million lost in 25 week delay

*Actual duration of 47 weeks due to weather

Location Grand RapidsCrew C-17BDaily Output (cy) 30.24Labor Hours (cy) 6.878Material ($) 242Labor ($) 253Equipment ($) 24Total ($) 519

Concrete (cy) 5707Material ($) 1,381,094Labor ($) 1,443,871Equipment ($) 136,968Total ($) 2,961,933Incl. O&P ($) 3,909,752Duration (weeks) 38

Flat PlateLocation MontereyCrew (3) C-17BDaily Output (cy) 30Labor Hours (cy) 8.2Material ($) 475Labor ($) 945Equipment ($) 31Total ($) 1451

Concrete (cy) 7228Material ($) 3,433,300Labor ($) 6,830,460Equipment ($) 224,068Total ($) 10,487,828Incl. O&P ($) 13,319,542Duration (weeks) 48

Post Tension (x3.0)Location MontereyCrew (2) C-17BDaily Output (cy) 20Labor Hours (cy) 8.2Material ($) 475Labor ($) 630Equipment ($) 31Total ($) 1136

Concrete (cy) 7228Material ($) 3,433,300Labor ($) 4,553,640Equipment ($) 224,068Total ($) 8,211,008Incl. O&P ($) 10,427,980Duration (weeks) 72

Post Tension (x2.0)

Page 39: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

IntroductionExisting Structure

Floor SystemLateral System

Structural RedesignFloor SystemLateral System

Architectural RedesignCost AnalysisConclusions/Recommendations

OUTLINE JW MarriottGreg Kochalski

Page 40: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

Non-linear response•Plastic hinging mechanism in beams•Shear walls well below yield, system deforms evenly

Conclusions and JW MarriottGreg Kochalski

Floor System•Post Tension system viable alternative•Costs of PT are staggering, use original flat plate system

Architecture•Atrium remains focal point•Original spaces accounted for

Recommendations

Page 41: Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System

JW MarriottGreg Kochalski

Acknowledgements

Questions?

Bert CrandellPete JacksonErika JohnsonDr. LepageMom and Dad And Everyone Else that Made Thesis a Reality

Ben KochalskiJeff StylesDr. BoothbyAll AE FacultyMy Friends