International Meeting on Very Large Power Systems State Grid of China Beijing, China October 25-25,...
-
Upload
joy-obrien -
Category
Documents
-
view
214 -
download
0
Transcript of International Meeting on Very Large Power Systems State Grid of China Beijing, China October 25-25,...
International Meeting onVery Large Power Systems
State Grid of China
Beijing, China
October 25-25, 2005
Presentation
Brazilian National InterconnectedPower System Operation
Luiz Eduardo BarataOperational Director
ONS – Operador Nacional do Sistema Elétrico – Brazilian ISO
2
Operating Environment:
The Brazilian National Interconnected Power
System – SIN Characteristics
3
Production & Market Data – 2004 – National Integrated Power System - SIN
Integrated Operation by the Independent System Operator Introduces 25 % of Synergic Gains
Isolated Systems 2% of the Brazilian
Market
2002 2004 2008
Installed capacity – MW 74,670 79,579 93,546
Hydro 63,834 66,429 75,315
Thermal-conventional 8,829 11,143 13,301
Nuclear 2,007 2,007 2,007
Renewable (Proinfa) 3,270
Max, Demand – MW 50,759 58,816 72,788
Production – TWh 347,5 384,1 468,7
TLs ≥ 230 kV – km 72,506 80,022 90,347
No. of circuits 614 693 775
No. of substations 303 321 351
Transformer capacity (GVA) 166 178 195
Customers – millions 47 52
Annual Revenue - US$/bi 19,3 24,2
4
SIN Relative size
Brazilian Transmission system x European
1 cm + 260 km365.9 468.2 248.0 376.0 319.7-
100
200
300
400
500
600
Brazil France Spain UK Italy
TW
h
Production (TWh) – 2003
5
Main Transmission Grid Role
The Main Grid in the SIN, due to the hydroelectricity predominance and power plant locations far from load centers, besides the power transport role:
Is the main vector of system economical optimization:
Allows for hydrothermal optimal dispatch and optimal use of reservoir storage, by exploring basin hydrological complementarities - adding synergic gains – more than 20% of the system's assured energy
Helps postpone important generation expansion investments
The Main Grid can be seen as:
A virtual power plant located at the border of power import regions
2004-2006 Configuration
LegendExistent Future Complex
3,45
0 km
2,780 km
Isolated Systems2% of Brazilian
market
6
Subsystems Integration in Brazil – Evolution of Imports Capacity and Energy Demand by Subsystem
(1) Itaipu as a Southeast/Midwest subsystem power plant
NorthNortheast
Southeast / Midwest
South
(1) Itaipu Binational
Integration leads toenhanced system security
Integration also leads toenhanced supply security
7
The National Interconnected System
Operator – ONS
8
What ONS does – Attributions and Macro Functions
National Interconnected
System – SIN Operations
Planning and Scheduling
Real Time Operations
Transmission Services
Administration
Operations planning and scheduling and optimal centralized generation dispatch
Supervision and coordination of utilities system operations centers
Operations supervision and control of the national power systems and international interconnections
Contracting and administration of transmission services, grid access and ancillary services
Proposition to MME of main grid installations upgrading and reinforcements
Definition of main grid operations rules
Issuing of actual dispatch performance statistics, for ANEEL auditing
Macro functio
ns
Macro functio
ns
Tight Pool operation
Transmission system owned by utilities
Attributio
ns
Attributio
ns
9
ONS activities chain
Grid procedures Operations rules
Proposes of Main Grid
upgrading & Reinforcements
(*)
Planning
Generation Operations Planning
Operation
Transmission Services
Accounting and Settling
Inputs from utilities
products
Pre-operation
Real time operation
utilities consumers
Electrical Operations Planning
Post-operation analysis
3 years ahead
Under demand Up to 5 years
ahead
Monthly, weekly and daily
During the day / real time
(*) Mandatory after ANEEL approval
Access andConnection
to grid
Operation Scheduling
10
ONS Control Centers Location and Hierarchy
ONS presently has 1 National
Control Center – CNOS, 4 Regional
Control Centers, 1 for each of SIN’s
subsystems, and 4 Local Control
Centers
ONS is responsible for:
systems operations of Main Grid
and centralized dispatched power
plants (> 30MW), while Utilities are
responsible by installations
operations;
Management of power grid above
230 KV
Recife
Brasília
Rio de Janeiro
Florianópolis
11
SIN Reliability:
ONS Experience
Permanent concern with all time frames
Expansion planning, Operation planning, Operation scheduling, Real Time operation, Post operation
Centralized Transmission Planning adjustments
Grid Procedures – Processes, Rules and Standards
- Requirements for substations arrangements & protection
- Requirements for generating units characteristics and controls
- Requirements, rules and procedures for new accessing Agents to the Main Grid
- Performance standards
Reliability – ONS Experience
13
Improvement of intrinsic characteristics of the existing substations, by means of refurbishing bus configurations, transpositions of circuits and other measures aimed at reducing the impact of large disturbances (11 Main Grid substations refurbished in the period 2000-2003);
Strategic installations identification related to system performance (84 out of 398 substations);
Constant upgrade of installations Control & Protection; Upgrading of system controls (around 250 special
protection systems and 4 regional interconnections out-of-step relays);
Yearly revision of controllers settings in the Brazilian major power plants (80 power plants);
Emergency dispatch evaluation; Implementation of observability and controlability
capacities
Reliability – ONS Experience
14
More extensive use of special protection systems (SPS) is relevant as demonstrated by experience
209 229 268 288
0
100
200
300
2002 2003 2004 2005(By september)
Nº
of
SP
S
Evolution of SPS in the SIN Period of 2005/2006
Revisions 21
Already implanted - 2005
Example: 440 kV double circuit loss
20
Being implanted 22
In planning and conception phase
88
Blackout avoided: 1 - 06/14/05 Nine 765 kV towers down at
Itaipu;2 - 08/11/05 Isolation of Tucuruí Hydro
Plant from SIN.
- Importance of participation: T, D and G Agents;
- ANEEL meeting – Set/05 to improve Resolution 158.
15
SIN Safety Status
1. Measures designed to minimize the probability of the occurrence of large disturbances.
Such measures must be effective in reducing the severity of events.
2. Measures designed to minimize the propagation of unavoidable disturbances.
Such measures must be effective in restricting the immediate spatial and temporal effects of the events.
3. Measures designed to minimize load restoration times.
These measures must be effective in reducing the load restoration times to the limits considered acceptable from the consumers point of view.
Based on three pillars
Brazilian Defense PlanPreventive Grid Corrective Actions
Disturbance AnalysisReproduction of disturbances through digital toolsIdentification of corrective measures and preventive actions
Follow-up of recommendations implementation Statistical analysis and protection performance
evaluation systems
Indices - Some examples:- Number of disturbances;- Geographical extension;- System robustness degree;- Non-supplied energy;- Severity (system, minute);- Average and total restoration times.
Analysis of events with no load-loss
Operating SecurityPost Operation Actions
By set of disturbances (aggregated time analysis)
By disturbance (individual analysis)
Control Centers Instrumentation and Personnel Training
The main efforts of ONS are focusing on:
Improving measurement system, in a joint Utilities-ONS project
Implement in ONS control centers a tool to dynamically assess system security and indicate corrective actions
Permanent system operators training on use of control room available support tools (and improvements)
Implementation of system operators training simulator tool
Effective restoration time in 1999 and 2002 blackouts
Indices – Some Examples
Power Quality / Continuity:
Average freq. & duration of SIN outages
System robustness degree (SRD) – Percentage of disturbances in the Main Grid with no load shedding related to the total number of disturbances:
Indices – Some Examples
YearSRD
200060%
200385%
200488,6%
Frequency (times/year): 1.6 (2000) to 1.4 (2003)Duration (hours/year): 2.8 (2000) to 2.2 (2003)
Frequency 2004 (times/year): 1.03Duration 2004 (hours/year): 2,04
21
Main Challenges
Define criteria to technical-economical optimal level of system security / reliability
Improve criteria to balance system electrical security and economically optimal generation dispatch
Evaluate adequacy of present risk of supply value of 5% to be used in system expansion planning
Policy and Regulations
Power Industry and Consumers
Regulations ISO Regulatory framework
Ensure system optimal dispatch considering commercial interests of each utility
Acceptance by utilities of disturbance analysis conclusions/recommendations
For key substations – to assure system reliability, how to manage the legitimate utility proposal by fully automated (unmanned) systems
During system post-disturbances recovery, how to manage the utilities operator’s reactions to non-explicitly defined situations cited in operations instructions
Manage the balance between environmental requirements and power system operation
Operations Environment
Operator and Utilities
Difficulties of utilities (time table and investment) to upgrade or reinforce older installations
Definition of load shedding schemes
Ensure system optimal operation face to increasing environmental restrictions
Ensure same reliability level for all system areas
Ensure a reliable measurement system
Ensure reliable protection systems
Ensure the use of adequate new technologies regarding system models, system applications and simulators
Ensure the use of new technologies to provide system operations flexibility and controllability regarding to power system equipment, protection and control, measurement and communications systems
Technical / Operational