The EIC Contractor‘s Guides
EIC Contractor‘s Guides on the FIDIC „New Books“ were produced between 2000 and 2003
and the EIC Guide on the DBO Contract in 2009. The EIC Guide on the “MDB Harmonised
Construction Contract” was published in April 2011.
March 2000March 2000 March 2002March 2002 March 2003March 2003 MayMay 200 20099
22 Wednesday 19 April 2023 MDB Harmonized Contract Conference 2012
April April 20112011
The EIC Contractor‘s Guides
International Construction Law Review, October 2011 (Introduction)
They [the EIC Contractor’s Guides] are valuable as they are the product of a responsible
and reputable international organisation. They also through a light on the approaches to
be adopted in drafting international construction contracts... As in the past,
EIC’s comments are balanced. They indicate what it regards as improvements and what
it believes to be retrogressions.
33 Wednesday 19 April 2023 MDB Harmonized Contract Conference 2012
Wednesday 19 April 2023
EIC acknowledges that there are no more deviations betweenFIDIC MDB 2010 and the World Bank’s GCC March 2012
44 MDB Harmonized Contract Conference 2012
New provisions / titles in the FIDIC MDB Edition
55 Wednesday 19 April 2023 MDB Harmonized Contract Conference 2012
Improvements on FIDIC 1999 Editions
The MDB Harmonised Construction Contract accommodates
some comments of the EIC Contractor’s Guides, such as
Rate of profit is pegged at 5% of the Cost
Both parties are required to keep the contract details
confidential
Obtaining building permit is responsibility of the Employer
28-days notification period applies also to Employer’s Claims
Time limit for Engineer’s determination is 28 days
Employer shall provide the necessary special or temporary rights-
of-way
Introduction of „pay-when-paid“ clause re. Nominated Subcontractor
66 MDB Harmonized Contract Conference 2012Wednesday 19 April 2023
Improvements on FIDIC 1999 Editions
The MDB Harmonised Construction Contract accommodates
some comments of the EIC Contractor’s Guides, such as
Ownership of Plant & Material has been revised
Commencement of the Works only upon fulfilment of
certain conditions precedent
Additional right to refuse a Variation (“economic imbalance”)
Repayment deduction does not commence until 30% of the
Accepted Contract Amount less Provisional Sums has been certified
DAB can be activated if the Engineer fails to respond within
deadline
77 MDB Harmonized Contract Conference 2012Wednesday 19 April 2023
EIC criticism towards FIDIC 2010 MDB Harmonised Contract
The MDB Harmonised Construction Contract has also
introduced some problematic concepts with regard to:
Role of the Engineer
Employer has now an unilateral right to change authority of
and to replace the Engineer
No authority to agree or determine extension of time
Limited authority to instruct a Variation
No authority to approve a Variation submitted by Contractor
No authority to specify the amount payable in each of the applicable
currencies
Whilst these provisions are understandable from the Employer’s
perspective, these limitations can lead to difficulties in practice
8Wednesday 19 April 20238 MDB Harmonized Contract Conference 2012
EIC criticism towards FIDIC 2010 MDB Harmonised Contract
The MDB Harmonised Construction Contract has also
introduced some problematic concepts with regard to:
Performance Security
Employer has now a discretionary right to make a claim
Corrupt and Fraudulent Practices
Employer has now an unilateral right to terminate the
Contract
Limitation of Liability
is watered down compared to the FIDIC 1999 forms and includes now a
reference to Sub-Clause 15.4 [Payment after Termination]
International Arbitration
The arbitration clause distinguishes between “foreign contractors”
(international arbitration applies) and “domestic contractors“
9Wednesday 19 April 20239 MDB Harmonized Contract Conference 2012
Conclusion: A positive outlook
EIC welcomes the various technical improvements introduced by FIDIC and
the MDBs which make the FIDIC 2010 MDB Harmonised Contract Edition a
more balanced contract than the two precursors in 2005 and 2006
Users should, however, be very conscious that MDB Sub-Clauses 3.1, 3.4,
4.2, 17.6 and 20.6 (and the new Sub-Clause 15.6) deviate significantly from
the FIDIC 1999 “Red Book” standard and may represent an opportunity
for abusive behaviour towards the Contractor
EIC is prepared to join forces with FIDIC and EFCA in order to make the
2010 version a truly “harmonised” FIDIC MDB Edition which is also used
by the European Commission and other European bilateral donor agencies
1010 MDB Harmonized Contract Conference 2012Wednesday 19 April 2023
EIC Contact
Address: EIC SecretariatKurfuerstenstrasse 129, D - 10785 Berlin, Germany
Phone: ++49 (0)30 /21286-244
Fax: ++49 (0)30 /21286-285
E-mail: [email protected]
Internet: www.eicontractors.de
11Wednesday 19 April 202311 MDB Harmonized Contract Conference 2012
International Federation of Consulting Engineers
President Geoff French, UK
Vice-President Pablo Bueno, Spain
Secretariat FIDICWorld Trade Center 2Geneva AirportBox 311 CH-1215 Geneva 15 Switzerland Tel: +41 22 799 49 00Fax: +41 22 799 49 01
[email protected] www.fidic.org
Managing Director Enrico Vink