MCE Deepwater Development 2016 PAU, FRANCE • 5-7 APRIL 2016 Intelligent Completions Improves Economics of Brazilian Pre-Salt Development Desiderio Rodrigues Co-Authors: Minassa L., Costa L., Silva R., Bonfim A. © 2016 Halliburton. All Rights Reserved.

Transcript of Intelligent Completions Improves Economics of Brazilian ...mcedd.com/wp-content/uploads/01_Desiderio...

MCE Deepwater Development 2016

PAU, FRANCE • 5-7 APRIL 2016

Intelligent Completions Improves Economics of Brazilian Pre-Salt Development

Desiderio Rodrigues Co-Authors: Minassa L., Costa L., Silva R., Bonfim A.

© 2016 Halliburton. All Rights Reserved.

MCE Deepwater Development 2016

Remote monitoring and control

throughout the life of the field with

no mechanical intervention.

• Optimization

• Production / injection

• Reservoir management

Intelligent Completion

MCE Deepwater Development 2016

Using Intelligent Completions to improve economics…

• Reduce Asset life CAPEX & OPEX

• Mitigate reservoir uncertainty

• Manage water/gas distribution

• Accelerate production

• Increase recovery

Source: http://www.catholiclane.com/falling-oil-prices-and-the-future-of-the-world-economy/

MCE Deepwater Development 2016

Source: IPTC-18521-MS

Pre-Salt Uncertainties • Complex behavior • High flow rates • Variable GOR • High CO2 and H2S • Flow assurance

Mitigation Plan • High material grade (SDSS or higher) • Early plan for Intelligent Completions • Standard well designs (3 designs) • Large volume contracts • Very informed user To

tal P

rodu

ctio

n in

mill

ions

of b

oe/d

Brazil’s Production

Pre-Salt Production

Post-Salt Production

Brazil’s Oil Output Track

MCE Deepwater Development 2016

Top Producing Fields

0

5

10

15

20

25

30

35

40

HAL IC#1 STD HAL IC#2 Other IC STD HAL IC#3 HAL STD HAL IC#4 HAL IC#5 HAL IC#6 Other IC HAL IC#7 HAL IC#8 HAL IC#9 HAL IC#10

Top Producing Wells In Brazil by Q4/15 ( ANP)

MCE Deepwater Development 2016

Notable Results

MCE Deepwater Development 2016

Source: OTC 174725-MS

Strategy for Pre-Salt

MCE Deepwater Development 2016

Expertise Develop local talents

Leverage global experience

Intensive training

Customized Fit-for-purpose

Proven design

Robust qualification

Predictable Modelling Repeatable Competency

Disciplined Design of service MOC Contingency

Reliable Long Term Contingency Pro-active corrections

MCE Deepwater Development 2016

HighLights Good Track Records (80%

of total IC installed)

Zero Equipment failures

95% Local personnel

Focus on Service Quality (API Q2) 99.8% Efficiency

Lowlights Barriers for new

technologies

Restrictions to different well designs

No leverage on performance

restricted ability to overcome new challenges

MCE Deepwater Development 2016

• Closed loop digital oilfield solution • Single well control system (All electric or hydrid?) • Higher density of sensing technologies

• Array sensing • Pushing P&T into reservoir • Downhole multiphase flow meter

• Advanced well design • Autonomous ICDs • Disconnect system • Open-hole Completions • Higher density of zones (3+ zones in DW) • Remotely actuated devices (wireless)

Trends

MCE Deepwater Development 2016

Conclusion

Intelligent Completion technology improved economics of Brazilian pre-salt:

• CAPEX reduction through optimized design and reduced installation time

• Small diference in installation time compared to conventional designs

• Acelerated production with high productive wells

• Highly reliable equipment and installation services

• Early to prove expected benefits for improved oil recovery

• Dificult to implement change in the standard designs

MCE Deepwater Development 2016

Acknowledgments

The author thanks Halliburton for permission to publish this study.