One-Axis Trackers -- Improved Reliability, Durability, Performance ...
Integration of First Principles and Empirical Modeling Technologies for Improved Plant Reliability...
Transcript of Integration of First Principles and Empirical Modeling Technologies for Improved Plant Reliability...
1 EtaPRO™, EPReporter™, EPTrendSetter™, EPAlert™, and Virtual Plant™ are trademarks of GP Strategies.
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
INTEGRATION OF FIRST PRINCIPLES AND EMPIRICAL
MODELING TECHNOLOGIES FOR IMPROVED PLANT
RELIABILITY AND EFFICIENCY
Dr. Jeff Parmar
International Operations Director
GP Strategies
UK
Dr. Elmer Hansen
Principle Engineer
GP Strategies
USA
Mr. Ron Griebenow
Director, Energy Services
GP Strategies
USA
ABSTRACT
As power generating companies seek to improve
plant reliability, maintain efficiency, and increase
outage intervals, many are turning to on-line
performance and condition monitoring to augment
traditional high-low control system alarms. Such
monitoring systems employ advanced modeling
techniques for automated early detection of incipient
problems and are an essential element in an effective
asset management program. Early warning provides a
reduction in repair costs, an increase in equipment
run times, reduction in fuel costs, reduction in
replacement power cost and economical use of
planned or unplanned outages.
Traditional first principles models provide the ability
to detect of abnormal behavior based on engineering
relationships related to heat transfer, conservation of
mass and energy, and fluid dynamics. Empirical
models use historical data to accomplish the same
goal on equipment where a first principles model is
unavailable or overly complex, (turbine shaft, fan
bearings, damper settings, etc.). This paper describes
a new method which uses hybrid equipment models
based on both empirical and first principles
techniques. Such hybrid models incorporate elements
unique to each method to provide comprehensive
monitoring of all plant equipment.
The on-line monitoring system to be discussed uses
hybrid physical-empirical models to detect
abnormalities and alert plant personnel. Asset
managers use the refined detection information from
models to oversee the six major plant concerns of
reliability, efficiency, environmental, chemistry,
fouling, and cycle leakage. Numerous case studies
demonstrating the results of the hybrid models at a
coal-fired power plant are included.
INTRODUCTION
As power generating companies seek to improve
plant reliability, maintain efficiency and increase
outage intervals, they are turning to on-line
monitoring to assist in this task. On-line monitoring
has greatly enhanced the traditional high-low control
system alarms. Automatic early detection of incipient
problems is now an essential tool in the hands of
asset managers. It alerts managers to sensors in
equipment that have moved outside of the normal
operating ranges so that they can make good timely
decisions as shown in Figure 1.
Figure 1 Management tool to turn Data into
Decisions
Companies have successfully used first principle-
based performance monitoring systems to track
parameters such as boiler efficiency, turbine cycle
heat rate, condenser pressure as shown in Figure 2,
2
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
and steam turbine efficiency, as well as overall plant
heat rate. General Physics’ EtaPRO™ and
VirtualPlant™ technologies utilize first principle
engineering relationships such as heat transfer,
thermodynamics, and fluid dynamics to quantify
degradation and need for overhaul. These same
companies have also successfully used empirically
based condition monitoring systems such as EtaPRO
APR™ (Advanced Pattern Recognition) to detect
anomalies associated with rotating equipment bearing
behavior, Figure 3.
Figure 2 First Principle calculation of condenser
pressure
Figure 3 Empirical calculation of vibration
The behavior of bearings, shafts, damper positions,
etc. is currently beyond the reach of first principle
models. VirtualPlant™ and EtaPRO APR™ are two
very different modeling methods that have one thing
in common: they both provide the user with an
expected value that can be compared with the actual
value. EtaPRO APR uses normal historical data as
the basis of the empirical model. Localized modeling
is used to provide the expected values of model
points. The APR algorithm selects historical time
slices that are near the current time slice and uses a
weighted average of these to predict the expected
values. Figure 4 is a comparison of these two
modeling technologies:
Figure 4 Hybrid Modeling using first principle
and empirical modeling
The goal of the hybrid models is to monitor the six
major areas of plant concerns: reliability,
environmental, chemistry, efficiency, fouling, and
cycle leakage, (field examples in each of these
categories are discussed further on in this paper).
Data for the plant assets are compared to the various
asset models and abnormalities are brought to the
attention of asset managers for timely decisions, as
shown in Figure 5.
Figure 5 APR Process - Data, Model, Concerns,
Reporting
Equipment behavior is shown to be abnormal when
the actual measured value moves away from the
historical (or expected) value of the model. In Figure
6 the IB (inboard) motor bearing temperatures are
well correlated with the motor stator temperature.
However, the OB (outboard) bearing temperature has
some points that are outside of the normal range of
operation. These are abnormal.
3
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 6 Normal and abnormal reference data
The automatic early detection of both performance
and integrity issues gives the operator or analyst the
ability to concentrate on solving problems rather than
searching for a potential problem. Performance and
integrity calculations are brought together in hybrid
asset models. These models allow the user great
flexibility in that actual values can come from sensor
measurements or calculations and real-time expected
values can come from an APR model, a Virtual Plant
model, or an EtaPRO Point ID.
Source of Actual Value
Sensor Measurement
EtaPRO calculation
Manually input value
Source of Expected Value
APR model
EtaPRO calculation
Virtual Plant model
For example actual and expected values pairs might
be:
Actual Value Source Expected Value Source
Measured HP turbine
exhaust pressure
HP turbine exhaust pressure
calculated from VirtualPlant™
Measured HP Turbine
exhaust pressure
HP turbine exhaust Pressure
from EtaPRO APR™
Main steam temperature Expected Main steam
temperature from EtaPRO
APR
Calculated HP turbine
efficiency
HP turbine design efficiency
calculated in EtaPRO
Calculated HP turbine
efficiency
HP turbine efficiency from
EtaPRO APR
PRESENTING RESULTS
Having the right combination of modeling techniques
to accurately predict expected behavior forms the
foundation of effective monitoring for anomalies.
Equally important is the ability to display, organize,
and manage such anomalies as they occur. The
EtaPRO Concerns Viewer shown in Figure 7 is one
such implementation. Each row represents a
measured or calculated point along with its
corresponding model attributes (expected value,
normal operating range and deviation). The red and
blue bars show the time and direction of the anomaly,
(red is high and blue is low). Pre-defined trends are
available for every modeled parameter and can be
displayed beneath any selected point row.
Figure 7 Concerns Viewer
When enlarged, the trend displays a yellow line as
the actual value along with a light blue line
representing the predicted value on a gray zone of the
normal range of operation and a purple line showing
the deviation plotted at the bottom. A concern is
triggered when the actual value is outside the gray
zone for a user-specified period of time, with the
concern marked with a red cross, as shown in Figure
8.
The early warning presented through the EtaPRO
Concerns Viewer can help produce a reduction in
repair costs, a life extension of equipment, a
reduction in fuel costs, a reduction in replacement
power cost and a reduction in EFOR (Equivalent
Forced Outage Rate) through the use of planned or
unplanned outages.
Concerns typically fall into these six major areas:
reliability, environmental, chemistry, efficiency,
fouling, and cycle leakage.
4
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 8 Region of normal operation and
indication of abnormality
These are not exclusive categories but have overlap
and interaction. The following sections provide
specific examples of applying hybrid models to a
working coal-fired generating plant.
RELIABILITY
Ash Pump Thrust Bearing. Reliability is important
to rotating equipment. The first example, Figure 9,
shows the heating of an ash pump thrust bearing. The
source of the problem was found to be a lack of
cooling water. The auxiliary cooling water was shut
down to replace a line to the PA fans but the cooling
water was not correctly swapped on this pump. Had
the screen below been available to operations, as it
now is, the pump situation would have been corrected
without turning the pump off.
Figure 9 Abnormal bearing temperature
Service Air Compressor. This air compressor has
been shutdown to replace a motor bearing which the
station staff believe is causing the high bull gear
vibration seen in Figure 10. Since there are three air
compressors, this one can be taken out of service and
repaired at the plant’s convenience. Having early
warning of the change in vibration, allows the
compressor to be repaired before the problem
becomes more costly.
Figure 10 High bearing vibration
ENVIRONMENTAL
Boiler Air Damper Maintenance. Correct boiler
combustion is essential to maintaining proper
emission levels. Correctly functioning boiler dampers
deliver the desired amount of air and fuel to maintain
correct boiler combustion. Boiler dampers can fail by
sticking in one position and by dragging behind the
command signal. The Boiler damper model uses the
damper position as the actual value and the damper
demand as the expected value (an EtaPRO point).
When the two values are different for a sufficient
time, a concern is triggered. As seen in Figure 11,
the first damper is stuck in one position as the
demand tries to move it. The second damper shows a
damper that drags behind the demand. It responds but
not all the way.
Figure 11 Abnormal boiler damper operation
Four months of keeping up with damper repairs have
almost all the dampers operating properly. The blue
and red bars indicate the times when the damper was
in concern. The time period of the bar chart is from 1
February to 6 May 2011. By looking at the bars one
can see the progress that has been made, as depicted
in Figure 12.
5
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 12 Increase in correct boiler damper
operation
CHEMISTRY
Boiler chemistry can also be monitored as shown in
Figure 13 to obtain two benefits. First, bad readings
from instruments can be quickly detected and repairs
made. Second, on-line instruments give quicker
indication of abnormal chemistry than do daily
samples. This allows operations to take immediate
corrective action to mitigate damage.
Figure 13 Boiler Chemistry
EFFICIENCY
High Energy Drain to Condenser. The condenser
pressure as seen in Figure 14, suddenly increased.
The problem was found to be that the cold reheat
drain to condenser opened up because of a bad level
switch. The level switch is isolated and will be fixed
on the upcoming outage. If the plant had temperature
sensors on the drain lines before the drain valve that
would have provided an additional indication of the
source of the problem. Lacking such instrumentation
the condenser must be walked down to find the
source of the problem.
This condenser pressure rise was also confirmed
using hotwell related temperature sensors, as shown
in Figure 15.
Figure 14 High condenser pressure
Figure 15 Confirming hotwell temperatures
Condenser Air In-leakage. The second condenser
example (Figure 16) looks very similar to the first
but had a different root cause. Some drains were
leaking into the condenser and a rupture diaphragm
and other minor areas were leaking air into the
condenser. They have been temporarily fixed and
will be repaired during outage. The condenser
diagnostics module pointed to the air inflow problem.
The cost of the high condenser pressure in the first
example was calculated using the integral over time
of the data shown in Figure 17 below with the
accumulated cost between 8 to 12 March 2011 of US
$67,000. This is exacerbated by low hot reheat temps.
Reheat Temperature Control Problem at Low
Loads. A third efficiency related item deals with low
hot reheat temperature and hot reheat spray seen in
Figure 18. Each item itself causes a heat rate penalty.
6
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 16 High condenser pressure
Figure 17 Cost of high condenser pressure
They should not occur together but in this case they
do. The model uses an EtaPRO calculation to provide
the expected values of spray and hot reheat
temperature. At very low loads hot reheat
temperature becomes difficult to maintain. During the
same time, reheat sprays are active and which should
not be needed. This only increases the loss.
Based on the cost of being off target shown in Figure
18, the loss due to low hot reheat and reheat sprays is
US $886 per day (Figure 19).
High Pressure Feedwater Heater Tube Leak. The
fourth example looks at a leak in a high pressure final
feedwater heater. The leak started on 16 January
2011. A jump is seen in heater 7 valve demand and
heater 6 valve demands (Figure 20).
When the valve demand is converted to a flow, the
jump in demand represents a flow of about 30 klb/hr
(11 Tonnes/hr). This corresponds well to the sonic
flow at saturation conditions for one open tube. There
is a second jump on 18 January 2011 of the same
magnitude indicating a second tube has opened. The
additional flow drove the heater 6 drain valve fully
open and began to open the emergency drain valve.
There are corresponding increases in heater levels for
both heaters. Finding a leak early and isolating the
heater can reduce the collateral damage and extend
the life of the heater. This heater has been in service
34 years and has 27 of 1,010 tubes plugged.
Figure 18 Excessive reheat spray
Figure 19 Cost of RH sprays and low RH
temperature
The heater isolation valves are leaking so that the
heater cannot be totally isolated. The heater will
remain out of service until a several day offline
outage is available to plug the tubes. The cost of
being out of service is about US $130 per hour or US
$3,120 per day as seen in Figure 21.
Condensate Pump Recirculation Valve. The next
two events deal with the recirculation valves of
pumps. Figure 22 shows strip charts for a condensate
pump which had the recirculation valve left in
manual. The valve was closed and the system
returned to normal. In his case there was no point to
indicate the percent open of recirculation valve.
7
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 20 Feed water heater tube leak
Figure 21 Cost of heater 7 (top heater) out of
service
Boiler Feed Pump Recirculation Valve. The boiler
feed pump recirculation valve of the same unit had to
be controlled manually because of a failure in
maintaining the desiccant in an instrument air dryer
at a regular interval; which contaminated the air
system with (now) powered desiccant. Figure 23
shows that the recirculation valve was open when it
should have been closed.
This valve had to be controlled locally in the field
during load drops. In this case it was not closed after
the load had increased which went unnoticed by the
operators until the speed controls on the feed pump
maxed out bringing an alarm to the DCS. This valve
will be changed out during upcoming outage as well
as purging the remaining desiccant out of the
instrument air system.
FOULING
One area of fouling that requires constant attention is
motor filters. These filters get dirty regularly in a
coal-fired power plant and are very dependent upon
local condition such as field and construction dust for
outside motors and coal dust for inside motors.
Figure 24 shows the development of a dirty filter.
Figure 22 Recirculation valve left in manual
Figure 23 Recirculation valve in manual
On the afternoon of the 4th, a concern is triggered in
the heat of the afternoon. On the afternoon of the 6th,
the temperature is much higher. The expected values
drop down; because the model is set to remove
sensors from actively contributing to the model once
the measured values are too far from the expected.
The value of catching a filter change early is that it
keeps the motor cooler and gives extra time to change
the filter before reaching an alarm or shut down
point. In this case, motor filter change out is based on
actual condition, not time or personal perceptions.
LEAKAGE
The air heater X-ratio calculated in an EtaPRO point
(Figure 25) is used to look at boiler and boiler
ducting air in leakage. At this time there has not been
a change in the X-ratio. Cycle make-up flow is also
calculated by an EtaPRO derivative of the make-up
tank level. It will be used in the detection of a boiler
tube leak.
8
POWER-GEN MIDDLE EAST 2012 February 6-8, 2012 Doha, Qatar
Figure 24 Development of a dirty motor air filter
Figure 25 X-Ratio monitoring to detect excess air
in leakage
SENSOR PROBLEMS
The type of problem encountered most frequently is a
sensor that gives a reading within the normal range of
operation but is not correct. When a sensor fails to
read correctly it may fail near an ambient
temperature, it may read high or low, or it may be
erratic. The DCS and the historian often indicate that
the signal is good even though it is not. Hybrid
models have the ability to predict expected sensor
values taking into account design performance
(VirtualPlant) and past performance (EtaPRO APR).
These models consider changes in ambient
conditions, load, and equipment in service to better
estimate a sensor’s true value. This information aids
in instrument maintenance.
Regulator Control Problem. A hybrid model will
often confirm a sensor’s reliability even when it
appears to be faulty. Figure 26 shows an example of
an erratic sensor initially thought to be in error.
The erratic behavior, first thought to be a sensor
issue, turned out to be a regulator having difficulty
controlling the leak-off temp on the outboard bearing
of the boiler feed pump drive turbine. A bypass valve
opened up around the regulator making the issue
harder to identify.
Figure 26 Temperature abnormality
CONCLUSIONS
The hybrid models available in EtaPRO bring
together two tool sets that have up to this point
existed separately. The combination of first principle
and empirical models has been able to provide the
ability to monitor the entire range of power plant
equipment from thermal performance, operations and
maintenance perspectives. Presenting the results of
the hybrid models in a real-time environment with
appropriate display and concern management tools,
allows the operator or analyst the ability to monitor
performance and condition from the same screen. It
provides a way to quickly identify abnormal
equipment behavior and direct resources to resolve
the problem in addition to determining the resultant
financial impact. The system described has proven
highly effective at detecting abnormal plant and
equipment behavior and for targeting limited
manpower resources to specific problem areas.