INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are...
Transcript of INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are...
![Page 1: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/1.jpg)
Ponz-Tienda, J.L., Pellicer, E., Alarcón, L.F., Rojas-Quintero, J.S., 2015. Integrating Task
Fragmentation and Earned Value Method into the Last Planner System using Spreadsheets. In: Proc.
23rd Ann. Conf. of the Int’l. Group for Lean Construction. Perth, Australia, July 29-31, pp. 63-72,
available at www.iglc.net
PRODUCTION PLANNING AND CONTROL 63
INTEGRATING TASK FRAGMENTATION
AND EARNED VALUE METHOD INTO THE
LAST PLANNER SYSTEM USING
SPREADSHEETS
José L. Ponz-Tienda 1, Eugenio Pellicer 2, Luis F. Alarcón3, and Juan S. Rojas-
Quintero4
ABSTRACT
Construction schedulers make use of several tools as project management software of
general purpose and spreadsheets for applying the Last Planner System of Production
Control. This widespread practice has the disadvantage of working with questionable
algorithms and models difficult to adapt to the construction industry, besides having
to work with disconnected and complex information to manage data. In this paper a
new layout and computation of multidimensional non-cyclic directed graphs based on
its adjacency matrices is presented. All the precedence relationships are considered,
in addition to the optimal and discretionary fragmentation of task in real conditions
with work and feeding restrictions. This approach has been implemented with Visual
Basic for Excel. A new approach for the representation and computation of projects
for the Last Planner System of Production Control is presented. This approach is
integrated with the management of the Earned Value and ad-hoc complex
optimization. LPSTM, CPM, EVM and PPC are found to be complementary, and the
Zaderenko´s algorithm modified and implemented in Excel can be used to integrate
them.
KEYWORDS
Lean construction, Last Planner System, Construction Scheduling with spreadsheets.
INTRODUCTION
To improve the efficiency of the planning process of construction projects,
practitioners schedule through a hierarchy of three levels from low to high level of
detail. Ballard and Howell (1998) propose The Last Planner System of Production
1 Assistant Professor, Dep. of Civil and Environmental Engineering. Director of Construction
Engineering and Management, Universidad de Los Andes, Bogotá, Colombia, (57-1) 3324312,
[email protected] 2 Associate Professor, School of Civil Engineering, Universitat Politécnica de València, Valencia,
Spain, (34) 963879562, [email protected] 3 Professor, Dept. of Construction Engineering and Management, Universidad Católica de Chile,
Escuela de Ingeniería, Santiago, Chile, (56-2) 2354 4201, [email protected] 4 Instructor, Department of Civil and Environmental Engineering. Universidad de Los Andes,
Bogotá, Colombia, (57-1) 3324312, [email protected]
![Page 2: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/2.jpg)
José L. Ponz-Tienda , Eugenio Pellicer , Luis F. Alarcón, and Juan S. Rojas-Quintero
64 Proceedings IGLC-23, July 2015 |Perth, Australia
Control (LPS™) as a hierarchy of three levels from low to high level of detail: master
plan and phase planning (long term), look-ahead planning (medium term), and
commitment planning (short term). The long term planning is to obtain a general plan
establishing the strategic targets (phase planning) aimed to developing more detailed
work plans and identify all the work packages for the construction project, showing
the main activities, their duration and sequences indexed at the top level of the work
breakdown structure (WBS henceforth). In the middle term planning, the schedulers
develop actions in the present to produce a desired future, preparing, analysing, and
solving the conflicts and restrictions in a lower and more detailed level of the WBS.
In the short term planning or Weekly Work Planning (WWP), collaborative
agreement or commitment planning works at the lowest levels of the WBS making
things happen, bearing in mind the work that is being done now and that is made-
ready to be done (Koskela, Stratton and Koskenvesa, 2010).
Lean construction practitioners make use of custom spreadsheets and project
management software of general purpose, which implements a group of mathematical
algorithms known in a generic form as Critical Path Method (CPM henceforth).
These tools are fluently used by practitioners and implemented in the commercial
software designed to assist them in the scheduling process. However, many times
practitioners are not aware of the implications about using these algorithms or they do
not understand CPM software properly. Furthermore, even skilled technicians may
have problems interpreting the implementing criteria of CPM algorithms as well as its
relaxations (Wiest, 1981), not properly documented in the management commercial
packages even those of the highest quality. In addition, the results obtained on the
benchmarking tests indicates that not only they are hardly applicable or feasible in
realistic environments, but that they are not currently competitive with the best state-
of-the-art algorithms available in the literature (Mellentien and Trautmann, 2001;
Trautman and Baumnn, 2009). This widespread practice has the disadvantage of
working with questionable obsolete algorithms and models difficult to adapt to the
construction industry, besides having to work with disconnected and complex
information to manage data.
CPM has been widely criticized as inadequate to the task of controlling work in
projects (Koskela, et al., 2014), and Earned Value Management (EVM) for managing
task at the operational level, suggesting that LPSTM and Percentage of Promises
Completed (PPC) are more appropriate to manage works when it is applied to the
operation level (Kim and Ballard, 2010). LPSTM is a collaborative, commitment-
based planning system, and CPM is a class of operations research algorithms for
computing the times of the activities based on its precedence restrictions. PPC is the
measure of promises completed on time and EVM is a tool for production control by
a comparison between budgeted and scheduled with performed, obtaining different
measures to report the progress of the project in terms of cost, production and time
(Ponz-Tienda, Pellicer and Yepes, 2012). LPSTM, CPM, EVM and PPC are
complementary rather than competitive, and the inadequacy is on the fitness of the
implemented algorithms to the construction industry. Research is heading towards the
establishment of alternative project control accounting systems not subject to the
traditional limitations of EVM, such as unbalanced process flows and lack of
predictability (Kim and Ballard, 2000), mainly in terms of workflow and value
generation (Kim, Kim and Cho, 2015)
![Page 3: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/3.jpg)
INTEGRATING TASK FRAGMENTATION AND EARNED VALUE METHOD INTO THE LAST
PLANNER SYSTEM USING SPREADSHEETS
PRODUCTION PLANNING AND CONTROL 65
In this paper a new layout and computation of multidimensional non-cyclic
directed graphs based on its adjacency matrices is presented with a realistic approach
in construction production planning. All the precedence relationships are considered,
in addition to the optimal and discretionary fragmentation of task in real conditions
with time, work and feeding restrictions. This approach has been implemented with
Visual Basic for Excel in a complete and adaptable application for the LPSTM
integrated with the management of the EVM and ad-hoc complex optimization
models.
The reminder of this paper is structured as follows: Section 2 provides a literature
review of the Project Scheduling Problem with GPRs and feeding precedence
relationships. Section 3 details the proposed algorithms for multidimensional non-
cyclic directed graphs based on its adjacency matrices. In section 4, the proposal
implemented for spreadsheets is shown. Finally, conclusions are drawn.
LITERATURE REVIEW
Projects are usually represented as acyclic directed graph without cycles and circuits
in two ways, considering the activities on the arrows of the graphs know as Activity-
on-Arrow (AoA) (Kelley and Walker, 1959; Malcolm, et al., 1959), and considering
the activities on the nodes of the graph, know as Activity-on-Node (AoN). The AoN
model was introduced by Roy (1962 cited in Kerbosch and Schell, 1975) and later
improved with the well-known Precedence Diagramming Method (PDM) (IBM,
1968).
The PDM graphs considered the activities as non-splitting allowed and
contemplated four kinds of Generalized Precedence Relationships (GPRs): finish-to-
start (FS(zij)), start-to-start (SS(zij)), finish-to-finish (FF(zij)) and start-to-finish
(SF(zij)). The PDM graphs with GPRs present an anomalous effect, called reverse
criticality, that grates against one´s natural feelings about the consequences of
lengthening or shortening a job (Wiest, 1981), changing the concept of a critical path
itself. Crandall (1973) proposed the first splitting allowed algorithm that partially
avoids the reverse criticality. This algorithm considers that “disallowing the splitting
of activities was an excessive relaxation of the real problem”, presenting a heuristic
algorithm to compute the times and the minimum duration of the project.
The Crandall´s algorithm was improved by Moder, Philips and Davis (1983),
including the start-to-finish relationship. More recently, Valls, Martí and Lino (1996)
analyse the Crandall's algorithm, proposing a new computation and more realistic
treatment of the start-to-finish relationship. Other relaxed algorithm have been
proposed by Hajdu (1996), but it provides infeasible solutions to the problem in some
cases.
An important and not well-known feature of graphs, especially project graphs, is
that they can be represented by indexed matrices, based on its precedence
relationships and represented by adjacency matrices. This characteristic is regardless
of its nature, no matter if it is an AoA graph or an AoN graph.
The first algorithm to compute the times of the activities of a project based on its
matrix representation was proposed by Zaderenko (1968). The Zaderenko´s algorithm
only considered the finish-to-start relationships, computing the early start and finish
of the activities. The Zaderenko´s proposal was improved by Ponz-Tienda (2011),
proposing a new representation and computation of multidimensional non-cyclic
![Page 4: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/4.jpg)
José L. Ponz-Tienda , Eugenio Pellicer , Luis F. Alarcón, and Juan S. Rojas-Quintero
66 Proceedings IGLC-23, July 2015 |Perth, Australia
directed graphs based on its adjacency matrices considering all the GPRs for the non-
splitting allowed case and feeding precedence relationships.
INDEXING CRITERIA WITH SPREADSHEETS
The indexing criterion is based on the Zaderenko´s proposal, in which each aj,j
element of the adjacency matrix correspond to the lead/lag of the relationship
between an activity j and its predecessor ones (i) (Figure ).
Figure 1: Indexing criterion of the adjacency matrix
If the activities of the project are ordered in a topological way, then
, obtaining the simplified matrix shown in Figure .
Figure 2: Simplified adjacency matrix
And the algorithm for computing the times of the activities is shown in pseudo-code 1:
Table 1: Pseudo-code 1 Conceptual algorithm
Forward Pass Backward Pass
The previous algorithm can be improved including all the GPRs precedence
relationships applying a multidimensional adjacency matrix with two rows and
columns for each activity (Figure ).
Furthermore, can be included the different nature of relationships as work and
feeding precedence relationships applying equation 1, and the discretional
fragmentation of activities applying the criterion exposed in Figure and equation 2.
duration 1 2 … i … n
1 d 1 a 1,1 a 1,2 a 1,… a 1,i a 1,… a 1,n
2 d 2 a 2,1 a 2,2 a 2,… a 2,i a 2,… a 2,n
… d … a ...,1 a ...,2 a ...,… a ...,i a ...,… a ...,n
j d j a j,1 a j,2 a j,… a j,i a j,… a j,n
… d … a ...,1 a ...,2 a ...,… a ...,i a ...,… a ...,n
n d n a n,1 a n,2 a n,… a n,i a n,… a n,n
Acti
vit
ies
Predecesor activities
iji j a NULL
duration 1 2 … i … n
1 d 1
2 d 2 a 2,1
… d … a ...,1 a ...,2
j d j a j,1 a j,2 a j,…
… d … a ...,1 a ...,2 a ...,… a ...,i
n d n a n,1 a n,2 a n,… a n,i a n,…
Predecesor activities
Acti
vit
ies
1, , 1j n FOR ,1, 1i n FOR
1, 1, 1i j FOR iLF makespan
,( ) i ja NULLIF THEN 1, , 1j i n FOR
,max( , ( ))j j i i jES SS EF a ,( ) i ja NULLIF THEN
ENDIF ,min( , ( ))i i j i jLF LF LS a
j j jEF ES d ENDIF
max( , )jmakespan makespan EF i i iLS LF d
![Page 5: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/5.jpg)
INTEGRATING TASK FRAGMENTATION AND EARNED VALUE METHOD INTO THE LAST
PLANNER SYSTEM USING SPREADSHEETS
PRODUCTION PLANNING AND CONTROL 67
(1)
Figure 3: Multidimensional adjacency matrix
Figure 4: Splitting criterion of activities
(2)
And the algorithm for computing the times of the activities with feeding/work GPRs
is shown in Table 2: Pseudo-code 2 and Table 3: Pseudo-code 3:
Table 2: Pseudo-code 2 Forward pass algorithm with feeding/work GPRs
0 1 is a feeding relationship|
1 is a work relationship
ij
ij
ij
z aa z z NULL
z a
2·i-1 2·i
Start Finish
2·j-1 Start a 2·j-1,2·i-1 a 2·j-1,2·i
2·j Finish a 2·j,2·i-1 a 2·j,2·i
Activity
j
Activity i
Columns
Rows
βj
FFij (z)
FFij (z)
i1
i2
j
EFj
EFi1
EFi2
ESj
dj - βj
max ( ), ( ) , predecessor of j ij ij
FF z SF z i j
1, , 1j n FOR
;j jES SS
1, 1, 1i j FOR
2 1, 2 1 : 1 ;ij ij ij ij iSSLag a j i SSLag SSLag SSLag d IF THEN
2 1, 2 ;ijFSLag a j i
2 , 2 1 : 1 ;ij ij ij ij iSFLag a j i SFLag SFLag SFLag d IF THEN
2 , 2 : 1 ;ij ij ij ij jFFLag a j i FFLag FFLag FFLag d IF THEN
max , , ;j j ij ijFFlag SFlag
max , ;j j ij ij i i ij i ij ij
ijj j i ij
d SSlag k EF d SSlag ES k SSlagSSlag
ES ES ES k
IF THEN ELSE
max , :
max , ;
ij j j i ij
ij j j i ij
FSlag ES ES EF FSlag
FFlag EF EF EF FFlag
max , ;j j ij ij i i ij i ij ij
ijj j i ij
d SFlag k EF d SFlag ES k SFlagSFlag
EF EF ES k
IF THEN ELSE
max , ;j j j jEF EF ES d
;j j jj is not fragmentable ES EF d IF THEN
![Page 6: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/6.jpg)
José L. Ponz-Tienda , Eugenio Pellicer , Luis F. Alarcón, and Juan S. Rojas-Quintero
68 Proceedings IGLC-23, July 2015 |Perth, Australia
Table 3: Pseudo-code 3 Backward pass algorithm with feeding/work GPRs
IMPLEMENTATION IN AN HOLISTIC PULL SYSTEM
The previously exposed algorithms have been implemented in an Excel add-in that
can be downloaded from http://goo.gl/a7G3L3 (Figure ). This app includes the matrix
algorithm exposed in pseudo-code 1 called Matrix Pro, the pseudo-code 2 and
pseudo-code 3 for multidimensional adjacency matrices for GPRs called Matrix
GPRs, and a suite of utilities for managing called Matrix Commitments.
Figure 5: Senda Matrix Ribbon for Excel
The software completely supports the pull system of the LPSTM, including location
and responsibilities definition, making use of Excel’s features, especially the
unlimited possibilities of exchange of information between books and sheets (Figure
6).
Figure 6: LPSTM (Ballard, 2000) Pull System with Senda Matrix
For a better understanding of the pull process with Senda Matrix, a practical example
of application that supports the LPSTM has been included. The example of application
is the construction of a five floors building for classrooms and offices.
MASTER AND PHASE SCHEDULE
The main program has been scheduled with Matrix GPRs and contemplates seventeen
activities (Figure 7), each one with different continuity conditions and feeding and
work precedence relationships.
,1, 1i n FOR
1, , 1j i n FOR
min , : min , ;i i j ij i i j ijLS i LS LS k LF LF LS FSlag
min , : min , ;i i j ij i i i iLF LF LF FFlag LS LS LF d
;i i ii is not fragmentable LF LS d IF THEN
Weekly Work Plans
Master and Phase Schedule
Look ahead Schedule
Should
Can
Will
![Page 7: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/7.jpg)
INTEGRATING TASK FRAGMENTATION AND EARNED VALUE METHOD INTO THE LAST
PLANNER SYSTEM USING SPREADSHEETS
PRODUCTION PLANNING AND CONTROL 69
Figure 7: Main Program representation with Matrix GPRs
The Structure activity of the Main Program was analysed in depth with twenty
detailed activities, as a Phase Schedule. The structure phase was scheduled using
Matrix Pro (Figure ) in a different book, applying a dynamic link from the main
program. A RCPSP (Resource Constrained Project Scheduling Problem) optimization
model was applied considering an availability of five workers. An optimal makespan
for the structure of 135 days was obtained against the initial makespan of 166 days
(Figure ) (Ponz-Tienda, 2011; Ponz-Tienda, Pellicer and Yepes, 2012; Ponz-Tienda et
al, 2013).
Figure 8: Phase schedule representation, Responsibles and Zones with Matrix Pro
Figure 9:Optimization Model for the Phase Structure with Matrix Pro
All of Excel’s features can be used, even allowing to create different reports as
temporal diagrams or Line of Balance (LBM) charts (Figure ).
Figure 10: Main Program representation with temporal and LBM diagrams
LOOK AHEAD SCHEDULE AND WEEKLY WORK PLAN
To manage the pre-requisites, restrictions, look-ahead programs and weekly work
es ≤ S.S. ls ≤ ls + δ δ act 116
Walls A 0 0 0 44 0 135
Walls B 6 6 10 54 0 160
Install A 6 11 6 50 5 δ Proyecto 44
Install B 11 11 15 59 0
Floor 0A 9 16 9 53 7
Floor 0B 17 17 17 61 0 Sum Squares 2832
Prepare St 0 11 18 62 11 k 0.00001
Floor 1A 23 23 23 67 0 k · ∑ δ act 0.00125
Floor 1B 34 34 34 78 0 Objetive 2832.001
Floor 2A 45 45 45 89 0
Floor 2B 56 56 56 100 0
Floor 3A 67 67 67 111 0
Floor 3B 78 78 78 122 0
Floor 4A 89 89 89 133 0
Floor 4B 100 100 100 144 0
Stair 1 88 123 113 157 35
Stair 2 99 126 113 157 27
Stair 3 110 129 113 157 19
Stair Com 111 111 111 155 0
Ptret 111 132 111 155 21
125
Initial makespan
Actual makespan
Precribed makespan
0
1
2
3
4
5
6
7
8
9
1 6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
10
1
10
6
11
1
11
6
12
1
12
6
13
1
13
6
14
1
14
6
15
1
15
6
16
1
16
6
17
1
es ≤ S.S. ls ≤ ls + δ δ act 116
Walls A 0 0 0 44 0 135
Walls B 6 6 10 54 0 160
Install A 6 11 6 50 5 δ Proyecto 44
Install B 11 11 15 59 0
Floor 0A 9 16 9 53 7
Floor 0B 17 17 17 61 0 Sum Squares 2832
Prepare St 0 11 18 62 11 k 0.00001
Floor 1A 23 23 23 67 0 k · ∑ δ act 0.00125
Floor 1B 34 34 34 78 0 Objetive 2832.001
Floor 2A 45 45 45 89 0
Floor 2B 56 56 56 100 0
Floor 3A 67 67 67 111 0
Floor 3B 78 78 78 122 0
Floor 4A 89 89 89 133 0
Floor 4B 100 100 100 144 0
Stair 1 88 123 113 157 35
Stair 2 99 126 113 157 27
Stair 3 110 129 113 157 19
Stair Com 111 111 111 155 0
Ptret 111 132 111 155 21
125
Initial makespan
Actual makespan
Precribed makespan
0
1
2
3
4
5
6
7
8
9
1 6 11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
10
1
10
6
11
1
11
6
12
1
12
6
13
1
13
6
14
1
14
6
15
1
15
6
16
1
16
6
17
1
Dynamic Link to
Phase Schedule
(Figure )
![Page 8: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/8.jpg)
José L. Ponz-Tienda , Eugenio Pellicer , Luis F. Alarcón, and Juan S. Rojas-Quintero
70 Proceedings IGLC-23, July 2015 |Perth, Australia
plans, Matrix Commitments was used. For the look-ahead programs, temporal charts
of 5 weeks (4+1) was selected in the WWP sheet manager, and 2 weeks (1+1) for the
weekly work plans (Figure ).
Figure 11: Look Ahead Program with Matrix Commitments
MEASUREMENT, LEARNING AND CONTINUAL IMPROVEMENT
The control and continual improvement process is developed in two levels with
different goals: the schedule level and the commitments level (Figure 3).
The commitments level control with PPC measures helps the team to work on the
basis of learning the continual improvement process. The PPC index does not
measure production rates; it teaches the team to improve the production rates from
what was “effectively done” to what “can be done” from now into the future.
The schedule level control with the EVM, provides cost and schedule deviations
values on productivity and economic terms from what was “really done” of the
Weekly work plans.
Figure 3: Integrated EVM and PPC for continual improvement
Both methods work together efficiently to reduce variability and to make the work
more predictable, closing the total improvement process (Figure 4). From the “done”
to the “can be done”, up to the "should be done" in terms of production through the
continual learning process.
Figure 4: Cost Deviation, Schedule Deviation, PPC and Pareto Chart
Kim and Ballard (2000) found that EVM method’s validity is compromised in
account for “unbalanced process flows and lack of predictability”. Advances are
needed in order to validate and integrate new production control approaches in terms
of workflow and value generation, with current practices (Kim, Kim and Cho, 2015).
WWP
29
/04
/20
13
30
/04
/20
13
01
/05
/20
13
02
/05
/20
13
03
/05
/20
13
04
/05
/20
13
05
/05
/20
13
06
/05
/20
13
07
/05
/20
13
08
/05
/20
13
09
/05
/20
13
10
/05
/20
13
11
/05
/20
13
12
/05
/20
13
13
/05
/20
13
14
/05
/20
13
15
/05
/20
13
16
/05
/20
13
17
/05
/20
13
18
/05
/20
13
19
/05
/20
13
20
/05
/20
13
21
/05
/20
13
22
/05
/20
13
23
/05
/20
13
24
/05
/20
13
25
/05
/20
13
26
/05
/20
13
Id Act Activity Class Resp Zone Area Restr Cause Start Finish Scheduled Performed Pct (%) Target lun mar mié jue vie sáb dom lun2 mar2 mié2 jue2 vie2 sáb2 dom2 lun3 mar3 mié3 jue3 vie3 sáb3 dom3 lun4 mar4 mié4 jue4 vie4 sáb4 dom4
Act.#1 Activity Number #1 Compr Resp1 Zone 1 Area 1 Rst.#5 Mat 29/04/2013 01/05/2013 3.00 2.00 66.67% No 1.0 1.0
Act.#2 Activity Number #2 Compr Resp3 Zone 3 Area 2 Rst.#5 30/04/2013 30/04/2013 1.00 1.00 100.00% Yes 1.0
Act.#3 Activity Number #3 Compr Resp1 Zone 3 Area 4 Rst.#1 01/05/2013 02/05/2013 2.00 2.00 100.00% Yes 1.0 1.0
Act.#4 Activity Number #4 Stock Resp7 Zone 2 Area 2 Rst.#5 06/05/2013 10/05/2013 5.00 5.00 100.00% Yes 1.0 1.0 1.0 1.0 1.0
Act.#5 Activity Number #5 Compr Resp1 Zone 3 Area 1 Rst.#4 Equ 02/05/2013 03/05/2013 2.00 2.00 100.00% No 1.0 1.0
Act.#6 Activity Number #6 Compr Resp3 Zone 2 Area 4 Rst.#2 08/05/2013 15/05/2013 4.00 4.00 100.00% Yes 1.0 1.0 1.0 1.0
Act.#7 Activity Number #7 Compr Resp1 Zone 1 Area 1 Rst.#4 Wea 13/05/2013 17/05/2013 12.00 11.00 91.67% No 2.0 2.0 2.0 3.0 2.0
Act.#8 Activity Number #8 Stock Resp2 Zone 3 Area 2 Rst.#3 09/05/2013 24/05/2013 55.00 56.00 101.82% Yes 2.0 5.0 3.0 5.0 5.0 5.0 5.0 6.0 5.0 6.0 5.0 4.0
Act.#9 Activity Number #9 Compr Resp8 Zone 4 Area 3 Rst.#1 Dsg 01/05/2013 08/05/2013 6.00 4.00 66.67% No 1.0 2.0 1.0
Act.#10 Activity Number #10 Compr Resp2 Zone 2 Area 3 Rst.#5 06/05/2013 31/05/2013 20.00 19.00 95.00% Yes 1.0 2.0 1.0 1.0 1.0 1.0 2.0 1.0 1.0 1.0 2.0 1.0
Act.#11 Activity Number #11 Compr Resp2 Zone 2 Area 2 Rst.#4 13/05/2013 15/05/2013 23.00 21.00 91.30% Yes 5.0 9.0 7.0
Act.#12 Activity Number #12 Stock Resp4 Zone 1 Area 3 Rst.#7 30/05/2013 07/06/2013 4.00 0.00 0.00%
Act.#13 Activity Number #13 Compr Resp7 Zone 7 Area 7 Rst.#1 06/05/2013 10/05/2013 7.00 7.00 100.00% Yes 2.0 1.0 1.0 2.0 1.0
Act.#14 Activity Number #14 Compr Resp2 Zone 6 Area 3 Rst.#7 13/05/2013 15/05/2013 12.00 0.00 0.00% Yes
Act.#15 Activity Number #15 Stock Resp3 Zone 2 Area 4 Rst.#4 13/05/2013 15/05/2013 1.00 0.00 0.00% Yes
Completed over Compromises 82.85% 63.64%
Completed over Planed & Stock 74.21% 66.67%
Week 21
Week_18_2013 Dates Production
Week 18 Week 19 Week 20
![Page 9: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/9.jpg)
INTEGRATING TASK FRAGMENTATION AND EARNED VALUE METHOD INTO THE LAST
PLANNER SYSTEM USING SPREADSHEETS
PRODUCTION PLANNING AND CONTROL 71
Nevertheless, EVM, together with the commitments level control, allows to
effectively recognizing the root causes of deviations, contributing to the reliability of
workflow.
CONCLUSIONS
In this paper, a new approach for the representation and computation of projects for
the Last Planner System of Production Control is presented. This approach is
integrated with the management of the Earned Value and ad-hoc complex
optimization models. The proposal has been implemented in an add-in for Excel
called Senda Matrix. This add-in takes into consideration the feeding and work GPRs,
allowing the splitting of activities in a discretionary way, avoiding the interruption of
the critical path and the reverse criticality issue, as well as including the balance of
process flows by integrating EVM with PPC calculations.
Senda Matrix is a Free and Open-Source Software (FOSS) under License Creative
Commons–CY (Attribution), and is used in different undergraduate and postgraduate
courses at Universidad de Los Andes at Bogotá, Colombia, and Universitat
Politècnica de València, Spain (Pellicer and Ponz-Tienda, 2014; Pellicer, et al., 2015).
It allows to effectively implementing advances. A base model for the integration of
metrics is developed to serve as a basis for future developments.
This add-in for Excel has been developed from academia to support AEC industry
and Lean practitioners that can use it in order to overcome some of the problems of
the current commercial applications and help them make better decisions.
REFERENCES Ballard, G. and Howell, G., 1998. Shielding production: essential step in production
control. ASCE, J. Constr. Eng. Manage., 124(1), pp. 11-17.
Ballard, G., 2000. The Last Planner System of Production Control. Ph. D. University
of Birmingham.
Crandall, K., 1973. Project Planning with Precedence Lead/Lag Factors. Project
Management Quarterly, 4, pp. 18-27.
Hajdu, M., 1996. Splitting Allowed. In: Network Scheduling Techniques for
Construction Project Management (p. 162), Vol. 16: Nonconvex Optimization
and Its Applications. New York: Springer Science & Business Media.
IBM, 1968. Project Management System, Application Description Manual (H20-
0210). s.l.: s.n.
Kelley, J. J. E. and Walker, M. R., 1959. Critical-Path Planning and Scheduling. Proc.
eastern joint computer conference, Boston, MA, December 1–3.
Kerbosch, J. A. and Schell, H. J., 1975. Network Planning by the extended metra
potential method (EMPM), Reports KS - 1.1, Netherlands, Eindhoven: Department
of Industrial Engineering, Group Operational research, University of Technology.
Kim, T., Kim, Y.W. and Cho, H., 2015. Customer Earned Value: Performance
Indicator from Flow and Value Generation View. J. Manage. Eng., pp. 04015017.
Kim, Y.W. and Ballard, G., 2000. Is the earned-value method an enemy of work
flow?. In: Proc. 8th Ann. Conf. of the Int’l Group for Lean Construction, Brighton,
UK, August 17-19.
![Page 10: INTEGRATING TASK FRAGMENTATION AND EARNED VALUE …...All the precedence relationships are considered, in addition to the optimal and discretionary fragmentation of task in real conditions](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c566cb65f9001f252b77/html5/thumbnails/10.jpg)
José L. Ponz-Tienda , Eugenio Pellicer , Luis F. Alarcón, and Juan S. Rojas-Quintero
72 Proceedings IGLC-23, July 2015 |Perth, Australia
Kim, Y. and Ballard, G., 2010. Management Thinking in the Earned Value Method
System and the Last Planner System. J. Manage. Eng., 26(4), pp. 223-228.
Koskela, L., Howell, G., Pikas, E. and Dave, B., 2014. If CPM is so bad, why have
we been using it so long? In: Proc. 22nd Ann. Conf. of the Int’l Group for Lean
Construction, Oslo, Norway, June 23-27.
Koskela, L. J., Stratton, R. and Koskenvesa, A., 2010. Last planner and critical chain
in construction management: comparative analysis. In: Proc. 18th Ann. Conf. of
the Int’l Group for Lean Construction, Haifa, Israel, July 14-16.
Malcolm, D. G., Roseboom, J. H., Clark, C. E. and Fazar, W., 1959. Application of a
technique for research and development program evaluation. Operations Research,
7(5), pp.646-670.
Mellentien, C. and Trautmann, n., 2001. Resource allocation with project
management software. OR Spektrum, 23, pp.383-394.
Moder, J., Philips, C. and Davis, E., 1983. Project Management with CPM, PERT
and Precedence Diagramming. New York: Van Nostrand Reinhold.
Pellicer, E., Cerveró, F., Lozano, A. and Ponz-Tienda, J. L., 2015. The Last Planner
System of Construction Planning and Control as a Teaching and Learning Tool. In:
INTED2015 Proceedings, 9th International Technology, Education and
Development Conference. Madrid, 2-4 March, 2015, Madrid, Spain: IATED.
Pellicer, E. and Ponz-Tienda, J., 2014. Teaching and Learning Lean Construction in
Spain: A pioneer Experience.In: Proc. 22nd Ann. Conf. of the Int’l Group for Lean
Construction, Oslo, Norway, June 23-27 .
Ponz-Tienda, J. L., Pellicer, E. and Yepes, V., 2012. Complete fuzzy scheduling and
fuzzy earned value management in construction projects. Journal of Zhejiang
University SCIENCE A, 13(1), pp.56-68.
Ponz-Tienda, J. L., Yepes, V., Pellicer, E. and Moreno-Flores, J., 2013. The Resource
Leveling Problem with Multiple Resources. Automation in Construction, 29,
pp.161-172.
Ponz-Tienda, J. L., 2011. Gestión de proyectos con Excel 2010. Madrid: Anaya
Multimedia.
Ponz-Tienda, J. L., Benlloch-Marco, J., Andrés-Romano, C. and Gil-Senbre, D., 2011.
Un algoritmo matricial RUPSP / GRUPSP "sin interrupción" para la planificación
de la producción bajo metodología Lean Construction basado en procesos
productivos. Revista de la construcción, 10(1), pp. 90-103.
Roy, B., 1962. Graphes et ordonnancements. Revue Française de recherche
operationelle, 25(6), p. 323.
Trautman, N. and Baumnn, P., 2009. Resource-constrained sceduling of a Real
Project from the onstruction industry: A comparison of Software Packages for
Project Management. In: Proc. IEEM2009, Hong Kong, China, December 8-11.
Valls, V., Martí, R. and Lino, P., 1996. A Heuristic Algorithm for Project Scheduling
with Splitting Allowed. Journal of Heuristcs, 2(1), pp.87-104.
Wiest, J. D., 1981. Precedence Diagramming method: Some Unusual Characteristics
And Their Implications For Project Managers. Journal of Operations
Management, 1(3), pp.121-130.
Zaderenko, S. G., 1968. Sistemas de Programación por camino crítico: PERT-CPM-
MAN SCHEDULING-RAMPS y otros métodos de elaboración y control de
programas. Buenos Aires, Argentina: Librería Mitre.