Integrated SystemsJ . Kerby
![Page 2: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/2.jpg)
24-25 Inner Triplet Review - J Kerby 2
Reference Documents Inner Triplet FS (LHC LQX ES 0001 30 20)
Functional Overview Component Manufacture Machine Optics Cryogenic System Electrical Systems Absorber systems
![Page 3: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/3.jpg)
24-25 Inner Triplet Review - J Kerby 3
Reference Documents Inner Triplet FS points to:
Typically IS exists for each
![Page 4: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/4.jpg)
24-25 Inner Triplet Review - J Kerby 4
Reference Documents LQXA Functional Spec
![Page 5: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/5.jpg)
24-25 Inner Triplet Review - J Kerby 5
Reference Documents LQXA Interface Spec
![Page 6: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/6.jpg)
24-25 Inner Triplet Review - J Kerby 6
Assembly Procedures Triplet Components installed IP end first, building out
Tunnel space, shielding, and detector interfaces limit access Interconnects and end closures follow Procedures initiated at FNAL; tuned / improved and
translated after warm fit up experience
![Page 7: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/7.jpg)
24-25 Inner Triplet Review - J Kerby 7
Load Transfer Alignment Requirements for the LHC Low-Beta Triplets (LHC-G-ES-
0016, 2002). Main points concerning supports: CERN supplies jacks, cups and other equipment for installation to the tunnel
floor. Lateral load specified as 1 ton No reference to vacuum load (assumed taken up by the tie-rods).
Decision to use PMPS jacks for the inner triplets (2004?) Jacks designed to take loads up to 8 tons
Specification for the motorization of the PMPS jacks (IT3200, 2004) Lateral load specified as 1.3 tons
Anchor specification (date?) Lateral load specified as 5 tons
All cases referred to assumed vacuum loading
![Page 8: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/8.jpg)
24-25 Inner Triplet Review - J Kerby 8
Load Transfer Need for reaction of vacuum loads noted at Cryostat
Conceptual Design review (1999) An action item from the Cryostat Interim Design
Review in 2000 Concern on number of tie bars (2 to 3 recommened) Concern on protruding into the aisle
Stability of tie rods under vacuum noted at Engr Design Review (2001)
![Page 9: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/9.jpg)
24-25 Inner Triplet Review - J Kerby 9
Load Transfer Tunnel jacks assumed to take no load in shear
for purposes of tie bars Full Q1-Q2-Q3 vacuum load (~78kN) reacted
through tie bars to DFBX and to ground
![Page 10: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/10.jpg)
24-25 Inner Triplet Review - J Kerby 10
![Page 11: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/11.jpg)
24-25 Inner Triplet Review - J Kerby 11
![Page 12: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/12.jpg)
24-25 Inner Triplet Review - J Kerby 12
![Page 13: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/13.jpg)
24-25 Inner Triplet Review - J Kerby 13
Load Transfer 4 M30 tie bars at each interconnect
Vacuum bellows contribution excluded In Q1-Q2 & Q2-Q3 interconnects stiffened at
intermediate location Stress in tie bars ~27MPa, nominal (ear deflection
to be considered) System successfully tested in Bat 181 Apr 2005 Measurements on deflections at ears during Apr
2005 corroborated by analysis
![Page 14: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/14.jpg)
24-25 Inner Triplet Review - J Kerby 14
Load Transfer Ear deflection for
vacuum load approx 0.52mm linearly scaled from Q1-Q2-Q3 model used for analyzing failure mode
42.7kN
R = 525.8mm
0.1mm
0.1mm
1.14mm
R = 467.4mm
![Page 15: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/15.jpg)
24-25 Inner Triplet Review - J Kerby 15
![Page 16: Integrated Systems](https://reader036.fdocuments.us/reader036/viewer/2022062400/56814a44550346895db75fa8/html5/thumbnails/16.jpg)
24-25 Inner Triplet Review - J Kerby 16
Vacuum Loads Measurements have also been taken in IR8R Resonable agreement w/ calculation when
including the stiffness of the jacks