Integrated Community Sustainability Plan for the Port au ... au Port East, Port au... · Integrated...
Transcript of Integrated Community Sustainability Plan for the Port au ... au Port East, Port au... · Integrated...
Integrated Community Sustainability Plan for the
Port au Port Region
A collaboration of the Municipalities of:
Port au Port East Port au Port West, Aguathuna, Felix Cove
Lourdes Cape St. George
March 31, 2010
Table of Contents
Introduction Community Assessment Vision Goals and Actions Partnerships Implementation Monitoring Conclusion Appendix A 2010 Municipal Budget for the Town of Port au Port East 2010 Municipal Budget for the Town of Port au Port West, Aguathuna, Felix Cove 2010 Municipal Budget for the Town of Lourdes 2010 Municipal Budget for the Town of Cape St. George
Introduction Geography The Port au Port Peninsula is situated on the west coast of Newfoundland. It is bound on the south by St. George’s Bay, on the west and north by the Gulf of St. Lawrence and on the east by Port au Port Bay. A tiny isthmus connects the peninsula to the rest of the island. The communities on the peninsula include Boswarlos, Campbell’s Creek, Town of Port au Port West, Aguathuna, Felix Cove, Abraham’s Cove, Piccadilly and Piccadilly Head, West Bay, Town of Lourdes, Mainland, Three Rock Cove, Black Duck Brook, Winterhouse, Ship Cove, Lower Cove, Jerry’s Nose, Sheaves Cove, Town of Cape St. George, Marche’s Point, Red Brook, and Degrau. The communities of Point au Mal, Fox Island River and the Town of Port au Port East are not on the peninsula itself, but they too are included in the region. It should also be noted that this region falls within the boundaries comprised by The Long Range Regional Economic Development Board – Zone 9. History
During the 16th-17th centuries, French and Basque fishermen used the west coast of Newfoundland, including the Port au Port region, for seasonal fishing settlements, and some began permanently inhabiting the area.
During and after the Treaty of Utrecht in 1713 and Treaty of Paris in 1763, France retained the right to use the west coast of the island. This area came to be known as the "French Shore" and the Port au Port region was at its centre.
Scattered settlement continued in the area until 1904 when France relinquished its right of use to the "French Shore". The Port au Port region represents the most varied ethnic and linguistic mix on the entire island of Newfoundland and Labrador, with the highest proportion of French-speaking settlement on the island (15%).
The French minority is a mix of Acadian, French and Basque and this has had an important influence on the area's culture. Newfoundland and Labrador’s unique folk music has been somewhat influenced by musicians from the Port au Port region. As well, the area's strong Roman Catholic tradition is reflected in the high visibility accorded to churches throughout the region’s communities.
As the centre of the province's Franco-Newfoundlander community, the region has been designated the only bilingual district on the island of Newfoundland and Labrador since 1971.
Economy
The Port au Port region's economy is based on natural resources, namely fishing. Limited forestry takes place in the unsettled areas of the interior and a small amount of
subsistence farming takes place along coastal areas. Many residents of the region, particularly the communities at the eastern end near the isthmus, work in nearby Stephenville.
Beginning in 1900 a limestone quarrying operation was established at Aguathuna, near the peninsula's isthmus where the Table Head mountain ridge extends from the Lewis Hills. The limestone was used by Dominion Steel and Coal Corporation at a steel mill in Sydney, Nova Scotia. The quarry was closed in 1966 following DOSCO's financial difficulties.
The construction of the US Air Force Base at Stephenville in 1941 was the biggest single factor to impact on the economy of the area. By 1964, the Earnest Harmon Air Force Base had a total non-military labor force of about 1429 people. Rumors were rampant of the impending Base closure and by 1966 this had become a reality.
In the 1980s, construction of a new fish plant and the establishment of the Shellfish Farming Program were the two major developments of that decade. Neither of these entities is in existence today. From 1981 to 2005, Abitibi Pulp and Paper operated a paper mill in Stephenville and they were the region’s largest employer. In 1985, a major limestone quarry began operating at Lower Cove. Today, Atlantic Minerals Ltd. is employing up to 120 people.
Presently, petroleum companies are exploring the region for oil. Some deposits were discovered in recoverable quantities and limited production wells are in place at some locations. Geologists have estimated that a much larger deposit exists deeper and possibly off shore from the peninsula in the 400-500 million barrel range, however exploration drilling has not yet confirmed this theory.
Today travelers access the area using the Marine Atlantic Ferry service to Channel - Port aux Basques or with Sunwing, Sky Service and Provincial Airlines to the Stephenville Airport.
Population
Population information was obtained from Community Accounts. The Port au Port region has been experiencing a slow population decline. According to Community Accounts, the 2006 Census population for Port au Port was 2,920. This represents a decline of 2.2% since 2001 (2,920 in 2006, down from 2,985). Over the same period, the entire province experienced a population decline of 1.5% since 2001 (505,470 in 2006, down from 512,930).
Unfortunately, additional details or population pyramids are still under construction and are not available at this time. There exists, a great deal of variety among community postal codes assigned by Canada Post. The current system can cause a great deal of confusion and in some instances, additional expense in terms of community communications.
General Outlook
The future of the region is uncertain. In many parts of the region, falling populations are happening as younger people leave and those few women who stay are having fewer children. “Volunteer burn out” will likely occur as the prime age survivors try to maintain community services such as the volunteer fire departments while at the same time taking care of elderly parents, relatives, friends, and neighbors.
However, there is much to be optimistic about. All four Towns recognize the important contribution that tourism and cultural preservation can provide in securing a positive economic future. Tourism provides an effective means to diversify the local economy. Port au Port is able to offer the tourist spectacular scenery as the scenic loop, called the French Ancestors Route, follows the coast and skirts along the edge of the sea cliffs that, in some places, plunge 500 meters into the ocean. In addition to the scenery, the Port au Port region provides a unique cultural experience with a heritage dating back to the French fishing fleets.
As well, the four Towns involved in this ISCP will seek improved public health and better quality of life for all its residents by limiting waste, preventing pollution, maximizing conservation and promoting efficiency, and developing local resources to enhance the local economy. They are committed to only using resources to meet current needs while ensuring that adequate resources are available for future generations
Community Assessment
During the Fall of 2008, each municipality, under the guidance of staff from Municipalities Newfoundland and Labrador, completed a Municipal Sustainability Self- Assessment Tool Kit. The subsequent reports generated by this process helped to identify issues that are detailed in the following tables.
Self Assessment Category
Issues or Needs identified for Port au Port East
Governance There wasn’t a contested election. There are no committees of Council.
Administration There is an adequate number of skilled staff.
Finance and Financial Management
Operating under sound financial practices. Debt levels are low. Able to deliver the current levels of service and meet the requirements of the Municipalities Act.
Service Delivery Waste diversion and reduction activities must be included in any future waste management plans. Recreation programs for all ages must be implemented.
Infrastructure Able to ensure the maintenance and development of the required infrastructure to sustain the services currently provided.
Community Well-Being
Youth retention programs and community building activities may help maintain the population. High unemployment and a shrinking tax base can be mitigated with innovative economic development strategies that capitalize on key assets. Implementing policies to educate people and encourage environmental protection. Supporting the local arts and culture development can enhance community connectivity and the well being of residents.
Regional Cooperation
Increasing regional cooperation efforts can lead to more increased communication, viable governance structures and possibly reduced costs and increased service levels. There needs to be increased regional cooperation in the areas of Service Delivery and Community Well-Being.
Self Assessment Category
Issues or Needs identified for Port au Port West, Aguathuna, Felix Cove
Governance There wasn’t a contested election. There are no committees of Council. There is a lack of planning.
Administration There is an adequate number of skilled staff.
Finance and Financial Management
More effective tax collection methods will increase operating budgets and reduce “lost” revenue. Debt levels are low.
Service Delivery Increasing the effectiveness of emergency response. Waste diversion and reduction activities must be included in any future waste management plans. Unable to provide regular preventative maintenance to ensure safe drinking water. Recreation programs for all ages must be implemented.
Infrastructure Struggling to maintain the current infrastructure and enhance service delivery.
Community Well-Being
Youth retention programs and community building activities may help maintain the population. Improving social capital by fostering a strong sense of connection to the community. Implementing policies to educate people and encourage environmental protection. Local initiatives in the areas of Health and Education can supplement a shortage of accessible institutions. Supporting the local arts and culture development can enhance community connectivity and the well being of residents.
Regional Cooperation
Increasing regional cooperation efforts can lead to more increased communication, viable governance structures and possibly reduced costs and increased service levels. There needs to be increased regional cooperation in the areas of Service Delivery and Community Well-Being.
Self Assessment Category
Issues or Needs identified for Lourdes
Governance There is a lack of planning
Administration There is an adequate number of skilled staff
Finance and Financial Management
More effective tax collection methods will increase operating budgets and reduce “lost” revenue Debt levels are low Accountability must become a priority, especially PSAB standards
Service Delivery Waste diversion and reduction plans must be included in any future waste management plans Recreation programs for all ages can be expanded upon
Infrastructure Able to ensure the maintenance and development of the required infrastructure to sustain the services currently provided
Community Well-Being
Youth retention programs and community building activities may help maintain the population Improving social capital by fostering a strong sense of connection to the community Implementing policies to educate people and encourage environmental protection Local initiatives in the areas of Health and Education can supplement a shortage of accessible institutions Supporting the local arts and culture development can enhance community connectivity and the well being of residents
Regional Cooperation
Proactively taking advantage of the benefits of regional cooperation, which could enhance long-term sustainability
Self Assessment Category
Issues or Needs identified for Cape St. George
Governance There wasn’t a contested election. There is a lack of planning.
Administration There is an adequate number of skilled staff.
Finance and Financial Management
Operating under sound financial practices. Debt levels are low. Able to deliver the current levels of service and meet the requirements of the Municipalities Act.
Service Delivery Waste diversion and reduction activities must be included in any future waste management plans.
Infrastructure Able to ensure the maintenance and development of the required infrastructure to sustain the services currently provided.
Community Well-Being
Supporting the local arts and culture development can enhance community connectivity and the well being of residents.
Regional Cooperation
Proactively taking advantage of the benefits of regional cooperation, which could enhance long-term sustainability.
In accordance with the ICSP guide and in addition to the self assessment process completed, the basic questions of sustainability are identified and addressed in the following tables.
Basic Questions of Sustainability for Port au Port East
YES NO In general are you able to get candidates to run for municipal council?
X
Does your council hold at least one public council meeting per month?
X
Has the municipality been able to avoid an operating deficit continuously in the past 2 years?
X
Is your debt servicing level within the provincial benchmark of 30%?
X
Is your municipal plan up to date?
X Do you have adequate municipal buildings to meet your current needs?
X
Do you currently meet all conditions of your permit to operate your water system?
X
Are you able to meet all provincial and federal requirements for sewage treatment?
X
Do you have sufficient water infrastructure to meet the needs of your residents?
X
Does your council keep at hand, adopted rules of procedure?
X Do you currently employ all the staff you require to meet the operational needs of your municipality?
X
Is your solid waste collected at least once a week and disposed of at a Department of Environment approved site?
X
Do you provide, or contract for, adequate emergency response services?
X
Basic Questions of Sustainability for Port au Port West, Aguathuna, Felix Cove
YES NO In general are you able to get candidates to run for municipal council?
X
Does your council hold at least one public council meeting per month?
X
Has the municipality been able to avoid an operating deficit continuously in the past 2 years?
X
Is your debt servicing level within the provincial benchmark of 30%?
X
Is your municipal plan up to date?
X Do you have adequate municipal buildings to meet your current needs?
X
Do you currently meet all conditions of your permit to operate your water system?
X
Are you able to meet all provincial and federal requirements for sewage treatment?
X
Do you have sufficient water infrastructure to meet the needs of your residents?
X
Does your council keep at hand, adopted rules of procedure?
X Do you currently employ all the staff you require to meet the operational needs of your municipality?
X
Is your solid waste collected at least once a week and disposed of at a Department of Environment approved site?
X
Do you provide, or contract for, adequate emergency response services?
X
Basic Questions of Sustainability for Lourdes
YES NO In general are you able to get candidates to run for municipal council?
X
Does your council hold at least one public council meeting per month?
X
Has the municipality been able to avoid an operating deficit continuously in the past 2 years?
X
Is your debt servicing level within the provincial benchmark of 30%?
X
Is your municipal plan up to date?
X Do you have adequate municipal buildings to meet your current needs?
X
Do you currently meet all conditions of your permit to operate your water system?
X
Are you able to meet all provincial and federal requirements for sewage treatment?
X
Do you have sufficient water infrastructure to meet the needs of your residents?
X
Does your council keep at hand, adopted rules of procedure?
X Do you currently employ all the staff you require to meet the operational needs of your municipality?
X
Is your solid waste collected at least once a week and disposed of at a Department of Environment approved site?
X
Do you provide, or contract for, adequate emergency response services?
X
Basic Questions of Sustainability for Cape St. George
YES NO In general are you able to get candidates to run for municipal council?
X
Does your council hold at least one public council meeting per month?
X
Has the municipality been able to avoid an operating deficit continuously in the past 2 years?
X
Is your debt servicing level within the provincial benchmark of 30%?
X
Is your municipal plan up to date?
X Do you have adequate municipal buildings to meet your current needs?
X
Do you currently meet all conditions of your permit to operate your water system?
X
Are you able to meet all provincial and federal requirements for sewage treatment?
X
Do you have sufficient water infrastructure to meet the needs of your residents?
X
Does your council keep at hand, adopted rules of procedure?
X Do you currently employ all the staff you require to meet the operational needs of your municipality?
X
Is your solid waste collected at least once a week and disposed of at a Department of Environment approved site?
X
Do you provide, or contract for, adequate emergency response services?
X Priority issues will be addressed first. The identification of specific goals and projects are highlighted in detail in the strategic goals and actions section of this plan.
Community Vision In order to create a community vision, all four municipal councils met as a group on November 29, 2009. A facilitator guided the group through a visioning session to create a common vision for 2015.
Port au Port Region Vision Statement
“All of the incorporated Municipalities in the Port au Port Region will strive to work together to protect the natural environment and provide for the long term
economic, social and cultural needs of all the region’s residents.”
Efforts to generate community buy-in and support for the plan were achieved through a serious of public meetings held in each municipality in February of 2010. At each meeting, a draft plan was presented and residents were asked to provide feedback and comments. The public meeting dates were advertised in the Western Star on Saturday, March 13, 2010 and Wednesday, March 17, 2010. The public meeting schedule was as follows: Town of Cape St. George French Center March 15, 2010 Town of Port au Port East Council Office March 16, 2010 Town of Port au Port West Aguathuna, Felix Cove Council Office March 17, 2010 Town Of Lourdes Council Office March 22, 2010
Strategic Goals and Actions In order to set priorities to reach the vision, each of the four municipal councils began a goal development process independently. The five pillars of sustainability were considered during the goal setting and given a priority rank. Action plans were then developed to achieve each goal. Priority # 1 April 1, 2010 to December 31, 2012 Priority #2 January 1, 2013 to December 31, 2014 Priority #3 January 1, 2015 to December 31, 2015
Environmental Sustainability Human health and its social and economic well-being are fundamentally linked to the quality of their environment. Therefore, individuals, businesses and all levels of government have a responsibility to ensure that their actions contribute to a sustainable environment on a local and global level. Sustainable development is defined in federal legislation as "development that meets the needs of the present without compromising the ability of future generations to meet their own needs." To become more sustainable, all four incorporated municipalities will work to reduce and eliminate unsustainable practices with respect to infrastructure, energy and water use, and waste management.
Municipalities in the Port au Port region have not included waste management goals in this Integrated Community Sustainability Plan because there is anticipation that direction regarding this responsibility will be addressed in the Western Regional Waste Management Plan.
The intention is to improve the environmental sustainability of the region by identifying goals and implementing projects. Success will be measured by meeting these goals.
Port au Port East Pillar Goal # Project Cost Funding Priority To partner
with Community and Environment groups
PAPE ENV 1A
Clean up Gravels Pond
$100 000 TBD 3
PAPE ENV 1B
Implement outcomes of flood study
TBD TBD 1
Environment PAPE ENV 1C
Develop play-ground
$30 000 Budget 2
PAPE ENV 1D
Discuss the idea of protection status for the Gravels pond
0 Not required
1
PAPE ENV 1E
Sponsor a Green Team
$750 Budget – GTF
3
Goal Description Goal: Partner with Community & Environment Groups Partner: Conservation Corps NL, Town of Port au Port West, Aguathuna, Felix Cove, Town of
Cape St. George, Town of Lourdes This Goal fits within the community Vision in the following way: Sustain partnerships and improved environmental stewardship
The following projects are related to the completion of this goal:
PAPE Env 1A Clean up Gravels Pond
PAPE Env 1B Implement outcomes of flood study
PAPE Env 1C Develop playground
PAPE Env 1D Discuss the idea of protection status for the Gravels Pond
PAPE Env 1E Sponsor a green team
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in youth employment
Qualitative • Improved environmental awareness
• Improved environmental stewardship
Project Description
Project & Goal # PAPE Env 1A
Project Title Clean up Gravels Pond
Associated Goal Partner with community & environment groups
Brief Description Facilitate the clean up of Gravels Pond
Project lead Port au Port East
Estimated Cost $100 000
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) To be determined
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Town of Port au Port West, Aguathuna, Felix Cove Support
Department of Environment and Conservation Experience and knowledge
Project Description
Project & Goal # PAPE Env 1B
Project Title Implement outcomes of flood study
Associated Goal Partner with community & environment groups
Brief Description Implement the recommendations outlined in the flood zone study upon its
completion
Project lead Port au Port East
Estimated Cost To be determined
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) To be determined
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Env 1C
Project Title Develop playground
Associated Goal Partner with community & environment groups
Brief Description Develop a community playground at the local elementary school
Project lead St. Thomas Aquinas elementary school playground committee
Estimated Cost $ 30 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Playground committee, Town of Port au Port West, Aguathuna, Felix Cove,
Department of Tourism, Culture and Recreation, Let Them Be Kids Foundation
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Town of Port au Port West, Aguathuna, Felix Cove Funding
Department of Tourism, Culture and Recreation Experience, knowledge and funding
St. Thomas Aquinas playground committee Funding
Let Them Be Kids Foundation Funding
Project Description
Project & Goal # PAPE Env 1D
Project Title Protection status for Gravels Pond
Associated Goal Partner with community & environment groups
Brief Description Start a diolouge with the adjacent community of Port au Port West, Aguathuna,
Felix Cove in an effort to obtain protection status for the Gravels Pond
Project lead Port au Port East
Estimated Cost $ 0
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Town of Port au Port West, Aguathuna, Felix Cove Support, lobby effort
Department of Environment and Conservation Experience and knowledge
Project Description
Project & Goal # PAPE Env 1E
Project Title Sponsor a Green Team
Associated Goal Partner with Community & Environment Groups
Brief Description Hire a green team to promote environmental strategies that reduce energy use
Project lead Cape St. George
Estimated Cost $ 750
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Town Council of Cape St. George, Town of Lourdes, Town of Port au Port
West, Aguathuna, Felix Cove, Town of Port au Port East
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X______Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
A reduction in energy use will lower green house gases
Partner(s) Involved Role of Partner(s)
Town of Cape St. George Funding partner
Town of Port au Port West, Aguathuna, Felix Cove Funding partner
Town of Lourdes Funding partner
Port au Port West, Aguathuna, Felix Cove
Pillar Goal # Project Cost Funding Priority Partner with
community and environment groups
PAPW ENV 1A
Discuss the idea of protection status for the Gravels pond
$ 0 Not required
1
Environment PAPW ENV 1B
Clean up Gravels Pond
$ 100 000 TBD 3
PAPW ENV 1C
Sponsor a Green Team
$ 750 Budget – GTF
3
Goal Description Goal: Partner with Community & Environment Groups Partner: Conservation Corps NL, Town of Port au Port West, Aguathuna, Felix Cove, Town of
Cape St. George, Town of Lourdes This Goal fits within the community Vision in the following way: Sustain partnerships and improved environmental stewardship
The following projects are related to the completion of this goal:
PAPW Env 1A Discuss the idea of protection status for the Gravels Pond
PAPW Env 1B Clean up Gravels Pond
PAPW Env 1C Sponsor a green team
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in youth employment
Qualitative • Improved environmental awareness
• Improved environmental stewardship
Project Description
Project & Goal # PAPW Env 1A
Project Title Protection status for Gravels Pond
Associated Goal Partner with community & environment groups
Brief Description Start a diolouge with the adjacent community of Port au Port East in an effort to
obtain protection status for the Gravels Pond
Project lead Port au Port East
Estimated Cost $ 0
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Town of Port au Port East Support, lobby effort
Department of Environment and Conservation Experience and knowledge
Project Description
Project & Goal # PAPW Env 1B
Project Title Clean up Gravels Pond
Associated Goal Partner with community & environment groups
Brief Description Facilitate the clean up of Gravels Pond
Project lead Port au Port East
Estimated Cost $100 000
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) To be determined
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Town of Port au Port East Support
Department of Environment and Conservation Experience and knowledge
Project Description
Project & Goal # PAPW Env 1C
Project Title Sponsor a Green Team
Associated Goal Partner with Community & Environment Groups
Brief Description Hire a green team to promote environmental strategies that reduce energy use
Project lead Cape St. George
Estimated Cost $ 750
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Town Council of Cape St. George, Town of Lourdes, Town of Port au Port
West, Aguathuna, Felix Cove, Town of Port au Port East
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X______Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
A reduction in energy use will lower green house gases
Partner(s) Involved Role of Partner(s)
Town of Cape St. George Funding partner
Town of Port au Port East Funding partner
Town of Lourdes Funding partner
Lourdes Pillar Goal # Project Cost Funding Priority To create
Energy efficient Infrastructure
LOR ENV 1A
To relocate the Town Office, Fire Hall and Maintenance Depot
$ 400 000 Budget GTF
1
Environment Partner with community and environment groups
LOR ENV 2A
Sponsor a Green Team
$ 750 Budget – GTF
3
Goal Description Goal: Create energy efficient infrastructure Partner: This Goal fits within the community Vision in the following way: Protect the natural environment The following projects are related to the completion of this goal:
LOR Env. 1A Relocate the Town office, fire hall and maintenance depot
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Reduction in energy use
• Reduction in water use
Qualitative • Increase environmental awareness
• Reduce impact of non environmentally friendly practices
• Improve environmental stewardship
Project Description
Project & Goal # LOR Env 1A
Project Title Relocate Town office, fire hall and maintenance depot
Associated Goal To create energy efficient infrastructure
Brief Description Relocate the Town office, fire hall and maintenance depot to a more energy
efficient building
Project lead Lourdes
Estimated Cost $ 400 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town of Lourdes - GTF
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
An energy efficient municipal building
Partner(s) Involved Role of Partner(s)
Goal Description Goal: Partner with Community & Environment Groups Partner: Conservation Corps NL, Town of Port au Port West, Aguathuna, Felix Cove, Town of Port au
Port East, Town of Cape St. George This Goal fits within the community Vision in the following way: Sustain partnerships and improved environment stewardship
The following projects are related to the completion of this goal:
LOR Env. 2A Sponsor a green team
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Less waste
• Increase in youth employment
Qualitative • Improved environmental awareness
• Greater community pride
• Improve environmental stewardship
• Create greater willingness to change habits that negatively effect the environment and increase Community unity
Project Description
Project & Goal # LOR Env 2A
Project Title Sponsor a Green Team
Associated Goal Partner with Community & Environment Groups
Brief Description Hire a green team to promote environmental strategies that reduce energy use
Project lead Cape St. George
Estimated Cost $ 750
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Town Council of Cape St. George, Town of Lourdes, Town of Port au Port
West, Aguathuna, Felix Cove, Town of Port au Port East
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X______Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
A reduction in energy use will lower green house gases
Partner(s) Involved Role of Partner(s)
Town of Cape St. George Funding partner
Town of Port au Port West, Aguathuna, Felix Cove Funding partner
Town of Port au Port East Funding partner
Cape St. George
Pillar Goal # Project Cost Funding Priority To create
Energy efficient Infrastructure
CSG ENV 1A
Install Energy efficient water pumping systems
$30 000 Budget – GTF
1
Encourage environmentally friendly actions
CSG ENV 2A
Encourage local entrepreneurs to recycle heavy materials
$500 Budget 1
Environment Partner with community and environment groups
CSG ENV 3A
Support green groups
$1 000 Budget 1
CSG ENV 3B
Allow the recycling of materials during clean up week
0 Not required
1
CSG ENV 3C
Sponsor a Green Team
$750 Budget – GTF
3
To provide environmentally friendly Municipal operations
CSG ENV 4A
Lobby the MMSB to improve services
0 Not required
1
CSG ENV 4B
Increase recycling of MMSB items
$500 Budget 2
CSG ENV 4C
Renovate Town building
$8 800 Budget - GTF
1
CSG ENV 4D
Raise awareness of recycling
$200 Budget 1
CSG ENV 4E
Establish an environment committee
0 Not required
3
To have Boutte
CSG
Lobby
0
Not
1
du Cap Parc and adjoining limestone barrens recognized as a protected area
ENV 5A
Government to recognize the area as a protected area
required
Goal Description
Goal: Create energy efficient infrastructure Partner: This Goal fits within the community Vision in the following way: Protect the natural environment The following projects are related to the completion of this goal:
CSG Env. 1A Install energy efficient water pumping systems
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Reduction in energy use
• Reduction in water use
Qualitative • Increase environmental awareness
• Reduce impact of non environmentally friendly practices
• Improve environmental stewardship
Project Description
Project & Goal # CSG Env 1A
Project Title Install energy efficient water pumping systems
Associated Goal To create energy efficient infrastructure
Brief Description To reduce the amount of energy presently being used to maintain the community
water supply
Project lead Cape St. George
Estimated Cost $ 30 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town Council of Cape St. George - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
_______ Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Increased energy efficiency
Partner(s) Involved Role of Partner(s)
Goal Description
Goal: Encourage environmentally friendly actions Partner: Private sector This Goal fits within the community Vision in the following way: Protect the natural environment The following projects are related to the completion of this goal:
CSG Env. 2A Encourage local entrepreneurs to recycle heavy materials
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of items being recycled
• Waste diversion from landfill site
• Reduce the amount of toxic substances leeched into the soil
Qualitative • Cleaner community
• Increased community pride
• Improve environmental stewardship
Project Description
Project & Goal # CSG Env 2A
Project Title Encourage local entrepreneurs to recycle heavy materials
Associated Goal Encourage environmentally friendly actions
Brief Description To reduce the amount of waste being directed to the local landfill site
Project lead Cape St. George
Estimated Cost $ 500
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town Council of Cape St. George
If gas tax the following outcome(s) will be achieved:
Cleaner Air
_______ Cleaner Water
Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Private sector Implementation of recycling program
Goal Description Goal: Partner with Community & Environment Groups
Partner: Conservation Corps NL, Town of Port au Port West, Aguathuna, Felix Cove, Town of Port au Port East, Town of Lourdes
This Goal fits within the community Vision in the following way: Sustain partnerships and improved environment stewardship
The following projects are related to the completion of this goal:
CSG Env. 3A Support Green Groups in the Community
CSG Env. 3B Allow “freecycle” during clean up week
CSG Env. 3C Sponsor a Green Team
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Less waste
• Increase in youth employment
Qualitative • Improved environmental awareness
• Greater community pride
• Improve environmental stewardship
• Create greater willingness to change habits that negatively effect the environment and increase community unity
Project Description
Project & Goal # CSG Env 3A
Project Title Support Green Groups in the Community
Associated Goal Partner with community & environment groups
Brief Description Facilitate the creation of financial and in-kind partnerships with volunteer green
groups in the community and region
Project lead Cape St. George
Estimated Cost $1,000.00
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town Council of Cape St. George
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Conservation Corporations NNL Experience/ Knowledge
Surrounding Municipalities/ LSD Community Co-operation
Other Environmental Groups Experience/ Knowledge
Project Description
Project & Goal # CSG Env 3B
Project Title Implement a “freecycle” program
Associated Goal Partner with Community & Environment Groups
Brief Description Allow the recycling of materials during clean up week
Project lead Cape St. George
Estimated Cost $ 0
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Residents Co-operation
Surrounding Municipalities/ LSD Community Co-operation
Private sector Co-operation
Project Description
Project & Goal # CSG Env 3C
Project Title Sponsor a Green Team
Associated Goal Partner with Community & Environment Groups
Brief Description Hire a green team to promote environmental strategies that reduce energy use
Project lead Cape St. George
Estimated Cost $ 750
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Town Council of Cape St. George, Town of Lourdes, Town of Port au Port
West, Aguathuna, Felix Cove, Town of Port au Port East
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X______Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
A reduction in energy use will lower green house gases
Partner(s) Involved Role of Partner(s)
Town of Port au Port East Funding partner
Town of Port au Port West, Aguathuna, Felix Cove Funding partner
Town of Lourdes Funding partner
Goal Description
Goal: To provide environmentally friendly municipal operations Partner: MMSB
This Goal fits within the community Vision in the following way: Protect the natural environment
The following projects are related to the completion of this goal:
CSG Env. 4A Lobby the MMSB to improve services to rural communities
CSG Env. 4B Increase recycling of MMSB items
CSG Env. 4C Renovate Town building to be energy efficient
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Waste diversion
• Reduced energy consumption
Qualitative • Improved services to rural communities
• Clean and tidy communities
Project Description
Project & Goal # CSG Env 4A
Project Title Lobby the MMSB to improve services
Associated Goal To provide environmentally friendly municipal operations
Brief Description Lobby the MMSB to improve services to rural communities with respect to
recycling and environmental awareness programs
Project lead Cape St. George
Estimated Cost $ 0
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
______ Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
MMSB Improve service delivery
Project Description
Project & Goal # CSG Env 4B
Project Title Increase recycling of MMSB items
Associated Goal To provide environmentally friendly municipal operations
Brief Description Encourage increased recycling of items to divert them from the local landfill site
Project lead Cape St. George
Estimated Cost $ 500
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Town Council of Cape St. George
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
______ Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Residents Co-operation
MMSB Experience and knowledge
Project Description
Project & Goal # CSG Env 4C
Project Title Renovations to Town building
Associated Goal To provide environmentally friendly municipal operations
Brief Description Renovate Town buildings to be energy efficient
Project lead Cape St. George
Estimated Cost $ 8 800
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town Council of Cape St. George - GTF
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
An energy efficient municipal building
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Env 4D
Project Title Raise awareness of recycling
Associated Goal To provide environmentally friendly municipal operations
Brief Description Use the community newsletter to raise awareness of the benefits of recycling
Project lead Cape St. George
Estimated Cost $ 200
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Town Council of Cape St. George
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
______ Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Residents Co-operation
MMSB Experience and knowledge
Project Description
Project & Goal # CSG Env 4E
Project Title Establish an environment committee
Associated Goal To provide environmentally friendly municipal operations
Brief Description Establish an environment committee of Council
Project lead Cape St. George
Estimated Cost $ 0
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
______ Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Goal Description Goal: To have Boutte du Cap Parc and adjoining limestone barrens recognized as a protected
area Partner: This Goal fits within the community Vision in the following way:
Protect the natural environment
The following projects are related to the completion of this goal:
CSG Env. 5A Lobby Government to recognize the park and limestone barrens as a protected area
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Establishment of a protected area
Qualitative • All levels of Government will recognize the value of protecting the natural environment
Project Description
Project & Goal # CSG Env 5A
Project Title Lobby Government to recognize the Boutte du Cap Parc and limestone barrens
as a protected area
Associated Goal To have Boutte du Cap Parc and adjoining limestone barrens recognized as a
protected area
Brief Description Lobby Government to recognize Boutte du Cap Parc and the adjoining
limestone barrens as a protected area
Project lead Cape St. George
Estimated Cost $ 0
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Not required
If gas tax the following outcome(s) will be achieved:
_______ Cleaner Air
________Cleaner Water
______ Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Government of Newfoundland and Labrador Legislative Economic Sustainability The main requirement of economic sustainability is that current or future economic activities should not result in an excessive burden on future generations. Economic Sustainability occurs when development, which moves towards social and environmental sustainability, is financially feasible.
Economic sustainability is concerned with the preservation of safe minimum levels of environmental assets in physical terms rather than the dollar value of natural and man-made capital. Safe minimum standards for environmental assets constrain efficiency in order to ensure the sustainability of the economic system. All four Towns have developed feasible goals and projects that will improve the economy without having any adverse effect on future generations. Port au Port East Pillar Goal # Project Cost Funding Rank Make
improvements PAPE ECO
Upgrade Tourist Chalet
$ 40 000 Budget, Service
1
to existing resources
1A Canada, Municipal Affairs
Economic PAPE ECO 1B
Develop a walking trail
$ 35 000 Budget, Service Canada, Municipal Affairs
3
Develop a business friendly town
PAPE ECO 2A
Update Municipal Plan
$ 3000 Budget 3
PAPE ECO 2B
Install sidewalks
$ 100 000 TBD 2
PAPE ECO 2C
Recap side streets
$ 50 000 Budget- GTF
2
PAPE ECO 2D
Pave street extension
$ 100 000 Budget- GTF
1
PAPE ECO 2E
Upgrades to water system
$ 500 000 Budget- GTF
1
Goal Description Goal: Make improvements to existing resources Partner: Service Canada, Municipal Affairs This Goal fits within the community Vision in the following way: Improve the economy of the region
The following projects are related to the completion of this goal:
PAPE Eco 1A Upgrade Tourist Chalet
PAPE Eco 1B Develop a walking trail
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in primary and secondary tourism generators
• Increased revenues for local business
• Increase in the number of visitors
Qualitative • Increased community pride
• Improved service delivery to the visiting public
Project Description
Project & Goal # PAPE Eco 1A
Project Title Upgrade tourist chalet
Associated Goal Make improvements to existing resources
Brief Description Maintain, expand and improve services at the visitor information center
Project lead Port au Port East
Estimated Cost $ 40 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget, Service Canada, Municipal Affairs
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Service Canada Funding
Municipal Affairs Funding
Project Description
Project & Goal # PAPE Eco 1B
Project Title Develop a walking trail
Associated Goal Make improvements to existing resources
Brief Description Erect signage and formally develop an existing local walking trail
Project lead Port au Port East
Estimated Cost $ 35 000
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Budget, Service Canada, Municipal Affairs
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Service Canada Funding
Municipal Affairs Funding
Goal Description Goal: Develop a business friendly Town Partner: This Goal fits within the community Vision in the following way: Reduce barriers to business start up and existing business development
The following projects are related to the completion of this goal:
PAPE Eco. 2A Update Municipal Plan
PAPE Eco. 2B Install sidewalks
PAPE Eco. 2C Recap side streets
PAPE Eco. 2D Pave street extension
PAPE Eco. 2E Upgrades to water system
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of business start ups
• Increase in existing business development
Qualitative • Improved water quality
Project Description
Project & Goal # PAPE Eco 2A
Project Title Update Municipal Plan
Associated Goal Develop a business friendly town
Brief Description Review and update the existing municipal land use plan
Project lead Port au Port East
Estimated Cost $ 3000
Time line Start Date: January 1, 2015
Completion date: December 31, 2015
Funding Source(s) Budget
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Eco 2B
Project Title Install sidewalks
Associated Goal Develop a business friendly town
Brief Description Install sidewalks in the town
Project lead Port au Port East
Estimated Cost $100 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) To be determined
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Eco. 2C
Project Title Recap side streets
Associated Goal Develop a business friendly town
Brief Description Recap paved side streets within the town
Project lead Port au Port East
Estimated Cost $ 50 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
A recap of the side streets will allow traffic to move more freely and thereby reduce greenhouse gas
emissions produced by vehicles slowing and stopping to avoid potholes
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Eco. 2D
Project Title Pave street extension
Associated Goal Develop a business friendly town
Brief Description Pave a gravel street extension in anticipation of additional residential
development
Project lead Port au Port East
Estimated Cost $100 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
________Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Improved traffic flow will reduce greenhouse gas emissions produced by vehicles
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Eco. 2E
Project Title Upgrades to water system
Associated Goal Develop a business friendly town
Brief Description Explore and develop a new source of groundwater supply
Project lead Port au Port East
Estimated Cost $ 500 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
X Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
At present, surface water is used for the community water supply. Development of a new groundwater well
will improve the quality of the community water supply.
Partner(s) Involved Role of Partner(s)
Port au Port West, Aguathuna, Felix Cove Pillar Goal # Project Cost Funding Priority Provide a PAPW Upgrades $ 2 100 Budget 1
business friendly Town
ECO 1A
to water system
000 GTF
Economic PAPW ECO 1B
To develop a Municipal plan
$ 25 000 Budget GTF
2
PAPW ECO 1C
Develop road network
$ 130 000 Budget 1
PAPW ECO 1D
Purchase a new Fire truck
$ 300 000 TBD 2
Goal Description Goal: Provide a business friendly Town Partner: This Goal fits within the community Vision in the following way: Reduce barriers to business start up and existing business development
The following projects are related to the completion of this goal:
PAPW Eco. 1A Upgrades to water system
PAPW Eco. 1B Develop a municipal plan
PAPW Eco. 1C Develop a road network
PAPW Eco. 1D Purchase a new fire truck
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of business start ups
• Increase in existing business development
Qualitative • Improved water quality
Project Description
Project & Goal # PAPW Eco. 1A
Project Title Upgrades to water system
Associated Goal Provide a business friendly town
Brief Description Replace and relocate a thirty five year old water main
Project lead Port au Port West, Aguathuna, Felix Cove
Estimated Cost $ 2 100 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
X Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
The community water main is over thirty years old and is now leaking in several places. A great deal of the
water main is installed in a marsh area or on private property. Much of the water main is three inches and
too small to accommodate a fire hydrant. Installing a new water main will improve the water quality
throughout the entire town.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPW Eco. 1B
Project Title To develop a municipal plan
Associated Goal Provide a business friendly town
Brief Description Develop a municipal land use plan
Project lead Port au Port West, Aguathuna, Felix Cove
Estimated Cost $ 25 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Development of a municipal plan will improve the town’s ability to reduce green house gas emissions by
allowing for more energy efficient planning practices.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPE Eco. 2E
Project Title Develop road network
Associated Goal Develop a business friendly town
Brief Description Pave the town streets
Project lead Port au Port West, Aguathuna, Felix Cove
Estimated Cost $ 130 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
X Emissions
The outcome(s) will be achieved as follows:
At present, the town has 1.8 km of gravel road to maintain. Paving these side streets will reduce the
emissions produced by vehicles travelling over these roads as traffic will be able to move at a more rapid
pace.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # PAPW Eco. 1D
Project Title Purchase a new fire truck
Associated Goal Provide a business friendly town
Brief Description To obtain a new fire truck to provide fire and emergency services
Project lead Port au Port West, Aguathuna, Felix Cove
Estimated Cost $ 300 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) TBD
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Lourdes Pillar Goal # Project Cost Funding Priority Provide a
business friendly Town
LOR ECO 1A
Improve the water system
$ 1 200 000 Budget GTF
2
Economic LOR Develop $ 100 000 Budget 3
ECO 1B
road network
GTF
LOR ECO 1C
Purchase a new Fire truck
$ 300 000 TBD 3
LOR ECO 1D
To develop a Municipal Plan
$ 30 000 Budget GTF
3
Goal Description Goal: Provide a business friendly Town Partner: This Goal fits within the community Vision in the following way: Reduce barriers to business start up and existing business development
The following projects are related to the completion of this goal:
LOR Eco. 1A Improve the water system
LOR Eco. 1B Develop a road network
LOR Eco. 1C Purchase a new fire truck
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of business start ups
• Increase in existing business development
Qualitative • Improved water quality
Project Description
Project & Goal # LOR Eco. 1A
Project Title Improve the water system
Associated Goal Provide a business friendly town
Brief Description Explore and develop a new source of groundwater supply, replace deteroriating
water main lines and install additional water main
Project lead Lourdes
Estimated Cost $ 1 200 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
X Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Making improvements to the community water supply will result in cleaner drinking water
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # LOR Eco. 1B
Project Title Develop a road network
Associated Goal Provide a business friendly town
Brief Description Pave the town’s side streets
Project lead Lourdes
Estimated Cost $ 100 000
Time line Start Date: January 1, 2014
Completion date: December 31, 2015
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
X Emissions
The outcome(s) will be achieved as follows:
Paving side streets will reduce the emissions produced by vehicles travelling over these roads as traffic will
be able to move at a more rapid pace.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # LOR Eco. 1C
Project Title Purchase a new fire truck
Associated Goal Provide a business friendly town
Brief Description Purchase a new fire truck to provide fire and emergency services
Project lead Lourdes
Estimated Cost $ 300 000
Time line Start Date: January 1, 2014
Completion date: December 31, 2015
Funding Source(s) TBD
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Cape St. George Pillar Goal # Project Cost Funding Priority Provide a
business friendly Town
CSG ECO 1A
Establish a business awards system
$ 200 Budget 2
CSG ECO
Develop road
$ 130 000 Budget 1
1B network GSG
ECO 1C
To develop a Municipal plan
$ 25 000 Budget GTF
2
CSG ECO 1D
Upgrades to water system
$ 2 100 000 Budget GTF
1
Economic Encourage new business opportunities
CSG ECO 2A
Welcome new business to the Town
Nil N/A 1
CSG ECO 2B
Upgrade Boutte du Cap Parc
$ 100 000 ACOA, Canadian Heritage, Dept. of T & C
2
CSG ECO 2C
Bilingual signage and trail development
$ 50 000 ACOA, Canadian Heritage, Dept. of T & C French Service Unit
2
CSG ECO 2D
Install signage on Route 460 and TCH
$ 4 500 Budget, Dept. of Tourism & Culture Private sector
1
To make CED a priority
CSG EOC 3A
Form a CED committee
0
None required
1
Economic CSG EOC 3B
Develop Loretto as a sub-division
$ 20 000 TBD 3
CSG EOC 3C
Install electricity at Loretto
$ 50 000 TBD 3
CSG Improve $ 130 000 ACOA 1
EOC 3D
road and bridge to Loretto
Budget
Goal Description Goal: Provide a business friendly Town Partner: This Goal fits within the community Vision in the following way: Reduce barriers to business start up and existing business development
The following projects are related to the completion of this goal:
CSG Eco. 1A Establish a business awards system
CSG Eco. 1B Develop a road network
CSG Eco. 1C Develop a municipal plan
CSG Eco. 1D Upgrades to water system
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of business start ups
• Increase in existing business development
Qualitative • Improved water quality
Project Description
Project & Goal # CSG Eco. 1A
Project Title Establish a business awards system
Associated Goal Provide a business friendly town
Brief Description Present an award for outstanding business service
Project lead Cape St. George
Estimated Cost $ 200
Time line Start Date: January 1, 2014
Completion date: December 31, 2015
Funding Source(s) Budget
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 1B
Project Title Develop a road network
Associated Goal Provide a business friendly town
Brief Description Pave the town’s side streets
Project lead Cape St. George
Estimated Cost $ 130 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
X Emissions
The outcome(s) will be achieved as follows:
Paving side streets will reduce the emissions produced by vehicles travelling over these roads as traffic will
be able to move at a more rapid pace.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 1C
Project Title To develop a municipal plan
Associated Goal Provide a business friendly town
Brief Description Develop a municipal land use plan
Project lead Cape St. George
Estimated Cost $ 25 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
X Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Development of a municipal plan will improve the town’s ability to reduce green house gas emissions by
allowing for more energy efficient planning practices.
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 1D
Project Title Upgrades to water system
Associated Goal Provide a business friendly town
Brief Description Replace deteroriating water main, install additional water main and a new
holding tank
Project lead Cape St. George
Estimated Cost $ 2 100 000
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget - GTF
If gas tax the following outcome(s) will be achieved:
Cleaner Air
X Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Making improvements to the community water supply will result in cleaner drinking water
Partner(s) Involved Role of Partner(s)
Goal Description Goal: Encourage new business opportunities Partner: ACOA, Canadian Heritage, Department of Tourism and Culture, Private sector This Goal fits within the community Vision in the following way: Reduce barriers to business start up
The following projects are related to the completion of this goal:
CSG Eco. 2A Welcome new business to the town
CSG Eco. 2B Upgrade Boutte du Cap Parc
CSG Eco. 2C Bilingual signage and trail development
CSG Eco. 2D Install signage on Route 460 and TCH
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in local business revenues
• Increase in the number of visitors to the region
Qualitative • Improved visitor experience
• Better tourism product
Project Description
Project & Goal # CSG Eco. 2A
Project Title Welcome new business to the town
Associated Goal Encourage new business opportunities
Brief Description Welcome new business start ups to the town
Project lead Cape St. George
Estimated Cost $ Nil
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 2A
Project Title Welcome new business to the town
Associated Goal Encourage new business opportunities
Brief Description Welcome new business start ups to the town
Project lead Cape St. George
Estimated Cost $ Nil
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 2B
Project Title Upgrade Boutte du Cap Parc
Associated Goal Encourage new business opportunities
Brief Description Welcome new business start ups to the town
Project lead Cape St. George
Estimated Cost $ 100 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Budget, ACOA, Canadian Heritage, Department of Tourism and Culture
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 2C
Project Title Bilingual signage and trail development
Associated Goal Encourage new business opportunities
Brief Description Install bilingual signage and develop a walking trail
Project lead Cape St. George
Estimated Cost $ 50 000
Time line Start Date: January 1, 2013
Completion date: December 31, 2014
Funding Source(s) Budget, ACOA, Canadian Heritage, Department of Tourism and Culture, French
Services Unit
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Project Description
Project & Goal # CSG Eco. 2D
Project Title Install signage on Route 460 and TCH
Associated Goal Encourage new business opportunities
Brief Description Install additional signage on Route 460 and TCH to make motorests aware of
the available services
Project lead Cape St. George
Estimated Cost $ 4 500
Time line Start Date: April 1, 2010
Completion date: December 31, 2012
Funding Source(s) Budget, Department of Tourism and Culture, Private sector
If gas tax the following outcome(s) will be achieved:
Cleaner Air
Cleaner Water
________Lower Greenhouse Gas
_______ Emissions
The outcome(s) will be achieved as follows:
Partner(s) Involved Role of Partner(s)
Goal Description Goal: Provide a business friendly Town Partner: This Goal fits within the community Vision in the following way: Reduce barriers to business start up and existing business development
The following projects are related to the completion of this goal:
CSG Eco. 1A Establish a business awards system
CSG Eco. 1B Develop a road network
CSG Eco. 1C Develop a municipal plan
CSG Eco. 1D Upgrades to water system
This goal may be impacted by the following land use issues: Project Land Use Plan Issue(s)
To measure the success of this goal the following indicators will be used: Quantitative
• Increase in the number of business start ups
• Increase in existing business development
Qualitative • Improved water quality
Social Sustainability For a community to be socially sustainable, the basic needs of its residents must be met. A socially sustainable community must have the ability to maintain and build on its own resources and have the willingness to prevent or address problems in the future.
There are two types or levels of resources in the community that are available to build social sustainability. Those are individual or human capacity, and social or community capacity. Individual or human capacity refers to the attitudes, attributes and resources that individuals can contribute to their own well-being and to the well-being of the community as a whole. Such resources include education, skills, health, values and leadership. Social or community capacity is defined as the relationships, networks and norms that facilitate collective action taken to improve upon quality of life and to ensure that such improvements are sustainable. To be effective and socially sustainable, both these individual and community resources need to be developed and used within the context of four guiding principles - equity, social inclusion and interaction, security, and adaptability. All four Towns have made an effort to engage and support other community based organizations in an effort to build social sustainability. Port au Port East Pillar Goal # Project Cost Funding Priority Increase
participation PAPE SOC
Support Heritage and
Nil Not required
1
among youth and seniors
1A Remembrance days at school
PAPE SOC 1B
Support activities of Seniors Club
$ 5000 Budget 1
PAPE SOC 1C
Support Canada Day activities
$ 500 Heritage Canada
1
PAPE SOC 1D
Upgrade Ball field and install lights and walking track
$ 50 000 Budget, Service Canada, Dept. of Recreation
Social To communicate more effectively with residents
PAPE SOC 2A
Develop a Town web-site
$ 1 000 Budget 1
Increase participation in municipal activities
PAPE SOC 3A
Keep residents informed about Municipal changes and activities
$ 500 Budget 1
PAPE SOC 3B
Establish appropriate non-council seats on committees
Nil Non required
1
Port au Port West, Aguathuna, Felix Cove Pillar Goal # Project Cost Funding Priority Ensure that
community PAPW SOC
Provide direct and
$ 2 000 Budget 1
services are appropriate
1A indirect support to community groups and projects
Social Increase participation among youth and seniors
PAPW SOC 2A
Support activities of Seniors Club
$ 5000 Budget 1
PAPW SOC 2B
Support Canada Day activities
$ 500 Heritage Canada
1
Lourdes Pillar Goal # Project Cost Funding Priority Ensure that
community LOR SOC
Provide direct and indirect
$ 2 000 Budget 1
services are appropriate
1A support to community groups and projects
Social Increase participation among youth and seniors
LOR SOC 2A
Support Canada Day activities
$ 500 Heritage Canada
1
Cape St. George Pillar Goal # Project Cost Funding Priority Ensure that
community CSG SOC
Provide direct and indirect
$ 2 000 Budget 1
services are appropriate
1A support to community groups and projects
CSG SOC 1B
Establish a social gathering place
$ 500 Budget 1
CSG SOC 1C
Support food bank services
$ 200 Budget 1
Social To make the Town more Senior friendly
CSG SOC 2A
Lobby for consistent medical services
0 Not required
1
CSG SOC 2B
Establish snow clearing services for seniors
$ 10 000 Health and Community services, Budget
2
CSG SOC 2C
Evaluate completed senior surveys.
0 Not required
1
CSG SOC 2D
Support the hiring of a part-time recreation director to build community activities with emphasis on Seniors
$ 25 000 ACOA, Service Canada
2
To increase community pride
CSG SOC 3A
Establish an annual award for outstanding property upkeep
$ 100 Budget 1
CSG SOC 3B
Feature award winner in newsletter
0 Not Required
2
Cultural Sustainability
Culture is a creative and dynamic process between people and their environment, including both material and immaterial aspects. A community’s vitality and quality of life is closely related to the vitality and quality of its cultural engagement, expression, dialogue, and celebration. The contribution of culture to building lively communities where people want to live, work, and visit is very important.
Through word, song, display and building, culture is preserved through many avenues, some of them being community memory, historic places and activities that have been carried on throughout the years so that they become identified with a specific set of community values.
Port au Port East Pillar Goal # Project Cost Funding Priority Collect
and display local history
PAPE CUL 1A
Partner with Twilight Seniors Club to prepare a living record
$ 5 000 Budget, Service Canada, Heritage Canada
1
Cultural PAPE CUL 1B
Develop a car museum
$ 250 000 Budget, Service Canada Heritage Canada
3
Promote local culture
PAPE CUL 2A
Install Bilingual signs and Lobby Provincial Government to install Bilingual signage
$ 25 000 Budget, Service Canada, Municipal Affairs
2
Port au Port West, Aguathuna, Felix Cove Pillar Goal # Project Cost Funding Priority Support
traditional activities
PAPW CUL 1A
Sponsor Community events
$ 2000 Budget 1
Cultural Promote local culture
PAPW CUL 2A
Install Bilingual signs and Lobby Provincial Government to install Bilingual signage
$ 10 000 Budget, Service Canada, Municipal Affairs
2
PAPW CUL 2B
Support Heritage recognition for OLOM Church
$ 0 Not Required
1
Lourdes Pillar Goal # Project Cost Funding Priority Support
traditional activities
LOR CUL 1A
Sponsor Community events
$ 2000 Budget 1
Cultural Promote local culture
LOR CUL 2A
Install Bilingual signs and Lobby Provincial Government to install Bilingual signage
$ 5 000 Budget, Service Canada, Municipal Affairs
2
Cape St. George Pillar Goal # Project Cost Funding Priority Support
traditional activities
CSG CUL 1A
Explore the creation of a working museum fishing exhibit
0 Not required
2
CSG CUL 1B
Expand the open air signage museum
$ 5 000 Canadian Heritage, ACOA
1
Cultural CSG CUL 1C
Organize weekly summer music nights
$ 3 000 Budget 2
CSG CUL 1D
Develop a traditional seasonal events schedule
$ 10 000 TBD 3
CSG CUL 1E
Sponsor Community events
$ 5000 Budget 1
CSG CUL 1F
Support local heritage in a local business
$ 1 500 TBD 2
Cultural Celebrate local history
CSG CUL 3A
Construct an enclosed sports/recreation/ cultural Center
$ 2 000 000 Budget GTF
3
Host an artist in residence
CSG CUL 4A
Feasibility study for artist in residence
$ 30 000 ACOA. ITRD
2
at Boutte du Cap Parc
program
Port au Port East Pillar Goal # Project Cost Funding Priority Ensure staff
level is appropriate
PAPE GOV 1A
Implement alternative employment structure
Nil Non required
1
Governance PAPE GOV 1B
Write job descriptions
Nil None required
1
Develop documented Policies and Procedures
PAPE GOV 2A
Implement official rules of procedure
Nil Non required
2
Secure appropriate financial resources
PAPE GOV 3A
Review tax and fee structure
Nil Non required
1
Port au Port West, Aguathuna, Felix Cove Pillar Goal # Project Cost Funding Priority Increase
financial capacity
CSG GOV 1A
Review tax structure
0 Not required
1
CSG GOV 1B
Explore other funding opportunities
0 Not required
1
Ensure staff level is appropriate
PAPE GOV 2A
Implement alternative employment structure
Nil Non required
1
Governance PAPE GOV 2B
Write job descriptions
Nil None required
1
Develop documented Policies and Procedures
PAPE GOV 3A
Implement official rules of procedure
Nil Non required
2
Secure appropriate financial resources
PAPE GOV 4A
Review tax and fee structure
Nil Non required
1
Lourdes Pillar Goal # Project Cost Funding Priority Ensure staff
level is appropriate
LOR GOV 1A
Implement alternative employment structure
Nil Non required
1
Governance LOR GOV 1B
Write job descriptions
Nil None required
1
Increase financial capacity
LOR GOV 2A
Review tax structure
0 Not required
1
CSG GOV 2B
Explore other funding opportunities
0 Not required
1
Develop documented Policies and Procedures
LOR GOV 3A
Implement official rules of procedure
Nil Non required
2
Secure appropriate financial resources
LOR GOV 4A
Review tax and fee structure
Nil Non required
1
Cape St. George Pillar Goal # Project Cost Funding Priority To increase
and improve communication with residents
CSG GOV 1A
Publicize all public Council meetings in advance
$ 500 Budget 1
CSG GOV 1B
Produce a regular newsletter
$ 200 Budget 1
Increase financial capacity
CSG GOV 2A
Review tax structure
0 Not required
1
CSG GOV 2B
Reduce rebates
0 Not required
1
CSG GOV 2C
Impose a utility tax
0 Not required
1
Governance CSG GOV 2D
Explore other funding opportunities
0 Not required
1
To maintain an appropriate level of staff
CSG GOV 3A
Examine opportunities to share resources
0 Not required
3
To document policies and procedures
CSG GOV 4A
Develop an operational policy
0 Not required
3
manual CSG
GOV 4B
Complete an annual evaluation of employees
0 Not required
2
CSG GOV 4C
Develop job descriptions
0 Not required
1
Implementation, Monitoring and Evaluation All four Towns realize that if the ICSP is to be a useful document, the implementation process has to be well-planned and well-managed. Successfully meeting the goals outlined in the plan requires strong leadership to support implementation. Effective implementation requires a structure and process with clear roles and responsibilities. Change and adjustments will be an ongoing part of the monitoring and evaluation process. Evaluation is a tool that will enable all four Towns to determine if they are on track and achieving the results that will move them towards their vision. The following is monitoring and evaluation schedule: Every Year Review and revise goals and projects Allow an opportunity for public comment Every Five Years Review and revise community vision Conclusion This ICSP outlines the goals and projects for the next five years for the Port au Port region. It has been developed and based on respecting people, improving the quality of living, appreciating and supporting cultural differences and being good stewards of the land, water and wildlife.
All four Towns are excited to begin implementation of the plan and to take collective action and generate solutions to common problems.