instrumentation testing
Transcript of instrumentation testing
-
7/30/2019 instrumentation testing
1/24
BN-SP-K10 Instrumentation Testing Calibration and
AcceptanceTable of Contents
1. Scope
2. Definition
3. General
4. Materials
5. Testing and Calibration
6. Commissioning
7. Administration
Attachments:
I Facilities and Equipment for Testing and Calibration II Classification of Instruments for Testing and Calibration
III Checklist for the Verification of Instrumentation
IV Loop Check Requirements
V Instrument Calibration and Loop Check Progress Recording
Reference Specifications:
BN-SP-K8 Specification for the Installation of Instruments
BN-SP-K2 Engineering Design Specification for the Accessibility of Instruments and Instrument Connections
- Requisition for Installation of Instrumentation.
1. Scope
1.1 This specification outlines the technical requirements and procedures for the inspection, verification,
testing, calibration and loop check of instrument installations. For the scope of work reference is made to the
requisition for instrument testing and calibration.
2. Definition
2.1 Loop
A loop will be defined in accordance with ISA 5.1 as a combination of one or more interconnected instruments
arranged to measure or control a process variable or both.
To this extent a loop also comprises dedicated systems such as alarm systems, safety and interlocking
systems, scanners, process computers, PLC systems, logging systems, ICS, DCS, etc.
2.2 Inspection
Examination of equipment for any physical defect or damage.
http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#6http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#6http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#6http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#7http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#7http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#7http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a5http://www.red-bag.com/jcms/component/mailto/?tmpl=component&link=a986b5cc848c3fbdc5b5a7a0f0ce0918be686876http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html?tmpl=component&print=1&page=http://www.red-bag.com/jcms/component/mailto/?tmpl=component&link=a986b5cc848c3fbdc5b5a7a0f0ce0918be686876http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html?tmpl=component&print=1&page=http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#a1http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#7http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#6http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#5http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#4http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#3http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#2http://www.red-bag.com/jcms/specifications/520-bn-sp-k10-instrumentation-testing-calibration-and-acceptance.html#1 -
7/30/2019 instrumentation testing
2/24
2.3 Verification
A visual examination to ensure that each instrument has been correctly installation is satisfactory.
2.4 Testing
To prove that the equipment stands the environment and functions in the manner expected.
2.5 Calibration
Comparison with approved standards of adequate precision and subsequent adjustment to meet the
manufacturers specification or the functional requirement.
2.6 Loop Check
A check of the instrument loop to prove the syncronization of components and the functional performance of
the system.
3. General
3.1 Contractor shall provide sufficient skilled labour and technically capable supervision to complete all aspects
of the testing and calibration within the agreed schedule for the contract.
3.2 The testing must be considered inclusive of all the operations necessary to have the instrumentation
perfectly operating.
3.3 Although it should be unnecessary for engineers personnel to participate in or witness every aspect of the
work described, the engineer shall have the right to do so without the need for justification. Engineer shall be
able to see a repeat of any particular test on request.
3.4 Attachment mentioned in the index form part of th is specification.
4. Materials
4.1 Handling of MaterialsInstrument materials shall be stored and handled in accordance with the specification for the installation of
instrumentation, BN-SP-K8.
4.2 Facilities and Equipment
4.2.1 Contractor shall supply and maintain all required test and calibration facilities including but not limited to
items listed in Attachment I of this specification.
4.2.2 All test apparatus used for calibration must be checked regularly against standards of at least comparable
-
7/30/2019 instrumentation testing
3/24
quality to the apparatus.
Discrepancies shall be noted, recorded and the source of discrepancy established. The discrimination and
absolute accuracy of the test apparatus for a given test must be better than the accuracy and discrimination
value quoted by the instrument manufacturer for the particular equipment under test.
Test equipment shall be approved by the engineer before use.
4.3 Materials Supplied by the Contractor
4.3.1 The contractor shall provide all tools, jigs, plastic tubing, compression ffittings, pipe fittings, valves, wire,
electrical terminals, plugs and sockets, and any other equipment necessary to follow the procedures contained
in this specification. Further, adequate provision for consumable material such as PTFE tape, thread
compound, solvent, contact cleaning fluid, graphite grease, lubricating oil, etc shall be made.
5. Testing and Calibration
5.1 General
5.1.1 Plastic sealing plugs should be kept firmly fixed in process connections, electricals entries, air supply
input, output and other connections, except during testing and calibration and immediately before final plant
connection.
5.1.2 Any air system, permanent or temporary used for instrumentation purposes should be blown down
throughly before use.
5.1.3 Any connection between any air supply system and an instrument under test shall be via an adequate
filter and regulator. Pneumatic instrumentation and related equipment requires a clean and dry instrument air
supply at all times. Excessive air supply pressure shall be avoided.
5.1.4 Care should be observed when connecting electrical power supplies to electric and electronic
instrumentation. Ensure correct voltage and frequency on AC suppliers, and where DC is used check that the
voltage regulation and any superimposed ripple is within the instrument manufacturers specification.
Disconnect all circuitry before the execution of HV cable insulation test (meggering), and point-pointidentification (ringing out).
5.1.5 Filling, test and drain plugs of instruments etc, should be put in place after use and checked for leakage.
5.1.6 Where a part of plant is deemed to be a hazardous or remotely hazardous area (zone 0, zone 1, and zone
2) caution is necessary if testing is performed after introduction of hydrocarbons, or other potentially hazardous
material into the plant, observe permit systems.
Where field devices are made safe by means of suitable enclosures (i.e. flameproof, explosionproof) some
restriction may be met in simulation if direct operation of float, displacer, pressure element, etc , is not possible,
-
7/30/2019 instrumentation testing
4/24
due to the possible need to remove safety covers for access.
The appropriate codes, permits and local regulations should be followed in these circumstances, normally
involving a periodic gas test in the area where covers are to be removed from enclosures.
Note that in any case power should be switched off prior to removing, and prior to replacing enclosure covers.
Contractor to provide portable gas test equipment.
5.2 Warehouse Inspection
5.2.1 Prior to the installation of f ield instruments the contractor shall inspect the instrument data plate
information against the equipment requisition to confirm correct model number, option, action, range, supply
voltage, hook-up requirements, etc.
5.2.2 Instruments not calibrated in accordance with the documents shall be readjusted.
5.2.3 Pressure switches shall be checked for the correct switch point and differential.
5.3 Flushing, Pickling and Pressure Testing
Prior to flushing and pickling operations of the main process lines all inline instrument components shall be
removed from the line and precautions shall be taken to avoid damage to instruments.
These will include but shall not be limited to:
- Flow measurement devices
- Control valves
- Analyzer probes thermowells, etc.
Control valves, pressure regulators, etc, shall not be hydrostatically tested with the line, as such testing can
damage the packing and diaphragms.
5.3.2 The contractor shall observe the correct handling of instrument components, avoid abuse and
disconnect/reconnect instrument tubing and cabling.
5.3.3 All process piping connections to instruments shall be removed and reinstalled before/after pickling,
flushing and pressure testing operations. Instrument primary block valves to in line instrument shall be closed.
Instrument process piping shall be subject to the same test pressure as the piping or equipment to which they
are connected. During this test any leakage and/or faults shall be eliminated.
The contractor shall verify that all instrument process lines and f ittings are clean and free from obstruction
before connection to the instrument.
5.3.4 Pneumatic piping shall be tested for leaks in accordance with ISA-RP. Final instrument connections shall
-
7/30/2019 instrumentation testing
5/24
be tested with a corrosion free soap solution. The normal instrument air supply pressure shall be used for
testing piping upstream of regulators, normally 4 to 7 bar.
5.4 Bench Test and Calibration
5.4.1 All instruments defined in Attachment II (paragraph 1.0) shall be calibrated in the field work shop for
bench calibration. This list is indicative not restrictive.
Instrument calibration shall be performed prior to mechanical completion.
5.4.2 The vendors published instructions for test and calibration shall be followed.
5.4.3 The calibration of indicating, recording and/or transmitting instruments shall be made at five points (10,
0,25, 50, 75 x 100 percent of range).
5.4.4 The instrument shall be suitably supported on the test bench (or in a dummy panel rig as appropriate) in
the position it would normally assume when installed. The applicable test equipment shall be connected to the
instrument and in the case of pneumatic instruments all external connections tested for leaks before
commencing calibration. Only those adjustments provided for the purpose of calibration shall be used to effect
correct calibration. Should calibration by means be impossible then the manufacturer should be consulted by
the engineer.
5.5 Field Test and Calibration
5.5.1 The primary purpose of field calibration is to calibrate those instruments which, because of their nature(weight, size, etc.) do not easily lend themselves to bench calibration, and which may be adequately and easily
calibrated in their installed position.
An indicative list of which may be field calibrated is presented in Attachment II, Section 2.0.
5.6 Panel and Panel Instrument Testing
5.6.1 All instruments mounted on panel front or integral with panels, cabinets and racks have been functionally
checked in the panel work shop.
Detailed testing of these instruments should therefore not be necessary unless the loop check reveals an
abnormal behavior or demonstrates misalignment.
5.7 Special Instruments
5.7.1 The calibration and testing of special instruments as identified in the requisition will be manufacturers
responsibility.
Procedure and prescriptions agreed with the manufacturer will be followed.
However, contractor is requested to supply assistance as required to the manufacturer for the field testing and
-
7/30/2019 instrumentation testing
6/24
calibration.
5.7.2 When testing of special instruments have been included in contractors scope but the contractor does not
have the skills required to test or calibrate special instruments the contractor must obtain the assistance of an
outside source, such in agreement with the engineer.
5.8 Verification
5.8.1 The instrument installation shall be verified to ensure that each instrument has been correctly installed in
accordance with the documents issued for the project.
5.8.2 Verification shall include the following:
- Visual examination to determine the good state of field instruments, accesories, supports, mounting stands,
process piping, air piping, electrical installation, etc.
- Visual examination of the correct installation of inline instruments.
- Visual examination of the correct installation of instruments in the control room, panel, and accesories.
- Visual examination of the completion of wiring and cabling.
An indicative list of instruments to be verified is included in Attachment III.
5.9 Loop Check
5.9.1 When all individual loop components have been tested and calibrated a complete functional check of the
instrument loop shall be made.
Loop checks are an oportunity to demonstrate that the instrumentation system performs satisfactorily. Each
loop check therefore should be witnessed by the engineer.
All calibration, wherever carried out, and all aspects of field inspection, verification and testing shall have
been satisfactorily completed before loop checks are performed.
For loop check requirements refer Attachment IV.
5.9.2 The following operations shall be performed during loop checking:
- Check against flowsheet to enclosure that all instruments and components are installed in the right place,
right direction of flow, etc.
- Check availability and performance of utility supply systems (electrical, pneumatic, )
- Apply a calibrated signal to the transmitter primary and check loop operation
-
7/30/2019 instrumentation testing
7/24
- Check for correct action and synchronization of all the components
- Activate primary devices
- Check on the functional performance of alarm, safety and sequence systems
- Any other check required to have the instrumentation working properly.
5.9.3 All defects in apparatus, wiring, tubing and connection errors, etc. should have been eliminated during the
various tests, prior to final loop check.
Loop checks are functional checks, and if an inoperative or badly calibrated or otherwise
unsatisfactory loop check result is encountered, all results for that loop should be considered null and void,
and the relevant earlier tests repeated, as necessary, after rework, replacement or repair. The loop check shall
then be repeated completely for that particular loop.
6. Commissioning
6.1 Commissioning includes all instrument activities associated with the initial start-up of the plant such as but
not limited to:
- The observance of instrument performance
- Zero checking/calibration under operating pressure
- Tuning of control loops
- Emergency repair and modifications
6.2 Control loops shall be commissioned in close cooperation with the plant operators.
Note : Commissioning belongs only to the scope of work of contractor if specifically stated so in the requisition
for instrument installation work.
Commission shall only proceed after a written order has been given to the contractor indicating coordination
procedures with plant operations department.
7. Administration
7.1 Contractor shall arrange for accurate and continuously record and keep engineer informed of progress by
regular formal reports, including an updated copy of the critical path diagram, and by cooperative day to day
communication when requested.
7.2 Contractor shall maintain his own filing system and organize the calibration and loop check recording as
detailed in Attachment V.
-
7/30/2019 instrumentation testing
8/24
7.3 Engineer to be notified of the planned commencement of each major activity, if different from latest
published time schedule.
Engineer shall be given the opportunity to review methods and procedures for the first test of a major type, first
inspection of a common type installation, etc.
7.4 Contractor shall pursue anomalies, clarify discrepancies in results, identify faulty instruments/materials,
progress replacement or repair of defective items and expedite/initiate rework or modification of unacceptable
installations with vendors or other contractors.
Attachment I
Facilities and Equipment for Testing and Calibration
1. Facilities
1.1 The contractor shall provide a mobile or temporary site workshop suitably clean and equipped for
instrument calibration.
1.2 Test Air Compressor
It shall be assumed that in the early stages of construction, instrument air will not be available, and therefore a
compressed air cylinder or small air compressor system shall be provided by contractor. An adequate storage
receiver, cooling provisions and facilities to remove any oil and water from the air shall be included.
1.3 Local/Temporary Electricity Supplies
When temporary electrical supply is being utilised on site for construction purposes, it should be ascertained
that the voltage, frequency and stability characteristics of the temporary supply are adequately similar to the
permanent supply which is to energize instrumentation equipment.
1.4 Workshop Transformers
Where necessary an isolation transformer of adequate rating should be available to step down (or up as
necessary) from the existing power supply voltage to the required voltage level.
1.5 Instrument Power Packs
Similarly where a special electrical supply is required for instrumentation, such as 24, 60 V AC, etc, the
contractor shall provide suitable power supplies for workshop use where it is not feasible or realistic to utilize
the supply equipment of the final system.
1.6 Electronic and Clean Instrumentation Facility
The site workshop should include suitable work benches and mounting facilities, and a separate clean sectionfor electronic and pneumatic instrumentation isolated from the area used for the test of heavy equipment,
-
7/30/2019 instrumentation testing
9/24
pressure and leak testing, etc.
1.7 Mercury Handling Precautions
Mercury manometers and any other equipment utilizing mercury should be well separated from all electronic
test gear and instrumentation.
If possible vendor to avoid using these instruments.
1.8 Basic Cleaning Facilities
To cover the situation where heavy instrumentation (level switches, displacer transmitters, control valves)
requires attention during the plant startup period, and has been exposed to process,at least rudimentary
cleaning facilities, including a drainage through and steam/water hoses, shall be provided by contractor.
A vacuum cleaner shall be available for the maintenance of dustfree shop cleanliness, when electronic and
pneumatic instrumentation is to be tested.
1.9 Satisfactory Storage
The site workshop shall incorporate clean, dry and secure storage for instrumentation waiting test or installation
after test.
1.10 Lifting and Handling Gear
A suitable lifting and weight handling facility shall be provided for handling control valves, large regulators, large
level switches, ball float level transmitters, displacer transmitter (when fitted to their stilling tube) and similar
heavy equipment.
1.11 Radioactive Radiation Sources
Where radioactive materials are utilized for level, density measurement etc, properly qualified personnel and
safe and plainly marked storage should be available.Proper handling and installation practices should be
observed.
1.12 Communication Equipment
Contractor shall provide for his own communication equipment for loop testing.
Radio transmitters/receivers shall comply with local and site regulations.
Where digital ICS or DCS systems or mV/phase equipment is used no ratio transmission is allowed within 3 m
of ant panels. This may necessitate the use of external (remote) arials for the control room end of radio
systems.
-
7/30/2019 instrumentation testing
10/24
2. Test and Calibration Equipment
Following equipment shall be provided as far as applicable.
2.1 Pressure Testing Equipment
2.1.1 Bucket Pump.
2.1.2 Air Pump (hand operated).
2.1.3 Vacuum Pump.
2.1.4 Test Gauges.
2.1.5 Hand-held Hydraulic Pumps.
2.2 Calibration Equipment for Pressure/Pneumatic Instruments
2.2.1 Dead weight tester.
2.2.2 Air filter regulator sets for use as sources of air signals.
2.2.3 Precision mercury manometer range 0-800 mm Hg.
2.2.4 Absolute pressure gauge.
2.2.5 Wallace and Tiernan pneumatic calibrator (dual scale), calibrated in mbar and bar.
2.2.6 Wallace and Tiernan precision low pressure gauge 0-250 mbar.
2.2.7 Precision inclined manometer (water).
2.2.8 Certified test gauges with an accuracy of 0.1% of range, calibrated for the required units of the following
ranges (barg) 0-1/0-2, 5/0-6/0-10/0-25/0-60/0-100.
2.3 Calibration Equipment for Electronic and Electrical Instrumentation
2.3.1 Digital voltmeter with an accuracy of 0.1% of range or better and with a discrimination of 10 mV or better
and incorporating an internal calibration/standardization feature.
2.3.2 Digital multimeters, Fluke or equivalent, (Exi) type preffered.
2.3.3 Portable pressure calibrator, 0-1 barg.
2.3.4 250 volts insulation resistance testers.
-
7/30/2019 instrumentation testing
11/24
2.3.5 Cable continuity testers, as required.
2.3.6 Vendors recommended calibration and test gear where this is unique to his equipment.
2.3.7 Stopwarch.
2.3.8 Oscilloscope portage frequency generator (sine square).
2.3.9 Test leads complete with clips, etc.
Note: For testing of circuits and cables within an operating plat, test equipment must have appropriate safety
certification.
2.4 Temperature Test and Calibration Equipment
2.4.1 Thermostatic temperature bath for use with oil.
2.4.2 High temperature bath for use with salt, or sand.
2.4.3 Standard (precision) thermometers.
2.4.4 Portable potentiometer and millivolt generator for field use, accuracy 0.05%.
2.4.5 One decade box 0.1-100.000 ohms accuracy 0.05% on any resistance value.
Attachment II
Classification of Instruments for Testing and Calibration
1. Bench Test and Calibration
1.1 Flow Instruments
1.1.1 Orifice Plates
All orifice plates should be checked visually for:
- Smooth perfectly flat surfaces without scratching or bowing
- A sharp nonreflecting edge on the upstream face where relevant, or radius on quadrant edge type orifices
-
7/30/2019 instrumentation testing
12/24
- The correct bore, as measured by inside micrometer
- Correctly stamped identification and bore dimensions on upstream face of tag handle.
1.1.2 Other Differential Pressure Producers
These include nozzles (of various designs), venturis, dall tubes and inserts.
It is normally impracticable to validate exactly the dimensions of these elements under site conditions.
However, every effort should be made to estimate dimensions internally and equipment should be visually
checked to ensure a good finish and freedom from damage.
1.1.3 Variable Area Flowmeters
Check for freedom damage, rough internal surfaces, the ability of the float to move freely and the correct
operation of indication and remote transmission (if any) when the float is operated by hand.
1.1.4 Turbine Meters
Check for damage, metal dust, rough internal surfaces, improper noise on bearings when the rotor is spun
(avoid overspeed).
Check for any damage to the pick-up head and electrical/mechanical connections.
In case of transmitting devices check the output signal as detailed for miscellaneous instruments.
1.1.5 Positive Displacement
Examine as for turbine meters including register head or linkage. Ensure free movement of mechanism. Handle
with care and avoid interference with inernal mechanism.
1.1.6 Vortex Meters
Check for damage to flange faces, buiff body and terminal housings.
1.1.7 Magnetic Flow Meters
Check for damage to flange faces, linings, electrodes and electrical housings, ensure earthing rings provided, if
required.
1.2 Level Instruments
1.2.1 Calibration testing of level measurement devices with sonic, conductivity, radiation, capacitance, etc.
measuring elements as detailed for miscellaneous instruments.
-
7/30/2019 instrumentation testing
13/24
1.3 Pressure Instruments
(Including differential pressure for flow and level).
1.3.1 Transmitters
Apply calibrated hydraulic pressure or vacuum to the measuring element(s) at 0, 25, 50 and 100% of full range.
Observe and record output corresponding to each calibrated input both going up and down scale. Adjust as
necessary, to obtain correct indicated process variable. After adjustment repeat above procedure until
calibration is within the tolerance stated by the manufacturer. Adjustment and alignment procedures shall be
carried out in accordance with the manufacturers instruction boo k.
1.3.2 Switches
Apply a test pressure in a similar manner as under paragraph 1.3.1. The switch point may be sensed by
multimeter or ohmmeter. The repeatability and hysteresis (differential) shall be determined and shown to lie
within the manufacturer;s published specification. The calibration shall be made with respect to the function
(high or low trip setting).
1.4 Temperature Instruments
1.4.1 Filled Systems
A constant temperature bath shall be used to calibrate all filled system, bi-metallic, and similar types of thermal
elements where used on transmitters, controllers, switches, etc.
The procedure shall be the same as above for transmitter calibration, except that two calibration points
(temperatures) only may be arranged, and they need not be at 0 and 100% of scale. The two temperatures
selected should, however, be sufficiently different to ensure satisfactory calibration. For temperature switches,
the tests should demonstrate the capacity of the device to sense and switch at any desired point within its
specified range. The repetability and differential should be checked to ensure that they are within the
manufacturers published specification. Adequate immersion of the sensing element, and steady conditions
within the temperature bath, is essential for accurate calibration.
1.4.2 Thermocouple Type Instruments
Use a millivolt source input, and follow the procedure detailed for pressure transmitters.
Conventional wire in ceramic bead thermocouples require no more than an inspection of the junction an d
check on the material type by means of a magnet and/or visually. Mineral insulated, insulated junction
thermocouples require no such check if a factory certification label is attached for the specified T/C material.
However, an insulation resistance test from thermocouple to metal sheath should be performed. Insulation
resistance should exceed 20 M at 20 C measured at 500 volts DC. Lower values may be indicative of moisureingress through a faulty seal of a batch of thermocouples check one for correct output whilst performing
-
7/30/2019 instrumentation testing
14/24
temperature bath test as 1.4.1.
1.4.3 Resistance Bulbs
A digital multimeter shall be connected to the RTD, and the resistance measured compared with the
specification figure for the bench temperature at the time. Check insulation resistance.
1.5 Miscellaneous Instruments
1.5.1 Transducers/Converters/Relays, etc
Connect the input terminals to an adjustable precision source and calibrate the output signal to its nominal
range. Check linerarity and hysteresis at the five cardinal points (0, 25, 50, 75 and 100%) which should be
within the manufacturers quoted specification.
1.5.2 Electronic Trip/Alarm Devices
The calibration shall be made in correspondence with the set point as detailed for pressure switches and
transducers.
2. Field Test and Calibration
Following instruments may be tested in the field. Unless otherwise indicated, the same procedures as detailed
for bench calibration (as far as applicable) shall apply.
2.1 Final Elements
2.1.1 Control Valves and Positioners
a. Valves shall be examined without dismantling
The data plate shall be checked against the requisition sheet
b. The action on air failure to be correct
If the action is incorrect it shall be changed
c. The lubricator, if fitted, shall be charged with the correct lubricant
d. The action of the handwheel shall be checked by manual operation
e. Air shall be applied to the valve and starting pressure and stroke checked and adjusted as necessary.
Stroking time shall be checked on applications with speed adjusters and quick re lease pilots
f. The valve positioner shall be checked and adjusted if necessary for correct stroking of the valve. All pivots on
-
7/30/2019 instrumentation testing
15/24
-
7/30/2019 instrumentation testing
16/24
should be fully drained from the system after test. The trip of the switch should be checked for both a rising and
a falling level (and/or interface). Normally the trip point should be at the centre of the float chamber or some
other well defined points.
2.2.2 External Displacer Level and Interface Transmitters/Controllers
Procedure should be similar to that level and interface switches but it will be necessary for the level (or
interface) to be raised and lowered over the calibrated length of the displacer. 5 Point calibration is preffered
but as a minimum the calibration should be checked at 1,50 and 100% of span, measurement of output
change, either pneumatic or electronic, shall be by calibration apparatus according to the requirements detailed
for pressure transmitters.
Where location or circumstances prohibit the use of water and/or other fluids for the calibration of displacement
transmitters/controllers, testing may be performed by removing the displacer from the torque or equivalent
suspension and hanging carefully calculated precision weights on the suspension. Weight combinations shouldcheck the transmitter/controller at 0,50 and 100% of span.
Where weight calibration is used, displacers shall be tested for leaks by immersing in cold water and heating
towards, but not to, boilding point. Any released bubbles, particularly at welding lines, is an adequate cause for
rejection to the manufacturer. If such tubes are weighed before immersion, and weighed again after allowing
the immersion water to cool before removing the displacer, any increase in weight is a clear indication of
leakage. Check knife edges for clean lines.
2.2.3 Tank Level Indicators
Floats to be raised and lowered using test facilities in accordance with manufacturers instructions.
Floats to move freely and synchronization of read-out system shall be checked.
Calibration should be made during plant start-up unless otherwise prescribed by the engineer.
2.3 Analytical Instruments
2.3.1 Procedure and prescriptions agreed with manufacturer shall be followed.
In general analytical instruments have been functionally checked in the manufacturers workshop.
Detailed checking of the associated electronics, transducer, programmer and read-out systems is not required
unless loop checking reveals abnormal operation.
2.3.2 The analytical section shall receive an operational field test. When calibration references/standards are
not available the calibration shall be made during plant start -up.
2.4 Miscellaneous Instruments
-
7/30/2019 instrumentation testing
17/24
2.4.1 General testing and calibration procedures to be followed.
Attachment III
Checklist for The Verification of Instrumentation
1. Visual Examination
1.1 Location
Contractor shall check that:
1.1.1 The right instrument is in the right location and correctly identified.
1.1.2 The location and instrument is accesible in accordance with BN-SP-K2.
1.1.3 The junction boxes are fabricated and located per specification.
1.1.4 Supporting of equipment, cable trays, piping and tubing is adequate and vibration free.
1.2 Installation
Contractor shall check that:
1.2.1 The instrument is installed in accordance with the process, air- and purge-piping details including any
recommendation given by the manufacturer.
1.2.2 Connections of piping and process equipment confirm to specification and instrument design.
1.2.3 Drains, purges, winterizing and isolation valves are properly installed.
1.2.4 The process instrument tubing and fittings meet specifications.
1.2.5 The necessary instrument bypass, shutoff, process block valves are provided as specified.
1.2.6 Each instrument item, controller, transmitter, motor valve, pressure switch, etc, meets purchase
specifications (check power supply level).
1.2.7 Instrument protection is completed (winterizing, purges, seals, fireproofing, etc).
1.2.8 All covers are installed and openings plugged (where required).
-
7/30/2019 instrumentation testing
18/24
1.2.9 Check each thermocouple to verify type of metal used and polarity of couple.
Check length of each thermocouple and thermometer, and corresponding depth of thermowell. Make sure
thermocouple bottoms in well.
1.2.10 Verify mechanical completion of the installation including the correct installation of nameplates.
1.3 In Line Instruments
Contractor shall check that:
1.3.1 In line instruments are installed in the right location and properly oriented.
1.3.2 Check supporting of vessel mounted instruments.
1.3.3 All thermowells are sealed against the entrance of water.
1.3.4 Check direction of flow through:
- Valves
- Flow meters such as variable area meters, positive displacement meters, turbine meters, orifice plates, sight
flow glasses, flow switches, etc.
1.4 Control Room
Contractor shall check that:
1.4.1 All scales and charts are correct as specified.
1.4.2 All instruments are properly supported.
1.4.3 Panel installation checked for mechanical completion.
1.5 Wiring and Cabling
This aspect covers all wiring and cabling and extends up to the field cable terminations and connections at
control panels and consoles including those in the main control center.
Contractor shall check that:
1.5.1 All cable, wiring, ducting, tray, conduit and fittings should be complete and secured in position.
1.5.2 All cables and wiring, completely disconnected from any equipment, shall have been checked for
continuity from end and for insulation resistance from core to core and each core to earth, using a 500 volt
insulation resistance tester. Correct routing of each conductor/pair shall be checked. Screens shall be checked
-
7/30/2019 instrumentation testing
19/24
as common conductor.
1.5.3 Check for correct installation of cable glands.
Attachment IV
Loop Check Requirements
1. Structure
On large plants (grater than 1000 input/output) it is considered time saving to perform loop check in two stages,
viz:
1.1 Stage 1 - Preliminary or Internal Loop Check
A check of the control room(s) or central control facilities first to the outgoing terminals of field marchalling
racks, where the field (multicore) cables are (or will be) connected. The field devices are simply simulated with
transmitter simulators, switches, mV sources or multimeters, per both inputs and outputs.
This achieves the following:
a. Enables the verification of all control room components including cross wiring, system cabling, ICS, logic
inputs/outputs, I/I converters, etc.
b. Often the control room(s) can be made ready before field equipment is installed, thus partial loop check can
be performed early
c. Trip devices can be set or checked
d. ICS,DCS and PLC configurations can be installed/checked/modified
e. A better indication can be obtained as to where any faults found at final loop check lie
f. Witnessing requirements at (final) loopcheck can be reduced
g. Loop check packages can be prepared in advance and partially marked up.
1.2 Stage 2 - Final (or overall) Loop Check
The check of the total loop from process, through the control room equipment back to process, as described in
paragraph 2.0 and 3.0 below.
2.1 Power Supply Systems
-
7/30/2019 instrumentation testing
20/24
2.1.1 Check designation and function of each isolator and fuse.
2.1.2 Check operation of automatic transfer systems, earth fault detection systems, reset mechanisms,etc, and
monitor performance.
2.1.3 Check fuse selectivity.
2.1.4 Determine in-rush current.
2.2 Instrument Air Supplies
2.2.1 Check supply system.
2.2.2 Check designation of air supply valves.
2.2.3 Adjust air supply to the required levels.
2.3 Steam Supply and Tracing Test
A functional test should ensure that a steam supply is available, that no noticable leaks appear with steam at
full pressure and that condensate is adequately disposed of. Checks for leaks shall be made by putting steam
on and off several times. Where main condensate headers are inoperative for one reason or another, a parallel
activity should seek to make the main condensate system operational and at the same time prove the tracing
system by draining condensate temporarily (and safely) to atmosphere.
2.4 Electrical Tracer Test
Electrical tracing, where used, should be energised circuit by circuit, to prove operability and validate individual
circuit isolation.
2.5 Purge Medium Test
A functional test of gasious and liquid purge systems should prove availability of the purge medium, correct
operation of regulatory and indicating devices and a pressure tight piping system.
2.6 Analyzer Utility Systems
All analyzer utility, sample recovery, vent gas and purge systems shall be functionally tested.
3. Measurement and Control Loops
3.1 Apply an appropriate reference source consistent with those described under calibration procedures to the
transmitter input.
Allow for filled legs on level applications. Zero adjustment is allowed at this stage, but for recalibration and
frange, transmitter must be returned to a workshop. Transmitter simulators may be used for remote seal
-
7/30/2019 instrumentation testing
21/24
transmitters.
3.2 Check each loop component at 1,50 and 100% of transmitter range.
Where a recorder forms part of the loop it should also be checked at this time.
3.3 Set any trip or alarm in the loop at the desired value. Adjust the transmitter output to initiate the device and
check the action of the interlock/alarm circuit.
3.4 Set transmitter output to say 50%. Switch to automatic and check, and if necessary set the correct action of
the controller.
3.5 On pneumatic controllers check, in seal position, for leaks.
3.6 On pneumatic loops perform bubble testing of pneumatic transmission lines from field to control room to
check for leaks.
3.7 Switch to manual, check controller output and control valve action. Check open and closed position and any
override control forming part of the control loop.
3.8 Correct any wiring or piping defect and adjust any faulty component as required.
3.9 Check that the instrument in the panel is in the correct location, that the nameplate is affixed. Leave all
controllers with conservative control mode settings prior to start-up.
3.10 Check burn-out protection, polarity and continuity of thermocouple and resistance bulb installations. Verify
correct indication and point selection of multipoint/datalogger systems.
4. Alarm, Shutdown and Interlocks
4.1 Check the action of the annunciator against its specification, i.e. fleeting contacts, first failure etc. Alarm
locations not already verified during measurement and control loop tests, should be completed.
4.2 Activate, or simulate, all inputs and observe system response.
Where interlock inputs have already been proved during measurement and control loop tests these inputs shall
be bypassed.
All other inputs shall be proven. The complete interlock system shall then be checked for correct sequence of
operation and all output devices shall be proven to work satisfactorily.
Attachment V
-
7/30/2019 instrumentation testing
22/24
Instrument Calibration and Loop Check Progress Recording
1. General
1.1 Accurate records are essential for the satisfactory, timely completion of the calibration and loop check.
In order to keep accurate records of all settings and work carried out, and subsequent re-work and re-test
where applicable, an acceptable and mutually agreed form of documentation is necessary.
Although the standard format of contractors may differ, a document shall be selected for use which is
convenient and appropriate for each type of inspection or test involved.
1.2 Record documentation of test and calibration is likely to be of only transident value to the ultimate customer
or operating company, once a plant is fully commissioned. However, value exists, at or about such a time, for
the purposes of ensuring accurate, as-built drawings and instrument schedules.
2. Recording Procedures
2.1 Instrument Schedule
The instrument schedule or instrument index or instrument data sheet prepared for the job is a reference
document that contains all components of the loops with location of instruments and reference to relevant
instrument requisition.
This document will be used for overall record purposes by keeping a master copy and signing-off instruments
and instrument loops as checked.
2.2 Recording of Verification Operations
2.2.1 Verification of field and other cable connections to the panel and rack instruments can be conveniently
recorded on wiring diagrams, again marking up as progress is made.
2.2.2 For field verification a meaningful record of installation, process piping, steam tracing, etc, can be made
by the use of relevant hook-up drawings.
2.3 Recording of Testing and Calibration
2.3.1 Each test shall be resumed in a report signed by contractor.
Contractor shall submit a form which has to be approved by the engineer. However, the engineer has the right
to prescribe the use of particular documents.
-
7/30/2019 instrumentation testing
23/24
2.3.2 Test reports shall be submitted not later than 40 hours after the date of testing.
2.3.3 Revisions to ranges, alarm and shutdown settings, etc, shall be recorded on appropriate documents.
2.4 Loop Checking
2.4.1 The recording of loop tests may convently be carried out on process and instrument flow diagrams
provided that all instrument functions are clearly marked.
2.4.2 For special loops on such diagrams which are grossly simplified, additional documentation may be
necessary in order to provide a checklist for every detail, setting, test, etc. This may take the form of the loop
sheet, with or without supplementary sheets, and/or control/shutdown/interlock schematic diagrams.
3. Marking
3.1 Marking Project Documentation for Record
The use of colour is recommended in the marking up of all test results. It is possible to easly read most detail
drawings, although heavily marked-up with a yellow feltpen or equivalent. Other colours may normally be
acceptable on P&I diagrams, particularly when used outside.
3.2 Marking Instrumentation
Following the completion of each step labels shall be applied to identify the status of inspection, calibration,
verification and loop checking.
Labels shall be supplied by contractor but the application will be supervised by the engineer.
Labels should be installed on visible and fixed parts of the instrument so they will not become removed during
the installation and connection of instruments.
3.2.1 Incoming Inspection (Apply Label 1)
Instrument has been inspected by contractor after it has been unpacked, against the data sheets and
manufacturers model, material, range, size, etc, are correct. This st ep is done normally at the warehouse.
3.2.2 Instrument Calibration (Apply Label 2)
Instrument is calibrated in the shop. Special instruments will be calibrated as per manufacturers instructions. In
special cases such as some analyzers, calibration will be done by vendor representatives. Calibration will
normally be done before instrument is installed.
3.2.3 Verification of Installation (Apply Label 3)
When 3 is on the instrument it indicates that the instrument is checked against the flowsheet for location anddirection of flow, that it is installed correctly according to the mounting drawings, tubing and fittings are correct,
-
7/30/2019 instrumentation testing
24/24
the instrument is accesible, air or electronic connections are completed and instrument is ready to be energized
for loop checking.
3.2.4 Loop Checking (Apply Label 4)
Instrument loop system has received a functional check and is fully operational.
At this stage the loop is completed and the instrument bears following information.
This sticker can only be applied after agreement with e ngineers instrument installation supervisor.