(Control Valve Perspective)(Control Valve Perspective)
Establishing and Sustaining Valve Performancefor World-Class Process Plants
Wisnu Anggoro
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 2/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 2
What is Instrument Performance Audit ?What is Instrument Performance Audit ?What is Instrument Performance Audit ?
An activity to audit the performanceof instrument to get best practice formaintenance and/or increasing theequipment performance andreliability
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 3/19
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 4/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 4
Business
Systems
ProductionManagement
Real-Time Optimization
Monitoring and Analysis
AdvancedProcess Control
Control Loop Performance(Includes Instrumentation) Level 1
Level 2
Level 3
Level 4
Level 5
Performance Optimization Initiatives
To Address These Demands,
Investment is Being Made at
Many Levels in the Business
Today’s Business Environment Has
Ever Increasing Performance Demands
TodayToday’’s Business Environment Hass Business Environment Has
Ever Increasing Performance DemandsEver Increasing Performance Demands
Reduce Manufacturing Costs
Increase Revenues
Achieve Positive Growth
Widen Profit Margins
Increase Shareholder Earnings
Where Should InvestmentBe Made
to Get the Best Return?
Where Should Investment
Be Madeto Get the Best Return?
Control Loop Performance(Includes Instrumentation) Level 1Control Loop Performance(Includes Instrumentation) Level 1
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 5/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 5
Control Valve
Performance
Tuning
Design
Loops
IncreasesVariability
20%
30%
30%
20%
Source: Entech---Resultsfrom audi ts of over 5000loops in Pulp & Paper Mills
“ The undesirable behavior of controlvalves is the biggest contributor topoor loop performance and thedestabilization of product uniformity” .
W. L. Bialkowski , President
EnTech Control Engineering
Loop Audit Studies:
Pulp and Paper Industries
Loop Audit Studies:Loop Audit Studies:
Pulp and Paper IndustriesPulp and Paper Industries
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 6/19
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 7/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 7
Gas Plant with advanced control
65% of loops > 2% process dead band
30% of loops > 4% process dead band
Blending Unit
55% of loops > 2% process dead band
Hydro cracker with advanced control 50% of loops > 2% process deadband
Overall statistics > 6000 control loops
54% of loops need valve/instrumentation help
Performance Audit Results:
Hydrocarbon Industries
Performance Audit Results:Performance Audit Results:
Hydrocarbon IndustriesHydrocarbon Industries
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 8/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 8
Leaders in Optimization Recognize
the Value of “ The Basement”
Leaders in Optimization RecognizeLeaders in Optimization Recognize
the Value ofthe Value of ““ The BasementThe Basement””
15-30% of control loopsimpact business
profitability. > 50% of critical loops
need valve attention.
“ Over half the value in
APC comes frompaying attention to thefield controlequipment”
ExxonMobil
Planning and Scheduling System
RTO System
APC System
Primary
Controls
Control Valves
I n c r e a s i n
g l y C r i t i c a l
f o r O
p t i m
i z a t i o n
Performance Monitoring is Applicable
to All Levels of Control & Optimization
1999 NPRA Presentation by Aspen Tech
“Optimal performance of the regulatorycontrol layer is a prerequisite for plants torealize the financial benefits of businessoptimization applications such as
advanced control, real-time optimization,and planning and scheduling.”
Honeywell Hi-Spec
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 9/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 9
When do we need Instrument
Performance Audit ?
When do we need InstrumentWhen do we need Instrument
Performance Audit ?Performance Audit ?1. Plant was operated for more than
5 years operation
2. Many issues for maintenance3. Alteration of the operation /
service condition
4. Obsolete issue for the equipment5. Advanced Process Control
Planning
6. Predictive maintenance planning
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 10/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 10
Which instrument are required to audit ?Which instrument are required to audit ?Which instrument are required to audit ?1. Critical or Severe application such as
Compressor anti surge, Main Oil Line
Pump, Separator application, Flareheader/vent application, water injectionapplication, pump recycle applicationetc.
2. Instrument that has many issue formaintenance
3. High pressure, high temperature and
high flow application4. Overall final control element
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 11/19
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 12/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 12
Friction - controlled & consistent
Seal design impacts Packing load and type Linkages, lost motion Impact of actuator design type
Positioner Design - sensitive & responsive Feedback scheme used Capability of tuning Ability to diagnose/monitor Must be matched to valve/actuator
Flow Geometry Design Stability is critical
Does the Valve Move?
How Fast Does the Valve Move?
Does the Valve Give the Right Loop Gain?
Control Valve Performance:
What Makes a Good Control Valve?
Control Valve Performance:Control Valve Performance:
What Makes a Good Control Valve?What Makes a Good Control Valve?
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 13/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 13
Reduce Manufacturing Costs
Increase Revenues
Achieve Positive Growth
Widen Profit Margins
Increase Shareholder Earnings
Business
Systems
ProductionManagement
Real-Time Optimization
Monitoring and Analysis
AdvancedProcess Control
Control Loop Performance(Includes Instrumentation) Level 1
Level 2
Level 3
Level 4
Level 5
Performance Optimization Initiatives
To Address These Demands,
Investment is Being Made at
Many Levels in the Business
Control Loop Performance
(Includes Instrumentation)Level 1
Once Achieved Best Performance, need to
Monitor & Maintain this Best Performance
Once Achieved Best Performance, need toOnce Achieved Best Performance, need to
Monitor & Maintain this Best PerformanceMonitor & Maintain this Best Performance“ The cost of predictive maintenance
on valves is 5 times less expensive
than scheduled maintenance and
ten times less expensive than
corrective maintenance, even
before the costs of down time are
figured in.”
From ARC Insights: July 14, 1999
Monitoring and Analys is Level 2
On-Line Diagnostics for
Process Optimization
Monitor Process Improvement
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 14/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 14
Maintaining Best Performance:
Predictive Maintenance
Maintaining Best Performance:Maintaining Best Performance:
Predictive MaintenancePredictive Maintenance
Time
T h r o u g h p u t
Practical plant limitsPractical plant limits
Comfort Zone: Operate here to make profit .
Safety Band: Operate into this area and make more profi t.
Typical OperatingTypical OperatingPointPoint – – devicesdevices
deteriorate withdeteriorate withtimetime
UnscheduledUnscheduledShutdown =Shutdown =
Lost RevenueLost Revenue
Quickly have theQuickly have theproblem fixed =problem fixed =Lost RevenueLost Revenue ScheduledScheduled
Shutdown =Shutdown =
Lost RevenueLost Revenue
Rebuild toRebuild toimproveimprove
throughputthroughput
Comfort Zone: Operate here to make profit .
Safety Band: Operate into this area and make more profi t.
Predictive maintenance can keep the plant operate at
a higher Prof itable level
Predictive maintenance can keep the plant operate at
a higher Prof itable level
AMS ValveLink® and Fisher control valves with
FIELDVUE® DVC are the right tools to monitor and
diagnose valve performance for Predictive
Maintenance
AMS ValveLink® and Fisher control valves with
FIELDVUE® DVC are the right tools to monitor and
diagnose valve performance for Predictive
Maintenance
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 15/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 15
The Advantage of Fisher Valves, DVC 6000 and
ValveLink Software on the loop performance :
The Advantage of Fisher Valves, DVC 6000 andThe Advantage of Fisher Valves, DVC 6000 and
ValveLinkValveLink Software on the loop performance :Software on the loop performance : To Establish Best PerformanceTo Establish Best Performance
To Maintain Best PerformanceTo Maintain Best Performance
To Retrieve Best PerformanceTo Retrieve Best Performance
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 16/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 16
Optimized control valve response:
Able to tune the valve to meet the exactrequirement of the process controlthrough DVC tuning
Optimized control valve response:
Able to tune the valve to meet the exactrequirement of the process controlthrough DVC tuning
Fisher Digital Valves and AMS ValveLink
Software Achieve Best Performance
Fisher Digital Valves and AMSFisher Digital Valves and AMS ValveLinkValveLink
Software Achieve Best PerformanceSoftware Achieve Best Performance
An X-ray to diagnose the valveconditions on: Packing wear, Seat
load, Actuator leakage, Valve
leakage, Insufficient air supply
An X-ray to diagnose the valveconditions on: Packing wear, Seat
load, Actuator leakage, Valve
leakage, Insufficient air supply
Valve Signature
Step Response
Dynamic Error Band
Overall control valve performance
indications: Able to provide
information on when to service and
when to recalibrate a control valve
Overall control valve performance
indications: Able to provide
information on when to service and
when to recalibrate a control valve
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 17/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 17
Fisher Digital Valves and AMS ValveLink
Software Maintaining Best Performance
Fisher Digital Valves and AMSFisher Digital Valves and AMS ValveLinkValveLink
Software Maintaining Best PerformanceSoftware Maintaining Best Performance
On-line trending graphscould reveal loop related to
control valve problems
On-line trending graphscould reveal loop related to
control valve problemsOn-line trending
Off-line analysis
On-line analysis of frict ionand deadband can be
compared with the off-line
data for potential valveperformance deterioration
On-line analysis of frictionand deadband can be
compared with the off-line
data for potential valveperformance deterioration
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 18/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 18
Fisher Digital Valves and AMS ValveLink
Software Retrieving Best Performance
Fisher Digital Valves and AMSFisher Digital Valves and AMS ValveLinkValveLink
Software Retrieving Best PerformanceSoftware Retrieving Best Performance
Current diagnostics graph data
can be overlaid on previous
graph data for comparison anddetection of potential control
valve deterioration
Current diagnostics graph data
can be overlaid on previous
graph data for comparison anddetection of potential control
valve deteriorationValve hunting at closing
due to galled bearing
Extended Valve Signaturedue to damage valve seat
Positioner gain is too highcausing hunting coulddue to wear in packing
8/13/2019 Instrument Performance Audit
http://slidepdf.com/reader/full/instrument-performance-audit 19/19
[File Name or Event]Emerson Confidential27-Jun-01, Slide 19
Control valve performance is a critical factor inprocess optimization.
Optimization of the control valve is essential forsuccessful Advanced Process Control.
Large economic returns result from proper sizing,selection, and maintenance of the control equipment.
Predictive monitoring of loop equipment is a keyelement for total asset optimization.
Process Optimization andProcess Optimization and
the Control Valvethe Control Valve