Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests...
-
Upload
darren-stephens -
Category
Documents
-
view
212 -
download
0
Transcript of Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests...
![Page 1: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/1.jpg)
Thomas C. Meyer/EP-AIT 1
Installation Review
March ‘03
TPCPre-installation and Functional Tests
Start Finish Certification of field cage………………….. 01-04 03-04
(Survey central electrode and end plates in horizontal) Close field cage (dummy chambers) Final leak test HV test in air or CO2
Installation of readout chambers …..……. 04-04 05-04 Place service support wheels on DELPHI frame Place scaffolding on both sides Mount insertion tool Installation of readout chambers (72) Tests for shorts on each chamber (20% HV, 100% Gate-V)
![Page 2: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/2.jpg)
Thomas C. Meyer/EP-AIT 2
Installation Review
March ‘03
TPCService Support Wheel & ROC Mounting Tool
![Page 3: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/3.jpg)
Thomas C. Meyer/EP-AIT 3
Installation Review
March ‘03
TPCPre-installation and Functional Tests
StartFinish
Survey of readout chambers……………… 06/04 06/04 Load TPC with dummy ITS
Combine with ITS rail deflection test Incline TPC to beam angle 1-2 mbar pressure in TPC Mount “I-bar” on shaft side Survey of chambers on both TPC
sides (photogrammetry) Record individual positions of
chamber mounting points 3 for IROCs and 4 for OROCs (serve as reference)
![Page 4: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/4.jpg)
Thomas C. Meyer/EP-AIT 4
Installation Review
March ‘03
TPCPre-installation and Functional Tests
StartFinish
Trial assembly of TPC in space frame…… 07/0407/04
Survey and adjustment of TPC-Space Frame rail system Move TPC into space frame and record insertion procedure Check for stability of reference positions Move TPC back into DELPHI frame
vertical deflection of TPC supports
-14
-12
-10
-8
-6
-4
-2
0
-9 -8 -7 -6 -5 -4 -3 -2 -1 0
position of TPC
V [mm]
back supportleading support
![Page 5: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/5.jpg)
Thomas C. Meyer/EP-AIT 5
Installation Review
March ‘03
TPC
StartFinish
Alignment of readout chambers…………… 08/04 08/04 TPC inclined and compensation (I-) bar mounted New survey of TPC end plates Individual machining (shimming) of mounting points Placement of shims and final survey Fill TPC with drift gas (Ar-CO2)
Requires that TPC gas system is temporarily installed in SXL2
Installation of laser calibration system……. 09/04 09/04 Mount beam telescopes and splitters on end plates Geometrical adjustments Tests with He-Ne-lasers
Pre-installation and Functional Tests
![Page 6: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/6.jpg)
Thomas C. Meyer/EP-AIT 6
Installation Review
March ‘03
TPC
StartFinish
Installation of electronics……………………10/04 01/05 Install service support wheel and scaffolding Mount front end- and readout electronics Mount DCS, LV, cooling and services Apply LV power (one 20° sector only); monitor temperature Pulser, grounding and crosstalk tests Check entire readout chain HV tests with cosmics and laser (266 nm)
Pre-commissioning of TPC………………… 02/05 02/06 Sector-wise tests with cosmics and laser Full functionality of readout system Full functionality of DCS and support systems
Pre-installation and Functional Tests
![Page 7: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/7.jpg)
Thomas C. Meyer/EP-AIT 7
Installation Review
March ‘03
TPCPre-installation Schedule
Delays prior to or during pre-installation shall be absorbed by the pre-commissioning period
![Page 8: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/8.jpg)
Thomas C. Meyer/EP-AIT 8
Installation Review
March ‘03
TPCInstallation Procedure Start
Finish Transfer of TPC from SXL2 to SX2………………...05-06 05-06
Lift DELPHI frame with TPC out of clean room Load both on a low-bed truck Move to SX2 by truck Unload truck in SX2
Transfer from SX2 to UX25………………………… 05-06 05-06 Crane in SX2 lowers TPC to underground Crane transfer from SX2 to UX25 Connect DELPHI frame to space frame
TPC insertion….…………………………………….. 05-06 06-06 Survey of TPC-Space Frame rail system (theodolites!) Slide TPC into space frame General survey & alignment (theodolites)
TPC in place and aligned………………………….. June 2006
![Page 9: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/9.jpg)
Thomas C. Meyer/EP-AIT 9
Installation Review
March ‘03
TPCTransport To SX2
![Page 10: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/10.jpg)
Thomas C. Meyer/EP-AIT 10
Installation Review
March ‘03
TPCLowering Of TPC Through Shaft
![Page 11: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/11.jpg)
Thomas C. Meyer/EP-AIT 11
Installation Review
March ‘03
TPCInsertion In Space Frame
![Page 12: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/12.jpg)
Thomas C. Meyer/EP-AIT 12
Installation Review
March ‘03
TPCInstallation Procedure Start Finish Preparation for ITS installation…………………….. 06-06 06-06
Installation of extension rails Removal of TPC from interaction point (IP)
TPC on stand-by during ITS installation………….. 06-06 10-06 Gas circulation active
Install Lasers and beam guides in UX25…………. 06-06 08-06 TPC reinsertion……………………………………… 10-06 11-06
Move TPC back into IP position Survey (theodolites) and inspection for damage Connection of power and services Connection of readout/DCS cables Removal of extension rails
TPC installation complete…………………………. Nov/Dec 2006
![Page 13: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/13.jpg)
Thomas C. Meyer/EP-AIT 13
Installation Review
March ‘03
TPCInstallation Schedule
![Page 14: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/14.jpg)
Thomas C. Meyer/EP-AIT 14
Installation Review
March ‘03
TPCInstallation Tools
Only one (major) tool used:
Serves as handling, transport and installation tool.
This frame is also used for the assembly of the TPC.
The DELPHI Barrel RICH Frame
![Page 15: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/15.jpg)
Thomas C. Meyer/EP-AIT 15
Installation Review
March ‘03
TPCSurvey and Alignment
TPC and service support wheels sit on sliding (friction) pads Need CERN survey team in all phases:
Photogrammetry on surface Traditional methods such as theodolites in cavern Need fiducial marks (“Taylor balls”) on end plates (6 + 6) Need identifiers (etiquettes) on service support wheel
Requires perhaps special supports on service support wheel to make identifiers visible through cabling layers.
Should be considered in view of frequent TPC movements Need lines of sight to Taylor balls
Space frame and rail sag Space frame sags each time another detector is mounted! --> do initial TPC survey and then a… …final survey when space frame is full.
![Page 16: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/16.jpg)
Thomas C. Meyer/EP-AIT 16
Installation Review
March ‘03
TPCCERN Infrastructure Use Service & Support groups:
EP-TA1 Gas working group EP-TA2 Construction & assembly, installation assistance,
emergency interventions EP-ED Front end electronics EST-LEA Installation & integration
Cabling from service support wheels to racks EST-SU/EXP Survey and alignment (Task Leader: C. Lasseur) ST-CV Cooling and ventilation systems TIS Authorization for use of equipment (lasers, field
cage HV)
Cranes and special vehicles Standard hall cranes One movable crane (35 t) plus driver for one day Low-bed truck (35 t) for one day and one transport Distance is only ~100 m from SXL2 to SX2!
![Page 17: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/17.jpg)
Thomas C. Meyer/EP-AIT 17
Installation Review
March ‘03
TPCCommissioning DCS fully functional to take control of operation
Imperative for all subsequent tasks and functions
Gas mixture and quality Detector was already filled with drift gas prior to ITS installation Gas quality (O2 and H2O) checked
If not okay, check for leaks. Full test of gas system and safety features
Startup of all cooling systems Electronics, resistor rods, thermal screens
Low voltage Monitor temperature Check for shorts Inspection of grounding and shielding
HV (all systems) Relies on gas quality Gradual ramp-up of all supplies and current monitoring
![Page 18: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/18.jpg)
Thomas C. Meyer/EP-AIT 18
Installation Review
March ‘03
TPCCommissioning (cont’d)
Readout system Check for correct cabling Check for oscillations, high pedestals, noise sources Pulse readout electronics Look for cosmic signals (if HV is operational)
Laser calibration system Power lasers Send beams to TPC
Requires special safety precautions! Beam alignment and correlation Read out tracks with DAQ Do first calibration series with B = 0
![Page 19: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/19.jpg)
Thomas C. Meyer/EP-AIT 19
Installation Review
March ‘03
TPCPersonnel and Resources
Field cage & CERN’s host responsibilities
2004 2005 2006 2007
EP-AIT
EP-TA1
EP-TA2
EP-ED
EST-LEA
EST-SU/EXP
ST-CV
TIS
3 3 3 0.25
0.5 0 0 0
0.6 0.1 0.5 0
18 0 4 0
Gas-WG
Front End Electr.
Install. & Integr.
Survey
Cooling
Safety
FC, DCS, Installation
Field Cage Constr.
General continuous support
0.01 0.010 0
3.5 1 0.2 0.1
![Page 20: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/20.jpg)
Thomas C. Meyer/EP-AIT 20
Installation Review
March ‘03
TPCPersonnel and Resources
2004 2005 2006 2007
Bratislava
Frankfurt
GSI
Heidelberg
x x x x
1.5 1.5 1.5 0
x x x 0
Electr., LV, Services,Calibr. Gating, SSW
SSW, Constr.
Construction
Constr. & Cool.
Bergen
Heidelberg
x x x x
x x x x ALTRO
PASA
Copenhagen 0.1 0.1 0.1 0 All systems
Readout chambers, cooling and services
Electronics
Laser calibration system
![Page 21: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/21.jpg)
Thomas C. Meyer/EP-AIT 21
Installation Review
March ‘03
TPCRisks and Concerns
Technical Commissioning period is short
(but we have extensive pre-commissioning!) Stability of readout chamber position in view of
frequent TPC movements Regular (yearly) TPC roll-outs for ITS maintenance and repair
Personnel Possible shortage of manpower Forecasting of resources difficult
Scheduling Slippage due to shortage of manpower Unknown delays from ITS maintenance scenario
Re-commissioning of TPC
![Page 22: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/22.jpg)
Thomas C. Meyer/EP-AIT 22
Installation Review
March ‘03
TPCMaintenance and Access In the Future
Field Cage (low risk item): The most critical components are the resistor rods
They are exchangeable but require, scaffolding, special handling tools and partial dismounting of electronics.
If failure is on absorber side, TPC must be moved out of IP position, necessitating complete uncabling of the service support wheels.
Un- and recabling of TPC: max. 20 work days (8 h)Repair work and debugging: 10 d
ROCs (low risk item): The most sensitive components are the wires (breakage and aging)
Same arguments as for the resistor rods
Electronics and DCS: Standard maintenance at the level of the service support wheels
Requires scaffolding for access
Laser Calibration System: Standard maintenance at the level of the end plates
![Page 23: Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish Certification of field cage………………….. 01-0403-04.](https://reader035.fdocuments.us/reader035/viewer/2022070401/56649f1f5503460f94c36c29/html5/thumbnails/23.jpg)
Thomas C. Meyer/EP-AIT 23
Installation Review
March ‘03
TPCITS Trial Assembly